Activity ID Activity Name Start Finish Original9 August 2019 S October 2019 N D January 2020 F March 2020 April 2020 May 2020 June 2020 July 2020 ust 2020
9 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14
Duration
28-Jul-19 31-Mar-20 247 31-Mar-20, SCEEI-45MVA Grid Mobile substations 1 x 132/33kV 45 MVA
SCEEI-45MVA Grid Mobile substations 1 x 132/33kV 45 M
SCEEI-45M
A1000 Contract Sign Date 28-Jul-19 0 Contract Sign Date
A1020 Project complete date 24-Mar-20 0 Project complete date
02-Sep-19 24-Dec-19 114 24-Dec-19, SCEEI-45MVA.1 Engineering
SCEEI-45MVA.1 Engineering
SCEEI-45
SCEEI-45MVA.1.2 Designing
SCEEI-45 02-Sep-19 29-Sep-19 28 29-Sep-19, SCEEI-45MVA.1.2 Designing
A1030 Basic Design 02-Sep-19 22-Sep-19 21 Basic Design
A1040 Basic Design Submission 23-Sep-19 0 Basic Design Submission
A1050 Basic design review by customer 23-Sep-19 29-Sep-19 7 Basic design review by customer
A1060 Design freeze 29-Sep-19 0 Design freeze
Primary Baseline Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation