Professional Documents
Culture Documents
Questions
1. Andrew has joined as the Project Manager of a project. One of the project documents
available to Andrew lists down all the risks in a hierarchical fashion. What is this
document called?
a. Risk Management Plan.
b. List of risks.
c. Monte Carlo diagram.
d. Risk Breakdown Structure.
3. Beta is the Project Manager of a Road construction project. During a project review,
Beta realizes that one particular risk has occured. To take appropriate action against
risk that has happened, Beta needs to refer to which document?
a. Risk response plan
b. Risk management plan
c. Risk breakdown structure
d. Risk register
: a. Beta needs to refer to the Risk response plan that documents responses to
identified risks.
4. During which stage of Risk planning are risks prioritized based on probability and
impact?
a. Identify Risks
b. Plan Risk responses
c. Perform Qualitative risk analysis
d. Perform Quantitative risk analysis
CORRECT: c. Risk probability and impact are defined during Qualitative risk
analysis.
5. During which stage of Risk planning are modeling techniques used to determine
overall effects of risks on project objectives for high probability, high impact risks?
a. Identify Risks
b. Plan Risk responses
c. Perform Qualitative risk analysis
d. Perform Quantitative risk analysis
CORRECT: d.
6. Andrew is a Project Manager for Green Valley project. A risk management plan has
been prepared for the project. Which of the following should Andrew do next?
a. Perform Qualitative risk analysis
b. Perform Quantitative risk analysis
c. Identify Risks
d. Plan Risk responses
7. Which of the following processes has risk register as the primary output?
a. Plan Risk Management
b. Identify Risks
c. Monitoring and Control Risks
d. Perform Qualitative Risk Analysis
CORRECT: b. Process of Identify Risks has Risk register as the major output.
8. Five of the processes in Project Risk Management are from which process group?
a. Initiating
b. Planning
c. Executing
d. Monitoring and Control
CORRECT: b. Five of the six processes in Project Risk Management are part of the
Planning process group.
9. John Strauss is a Project Manager for a reforestation project. To identify the risks
involved, John sends a questionnaire to gather inputs from experts. Which technique
is John using?
a. Delphi technique
b. Interviews
c. Brain storming
d. Documentation review
10. Mathew is a Project Manager for software migration at a bank. A major risk that has
been identified is attrition of resources. As a strategy to respond to this risk, Mathew,
with support from Senior Management, provides good increments to his team
members. What type of risk response is Mathew following?
a. Accept
b. Avoid
c. Transfer
d. Mitigate
CORRECT: Risk mitigation is a response to negative risks and not positive risks.
Positive risks may be responded by - "Exploit", "Enhance", "Share", "Accept".
INCORRECT: b. Cleaning the city centre is done every day. It is an operation and not
a project. A project must be unique and time-limited.
2. Claire is a Project Manager for building a new apartment complex. The planning of
the project is complete and an Exit Gate meeting is scheduled. What is likely to
happen in this meeting?
a. Project's learning will be doucumented and the project will be closed.
b. Claires performance will be critically analyzed by the management.
c. The performance of the project team members will be reviewed by Claire.
d. Projects deliverables will be reviewed and a decision will be made on
projects continuation.
CORRECT: d. During exit gate or kill point, projects deliverables are evaluated. A
decision is made whether the project should be continued.
3. Alice is joining a new project. Her manager informs Alice that requirements of the
project will be defined using progressive elloboration. Which of the following option
best describes progressive eloboration?
a. The requirements of the project will be defined over a period of time
in iterative fashion based upon feedback received.
b. Requirements are unknown at this time and will be defined later.
c. Requirements will be defined based upon discussions with the customer.
d. Requirements will be defined based upon discussions with the subject
matter expert.
CORRECT: a.
4. In which type of organization does the Project Manager has maximum authority?
a. Balanced matrix.
b. Strong Matrix.
c. Functional.
d. Projectized.
5. Chris has joined ABC organization as a Project Manager. The project team members
do not report to Chris. They report to Engineering and Accounting departments.
Which type of organization structure best represents ABC style of functioning?
a. Balanced matrix.
b. Strong Matrix.
c. Functional.
d. Projectized.
