You are on page 1of 9

RAB DRIOREJO

NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH

1 Pekerjaan tanah
a. Galian tanah pondasi m3 5.63 40,000.00 225,000.00

225,000.00
1 Pekerjaan Beton
a. Lantai kerja sloof m3 0.56 400,000.00 225,000.00
b. Beton Sloof m3 1.13 1,500,000.00 1,687,500.00
c. Beton Kolom m3 1.37 1,500,000.00 2,047,500.00
d. Beton Ring m3 1.13 1,500,000.00 1,687,500.00
e. Rabat + Aci Carport m2 16.00 50,000.00 800,000.00

6,447,500.00
2 Pasangan Dan Pelapis Dinding
a. Pas. Bata m2 102.50 80,000.00 8,200,000.00
b. Plester + Aci m2 118.00 40,000.00 4,720,000.00
d. Pas. Keramik KM m2 7.50 105,000.00 787,500.00
e. Pas. Lantai KM m2 2.25 105,000.00 236,250.00
f. Pas . Keramik Lantai Utama m2 27.75 95,000.00 2,636,250.00
g. Pas. Keramik Teras ls 2.00 95,000.00 190,000.00

16,770,000.00
3 Atap Dan Langit2
a. Rangka Atap Baja Ringan m2 36.00 120,000.00 4,320,000.00
b. Plafond m2 36.00 60,000.00 2,160,000.00
c. Genting m2 42.12 90,000.00 3,790,800.00
d. Bubungan m1 6.00 90,000.00 540,000.00
e. Listplank m1 12.00 35,000.00 420,000.00

11,230,800.00
4 Kusen Pintu
a. Kusen m1 39.40 65,000.00 2,561,000.00
b. Pintu Unit 5.00 650,000.00 3,250,000.00
c. Jendela Unit 4.00 350,000.00 1,400,000.00

7,211,000.00
5 Cat
a. Cat Binding m2 118.00 11,000.00 1,298,000.00
b. Cat Plafond m2 36.00 11,000.00 396,000.00
d. Cat Lisplank m2 12.00 10,000.00 120,000.00

1,814,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH
6 Elektrikal
a. Panel MCB m2 1.00 250,000.00 250,000.00
b. Titik Lampu m2 4.00 100,000.00 400,000.00
c. Titik Stop Kontak m2 3.00 120,000.00 360,000.00

1,010,000.00
7 Pipa Dan Sanitair
a. Closet Jongkok m2 1.00 200,000.00 200,000.00
b. Bak Mandi m2 1.00 300,000.00 300,000.00
c. Avor m2 1.00 25,000.00 25,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH
d. Saluran PVC Air Kotor m2 7.00 25,000.00 175,000.00
e. Saluran PVC Kotoran m2 5.00 25,000.00 125,000.00
f. Septictank unit 1.00 250,000.00 250,000.00
g. Resapan unit 1.00 200,000.00 200,000.00

1,275,000.00

45,983,300.00

Surabaya, 1 November 2016


CV. PUNCAK PANORAMA

Mohamat Solikin
Direktur
RAB DRIOREJO

NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH

1 Pekerjaan tanah
a. Galian tanah pondasi m3 5.18 40,000.00 207,000.00

207,000.00
1 Pekerjaan Beton
a. Lantai kerja sloof m3 0.52 400,000.00 207,000.00
b. Beton Sloof m3 1.04 1,500,000.00 1,552,500.00
c. Beton Kolom m3 1.37 1,500,000.00 2,047,500.00
d. Beton Ring m3 1.04 1,500,000.00 1,552,500.00
e. Rabat + Aci Carport m2 13.50 50,000.00 675,000.00

6,034,500.00
2 Pasangan Dan Pelapis Dinding
a. Pas. Bata m2 133.25 80,000.00 10,660,000.00
b. Plester + Aci m2 179.50 40,000.00 7,180,000.00
d. Pas. Keramik KM m2 7.50 105,000.00 787,500.00
e. Pas. Lantai KM m2 2.25 105,000.00 236,250.00
f. Pas . Keramik Lantai Utama m2 28.75 95,000.00 2,731,250.00
g. Pas. Keramik Teras m2 5.00 95,000.00 475,000.00

22,070,000.00
3 Atap Dan Langit2
a. Rangka Atap Baja Ringan m2 43.50 120,000.00 5,220,000.00
b. Plafond m2 43.50 60,000.00 2,610,000.00
c. Genting m2 50.90 90,000.00 4,580,550.00
d. Bubungan m1 6.50 90,000.00 585,000.00
e. Listplank m1 20.50 35,000.00 717,500.00

