WEEK 1 Meeting and consultation with Ar. Austria for the Prelim requirement
November 17-30, 2019 Going to New Lucena Central School to gather the datq regard to the school’s population
Distribution of works
WEEK 2 Gather Data about evacuation plan
November 24- 30, 2019 Spatial requirements from the Time saver,DepEd and Survey
Collect other Design considerations
WEEK 3 Organizational chart and evacuation plan from new Lucena Central school
December 1-7, 2019
Interview the SPED teacher, Gather data and Space requirements
LGU findings about the new lucena central school
Space planning of the site
Consultation with Ar. Diasanta
WEEK 4 Combining ideas into final Site Development Plan
December 8-14, 2019 List of Spatial requirements:
Time savers Standards
DepEd
Survey
Consulation with Ar. Diasanta
WEEK 5 Finalization of works
Dec. 15- 18, 2019 Prelim deadline