ANALISA 2015 Semester 1
ANALISA 2015 Semester 1
HARGA DASAR
No. JENIS BAHAN SATUAN KETERANGAN
(Rp)
4. BATU BATA Batu bata bh 550.00 uk. 8x8x16 cm; batu bata lubang press mesin
1. SENG BJLS Seng gelombang uk. 5' kpg 31,000.00 uk. 0,8 x 1,50 m
Seng gelombang uk. 7' kpg 43,400.00 uk. 0,8 x 2,1 m
Seng gelombang uk. 10' kpg 62,000.00 uk. 0,8 x 3,0 m
Seng Polos t.40 m 14,000.00
4. GENTENG METAL Genteng metal uk. 2x4 (0.25mm) lbr 29,500.00 setara Sakura roof; 1 m2 @ 1,62 lbr
Genteng metal berpasir 2x5 (0,4mm) lbr 92,000.00 setara Sakura roof; 1m2 @ 1,3 lbr
Nok genteng metal bh 23,000.00 panjang 90 cm
Nok genteng metal berpasir bh 45,000.00 panjang 80 cm
7. ATAP ZINCALUME Atap Zincalume (t.0,35 mm) m' 63,500.00 uk.lebar 105 cm
Atap Alkan (t.0,35 mm) m' 55,000.00 uk. Lebar 105 cm
Nok Zickcalume 0,30 m' 25,666.67 uk. 300x60
Atap Zincalume warna (t.022mm) lbr 52,000.00 uk. 1600 mm x 740 mm
8. ATAP BITUMEN Atap bitumen motif gelombang lbr 128,500.00 setara onduline; uk. 200x95 cm
Atap bitumen motif genteng lbr 39,000.00 setara onduline; uk. 106x40 cm
Nok bh 75,000.00 setara onduline;; uk. Panjang 100 cm
9. LAIN-LAIN Aluminium foil m2 10,710.42 tipe woven two side; 1 roll @ 30m x 1,2m
Kalsiplank btg 46,000.00 1 btg @ 3m
Karpet talang t. 55cm m` 9,000.00 lebar 55 cm
1
Balok kayu m3 3,800,000.00 Kayu klas III
V BAHAN CETAK
1. BUIS BETON Buis beton dia. 100cm m 800,000.00 d0=100 cm; d1=120cm
Buis beton dia. 80cm m 500,000.00 d0=80 cm; d1=100cm
Buis beton dia. 60cm m 350,000.00 d0=60 cm; d1=75cm
Buis beton dia.40cm m 150,000.00 d0=40 cm; d1=48cm
Buis beton dia. 30cm m 90,000.00 d0=30 cm; d1=38cm
Buis beton dia. 20cm m 45,000.00 d0=20 cm; d1=25cm
2
Persegi panjang t. 8 cm bh 2,102.27 1 m2 @ 44 bh; K200
Segi enam warna t. 6 cm bh 2,567.57 1 m2 @ 37 bh; K 200
Persegi panjang warna t. 6 cm bh 2,159.09 1 m2 @ 44 bh; K200
Segi enam warna t.8 cm bh 2,837.84 1 m2 @ 37 bh; K 200
Persegi panjang warna t. 8 cm bh 2,386.36 1 m2 @ 44 bh; K200
1. PIPA PVC Pipa PVC AW 1/2" btg 17,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 3/4" btg 22,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 3" btg 120,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 4" btg 210,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC DW 3" btg 75,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC DW 4" btg 116,000.00 setara Wavin; 1 batang @ 4 m
4. PLAFOND PVC Plafond PVC putih + pasang m2 175,000.00 setara Shunda plafond
Plafond PVC warna + pasang m2 250,000.00 setara Shunda plafond
Ornamaen PVC unit 3,500,000.00 setara Shunda plafond; uk. 1,2m x 1,6m
3
Paku plywood kg 25,000.00
Hollow galvanis 20x40 m 4,000.00 1 btg @ 4 m
Hollow galvanis 40x40 m 5,375.00 1 btg @ 4 m
3. TEMBOK Cat tembok eksterior liter 90,000.00 setara Dulux Ws; 1 galon @ 2,5 l
Cat tembok interior kg 21,200.00 setara Vinilex; 1 galon @ 5 kg