13,713,050.00
4 Kusen Pintu
a. Kusen Pintu Plong 5.00 350,000.00 1,750,000.00
b. Kusen Jendela Plong 6.00 350,000.00 2,100,000.00
c. Pintu Unit 5.00 600,000.00 3,000,000.00
d. Jendela Unit 4.00 450,000.00 1,800,000.00
e. Kaca m2 0.81 150,000.00 121,500.00

8,771,500.00
5 Cat
a. Cat Dinding m2 179.50 11,000.00 1,974,500.00
b. Cat Plafond m2 43.50 11,000.00 478,500.00
d. Cat Lisplank m1 20.50 10,000.00 205,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH

2,658,000.00
6 Elektrikal
a. Panel MCB m2 1.00 250,000.00 250,000.00
b. Titik Lampu m2 4.00 100,000.00 400,000.00
c. Titik Stop Kontak m2 3.00 120,000.00 360,000.00

1,010,000.00
7 Pipa Dan Sanitair
a. Closet Jongkok m2 1.00 200,000.00 200,000.00
b. Bak Mandi m2 1.00 300,000.00 300,000.00
c. Avor m2 1.00 25,000.00 25,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH
d. Saluran PVC Air Kotor m2 7.00 25,000.00 175,000.00
e. Saluran PVC Kotoran m2 5.00 25,000.00 125,000.00
f. Septictank unit 1.00 250,000.00 250,000.00
g. Resapan unit 1.00 200,000.00 200,000.00

1,275,000.00

55,739,050.00

Surabaya, 1 November 2016


CV. PUNCAK PANORAMA

Mohamat Solikin
Direktur
RAB DRIOREJO

NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH

1 Pekerjaan tanah
a. Galian tanah pondasi m3 4.05 40,000.00 162,000.00

162,000.00
1 Pekerjaan Beton
a. Lantai kerja sloof m3 0.41 400,000.00 162,000.00
b. Beton Sloof m3 0.81 1,500,000.00 1,215,000.00
c. Beton Kolom m3 1.05 1,500,000.00 1,575,000.00
d. Beton Ring m3 0.81 1,500,000.00 1,215,000.00

4,167,000.00
2 Pasangan Dan Pelapis Dinding
a. Pas. Bata m2 84.50 80,000.00 6,760,000.00
b. Plester + Aci m2 90.00 40,000.00 3,600,000.00
d. Pas. Keramik KM m2 7.50 105,000.00 787,500.00
e. Pas. Lantai KM m2 2.25 105,000.00 236,250.00
f. Pas . Keramik Lantai Utama m2 17.75 95,000.00 1,686,250.00
g. Pas. Keramik Teras m2 4.00 95,000.00 380,000.00

13,450,000.00
3 Atap Dan Langit2
a. Rangka Atap Baja Ringan m2 24.00 100,000.00 2,400,000.00
b. Plafond m2 24.00 60,000.00 1,440,000.00
c. Asbes m2 24.00 75,000.00 1,800,000.00
e. Talang m1 4.00 60,000.00 240,000.00

5,880,000.00
4 Pintu
a. Pintu rollingdoor m2 10.00 600,000.00 6,000,000.00

6,000,000.00
5 Cat
a. Cat Dinding m2 90.00 11,000.00 990,000.00
b. Cat Plafond m2 24.00 11,000.00 264,000.00
d. Cat Lisplank m1 4.00 10,000.00 40,000.00

1,294,000.00
6 Elektrikal
a. Panel MCB m2 1.00 250,000.00 250,000.00
b. Titik Lampu m2 3.00 100,000.00 300,000.00
c. Titik Stop Kontak m2 2.00 120,000.00 240,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH

790,000.00
7 Pipa Dan Sanitair
a. Closet Jongkok m2 1.00 200,000.00 200,000.00
NO PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH
b. Bak Mandi m2 1.00 300,000.00 300,000.00
c. Avor m2 1.00 25,000.00 25,000.00
d. Saluran PVC Air Kotor m2 10.00 25,000.00 250,000.00
e. Saluran PVC Kotoran m2 5.00 25,000.00 125,000.00
f. Septictank unit 1.00 250,000.00 250,000.00
g. Resapan unit 1.00 200,000.00 200,000.00

1,350,000.00

33,093,000.00

Surabaya, 1 November 2016


CV. PUNCAK PANORAMA

Mohamat Solikin
Direktur