Professional Documents
Culture Documents
Daily Progress
Daily Progress
1. General Maintenance of cleaning of T/F Bays and transformer T-5 was carried out.
2. Checked the cooling fans, and oil leakages cleaned the cubical boxes of CBs, & isolators.
3. Remove the kite & threads from 132KV yard site
4. General Maintenance & cleaning of 220KV yard bus bar isolators was carried out .
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of main gate outside green belt along with boundary wall
Attended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023602, Cleaned/washed disc
insulators at loc no.207-209,211-217,219-224 & tightened dead end tower's jumper pads at loc no.210
& 218.
1. Annu.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chocks
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of main gate outside green belt along with boundary wall
Attended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023602, Cleaned/washed disc
insulators at loc no.207-209,211-217,219-224 & tightened dead end tower's jumper pads at loc no.210
& 218.
1. Annu.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chockes
1. General Cleaning of Control House Building, Old colony roads and main gate.
Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008
Attended shutdown on 220KV T/L Bandala-KSK CCT-1, PTW no.113993, Cleaned/washed disc insulators
at loc no. 148-135.
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of Division office front grassy plot.
3. Cleaning of old Colony grassy plot along with roads
4. Washing/cleaning of AC Panels out door Unit
1. Attended the fault of 11KV O/G VCB Trolley of Khizra feeder. Racked out the trapped trolley from panel
which was trapped during issuing the PTW to LS FESCO sub Divison due to dead fault. Racked out trolley
and setted right its interlocking Rod & shutter.
2. General cleaning of 110V DC Battery set No. I was carried out. Checked the specific gravity, voltage &
electrolyte level per cell.
3. Thermovision of 220/132KV, 160MVA auto T/F Bushing & bays clamps was carried out.
4. Painted the structure of 132KV Bus bar isolatorE5Q11 & E5Q12 in 132KV yard
5. setted right 2 No. search lights of 220KV yard lights & replaced the defective search Rods and ignators.
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of Division office front grassy plot.
3. Cleaning of battery Bank Room
1. Testing of earth mesh of 132KV yard equipment and control room panels.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chockes
1. General Cleaning of Control House Building, Old colony roads and main gate.
Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008
1. General Cleaning of Control House Building, Old colony roads and main gate.
Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008
1. DES Test of T/Oil of 220/132KV 160mVA Auto T/F T_1,T-2, T-3,T-4 and 132/11KV Power T/F T-5 & T-6
was carried out.
2. Removed the kite thread from 220kV Yard Area
3.Painted the structure of 132KV Bus bar isolator E4Q11 & E4Q12 in 132KV Yard
4. General Cleaning of 110V DC Batteries set NO. I & II was carried out Removed the sulphation /corrosion
and corrosion and applied white Vaseline.
5. Setted right 2 No. Tube lights of 220V DC Battery Room.
1. General Cleaning of Control House Building, Old colony roads and main gate.
Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008
1. General Cleaning of Control House Building, Old colony roads and main gate.
Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008
1. General Cleaning of Control House Building, Old colony roads and main gate.
3 Trimming of Tree front of Division office and cleaning of Front grassy plot.
1. Attended the approved shutdown vide PTW # 2623 dated 28-10-19 on 220 KV Gatti line-I D3Q1.
During shutdown replaced the electromechanical distance relay LZ31-24 with new digital/numerical
distance relay 7SA87 siemens make.
1. General Cleaning of Control House Building, Old colony roads and main gate.
3 Trimming of Tree front of store and cleaning of Front grassy plot of control room.
1. Attended the shutdown on 220 KV Gatti line-I D3Q1. During shutdown tested the new installed
numerical relay 7SA87 also tested the electromechanical relay LZ31-24. Checked the tripping and closing
of breaker through relay.
Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-1 Cleaning of disc insulators and
retightening of hardware from tower no. 01 to 29 was carried out Total towers cleaned =29 Total
cleaned disc insulators =1638*
Attended shutdown on 220KV T/L Gatti-JWR CCT-1, PTW no.629, Cleaned/washed disc insulators at loc
no. 3-11,12,14, 23,24,25
1. General Cleaning of Control House Building, Old colony roads and main gate.
1. Attended the shutdown on 220 KV Gatti line-II D2Q1. During shutdown replaced the
electromechanical distance relay LZ31-24 with new Numerical distance relay 7SA87 siemens make. also
Tested the secondary distance relay.
Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 02 to 10 and 13,16 to 22,23, 25 was carried outTotal towers
cleaned =19 Total cleaned disc insulators =966
Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.632, Cleaned/washed disc insulators at loc
no. 2-10 & 25.
1. Opened the all clamps of line isolator D2Q10, Cts and CB D2Q1, cleaned the conductor & clamps.
Replaced the defective Nut/Bolts & Cleats.
