Initiating
dDevelop Project Charter is the process of developing a document that formally authorizes
the existence of a project and provides the project manager with the authority to apply
organizational resources to project activities. It also ensures satisfaction of stakeholders.
2) 1
Executing
4) Initiating
Answer: 1
References: PMBOK® Guide 6th Edition, pages 81 and 405.
Project documents high level information such as project purpose and overall project risk etc.
Risk management plan is component of project management plan that describes how risk
management activities will be structured and constructed. Both documents are very crucial for
mapping the project risk.
5 ) Planning
Answer: 2
Reference: PMBOK® Guide 6th Edition, page 162.
The WBS dictionary is a document that provides detailed deliverable, activity, and
scheduling information about each component in the WBS.
6) Executing
Answer: 3
Reference: PMBOK® Guide 6th Edition, page 342.
Since Project is just promoted to the execution phase, it is a problem related to conflicts
of opinions. Meetings are the best way to resolve the misunderstanding among all project
team members.
8) Executing
Answer: 4
References: PMBOK® Guide 6th Edition, pages 67, 83, 96, 115, 120.
Change request may not be because of improper planning. It can be possible because of different reasons like
stakeholder request, external sources and technological advances. It is a responsibility of project manager to
assess the impact of change request.
9) Executing
Answer: 2
Reference: PMBOK® Guide 6th Edition, pages 325.
It is the responsibility of functional manager to manage the resource calendar and availability.