*220kV G/S J/Wala road Fsd*

*Work activities on 14-01-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out,


2. General Cleaning of all porcelain parts, T/F Bushing body and allied equipment was carried out.
3. Cleaned the leakage spot from T/F body with Soda hot water. Cleaned the 11KV Bus Bar and 11KV
panels from front and near side. Cleaned all the 11KV I/Coming & outgoing VCBS,
3. Tightened the nut/bolts of all the clamps and 11KV Bus bar and mechanism of VCBs isolators. Tightened
the mechanism of VCB isolators.
4. Tightened the nut/bolts of cable glands. Repaired the hydraulic unit of 132KV CB E5Q1 from local
market and refitted it.
5. Lubricated the moving parts of mechanism of isolator VCBs and level of T/F.

*By P&I S/D*

1 attended the shutdown on 132/11 KV 20/26 MVA T/F T-5

*DM 220kV J/wala road Fsd*

*220kV G/S J/Wala road Fsd*

*Work activities on 24-12-2019*


*By Maintenance S/D*

1. General Maintenance of cleaning of T/F Bays and transformer T-5 was carried out.
2. Checked the cooling fans, and oil leakages cleaned the cubical boxes of CBs, & isolators.
3. Remove the kite & threads from 132KV yard site
4. General Maintenance & cleaning of 220KV yard bus bar isolators was carried out .

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of main gate outside green belt along with boundary wall

3. Trimming and watering of front grassy plot control room building

*By P&I S/D*

1 visual inspection and general cleaning of Relay Panels

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023602, Cleaned/washed disc
insulators at loc no.207-209,211-217,219-224 & tightened dead end tower's jumper pads at loc no.210
& 218.

*DM 220kV J/wala road Fsd*

*220kV G/S J/Wala road Fsd*

*Work activities on 19-12-2019*


*By Maintenance S/D*

1. Annu.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chocks

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of main gate outside green belt along with boundary wall

3. Trimming and watering of front grassy plot control room building

*By P&I S/D*

1 Visual inspection of transformer temperature gauges

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023602, Cleaned/washed disc
insulators at loc no.207-209,211-217,219-224 & tightened dead end tower's jumper pads at loc no.210
& 218.

*DM 220kV J/wala road Fsd*


*220kV G/S J/Wala road Fsd*

*Work activities on 16-10-2019*

*By Maintenance S/D*

1. Annu.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chockes

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of main gate outside green belt alongwith boundary wall

3. Trimming and watering of front grassy plot control room building

*By P&I S/D*

1 Visual inspection of transformer temperature gauges


2. Visual inspection and general cleaning of relay pane

*By Gatti-Y/wala S/D*

Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Bandala-KSK CCT-1, PTW no.113993, Cleaned/washed disc insulators
at loc no. 148-135.

*DM 220kV J/wala road Fsd*

*220kV G/S J/Wala road Fsd*

*Work activities on 17-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & Testing was carried out.


2. Tightened the Nut/Bolts of clamps & replaced the defective Nut/Bolts & Cleats.
3. Cleaned the cubical boxes and tightened the terminal connection.
4. Vermin proofing was carried out.
5. Checked the wear & tear of finger contacts and cleaned the finger contacts and all porcline parts of
isolators CBs & CTs.
6. Cleaned the oil gauge of CTs. Cleaned & Tightened the earth clamps.
7. Lubricated the moving parts of mechanism. Checked the hydraulic oil pressure, Leakage and SF6 gas
pressure and maintained them.
8. Painted the equipment heads for R-Y-B phase marking.
9. During shutdown for FESC T/L staff attended the hot spot of line isolator No. 114 Yellow phase towards
line. Also Tightened the Nut/Bolts of all other clamps of all phases General Cleaning was carried out.
Lubricated the moving parts of mechanism.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of Division office front grassy plot.
3. Cleaning of old Colony grassy plot along with roads
4. Washing/cleaning of AC Panels out door Unit

*By P&I S/D*

1 attended the shut down on 132 KV CB E4Q1

*By Gatti-Y/wala S/D*


Attended shutdown on 220 kV T/L BANDALA-KSK CCT-1 Cleaning of disc insulators from tower no. 149 to
172 was carried out. Total towers cleaned =24
Total cleaned disc insulators =1152

*By Gatti-KSK S/D*


Attended shutdown on 220KV T/L Bandala-KSK CCT-1, PTW no.113996, and Cleaned/washed disc
insulators at loc no. 149- 162.

