Activity Normal DuratNormal Cost Crash time Crash Cost Slope

1--2 7 700 4 850 50


1--3 5 500 3 700 100
1--4 8 600 5 1200 200
2--5 9 800 7 1250 225
3--5 5 700 3 1000 150
3--6 6 1100 5 1300 200
4--6 7 1200 5 1450 125
8--7 2 400 1 500 100
6--7 3 500 2 850 350
6500 9100 1500

Activity Crash Limit Cost of Slope


CP= 1-2-3-7 1--2 3 50 Formulae For crash limit
2--5 2 225 Normal Duration - Crash time
5--7 1 100

1-4-6-7 1--4 3 200


4--6 2 125
6--7 1 350

we selected the least cost slope and reduced 1 week in both the activities. And made a new network d

9
2 5
6 2
5
5 6
1 3 6
3
8
4 6
cp= 17 wks Cost
Fixed cost 6500
Indirect cos 3400
9900
175
10075
Activity Normal DuratNormal Cost Crash time Crash Cost Slope
1--2 6 700 4 850 50
1--3 5 500 3 700 100
1--4 8 600 5 1200 200
2--5 9 800 7 1250 225
3--5 5 700 3 1000 150
3--6 6 1100 5 1300 200
4--6 6 1200 5 1450 125
8--7 2 400 1 500 100
6--7 3 500 2 850 350
6500 9100 1500

Activity Crash Limit Cost of Slope


CP= 1-2-3-7 1--2 1 50 Formulae For crash limit
2--5 2 225 Normal Duration - Crash time
5--7 1 100

1-4-6-7 1--4 3 200


4--6 0 125
6--7 1 350

cp= 16

9
2 5
5 2
5
5 6
1 3 6
3
8
4 5
Cost
Fixed cost 6500
9 3600
2 5 10100
7 2
5
5 6
3 6 7
3
8 7
4

rmulae For crash limit 1 2 5 7


rmal Duration - Crash time 1 3 5 7
1 3 6 7
1 4 6 7

ties. And made a new network diagram

1 2 5 7=
1 3 5 7=
1 3 6 7=
1 4 6 7=
Slope never changes. We only calculate it once in beginning
rmulae For crash limit
rmal Duration - Crash time

Cost
last cost = 10075
-25
10050

1 2 5 7=
1 3 5 7=
1 3 6 7=
1 4 6 7=
= 18
= 12
= 14
= 18

17
12
14
17
16
12
14
16