90-Day Look-Ahead for High Risk Activities Date of Assessment :

Contract Number: 560-C37 January 2020

The construction management team and Foremen must


Select most relevant Life evaluate the activity and list any requirements prior to Duration
Foreman Name (if multiple Planned Start Date
# Activity Description Hazards Mitigation Physical Mitigation Documentation Critical Requirement (drop commencing works e.g. revise Method Statement, (no.
list all) (dd/mm/yy)
down list) resource requirement, specific training for work crew days)
etc.
100% tie off while scaffold erection and a.Training for new workers -working adjacent
Code-1 approved Method Of Statement.
Fanateer Marina - Repair of complete scaffold for Civil works.Counter Fall Protection and to water - ESH Standard 230
1 Working above water Reaction Calculation Mohammed Salama Ongoing 120
Seawall cappoing beam weights with Structural load balance Prevention b.Emergency Drill for every 6 months
Encroachment Permit
calculations. Life Guard and Stand by boat c.High Tide/Low tide Forecast
a.Water sample test to be done from
Environmental Services for discharge to
Access / Egress opening for Tank Shell ,
Code-1 approved Method Of Nayeem another manhole
Confined Space, Heavy Third party Certified Lifting jacks
Statement.Lift calcualtion for tank shell Foreman/Mohammed b.Procure sump pump for Coastal Road 02
2 Tank E4 Lift,Hot Works,Incoming ,Addtiional raker support for the shell , Lifting Operations 15 December 2019 45
uplifting.Competent welders. Elmannan (Welding c.Underground utility scanning by third party -
irrigation line support by beams to the shell from the
Encroachment Permit Foreman) Purchase order under process
central shalft,LOTO
d.NDT Risk assessment to be done.

Working on Live Roads a.Water sample test to be done from


Culvert Replacements 15 December 2019 30
Traffic Deviations Dewatering pump, Traffic barriers Code-1 Approved MoS , Environmental Services for discharge to
1. C2-Cosatal Road 2 01 January 2020 45
Excavations installation , Timber shoring,Pedestrian Entry ApprovApproved TMP,As Built another manhole
2. C5-T162 Salah Foreman /naresh
3 Confined Space and Segregation, Security Fencing and Drawings , Utility mapping , Access Excavation & Trenching b.Procure sump pump for Coastal Road 02
3. LULU Dist Culvert Foreman 15 February 2020 60
Ground water / Sea water Multilingual signages alerting public,Security permits from landscaping. c.Underground utility scanning by third party -
4. SEC Culvert T 275/130 25 November 2019 50
seepage guard for night hours Encroachment Permit Purchase order under process
5.C12 T218 25 March 2019 150
Heavy Equipment
Code-1 Approved , Structural Design for a.Weekly Inspection by Competent person
Live Pipelines, Abrasive Scaffolding approved from RC Structural b.harness and Lanyard inspection every month
Steel Structure Coating - Structural Scaffold erected by certified Fareed Foreman / Leo
4 blasting ,Scaffold Erection , . Scaffolding c.Work at height and Emergency Evacuation Ongoing 200
Pipeline Corridor Erectors, Ecofirendly Grit , Nelson
Work at height Encroachment Permit. training
RC PLC Permit
1. Pipeline Corridor- Repair Live Pipelines, Chipping Fire Blanket while chipping , Gas Monitoring Code 1- Approved for MoS, Structural No Life Critical a.Permit renewal every 2 weeks 120
5 Billy , Mostafa Golam, Ongoing
of Pipe Sleepers_port Activity below pipeline, using Multigas Detector,Temporary support Support and Temporary Support, permit Requirements b.Gate pass renewal every 45 days 180
a.Caliberation of Gas monitor at a frequency of
Inadequate lighting , Dust Code 1-Approved , Hard barriers
Tower lights installed , Local Ventillations, 6 months
Pipeline Corridor - Shotcrete accumulation , Exposed installation by competent workers during Barricades (Hard and
6 hard barriers for conveyors, Fire Blankets Shalan , Edgardo b.Emergency response plan refresher training Ongoing 90
culverts conveyor belt ,Live conveyor shut down period, Soft)
while working adjacent toio pipelines c.Waste removal on regular frequency
pipelines Pipeline Work Permit

a.Daily gas Monitoring inside confined space


Confined Space , Lifting
b.Confined Space Refresher Training for Entry
Storm Drainage - Arch Pipe Operation , Inadequate Code -1 Approved MoS and Pipe Rolling
Exhaust ventillation , Gas monitoring , Foreman attendant
7 Installation - SDS 26,29 & Lighting , temporary structure. Confined Space Entry Ongoing 150
Timber shoring for insert point Naresn,Foreman Salah c.Third aprty renewal of Confined space
10 Excavation,Heavy Encroachment Permit
supervisor
Equipment Operation