2. Applied inhibitor compound and refilled them.
3. Cleaned the earth clamps & tightened also replaced the defective Nut/Bolts
4. Checked the hydraulic oil level and its pressure found OK.
5. Cleaned the cubical boxes tightened the terminal connection and vermin proofing was carried out.
6. Opened the finger contacts of isolator cleaned the finger contacts and their studies.
7. Lubrication was carried act and then refilled it.
8. Painted the equipment heads for R-Y-B phase marking.
9. Lubricated the moving parts of mechanism
10. Painted the structure of 132KV Yard Bus bar isolators of PTs-3 & PTs-4 in 32KV Yard.
1. General Cleaning of Control House Building, Old colony roads and main gate.
1. Attended the annual shutdown for annual protection testing. During shutdown checked/ tested the
distance relay primary protection 7SA87 Siemens make with XS92A universal test set and tested the
breaker failure relay with secondary injection test set. Test results found satisfactory. Tightened the all
connections in control panel and relay panel. Tightened the CT and PT terminal and also carried out the
general Cleaning. Checked/confirmed the tripping of CB through distance relays found OK. Verified the
annunciation circuit of CB, found healthy..
Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 01,11,12,14,15,24,26 to 29 was carried outTotal towers
cleaned =10 Total cleaned disc insulators =588*
Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.635, Cleaned/washed disc insulators at loc
no. 1,11,12,14, 15,24 & 26.
1. General cleaning of 220V DC Battery Set No. I was carried out. Checked the specific gravity voltage and
electrolyte level per cell
2. thermovision of clamps/jumpers of 132KV Yard equipement
3. Setted right 2 No. Search lights of 132KV yard lights replaced the defective bul/search rods & Cables.
4. Cleaned the cubical boxes of 160MVA auto T/F T-1, T-2, T-3 & T-4 and vermin proofing was carried out.
*By Operation S/D*
1. General Cleaning of Control House Building, Old colony roads and main gate.
1. Attended the annual shutdown for annual protection testing. During shutdown checked/ tested the
distance relay primary protection 7SA87 Siemens make with XS92A universal test set and tested the
breaker failure relay with secondary injection test set. Test results found satisfactory. Tightened the all
connections in control panel and relay panel. Tightened the CT and PT terminal and also carried out the
general Cleaning. Checked/confirmed the tripping of CB through distance relays found OK. Verified the
annunciation circuit of CB, found healthy..
Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 01,11,12,14,15,24,26 to 29 was carried outTotal towers
cleaned =10 Total cleaned disc insulators =588*
Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.635, Cleaned/washed disc insulators at loc
no. 1,11,12,14, 15,24 & 26.
1. General cleaning of 220V DC Battery Set No. I was carried out. Checked the specific gravity voltage and
electrolyte level per cell
2. Thermovision of clamps/jumpers of 132KV Yard equipment
3. Setted right 2 No. Search lights of 132KV yard lights replaced the defective bulB/search rods & Cables.
4. Cleaned the cubical boxes of 160MVA auto T/F T-1, T-2, T-3 & T-4 and vermin proofing was carried out.
2. Trimming of grassy plot in front of division office and control house building
1. General Maintenance & cleanng of cubicalboxs of their CBs and isolators was carried out. Checked the
H/oil level and leakage.
2. removed the kite & threads from 220KV Yard Area
3. Setted right 3 No. search lights of 220KV and replaced the defective search rods & chocke sets.
4. LCM of lightening arrestor of both side of all the T/F T-1 , T-2,T-3, T-4,T-5 & T-6 was carried out.
5. Performed duty with TSG technical audit team visited the yard equipment.
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Trimming of grassy plot in front of division office and control house building
Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 25 to 37 and 48 to 56 was carried out Total towers cleaned =22
Total cleaned disc insulators =1008*
7+22+2
378+168
1008
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Trimming of grassy plot in front of division office and control house building
1. Annual Testing of 220/132KV 160MVA Auto T/F T-1 with cont CB D5Q1 & E9Q1
Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 01 to 02 was carried out Total towers cleaned =02 Total cleaned disc
insulators =168*
Attended shutdown on 220 kV T/L Gatti-Bandala CCT-II Cleaning of disc insulators from tower no.
221/9,221/11 & 237-254 was carried out. Total towers cleaned =21Total cleaned disc insulators =966
1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Trimming of grassy plot in front of division office and control house building
1. Annual Testing of 220/132KV 160MVA Auto T/F T-1 with cont CB D5Q1 & E9Q1
Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 03 to 08 and 10 was carried out Total towers cleaned =07 Total cleaned disc
insulators =378*
4. Cleaning of old colony roads and main gate from out side
Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaninig of disc insulators and retightening
of hardware from tower no. 103 to 124 was carried out Total towers cleaned =22 Total cleaned disc
insulators =1050*
Attended shutdown on 220KV T/L Gatti-Y/Wala CCT-II, PTW no.670, Cleaned/washed disc insulators at
loc no. 103-116 & 118.
1. General cleaning of 110V DC batteries of Volta set No. I & II was carried out and applied Vaseline on
terminal panels
2. Removed the kite and thread from 220KV yard area
3. Setted right 2 No mercury light of 220KV yard lights & replaced the defective bulb & chocks
4. Replaced the 2 No. cell for low performance of 110 V DC battery set no. 1 serial No. 28 & 42.
4. Cleaning of old colony roads and main gate from out side
ttended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023595, Cleaned/washed disc
insulators at loc no.296-289 & tightened dead end tower's jumper pads at loc no.287 & 288.