Professional Documents
Culture Documents
#9#waste Disposal#sewer Appurtenances
#9#waste Disposal#sewer Appurtenances
SEWER APPURTENANCES
SEWER APPURTENANCES-
INTRODUCTION
• In order to make the process of construction easy and to have
efficient working and maintenance.
• Rectangular manholes
▪ 90 × 80 cm are generally constructed within compound for house drainage only and near the
buildings for house drainage.
▪ Manholes 1.2 m × 90 cm are generally constructed for main drainage work for depths less than 1.5
m.
• Arched type Manholes
▪ 1.4 m × 90 cm is of the arched type and is generally constructed for main drainage works where
depth is 1.50 m or more.
▪ The width of manholes shall be increased more than 90 cm on bends or junctions or pipes with
diameter greater than 450 mm and that the benching width on either side of the channel is minimum
20 cm.
• Circular manholes are straight down in lower portion and slanting in top portion so as to narrow
down the top opening equal to dia. of manhole cover.
▪ For depth above 0.90m and up to 1.65m, 900mm diameter.
▪ For depth above 1.65m and up to 2.30m, 1200mm diameter.
▪ For depth above 2.30m and up to 9.0m, 1500mm diameter.
▪ For depth above 9m and up to 14m, 1800mm diameter.
MANHOLES
MANHOLES- CIVIL SPECIFICATIONS
Bed Concrete
• The manhole shall be built on a bed of cement concrete 1:4:8 (1 cement: 4 coarse sand: 8
graded stone aggregate 40 mm nominal size) unless required by local authorities.
• The thickness of the bed concrete shall be 20 cm for manholes up to 4.25 m depth and
30 cm for depths beyond 4.25 m unless otherwise specified.
Brick Work
• The brick work shall be with class 75 bricks in cement mortar 1:4 (1 cement: 4 coarse
sand). The external joints of the brick masonry shall be finished smooth, and the joints
of the pipes with the masonry shall be made perfectly leak proof. For arched type and
circular manholes,
• Brick masonry in arches and arching over the pipes shall be in cement mortar 1.3 (1
cement: 3 fine sand). In the case of manholes of circular type the excess shaft shall be
corbelled inwardly on three sides at the top to reduce its size to the cover frame to be
fitted.
• The walls shall be built of one brick thickness for depths up to 4.25 m. Below a depth of
4.25 m in ordinary subsoil the wall thickness shall be increased to one and half brick and
at 9.75 m below ground two brick thick walls shall be built.
MANHOLES- CIVIL SPECIFICATIONS
Plaster and Pointing
• The walls of the manholes shall be plastered inside with 12 mm thick cement plaster 1:3
(1 cement: 3 coarse sand) finished smooth. In the case of arched type manhole the walls
of the manhole shall be plastered inside all-around only up to the crown level, and flush
pointed for the shaft with cement mortar 1:2 (1 cement: 2 fine sand).
• Where the saturated soil is met with, also the external surface of the walls of the
manhole shall be plastered with 12 mm thick cement plaster 1:3 (1 cement: 3 coarse
sand) finished smooth up to 30 cm above the highest sub-soil water level.
• The plaster shall further be water proofed
Benching
• The channels and benching shall be done in cement concrete 1:2:4 (1 cement: 2 coarse
sand: 4 graded stone aggregate 20 mm nominal size) and rendered smooth with neat
cement.
Foot Rests
• All manholes deeper than 0.8 m shall be provided with M.S. foot rests. These shall be
embedded 20 cm deep in 20 x 20 x 10 cm blocks of cement concrete 1:3:6 (1 cement: 3
coarse sand 6 graded stone aggregate 20 mm nominal size).
LAMPHOLES
• An opening or hole constructed in a sewer
for the purpose of lowering a lamp inside.
Purpose-
• Flushing device.
• Fresh air inlet.
Location-
• In narrow lanes change of gradient and
slight curves where space is insufficient .