Live Pipelines, Chipping


Piers and Structures a.Gate pass to be done for subcontractors
Activity below pipeline, Gas monitoring . Permit to work from Fire and Safety Fall Protection and
8 trasversing SWCC- Inside Yet to be assigned b Subcontractor to attend Induction training 30 November 2019 150
Excavation Working in 300m range Department (RC). Prevention
PLC from Pipeline Fire and Safety
Work at height
Code 1- Approved MoS.Scaffold a.Permit from Marafiq SWCC for Piers
Canal water discharge ,
Piers and Structures Dewatering Pump installation , Structural erection by certified Erector,Design b.Works inside canal -Canal wall repair after
Work at height , Lifting
9 trasversing SWCC-Insied Scaffold for access / egress to canal , Utility approval from RC for access / egress to Scaffolding Foerman Suresh , Jithin schedule confirmation from MaSa ongoing 210
Operations , manual
Marafiq scanner , Shoring by timber canal, c.Marafiq Orientation for new employees
handling ,Excavation
Work Permit from Marafiq
COde-1 Approval ,
Street Lighting Pole Traffic Barriers installation in work area in a.LOTO applicable for Lighting panel
10 Working on Live Roads, Encorachment Permit , Uncontrolled 10 January 2020 60
Installation 10.7 m coordination with Roads Department .100% disconnection
MEWP Operation ,Lifting Road Permit , Vehicle/Pedestrian Foreman Shaji joseph
Decorative Lighting Pole Tie off while working at MEWP,Outrigger b.To fabricate support structure for Lighting
11 Operation Access permit , Interface 01 March 2020 150
Installation extended hard ground pole placement in Boom truck
Over size permit
c.Energization
a.All workers to/ De-energeization permitEntry
attend Confined Space
Confined Space , Exhasut fan installed for continous s air Code -1 approved . Confined Space refresher
Teleom Chamber Repair
12 Inadequate lighting , Dust circulation, Intrinsic led lights,Continous Gas permit Confined Space Entry Foreman Randy b.Gas monitor caliberation Ongoing 210
Works
accumulation monitoring and tripod installed Encroachment Permit c.Emergency drill every 6 months
90-Day Look-Ahead for High Risk Activities Date of Assessment :
Contract Number: 560-C37 January 2020

The construction management team and Foremen must


Select most relevant Life evaluate the activity and list any requirements prior to Duration
Foreman Name (if multiple Planned Start Date
# Activity Description Hazards Mitigation Physical Mitigation Documentation Critical Requirement (drop commencing works e.g. revise Method Statement, (no.
list all) (dd/mm/yy)
down list) resource requirement, specific training for work crew days)
etc.
a.base coarse to be stock pile for back filling
Excavation, Demolition Cordonned of area to prevent unauthorized
Code 1- approved Letter from Royal b.Utility marked areas to have flagged off
activity , Emissions from entry, Multilingual siganges placed, Scaffold
13 Mutrafiah Housing Commission IOM and Encroachment Excavation & Trenching Foreman Nayeem c.upport shall be removed only after curing Ongoing 15
stationary sources in structure and temporary structure erected to
Pemrits period
Residential area prevent any collapse of wall

Code-1 approved Certified operator and a.Controlled access / egress


Work at height , Excavation Codronned off operational area and motion Equipment , Utility mapping and marked b.Additional supports for Masjid side
14 O&M Building Elevated Work Platforms Subul Foreman Ogoing 60
, Asphalt cutting alarm isntalled in equipement off at siite. c.Training for Working at height from MEWP
Encroachment Permit

Deep Excavation
Area shall be cordonned off by hard physical
Ground water / Sea water a.New MS to be submitted
barricades.
seepage b.Risk Assessment to consider dewatering
Fanateer shoreline Cathodic Underground utlity scan shall be done and Dewatering approval gavino (Subcontractor).
15 Contact with Underground Excavation & Trenching method and discharge location 01 January 2020 45
Protection Works utility shall be marked off Encroachment Permit Shyju
utlities c.Equipments to eliminate manual handling
Working in Public area

AirField traffic
Medium Voltage cable
a.submission of method statement
exposing and other Permit shall be attianed from ATC ( Airport
Naval Airport - Air Field b.coordination with Aiport O&M
16 underground utilities . Tower Center) Breakers shall be physically Permit from the Navsl Aiport Authority LOTO (Lockout/Tagout) Raees Supervisor Ongoing 30
Lighting Works c.gate pass renewal every 10 days
Excavation. turned off and LOTO shall be applied
Electrucal Tie in
connections

Interfeeence with moving


Escort vehicle shall assist the operation as
vehicles while the natation
per Methodology made for Traffic Barrier Encroachment Permit. Traffic a.TMP model mock up
of traffic
TS1 Expansion Joint installationFlashing hae one shall be Management Plan approved from Roads b. Complete procurement and inspection of
equipment’s.Traffic barriers Aymen Foreman and
replacement work with road provided to alert other vehicles. Activity Department .Approved Method Barricades (Hard and TMP signages
17 replacement or maintenance Asphalt Supervisor 15 January 2020 60
closure and traffic shall be carried out during early hours on Statement for Installation and Soft) c.Assignning competent person for TMP
of lights.Crossing Wilson
management holidays. Coordination with RC road maintenance sequence of traffic management
roads.Inadequate traffic
department shall be made.Barriers with equipment’s
deviations.Demoizing I’m
lights.
wrong sequence