*DM 220kV J/wala road Fsd*

*220kV G/S J/Wala road Fsd*

*Work activities on 18-10-2019*

*By Maintenance S/D*

1. Attended the fault of 11KV O/G VCB Trolley of Khizra feeder. Racked out the trapped trolley from panel
which was trapped during issuing the PTW to LS FESCO sub Divison due to dead fault. Racked out trolley
and setted right its interlocking Rod & shutter.
2. General cleaning of 110V DC Battery set No. I was carried out. Checked the specific gravity, voltage &
electrolyte level per cell.
3. Thermovision of 220/132KV, 160MVA auto T/F Bushing & bays clamps was carried out.
4. Painted the structure of 132KV Bus bar isolatorE5Q11 & E5Q12 in 132KV yard
5. setted right 2 No. search lights of 220KV yard lights & replaced the defective search Rods and ignators.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.
2. Cleaning of Division office front grassy plot.
3. Cleaning of battery Bank Room

*By P&I S/D*

1. visual inspection of transformer temperature gauges

*By Gatti-Y/wala S/D*


Attended shutdown on 220 kV T/L BANDALA-KSK CCT-1 Cleaning of disc insulators from tower no. 173 to
184 was carried out. Nuts/Bolts of tower no. 219/1 and 219/11 retighten and also 04 no. Replaced
Total towers cleaned =12 Total cleaned disc insulators =504*

*By Gatti-KSK S/D*


Attended shutdown on 220KV T/L Bandala-KSK CCT-1, PTW no.113997, and Cleaned/washed disc
insulators at loc no. 173- 184.

*DM 220kV J/wala road Fsd*

*220kV G/S J/Wala road Fsd*

*Work activities on 16-10-2019*

*By Maintenance S/D*

1. Testing of earth mesh of 132KV yard equipment and control room panels.
2. Removed the kite and threads from 132KV yard near T-5 & T-6 bays.
3. Painted the structure of 132KV Bus bar Isolator E4Q11 & E4Q12 in 132KV yard
4. Removed the sulphation /corrosion & applied white Vaseline
5. setted right 2 No. mercury lights of 132KV yard lights and replaced the defective bulb & chockes

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3. Cleaning of sewerage gutter of old colony

*By P&I S/D*

1 Visual inspection of transformer temperature gauges


2. Visual inspection and general cleaning of temperature gauges and MK Box of T-4

*By Gatti-KSK S/D*

Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008

*DM 220kV J/wala road Fsd*

*Work activities on 22-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & Testing was carried out.


2. Tightened the Nut/Bolts of clamps & replaced the defective Nut/Bolts & Cleats.
3.Attended the 3 No. Hot Spot of thermovision survey and repaired the arm contact of line isolator No.
107 red phase from local market and refitted it.
4. Also repaired 2 No. PG Clamps and polished from bazar of 1321KV CB to CT Red phase & yellow phase
and refitted them.
5. Checked the sf6 Gas pressure and hydraulic oil pressure found the hydraulic unit leakage , which was
repaired the hydraulic unit from local market and refitted it of 132kV CB E7Q1
6. Cleaned the finger contacts & porlciline parts of isolators CB & CTs.
7. Cleaned the oil gauge of glasses of CTs tightened the terminal connection of cubical boxes and vermin
proofing was carried out.
7. Lubricated the moving parts of mechanism. Checked the hydraulic oil pressure, Leakage and SF6 gas
pressure and maintained them.
8. Painted the equipment heads for R-Y-B phase marking.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3. Washing/cleaning of AC Panels out door Unit

