MS 312 Construction Engineering and Management Fall, 2019
Section B Complex Engineering Problem
A 2-lane undivided collector road of 1 kilometer length is to be constructed in Lahore. The
pavement is of flexible type. The subgrade consists of suitable material and will have a good bearing capacity upon compaction. You are hired as a construction manager by the main contractor. As a construction manager: a) Identify the stakeholders involved in the project (no fictitious stakeholders) (maximum points: 5) b) Keeping the project deliverables in mind, list down all the activities and generate work breakdown structure (WBS); use proper WBS coding (maximum points: 5) c) Estimate activities time duration, cost expenditure, and resource requirement (make appropriate assumptions) (maximum points: 10) d) Establish precedence relationships and draw the project network using suitable techniques (maximum points: 10) e) Determine the minimum time required to complete the project by using an appropriate technique (show complete procedure and calculations) (maximum points: 10)