6. In which type of Matrix organization, does the PM have very little authority.
a. Weak Matrix.
b. Strong Matrix.
c. Balanced Matrix.
d. Functional Matrix.
11. Which process group has processes from all the ten knowledge areas?
a. Initiating.
b. Planning.
c. Executing.
d. Monitoring and Control.
CORRECT: b. Planning process group has processes from all nine knowledge areas.
13. Tom is a Project Manager helping his company on selection of a new project. Tom is
using Payback period project selection method. Which one of the four projects should
his company select?
a. Project A requires an investment of one million dollars. After six months
of investment, project will generate profits of $50K per month.
b. Project B requires an investment of $100K dollars. It will yield returns of
$5K per year.
c. Project C requires an investment of one million dollars. It will yield
returns of $40K per month.
d. Project D requires an investment of $500K dollars. It will yield
returns of $50K per month.
14. Mary is a Project Manager helping her company on selection of a new project. Mary
is using Benefit Cost ratio project selection method. Which one of the four projects
should her company select?
a. Project A has a construction cost of $1 million and a projected sale price
of $1.2 million.
b. Project B has a construction cost of $2 million and a projected sale
price of $2.5 million.
c. Project C has a construction cost of $5 million and a projected sale price
of $6 million.
d. Project D has a construction cost of $10 million and a projected sale price
of $11.5 million.
CORRECT: b. Project B has benefit cost ratio of 1.25. This is the highest among the
four projects.
15. Tim is a Project Manager helping his company on selection of a new project. Tim is
using Net Present Value project selection method. Which one of the four projects
should his company select?
a. Project A has a net present value of $300K.
b. Project B has a net present value of $400K.
c. Project C has a net present value of $500K.
d. Project D has a net present value of $600K.
CORRECT: d. A Project with the highest net present value must be selected during
project selection.
16. Chen is a Project Manager helping his company on selection of a new project. Tim is
using Opportunity Cost project selection method. Which one of the four projects
should his company select?
a. Project A has a opportunity cost of $300K.
b. Project B has a opportunity cost of $400K.
c. Project C has a opportunity cost of $500K.
d. Project D has a opportunity cost of $600K.
17. Kumar is a Project Manager helping his company on selection of a new project.
Kumar is using Payback period project selection method. Which one of the four
projects should his company select?
a. Project A has a Payback period of three years.
b. Project B has a Payback period of four years.
c. Project C has a Payback period of five years.
d. Project D has a Payback period of twentyfour months.
CORRECT: d. Project d has the minimum payback period. The project manager
should select the project with the least payback period.
18. Jim is a Project Manager helping his company on selection of a new project. Jim is
using Internal rate of return project selection method. Which one of the four projects
should his company select?
a. Project A has an internal rate of return of 5%.
b. Project B has an internal rate of return of 6%.
c. Project C has an internal rate of return of 7%.
d. Project D has an internal rate of return of 8%.
CORRECT: d. The Project Manager should choose a project with highest internal rate
of return.
19. Samantha is a Project Manager of a Software product. The project required an initial
investment of $100,000. The project generated a revenue of $20,000 in the first year.
There were operational cost of $5000 and tax liability of another $5000. What is the
return on invested capital?
a. 5%
b. 10%
c. 20%
d. 0%
CORRECT: b. After tax profits of the project are $10000. Return on invested capital
= $10000 divided by $100000.
21. Which of the following is tru about the Project Management Plan?
a. Project Management Plan identifies and authorizes the Project Manager.
b. Project Management Plan is a detailed project schedule defining tasks,
their dependencies as well as primary milestones of the project.
c. Project Management Plan is a formal document that defines how the
project is to be managed.
d. Project Management Plan is prepared as part of the Direct and Manage
Project Work process.
22. George is the Project Manager of a project responsible for manufacturing shirts for a
large order. During which process the shirts will get manufactured?
a. Develop Project Management Plan
b. Direct and Manage Project Work
c. Monitor and Control Project Work
d. Create WBS
INCORRECT: b. During the Direct and Manage Project Work process the PMP gets
executed. The deliverables get generated during this process.
23. Perform Integrated Change Control process is part of which process group?
a. Initiating.
b. Planning.
c. Executing.
d. Monitoring and Control.