4. Cleaning of sewerage gutter of old colony

5. Cleaning/washing of washroom of control house building.

6. Cleaning of Control panel of Control room.

*By P&I S/D*

1. Attended shut down on 132 KV CB E7Q1

*By Gatti-KSK S/D*

Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008

*DM 220kV J/wala road Fsd*

*Work activities on 22-10-2019*

*By Maintenance S/D*

1. DES Test of T/Oil of 220/132KV 160mVA Auto T/F T_1,T-2, T-3,T-4 and 132/11KV Power T/F T-5 & T-6
was carried out.
2. Removed the kite thread from 220kV Yard Area
3.Painted the structure of 132KV Bus bar isolator E4Q11 & E4Q12 in 132KV Yard
4. General Cleaning of 110V DC Batteries set NO. I & II was carried out Removed the sulphation /corrosion
and corrosion and applied white Vaseline.
5. Setted right 2 No. Tube lights of 220V DC Battery Room.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3. Washing/cleaning of AC Panels out door Unit

4. Cleaning of sewerage gutter of old colony

5. Cleaning/washing of washroom of control house building.

6. Cleaning of Control panel of Control room.

*By P&I S/D*

1. Visual inspection and general cleaning of MK and PT boxes of 132 KV.


2. Visual inspection of transformer temperature gauges

*By Gatti-KSK S/D*

Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008

*DM 220kV J/wala road Fsd*

*Work activities on 24-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Tightened the Nut/Bolts of clamps & Replaced the defective Nut/Bolts & Cleats.
3. Cleaned the cubical boxes and tightened the terminal connection and vermin proofing was carried out.
4.Checked the finger contacts and cleaned the finger contacts and porciline parts of isolators, CB & Cts.
5. Cleaned oil gauge glasses of CTs.
6. Cleaned & Tightened the earth clamps, lubricated the moving parts of mechanism of CB & isolators.
7. Checked the Dash pot oil level of CB mechanism. Checked the SF6 gas pressure.
8. Repaired the Arm contacts of line isolators No. 113 yellow phase. And refitted it.
9. Painted the equipment heads for R-Y-B phase marking.
10.After completion of testing refilled /Maintained the SF6 gas pressure up to required level.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3 Maintenance of CCTV Cameras .

*By P&I S/D*

1. Visual inspection and general cleaning of MK and PT boxes of 132 KV.


2. Visual inspection of transformer temperature gauges

*By Gatti-KSK S/D*

Attended shutdown on 220 kV T/L Gatti-BANDALA CCT-1 Cleaning of disc insulators from tower no.
221/5,221/4,224,239-244 & 246-258 was carried out. Total towers cleaned =23
Total cleaned disc insulators =1008

*DM 220kV J/wala road Fsd*

*Work activities on 28-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Tightened the Nut/Bolts of clamps & Replaced the defective Nut/Bolts & Cleats.
3. Cleaned the cubical boxes and tightened the terminal connection and vermin proofing was carried out.
4.Checked the finger contacts and cleaned the finger contacts and porciline parts of isolators, CB & Cts.
5. Cleaned oil gauge glasses of CTs.
6. Cleaned & Tightened the earth clamps, lubricated the moving parts of mechanism of CB & isolators.
7. Painted the equipment heads for R-Y-B phase marking.
8.After completion of testing refilled /Maintained the SF6 gas pressure up to required level.
9. Painted the structure of 132KV yard bus bar isolator E1Q11 & E1Q12 in 132KV yard

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3 Trimming of Tree front of Division office and cleaning of Front grassy plot.

4. Cleaning of relay room panels of control room

*By P&I S/D*

1. Attended the approved shutdown vide PTW # 2623 dated 28-10-19 on 220 KV Gatti line-I D3Q1.
During shutdown replaced the electromechanical distance relay LZ31-24 with new digital/numerical
distance relay 7SA87 siemens make.

*DM 220kV J/wala road Fsd*

*Work activities on 29-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Opened the clamps of Line isolators D3Q10 from both side.
3. Cleaned the clamps & Conductors, Also cleaned the finger contacts of post insulators studs and washed
with the petrol.
4. Tightened the spring of finger contacts of rolling studs.
5. Refitted its caps and replaced the defective Nut/Bolts and cleats. Then refitted it.
6. Replaced the defective Clamps of blue of line isolator D3Q10 towards line.
7. Tightened all the nut/bolts of all other clamps and replaced the defective nut/bolts & Cleats
8. Lubricated the moving parts of mechanism.
9. Painted the structure of 132KV yard bus bar isolator E2Q11 & E2Q12 in 132KV yard

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning/Washing the battery bank room

3 Trimming of Tree front of store and cleaning of Front grassy plot of control room.

*By P&I S/D*

1. Attended the shutdown on 220 KV Gatti line-I D3Q1. During shutdown tested the new installed
numerical relay 7SA87 also tested the electromechanical relay LZ31-24. Checked the tripping and closing
of breaker through relay.

