Backlog work of Adit-1:

As we are aware that on dated 14/01/2020 Adit-1 excavation done upto 84 RMT both is Heading &
Benching portion, but primary supporting work ( Rockbolts & Shotcreting) is still not completed in
Portal as well as tunnel.

Portal

Rock bolts: As per submitted drawings contractor has to install rockbolts from
chainage 120 to 110 ( elevation 639.00 to 623.00) that includes front portion of
portal and both side walls. Rockbolts in both side walls are still uncomplete from
elevation 633 to 623 between chainage 120 to 110.

Wiremesh & Frist layer shotcrete: Same in this case of Wiremesh & 1st layer
shotcreting both side walls are still uncomplete from elevation 633 to 623 between
chainage 120 to 110.

2nd layer shotcreting : 2nd layer shotcete is not done in any portion of portal

Tunnel

Shotcrete 1st layer: on dated 14/01/2020 exavation of Adit-1 is done upto 84 mtrs.
Both heading and benching portion. 1st layer shocreting completed in heading
portion and benching portion which is 80 mtr. Is without shotcreting.

Shotcreting 2nd layer: on dated 14/01/2020 70 Rmt. 2nd layer shotcreting is balance
heading portion and 80 Rmt. is balance In benching portion.

Rockbolts: From chainage 41.00 to 76.5 50 % Rockbolts are balance.