Dempul/Plamir kg 6,000.00 setara kingkong
Cat dasar/Sealer kg 25,000.00 setara Vinilex
X. BAHAN KACA
4
Klem pipa bh 1,500.00
2. ENGSEL/GRENDEL Engsel 3" stainless steel ktk 45,000.00 setara paloma; 1 ktk @ 2 pcs
Engsel 3" biasa ktk 15,000.00 1 ktk @ 2 pcs (untuk jendela)
Engsel 4" stainless steel ktk 70,000.00 setara paloma; 1 ktk @ 2 pcs (untuk pintu)
Engsel 4" biasa ktk 19,000.00 1 ktk @ 2 pcs (untuk pintu)
Engsel tanam set 850,000.00 setara Dekson
Grendel 2" stainless steel bh 23,000.00
Grendel 3" stainless steel bh 30,000.00
Grendel 12 " bh 47,000.00
Grendel tanam bh 115,000.00
7. PENAMPUNG AIR Penampung air fiber kap. 550 L unit 800,000.00 setara tedmont
Penampung air fiber kap. 1100 L unit 1,150,000.00 setara tedmont
Penampung air stainless kap. 550 L unit 1,880,000.00 setara tedmont
Penampung air stainless kap. 1,1 L unit 3,775,000.00 setara tedmont
Penampung air stainless kap. 2000 unit 6,470,000.00 setara tedmont
5
XV. LAIN-LAIN
1 Pekerja OH 75,000.00
2 Tukang OH 90,000.00
3 Kepala Tukang OH 110,000.00
4 Mandor OH 120,000.00
6
aja; 1 zak @ 50 kg 65,000.00
1,300.00
12,000.00
7,000.00
6,000.00
75,000.00
3,750.00
85,000.00
60.71
65,000.00
46.43
465,000.00
435,000.00
322.22
475,000.00
351.85
57,000.00
80,000.00
Rp 11000/kaki 50,000.00
40,000.00
10,396.00
16,336.00
20,000.00
33,500.00
1,000.00
1,500.00
90,799.03
63,500.00
55,000.00
1 kpg 3 m; Rp 77000 25,666.67
setara soka
127,500.00
39,000.00
105,000.00
10,710.42
45,000.00
8,000.00
5,500,000.00
5,800,000.00
3,500,000.00
7
3,800,000.00
1,200,000.00
1,600,000.00
8,000.00
10,000.00
48,000.00
2,400.00
45,000.00
4,090.91
48,000.00
8,000.00
50,000.00
2,500.00
56,430.00
2,257.20
135,850.00
12,350.00
50,000.00
4,545.45
61,000.00
10,166.67
140,000.00
1,500,000.00
140,000.00
70,000.00
90,000.00
160,000.00
17,500.00
81,250.00
177,060.24
40,333.00
12,000.00
800,000.00
500,000.00
350,000.00
150,000.00
90,000.00
45,000.00
47,000.00
35,000.00
8,000.00
5,000.00
19,500.00
157,500.00
137,500.00
90,000.00
2,027.03
1,704.55
2,297.30
8
1,931.82
2,351.35
1,977.27
2,621.62
2,204.55
50,000.00
48,000.00
28,000.00
2,000.00
18,000.00
46,666.67
33,333.33
82,000.00
72,000.00
34,500.00
165.00
1,000.00
37,500.00
17,000.00
22,000.00
136,000.00
224,000.00
109,000.00
116,000.00
65,000.00
85,000.00
8,000.00
45,000.00
60,000.00
75,000.00
115,000.00
150,000.00
60,000.00
68,000.00
14,000.00
175,000.00
250,000.00
3,500,000.00
8,000.00
17,000.00
13,000.00
16,000.00
120,000.00
40,000.00
15,000.00
9
25,000.00
4,000.00
5,375.00
34,000.00
12,000.00
31,000.00
49,000.00
57,500.00
76,500.00
4,500.00
45,000.00
46,500.00
34,000.00
49,000.00
96,120.00
19,600.00
9,000.00
25,000.00
25,000.00
4,000.00
5,000.00
8,000.00
12,000.00
16,000.00
25,000.00
65,000.00
95,000.00
200,000.00
350,000.00
450,000.00
75,000.00
110,000.00
200,000.00
400,000.00
65,000.00
