Professional Documents
Culture Documents
PUNE, INDIA.
Both the gas and water side of a boiler should be protected against corrosion
during out of service periods. It is known that many of the corrosion problems of
boiler and auxiliary equipment have their inception during storage. Rusting of
tube surfaces, as indicated by the formation of the red hematite (Fe2O3), not
only cause a roughened tube surface but also results in attack of parent metal.
The advantages of efficient feed water and boiler water treatment during
operation may be lost if the same diligence is not applied to protect heat.
Transfer surfaces during idle periods. Protection from corrosion during storage
becomes vitally important considering the number of times during the life of a
boiler when it and its auxiliary equipment are idle.
Station service water - Water normally used for drinking, fire protection, etc.
Softened water - Filtered, sodium zeolite softened water with total hardness less
than 1 ppm.
Two- bed, de-mineralised water - Water that has been passed through cation
and anion, ion exchanges in series.
Mixed bed de-mineralised water - Water that has been passed through a mixed
bed de-mineraliser. Water from an evaporator is considered to be of equal
quality.
Treated de-mineralised water - Mixed bed de-mineralised water that has 200
ppm of hydrazine and enough pH builder added to give final concentration of pH
Page 1 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
DRY STORAGE:
When it is known that a boiler is to be idle for a considerable length of time and
that a brief period will be allowed for preparation to return it to service, the dry
storage method is recommended. In this method the unit is emptied, thoroughly
cleaned internally and externally dried, and then closed up tight to exclude both
moisture and air. Trays of silica gel, or other moisture absorbent may be placed
in the drums to draw off the moisture in the air trapped by the closing up of the
boiler.
The following general procedure is recommended when placing a unit into dry
storage.
Step-1
Fire the boiler according to the normal start-up procedure and establish 3 to
2
4kg/cm (g) drum pressure and stop the firing. Secure the boiler and when the
pressure drops to 1.5 kg/cm2(g) immediately drain the boiler and headers under
air. As soon as possible, open the drums to allow air to circulate for drying of all
internal surfaces.
This step is included for a unit that has been in service and is to be placed into
storage. For a unit that has never been in service, start with Step 2.
Step-2
If the unit is full of water and cold, drain the unit under air. All non-drainable boiler
tubes and superheater tubes should be blown with compressed air. If an external
source of heat is available such as a steam coil air heater, portable heaters, etc.,
operate these heaters to assist in drying the internal boiler surfaces.
Install trays (of non-porous construction and capable of passing through the drum
man way) containing the moisture absorbent (silica gel is preferred) into the
drums. Insert the trays into the drum being certain that none of the absorbent
comes into contact with the metal surface of the drum. To insure against an
overflow of corrosive liquid after the moisture has been absorbed, the trays
should not be more than ½ full of dry absorbent. The amount of absorbent can
vary but the recommended minimum is 1kg of absorbent per 1000 kgs per hour
steam flow capacity of the unit.
Step-3
Attach a source of nitrogen to the steam drum vent, close all other vents and
drains and pressurize the boiler to 0.3 to 0.6 kg/cm 2(g) with nitrogen. The amount
of nitrogen required will vary according to the volume of the unit.
Page 2 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
Step-4
With the boiler and superheater pressurized, alternately open all boiler drains
(including superheater) to purge air from the unit until pressure decays to zero. It
may be necessary to repeat this process several times to reduce the amount of
oxygen left in the unit to a minimum.
The unit should now be stored under 0.3 to 0.6 kg/cm 2(g)nitrogen pressure
maintained at the steam drum. To maintain the nitrogen pressure, all connections
and valves should be blanked or tightly closed. Check gas pressure daily to
ensure protection.
CAUTION:
THE UNIT SHOULD BE PROPERLY TAGGED AND THE APPROPRIATE
WARNING SIGNS ATTACHED NOTING THAT THE BOILER IS STORED
UNDER NITROGEN PRESSURE AND THAT COMPLETE EXHAUSTION OF
THE NITROGEN MUST OCCUR BEFORE ANYONE ENTERS THE DRUM.
BEFORE ENTERING DRUMS TEST TO PROVE THAT THE OXYGEN
CONCENTRATION IS AT LEAST 19.5%.
Page 3 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
WET STORAGE
The advantage of employing the wet storage procedure is that the unit is stored
completely wet with the recommended levels of chemicals to eliminate a wet-dry
interface where possible corrosion can occur. It is suggested that volatile
chemicals be used to avoid increasing the level of dissolved solids in the water to
be used for storage.
1. The unit should be filled with deaerated, de-mineralized water treated with
200 ppm hydrazine (N2 H4) for oxygen removal and a pH of 10.
3. Fill the unit with the treated de-mineralized water to the normal centerline
of the steam drum. Stop filling further.
Page 4 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
6. At some later date when the unit is to be placed into service, the boiler can
be drained to normal start-up water level and placed into operation.
Page 5 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
NITROGEN BLANKET
Nitrogen should be introduced through a “T” fitting or one vent (or drain) at each
of the following locations:
1. Drum vents.
2. Superheater outlet header connection.
The “T” fitting is to be installed between the pipe (or header) and the vent (or
drain) valve. The nitrogen inlet to the “T” should include a stop valve identical to
the vent (or drain) valve. The stop valve and “T” fitting should be a permanent
addition to the location listed.
The nitrogen required to seal the drainable components may be supplied from a
permanent nitrogen system or portable tanks located near the vent elevations.
Due to differences in plant layout, the owner should choose his own method of
piping the nitrogen, either from their permanent system or from portable tanks, to
the vent (or drain) locations listed.
CAUTION:
THE UNIT SHOULD BE PROPERLY TAGGED AND THE APPROPRIATE
WARNING SIGNS ATTACHED NOTING THAT THE BOILER IS IS STORED
UNDER NITROGEN PRESSURE AND THAT COMPLETE EXHAUSTION OF
THE NITROGEN MUST OCCUR BEFORE ANYONE ENTERS THE DRUM.
BEFORE ENTERING DRUMS TEST TO PROVE THAT THE OXYGEN
CONCENTRATION IS AT LEAST 19.5%.
Page 6 of 7 REV. 0
THERMAX BABCOCK & WILCOX LTD Project: Mawana Sugars
PUNE, INDIA.
Page 7 of 7 REV. 0