*By Gatti-Y/Wala S/D*

Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-1 Cleaning of disc insulators and
retightening of hardware from tower no. 01 to 29 was carried out Total towers cleaned =29 Total
cleaned disc insulators =1638*

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Gatti-JWR CCT-1, PTW no.629, Cleaned/washed disc insulators at loc
no. 3-11,12,14, 23,24,25

*DM 220kV J/wala road Fsd*

*Work activities on 30-10-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Tightened the Nut/Bolts of clamps & Replaced the defective Nut/Bolts & Cleats
3. Attended the 3 No. hot spot of thermovision survey opened these clamps & cleaned the clamps &
conductor
3. Cleaned the poriciline parts of CB , CTs & isolator Lubricated the moving parts of CB, CTs & isolators.
4. Lubricated the moving parts of mechanism.
5. Repaired the hydraulic jack pot of 220KV CB D2Q1 of yellow phase from local market
5. 1 No. arm contact of blue phase of line isolator D2Q10 from local market and refitted it.
6. Cleaned & Tightened the earth clamps, lubricated the moving parts of mechanism of CB & isolators.
7. After completion of testing refilled /maintained the SF6 gas pressure up to required level.
8. Setted right 2 No. search lights of 220KV Yard & replaced their search rods & clock sets

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of grassy plot along with old colony roads

3. Cleaning/Washing the battery bank room.

*By P&I S/D*

1. Attended the shutdown on 220 KV Gatti line-II D2Q1. During shutdown replaced the
electromechanical distance relay LZ31-24 with new Numerical distance relay 7SA87 siemens make. also
Tested the secondary distance relay.

*By Gatti-Y/Wala S/D*

Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 02 to 10 and 13,16 to 22,23, 25 was carried outTotal towers
cleaned =19 Total cleaned disc insulators =966

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.632, Cleaned/washed disc insulators at loc
no. 2-10 & 25.

*DM 220kV J/wala road Fsd*

*Work activities on 31-10-2019*

*By Maintenance S/D*

1. Opened the all clamps of line isolator D2Q10, Cts and CB D2Q1, cleaned the conductor & clamps.
Replaced the defective Nut/Bolts & Cleats.
2. Applied inhibitor compound and refilled them.
3. Cleaned the earth clamps & tightened also replaced the defective Nut/Bolts
4. Checked the hydraulic oil level and its pressure found OK.
5. Cleaned the cubical boxes tightened the terminal connection and vermin proofing was carried out.
6. Opened the finger contacts of isolator cleaned the finger contacts and their studies.
7. Lubrication was carried act and then refilled it.
8. Painted the equipment heads for R-Y-B phase marking.
9. Lubricated the moving parts of mechanism
10. Painted the structure of 132KV Yard Bus bar isolators of PTs-3 & PTs-4 in 32KV Yard.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of grassy plot along with old colony roads

3. Cleaning of old colony road and grassy plots

*By P&I S/D*

1. Attended the annual shutdown for annual protection testing. During shutdown checked/ tested the
distance relay primary protection 7SA87 Siemens make with XS92A universal test set and tested the
breaker failure relay with secondary injection test set. Test results found satisfactory. Tightened the all
connections in control panel and relay panel. Tightened the CT and PT terminal and also carried out the
general Cleaning. Checked/confirmed the tripping of CB through distance relays found OK. Verified the
annunciation circuit of CB, found healthy..

*By Gatti-Y/Wala S/D*

Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 01,11,12,14,15,24,26 to 29 was carried outTotal towers
cleaned =10 Total cleaned disc insulators =588*

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.635, Cleaned/washed disc insulators at loc
no. 1,11,12,14, 15,24 & 26.