• If the construction of manhole is difficult.
• When the sewer length is straight for a
considerable distance beyond the usual
spacing between manholes.
CATCH BASINS
• It is a structure in the form of a chamber which is provided
along the sewer line to admit or allow the clear rain water
free from silt, grit, debris etc. into the combined water.
• Chambers (75 to 90 cm in dia. And 75 to 90 cm in deep).
• The outlet pipe of catch basin is fixed about 60 cm above
the bottom of catch basin.
Purpose-
• To prevent the entry of silt, grit, debris, etc. contained in the
rain water.
• To prevent the sewer gas.
Maintenance –
• It requires a periodical cleaning.
• It also then forms a breeding place for mosquitoes and
causes annoyance to the person passing.
Use –
• The catch basins are adopted for the combined sewerage
system.
DROP MANHOLE
Quality of water-
It is not required treated water. Untreated can be prefered.
OIL AND GREASE TRAP
• The grease and grit trap is placed at the discharge point of the canteen/ kitchen
area itself to arrest solid and fatty matter at source. The wastewater output from
this unit is taken to the RECHARGE WELL/ equalization tank.
• The solids and fats that are separated in this unit are disposed off along with other
biodegradable waste.
OIL AND GREASE TRAP
Design Criteria- Typical design criteria used for the grease trap include:
• Shallow trap (to allow quick rise of oils and fats to the surface)
• The length of trap should be approximately 2 times its depth
• Residence time in the trap is optimally 5-20 minutes at peak flow. (Increasing the time
does not result in appreciable improvement)
• Surface area of the trap in m2 should be approximately 1.5 to 2 times the depth of trap in
metres.
Technical Specifications
• The tank should have waterproof plastering inside and out.
• The end of the incoming pipe is kept below the water level, so that the incoming water
does not disturb (and break up) the upper floating layer of grease.
• The trapped material (both floating film of grease/ fat and the grit settled at bottom)
must be collected frequently; otherwise the trap will fail to serve its fundamental
purpose. Therefore the trap must be engineered to facilitate frequent removal of these
two layers. For example, the covers must be made of lightweight materials for easy
lifting. Large traps may be provided with vent pipes to release gases.
INVERTED SIPHON
• It is a sewer section which is constructed lower than the adjacent sewer sections and
which runs full under gravity with pressure greater than the atmosphere.
• It will be more appropriate to refer it as a depressed sewer or a sag pipe.
Purpose-
• To carry the sewer line below obstructions such as ground depression, streams,
rivers, railway etc.
INVERTED SIPHON
Velocity-
• The self cleaning velocity 1.0 mps for minimum flow to avoid the deposition in the
line.
STREET INLETS -
• Opening through which storm water and
surface wash flowing along the streets are
admitted and conveyed to the storm water
sewer by means of pipe.
Types-
• Vertical inlet or curb inlet.
• Horizontal inlet or gutter inlet.
• Combine inlet.
STORM WATER INLETS
Location-
• The inlets are located or placed by
the sides of roads at a distance of
about 30 to 60 m.
• The inlets are connected to nearby
manholes by pipe line.
• The dia. of connecting pipe to
street to main street sewer should
not be less than 200mm.
Openings-
• least opportunity is given for the
storm water to stop.
• Chances of clogging are brought
down to minimum possible extent.
• The objects that are cause most of
the trouble.
• The cleanliness of footpaths and
streets.
VENTILATORS IN SEWERS
• Various gases are produced in the sewers
due to decomposition of organic materials
of sewage.
• Highly explosive .
• The structures constructed to divert part of sewage in case of combined sewers are
known as the storm water regulators and they come into operation when discharge
exceed certain value.
Object-
• To divert the excess storm water to natural stream or river.
• Decrease in load on the treatment units or pumping stations.
Leaping weir-
Overflow weir-
• Inspection chamber-
• Water seal of about 100mm and it is
provided in the last manhole house drainage
system.