Amendment to Draft Contract Agreement

S. Ref Existing Description as per DCA Amendment


No. Clause
No.
1 CI.19.2.1 The Authority shall make an interest free advance payment The Authority shall make an interest-bearing advance
(the "Advance Payment"), equal in amount to 10 (ten) payment (the “Advance Payment”) equal in amount to 10
percent of the Contract Price, for mobilisation expenses (ten) percent of the contract price, for mobilisation
and for acquisition of equipment. The Advance Payment expenses and for acquisition of equipment. The Advance
shall be made in two instalments each equal to 5% (five payment shall be made in two instalments each equal to
percent) of the Contract Price. 5% (five percent) of the Contract Price. The advance
payment would be deemed as interest bearing advance at
an interest rate of 10% (ten) per annum, to be compounded
quarterly. The interest would be recovered along with the
recovery of advance payment.
2 CI.19.2.4 At any time, after 60 (sixty) days from the Appointed Date, At any time, after 60 (sixty) days from the Appointed Date,
the Contractor may apply to the Authority for the second the contractor may apply to the Authority for the second
instalment of the Advance Payment along with an instalment of the advance payment along with an
irrevocable and unconditional guarantee from a Bank for an irrevocable and unconditional guarantee from a bank for an
amount equivalent to 110% (one hundred and ten per cent) amount equivalent to 110% (one hundred and ten per cent)
of such instalment, substantially in the form provided at of such instalment, substantially in the form provided at
Annex-III of Schedule-G, to remain effective till the Annex-III Schedule-G, to remain effective till the complete
complete and full repayment thereof. and full repayment thereof.
3 CI.19.2.5 The first and the second instalments shall be paid by the The first and the second instalments shall be paid by the
Authority to the Contractor within 15 (fifteen) days of the Authority to the contractor within 15 (fifteen) days of the
receipt of its respective requests in accordance with the receipt of its respective requests in accordance with the
provisions of this Clause 19.2. provisions of this Clause 19.2.
4 CI.19.2.7 The advance payment shall be repaid through percentage The advance payment shall be repaid through percentage
deductions from the stage payments determined by the deductions from the stage payments determined by the
Authority's Engineer in accordance with Sub-Clause 19.5, Authority’s Engineer in accordance with Sub-Clause 19.5,
as follows: as follows:

(a) Deductions shall commence in the next Stage Payment (a) Deductions shall commence in the next Stage payment
Statement following that in which the total of all certified statement following that in which the total of all certified
stage payments (excluding the advance payment and stage payments (excluding the advance payment and
S. Ref Existing Description as per DCA Amendment
No. Clause
No.
deductions and repayments of retention) exceeds 20% deductions and repayments of retention) exceeds 20%
(twenty percent) of the Contract Price; and (twenty percent) of the Contract Price; and

(b) Deductions shall be made at the rate of 15% (fifteen (b) Deductions shall be made at the rate of 15%
percent) of each Stage Payment Statement until such time (fifteen percent) of each Stage Payment Statement with
as the advance payment has been repaid; provided that the interest until such time as the advance payment has been
advance payment shall be completely repaid prior to the repaid; provided that the advance payment shall be
time when 80% (80 percent) of the Contract Price has been completely repaid along with interest prior to the time when
certified for payment. 80% (80 percent) of the Contract Price has been certified
for payment.