65,000.00
2,000,000.00
20,000.00
9,000.00
11,000.00
11,000.00
15,000.00
17,000.00
14,000.00
46,000.00
55,000.00
35,000.00
295,000.00
6,000.00
2,500.00
8,000.00
5,000.00
3,000.00
10
250,000.00
95,000.00
125,000.00
150,000.00
100,000.00
30,000.00
12,000.00
35,000.00
15,000.00
650,000.00
20,000.00
312,000.00
57,000.00
56,000.00
45,000.00
32,000.00
120,000.00
35,000.00
225,000.00
1,250,000.00
140,000.00
75,000.00
198,000.00
35,000.00
550,000.00
950,000.00
1,550,000.00
552,000.00
9,392,000.00
800,000.00
1,150,000.00
1,880,000.00
3,775,000.00
6,470,000.00
395,000.00
400,000.00
25,000.00
125,000.00
3,000.00
18,000.00
20,000.00
25,000.00
Rp 11.000,- / bungkus
13,000.00
45,000.00
11
150,000.00
125,000.00
37,500.00
3,500.00
194,400.00
115,000.00
40.00
11,125.00
23,500.00
6,666.67
6,666.67
11,125.00
350,000.00
450,000.00
1,250,000.00
165.00
25,000.00
40,000.00
5,000.00
200,000.00
1,800,000.00
45,000.00
75,000.00
90,000.00
110,000.00
110,000.00
12
DAFTAR HARGA SATUAN PEKERJAAN
13
8 . Pemasangan 1 m kusen pintu alluminium m 69,920.00
9 . Pemasangan 1 m2 pintu aluminium strip lebar 8 cm m2 710,901.50
10 . Pemasangan 1 m2 pintu kaca rangka aluminium m2 542,392.50
11 . Pemasangan 1 m2 terali besi strip (2x3) mm m2 410,593.85
12 . Pemasangan 1 m' talang datar/jurai seng bjls 28 lebar 90 cm m 89,727.50
13 . Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60x120cm, dinding partisi m2 78,785.00
14 . Pemasangan 1 m2 rangka besi hollow 1x40.20.2mm, modul 60x60cm, plafon m2 92,797.50
14
17 . Pemasangan 1 m2 atap zincalume warna t. 0,22mm m2 95,013.00
18 . Pemasangan 1 m2 genteng tanah liat m2 50,991.00
19 . Pemasangan 1 m' nok genteng tanah liat m 101,685.30
15
Taksir HARGA SATUAN PEKERJAAN LAIN-LAIN
1 . Pemasangan 1 m2 rangka atap baja ringan ex. TASO m2 188,602.30
2 . Pemasangan 1 m2 paving blok persegi panjang t. 8 cm mutu K200 m2 148,177.50
3 Pemasangan 1 m2 paving blok persegi panjang warna t. 8 cm mutu K200 m2 162,552.50
4 . Pemasangan 1 m2 paving blok segienam t. 8 cm mutu K200 m2 148,177.50
5 Pemasangan 1 m2 paving blok segienam warna t. 8 cm mutu K200 m2 162,552.50
6 . Pemasangan 1 titik nyala Lampu titik 225,957.75
7 . Pemasangan 1 titik nyala stop kontak titik 281,847.75
8 . 1 m2 labur aspal + labur pasir m2 19,296
16
2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
PERSIAPAN
Semen portland Kg 35.000 1,340.00
Pasir pasang m3 0.150 100,000.00
Pasir beton m3 0.100 100,000.00
Koral beton m3 0.150 435,000.00
Bata merah Bh 30.000 550.00
Seng plat Lbr 0.250 14,000.00
Jendela naco Bh 0.200 175,000.00
Kaca polos m2 0.080 95,000.00
Kunci tanam Bh 0.150 65,000.00
Plywood 4 mm Lbr 0.060 65,000.00
Seng gelombang Lbr 1.500 31,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
PERSIAPAN
JUMLAH TENAGA ALAT
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
