You are on page 1of 3

IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308

REDUCTION OF NON-VALUE ADDED ACTIVITIES IN AN APPAREL


MANUFACTURING THROUGH VALUE STREAM MAPPING (VSM)

S Appaiah1, C.S.Chethan Kumar2, Varun Bhatt3


1
Associate Professor, Department of IEM, MSRIT
2
Associate Professor, Department of IEM, MSRIT
3
PG Student, Department of IEM, MSRIT, Bengaluru
Abstract
This paper discusses the problems with the Current State Map (CSM) were identified, by highlighting non-value added activities,
The existing system is investigated for lead time problems and suitable remedial measures were implemented through VSM. The
lean concepts and techniques are implemented in a garment unit . The outcome is that the the complete lead time is once
decreased from 51 days to 43 days. The WIP at every work station has also been decreased.

Keywords: Lean Manufacturing, Lead Time, Non-value added activity, Value added activity, Value Stream Mapping,
WIP, Wastage.
---------------------------------------------------------------------***--------------------------------------------------------------------

1. INTRODUCTION logistic, conversion process and outbound logistic.


Integrated line balancing is minimization of cost for inbound
Medium scale garment manufacturing industry for the shorts and outbound logistic subsystems. The generic approach has
and pants, as a way to critically analyze the manufacturer’s been developed for linking the balancing of the line of
manufacturing method and subsequently to establish the production in the conversion area with the customers’ rate of
waste streams. Industry is operating under the “make to demand in the market and for configuring the related stock
order” technique of lean manufacturing, which means it chambers [5].
does now not hold a giant stock of completed components
and best creates a precise number of production depends on In the paper of Dr.C.S. Chethan Kumar and Dr.N.V.R.
the customer demand .Whereas the fundamental objective Naidu [6] explains about the Lean manufacturing methods
was to scale down the current lead time by way of at least that are appropriate for a company will vary according to the
50%, In order to achieve that goal, required to document the company’s maturity in lean manufacturing and the issues
present state of the creation method, future state map was they are facing.
once developed with the objective of making improvements
to the productivity With the construction of a preliminary
2.1 Problem statement
and final state VSM, we were able to attract conclusions
founded on the research and information collected. Based on the analysis of the existing system studies done, as
the garment industry manufactures variety of readymade
2. LITERATURE REVIEW garments and exports the garments to other countries, but
now a day the company plans to improve production rate
A headlong rush to decrease the lead time by becoming lean with less wastages. Generally these wastes are
has created urgency for researchers and practitioners to overproduction, correction (rework), waiting and inventory
apply new tools and strategies for dictating wastages. This of the manufacturing product .where the company ploy to
research addresses the application of value stream mapping increase the productivity of the industries alongside it tries
in garments industry to implement lean manufacturing. to reduce the wastages of the manufacturing and lead time to
Value stream mapping is different than conventional manufacture the products.
recording approaches as it helps in the visualization of
Material Flow, Information Flow, cycle times and utilization
2.2 Objectives
of resources. Assurance of effective integration and
communication, lean systems may also be accomplished Henceforth the objective of this work is to make sense of by
with higher efficiency [1]. what method can lean manufacturing is used to accomplish
the following:
Chethan Kumar C.S, N.V.R Naidu, illustrated the  To reduce the defects in sewing section
importance of using the lean principles to eliminate non  To identify the wastes in storage, cutting, sewing,
value added wastes in garment industry [2]. The redesigned finishing and packing department
process is more effective and efficient than the previous one  Identifying the areas where changes have been made to
[4]. The moderate to large manufacturing industry depends implement lean
on a long and integrated supply chain, consisting of inbound  To reduce the lead time

_______________________________________________________________________________________
Volume: 05 Special Issue: 16 | ICRAES-2016 | Sep-2016, Available @ http://www.esatjournals.org 72
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308

Value stream mapping is drawn for the existing system by


3. METHODOLOGY following the following procedures.
Steps to use the value stream mapping tool
1. Selection of Product Family Step 1: Identify the product or service to map.
2. Current State Map Step 2: Draw the current value stream map.
Step-1 Calculate Takt Time Step 3: Assess the current value stream.
Step-2 Understand customer demand Step 4: Develop a Future State value stream map.
Step-3 Map the process flow Step 5: Develop a plan to implement the desired state.
Step-4 Map the material flow
Step-5 Map the information flow
Step-6 Draw the Time line
3. Future State Map
4. VALUE STREAM MAPPING OF CURRENT
STATE (CSM)

Customer Demand
KI-1 UNIT 300 pieces per day
Orders (Takt Time 1.5 minutes)
Orders
raw mateials from
customers
buyer

Ship
Schedule

Information Information Information Information


Information
transportation Transportation

Fabrics and Cutting Sewing and Washing finishing and Shippment section
storage assembly packing