*DM 220kV J/wala road Fsd*

*Work activities on 31-10-2019*

*By Maintenance S/D*

1. General cleaning of 220V DC Battery Set No. I was carried out. Checked the specific gravity voltage and
electrolyte level per cell
2. thermovision of clamps/jumpers of 132KV Yard equipement
3. Setted right 2 No. Search lights of 132KV yard lights replaced the defective bul/search rods & Cables.
4. Cleaned the cubical boxes of 160MVA auto T/F T-1, T-2, T-3 & T-4 and vermin proofing was carried out.
*By Operation S/D*
1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of grassy plot along with old colony roads

3. Cleaning of old colony road and grassy plots

*By P&I S/D*

1. Attended the annual shutdown for annual protection testing. During shutdown checked/ tested the
distance relay primary protection 7SA87 Siemens make with XS92A universal test set and tested the
breaker failure relay with secondary injection test set. Test results found satisfactory. Tightened the all
connections in control panel and relay panel. Tightened the CT and PT terminal and also carried out the
general Cleaning. Checked/confirmed the tripping of CB through distance relays found OK. Verified the
annunciation circuit of CB, found healthy..

*By Gatti-Y/Wala S/D*

Attended shutdown on 220 kV T/L Gatti-jaranwala road CCT-2 Cleaninig of disc insulators and
retightening of hardware from tower no. 01,11,12,14,15,24,26 to 29 was carried outTotal towers
cleaned =10 Total cleaned disc insulators =588*

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Gatti-JWR CCT-II, PTW no.635, Cleaned/washed disc insulators at loc
no. 1,11,12,14, 15,24 & 26.

*DM 220kV J/wala road Fsd*

*Work activities on 01-11-2019*

*By Maintenance S/D*

1. General cleaning of 220V DC Battery Set No. I was carried out. Checked the specific gravity voltage and
electrolyte level per cell
2. Thermovision of clamps/jumpers of 132KV Yard equipment
3. Setted right 2 No. Search lights of 132KV yard lights replaced the defective bulB/search rods & Cables.
4. Cleaned the cubical boxes of 160MVA auto T/F T-1, T-2, T-3 & T-4 and vermin proofing was carried out.

*By Operation S/D*


1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Trimming of grassy plot in front of division office and control house building

3. Cleaning of battery banks room

3. Cleaning of old colony road and grassy plots

*By P&I S/D*

1. Visual inspection of transformer temperature gauges


2. Visual inspection and general cleaning of relay paneL

*DM 220kV J/wala road Fsd*

*Work activities on 05-11-2019*

*By Maintenance S/D*

1. General Maintenance & cleanng of cubicalboxs of their CBs and isolators was carried out. Checked the
H/oil level and leakage.
2. removed the kite & threads from 220KV Yard Area
3. Setted right 3 No. search lights of 220KV and replaced the defective search rods & chocke sets.
4. LCM of lightening arrestor of both side of all the T/F T-1 , T-2,T-3, T-4,T-5 & T-6 was carried out.
5. Performed duty with TSG technical audit team visited the yard equipment.

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Trimming of grassy plot in front of division office and control house building

3. Cleaning of battery banks room

3. Cleaning of old colony road and grassy plots

*By P&I S/D*

1. Visual inspection of transformer temperature gauges


2. Visual inspection and general cleaning of relay panel

*By Gatti-Y/wala S/D*

Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 25 to 37 and 48 to 56 was carried out Total towers cleaned =22
Total cleaned disc insulators =1008*

*DM 220kV J/wala road Fsd*

7+22+2

378+168

1008

*Work activities on 06-11-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Tightened the Nut/Bolts of clamps & replaced the defective Nut/Bolts & Cleats.
3. cleaned the cubical boxes and tightened the terminal connection and vermin proofing was carried out.
4. Checked the finger contacts and cleaned the finger contacts and porciline parts of isolators, CB & Cts.
5. Cleaned oil gauge glasses of CTs.
6. Cleaned & Tightened the earth clamps, lubricated the moving parts of mechanism of CB & isolators.
7. Attended the 1 No. hot spot of thermovision survey of 132KV Bus bar isolator E9Q11 towards E9Q12
clamps.
7. Opened the clamp, cleaned the clamp & conductor & applied inhibitor compound and refitted it.
8. After completion of testing refilled /maintained the SF6 gas pressure up to required level.
9. Performed duty with TSG Technical Audit team visited the yard equipments

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Trimming of grassy plot in front of division office and control house building