24. Greg is a Project Manager of a construction project. The customer has requested that
an additional room needs to be constructed at an extra cost? How should Greg
respond to this request
a. Document the request and present it to Change Control Board.
b. Refuse the request as this was not part of the original scope.
c. Accept the request as the customer is willing to pay for it.
d. Consult the project sponsor.
CORRECT: a. The Change Control Board should review and evaluate the change
request in this case.
25. Michael is the Project Manager of a software project being developed for a large
customer. A senior management executive of Michaels organization suggests Michael
that adding a new feature will be a good addition to his project. What is the best
course of action for Michael?
a. Document the request and present it to change control board.
b. Refuse the request as this was not part of the original scope.
c. Accept the request as it is being suggested by a senior member of the
organization.
d. Consult the project sponsor.
26. Doug is a Project Manager for a project to build a bridge. During his review of the
progress, Doug finds out that the project is likely to be completed in six months
before schedule. Which is the most suitable thing for Doug to do next?
a. Organize a party for the project team to ensure employee motivation
remains high.
b. Raise a change request to reduce staff.
c. Doug does not need to do anything.
d. Doug needs to use the additional six months to make sure the bridge
exceeds thq quality goals.
27. Which of these is not done during the Close Project process?
a. Creation of deliverables of the project.
b. The handing over of deliverables to the receiving party.
c. Documenting the project learnings.
d. Release of project resources.
28. Mary is taking over an ongoiung project as a Project Manager. The earlier project
manager is no more with the organization. Mary wants to understand why the project
should be executed, the high level project requirements and budget of the project.
Which document should Mary refer to?
a. Project Management Plan.
b. Project Statement of work.
c. Business case.
d. Project charter.
CORRECT: d. The project charter explains the purpose of the project, high level
requirements and high level budget.
Questions
CORRECT: b. In the middle stages, the resources and cost usage is maximum.
CORRECT: a. It is easy to make changes to project goals and approach at the initial
stage. Stake holders have maximum influence at this stage.
5. You are the Project Managers of XYZ consultants. The Project team members are
from Finance and HR departments. The team members report to Finance and HR
Managers respectively, and you have limited control over them. What type of
organizational hierarchy does XYZ consultants follow?
a. Matrix organization
b. Projectized organization
c. Functional organization
d. None of these.
CORRECT: c. The team members report to Functional Managers.
9. There are two processes in the initiating process group. These are part of which
knowledge area?
a. Project Cost Management
b. Project Scope Management
c. Project Time Management
d. Project Integration Management
CORRECT: d. The two processes Develop Project Charter, and Develop Project
Scope statement are part of project integration management knowledge area.
1. The project you are managing has nine stakeholders. How many channel of
communications are there between these stakeholders?
a. 9
b. 8
c. 45
d. 36
Questions
2. Sam Consultancy has a large internal project to be initiated. To staff this project, Sam
Consultancy is working with People Consultancy to provide three resources for six
months. The resources will be part of the team managed by Sam Consultancy for six
months. Which contract type should be used by Sam Consultancy?
a. Purchase Order
b. Cost plus Fee
c. Fixed cost
d. Time and Material
3. Sam Consultancy is planning to buy ten desktops for $1500 each from a leading
computer store. Which type of contract will get signed in this case?
a. Purchase Order
b. Cost plus Fee
c. Fixed cost
d. Time and Material
4. Tree Consultancy is getting 200 computers installed from a vendor. The vendor will
be paid the cost involved and a 10% incentive. Which contract will be used in this
case?
a. CPPC
b. CPIF
c. CPFF
d. Fixed Cost
INCORRECT: A. During the Conduct Procurements process, bidders can clarify their
doubts using bidder conference.
1. The implementation of which of the following processes decreases the risk of project
failure?
a. Manage stakeholder engagement
b. Control stakeholder engagement
c. Plan stakeholder management
d. Develop stakeholder engagement
4. You are engaged in gathering information from stake holders regarding whose
interests should be taken into account throughout the project. This is called:
a. Identify stakeholders
b. Stakeholder analysis
c. Expert judgment
d. Plan stakeholder management