3 days 2 days 1 days


4 days 2 days 2 days
Cycle Time 6 days Cycle Time 3 days Cycle Time 16 days Cycle Time 2 days Cycle Time 5 days Cycle Time 5 days
VA CT 2 days VA CT 2.5 days VA CT 11 days VA CT 2 days VA CT 4 days VA CT 3 days
NVA CT 4 days NVA CT 0.5 days NVA CT 5 days NVA CT 0 min NVA CT 1 days NVA CT 2 days

Total Cycle Time = 277.5 hr


Total VA Cycle Time = 183.75 hr
4 days 6 days 3 days 3 days 2 days 16 days 1 days 2 days 5 days 2 days 5 days Total NVA Cycle Time = 93.75 hr
2 days 2.5 days 11 days 2 days 4 days 3 days Lead Time = 51 days
WIP Time = 47 days
Total Distance =

Fig.1: Value Stream Mapping of Current State

The outcomes from Future State Value Stream Map are as WIP=47 day
follows:
Disadvantages in the current scenario
The Total Cycle Time =277.5 hr  More of in-process inventory.
Value Added Cycle Time =183.75 hr  Excessive setup time
Non Value Added Cycle Time=94 hr
Lead Time =51 days

_______________________________________________________________________________________
Volume: 05 Special Issue: 16 | ICRAES-2016 | Sep-2016, Available @ http://www.esatjournals.org 73
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308

5. FUTURE STATE VALUE STREAM MAPPING (FSM)

Customer Demand
KI-1 UNIT 380 pieces per day
Orders (Takt Time 1.1842 minutes)
Orders
raw mateials from
customers
buyer

Ship
Schedule

Information Information Information Information


Information
transportation Transportation

cutting super sewing


vision supervision

line incharge

Fabrics and Cutting Sewing and Washing finishing and Shippment section
storage assembly packing

2 days 2 days 1 days


2 days 2 days
Cycle Time 6 days Cycle Time 3 days Cycle Time 14 days Cycle Time 2 days Cycle Time 5 days Cycle Time 4 days
VA CT 2 days VA CT 2.5 days VA CT 10 days VA CT 1.5 days VA CT 4 days VA CT 2 days
NVA CT 4 days NVA CT 0.5 days NVA CT 4 days NVA CT 0.5 days NVA CT 1 days NVA CT 2 days

Total Cycle Time = 255 hr


Total VA Cycle Time = 165 hr
2 days 6 days 2 days 3 days 14 days 2 days 2 days 1 days 5 days 2 days 4 days Total NVA Cycle Time = 90 hr
2 days 2.5 days 10 days 1.5 days 4 days 2 days Lead Time = 43 days
WIP Time = 41 days
Total Distance =

Fig.2: Future State Value Stream Mapping

The outcomes from Future State Value Stream Map are as REFERENCES
follows:
The Total Cycle Time =255 hr [1]. Dilip Roy And Debdip Khan, (2010) “Integrated Model
Value Added Cycle Time =165 hr For Line Balancing With Workstation Inventory
Non Value Added Cycle Time=90 hr Management”, International Journal Of Industrial
Lead Time =43 days Engineering Computations.
WIP=41 day [2]. Chethan Kumar C S, Dr. N V R Naidu, Minimizing the
eighth waste of lean- Absenteeism through Six sigma
Value stream mapping activities should be developed with methodology, International journal for Quality Research,
specific implementation to plans This process is repeated Vol. X No. X, pp.505-512, 2011.
for all value streams across the organization in order to [3]. EdrawSoft (2012). Value stream mapping
achieve world class improvement results. The true value in software.Edraw Max, Retrieved February 20, 2012, from
value stream mapping is the creation of process http://www.edrawsoft.com/Value-Added-Flow-Chart.php
improvement plans that can be implemented systematically [4]. G. Sahitya Reddy, Harsha Lingareddy, K.Jagadeeshwa,
across the company with sustainable results. “Value Stream Mapping In a Manufacturing Industry”
International Journal of Advanced Engineering Technology.
[5]. R.M. Belokar, Sandeep Singh Kharb, Vikas, 2012 “An
6. CONCLUSION
Application Of Value Stream Mapping In Automobile
Lead time is diminished with the application of VSM. The Industry: A Case Study “, International Journal Of
result is that the lead time is reduced from 51 days to 43 Innovative Technology and Exploring Engineering.
days. [6]. A Survey on Awareness of Lean Manufacturing
Concepts in Indian Garment Manufacturing Industries by
Dr.C.S. Chethan Kumar and Dr.N.V.R. Naidu, Page No. 783
[7]. Emil suciu, Mihal, Arvinte value stream mapping-A
lean production methodology, 2011
_______________________________________________________________________________________
Volume: 05 Special Issue: 16 | ICRAES-2016 | Sep-2016, Available @ http://www.esatjournals.org 74

You might also like