3. Cleaning of battery banks room

4. Cleaning of control room panels

*By P&I S/D*

1. Annual Testing of 220/132KV 160MVA Auto T/F T-1 with cont CB D5Q1 & E9Q1

*By Gatti-Y/wala S/D*

Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 01 to 02 was carried out Total towers cleaned =02 Total cleaned disc
insulators =168*

*By Gatti-KSK S/D*

Attended shutdown on 220 kV T/L Gatti-Bandala CCT-II Cleaning of disc insulators from tower no.
221/9,221/11 & 237-254 was carried out. Total towers cleaned =21Total cleaned disc insulators =966

*DM 220kV J/wala road Fsd*

*Work activities on 08-11-2019*

*By Maintenance S/D*


1. General Cleaning of 220V DC Battery set No. II was carried out.
2. Checked the specific gravity voltage and electrolyte level per cell.
3. Thermovision of clamps/jumpers of 220KV Yard equipment was carried out.
4. Setted right the 2 No. Mercury lights of 132KV lights and replaced the defective bulb & Choke sets.
5. Removed the kite & Threads from 220KV yard area

*By Operation S/D*

1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Trimming of grassy plot in front of division office and control house building

3. Cleaning/washing of Divison office Store /record room

4. Cleaning of control room panels

*By P&I S/D*

1. Annual Testing of 220/132KV 160MVA Auto T/F T-1 with cont CB D5Q1 & E9Q1

*By Gatti-Y/wala S/D*

Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaning of disc insulators and retightening
of hardware from tower no. 03 to 08 and 10 was carried out Total towers cleaned =07 Total cleaned disc
insulators =378*

*DM 220kV J/wala road Fsd*

*Work activities on 14-11-2019*

*By Maintenance S/D*

1. Annual Maintenance & testing was carried out.


2. Tightened the nut/bolts of clamps & replaced the defective Nut/Bolts & cleats.
3. Opened the all clamps and cleaned the clamps and conductor. Applied inhibitor compound and refitted
them.
4. Checked the wear & tear of finger contacts and cleaned the finger contacts and all the porciline parts
of CB , Cts & isolator part of CB side only
5. Cleaned the oil gauges of CTS cleaned & tightened the earth clamps. Cleaned the cubical boxes and
tightened the terminal connection and vermin proofing was carried out.
6. Lubricated the moving parts of mechanism.
7. Checked the hydraulic oil pressure & SF6 gas pressure.
8. After completion of testing refilled/maintained the SF6 gas pressure up to required level.
9. Painted the equipment heads for R.Y.B phase marking.

*By Operation S/D*


1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of battery banks room

3. Cleaning of sewerage gutter of old colony

4. Cleaning of old colony roads and main gate from out side

*By P&I S/D*

1. Attended the annual protection testing on 132kv bus coupler E11Q1

*By Gatti-Y/wala S/D*

Attended shutdown on 220 kV T/L Gatti-Yousafwala CCT-2 Cleaninig of disc insulators and retightening
of hardware from tower no. 103 to 124 was carried out Total towers cleaned =22 Total cleaned disc
insulators =1050*

*By Gatti-KSK S/D*

Attended shutdown on 220KV T/L Gatti-Y/Wala CCT-II, PTW no.670, Cleaned/washed disc insulators at
loc no. 103-116 & 118.

*DM 220kV J/wala road Fsd*

*Work activities on 17-12-2019*

*By Maintenance S/D*

1. General cleaning of 110V DC batteries of Volta set No. I & II was carried out and applied Vaseline on
terminal panels
2. Removed the kite and thread from 220KV yard area
3. Setted right 2 No mercury light of 220KV yard lights & replaced the defective bulb & chocks
4. Replaced the 2 No. cell for low performance of 110 V DC battery set no. 1 serial No. 28 & 42.

*By Operation S/D*


1. General Cleaning of Control House Building, Old colony roads and main gate.

2. Cleaning of battery banks room

3. Cleaning of sewerage gutter of old colony

4. Cleaning of old colony roads and main gate from out side

*By P&I S/D*

1. Visual inspection of transformer temperature gauges

*By Gatti-KSK S/D*

ttended shutdown on 220KV T/L Chashma-Ludewala CCT-II, PTW no.023595, Cleaned/washed disc
insulators at loc no.296-289 & tightened dead end tower's jumper pads at loc no.287 & 288.

*DM 220kV J/wala road Fsd*