10% E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
PERSIAPAN
9. Pembongkaran 1m3 beton bertulang
D. Jumlah (A+B+C)
10% E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
PERSIAPAN
Jumlah Harga (Rp)
7,500.00
9,000.00
1,100.00
600.00
18,200.00
10,000.00
3,350.00
52,080.00
500.00
3,915.00
1,080.00
15,300.00
86,225.00
-
-
104,425.00
15,663.75
120,088.75
7,500.00
9,000.00
1,100.00
600.00
18,200.00
19,200.00
360.00
9,100.00
28,660.00
-
-
46,860.00
7,029.00
53,889.00
75,000.00
180,000.00
90,000.00
22,000.00
6,000.00
373,000.00
10,000.00
288,000.00
1,440.00
10,700.00
PERSIAPAN
46,900.00
15,000.00
10,000.00
65,250.00
16,500.00
3,500.00
35,000.00
7,600.00
9,750.00
3,900.00
46,500.00
570,040.00
-
-
943,040.00
141,456.00
1,084,496.00
75,000.00
180,000.00
22,000.00
6,000.00
283,000.00
13,600.00
288,000.00
5,400.00
14,070.00
3,000.00
21,750.00
46,500.00
3,500.00
395,820.00
-
-
678,820.00
101,823.00
780,643.00
75,000.00
180,000.00
22,000.00
6,000.00
283,000.00
10,000.00
297,600.00
5,400.00
24,120.00
3,000.00
21,750.00
46,500.00
87,750.00
496,120.00
PERSIAPAN
-
-
779,120.00
116,868.00
895,988.00
7,500.00
6,000.00
13,500.00
-
-
-
-
13,500.00
1,350.00
14,850.00
18,750.00
1,530.00
220.00
1,560.00
22,060.00
47,500.00
7,068.00
-
54,568.00
-
-
76,628.00
11,494.20
88,122.20
27,000.00
3,300.00
30,300.00
46,800.00
22,400.00
1,440.00
-
70,640.00
-
-
100,940.00
15,141.00
116,081.00
PERSIAPAN
Jumlah Harga (Rp)
1,000,050.00
79,920.00
1,079,970.00
-
-
-
-
1,079,970.00
107,997.00
1,187,967.00
500,025.00
39,960.00
539,985.00
-
-
-
-
539,985.00
53,998.50
593,983.50
3,150.00
360.00
220.00
5,040.00
8,770.00
27,876.96
27,876.96
-
-
36,646.96
5,497.04
42,144.00
PERSIAPAN
2.3.1. HARGA SATUAN PEKERJAAN TANAH
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.750 75,000.00 56,250.00
Mandor L.04 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
-
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.900 75,000.00 67,500.00
Mandor L.04 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 72,900.00
B BAHAN
-
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -
TANAH
D. Jumlah (A+B+C) 95,400.00
E. Overhead & Profit 10% X D 9,540.00
F. Harga Satuan Pekerjaan (D+E) 104,940.00
TANAH
-
JUMLAH TENAGA ALAT -
TANAH
3.2.1. HARGA SATUAN PEKERJAAN PONDASI
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 75,000.00 112,500.00
Tukang Batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 110,000.00 8,250.00
Mandor L.04 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 197,250.00
B BAHAN
Batu kali m3 1.200 465,000.00 558,000.00
Sement Portland kg 202.000 1,340.00 270,680.00
Pasir Pasang m3 0.485 100,000.00 48,500.00
JUMLAH TENAGA BAHAN 877,180.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 75,000.00 112,500.00
Tukang Batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 110,000.00 8,250.00
Mandor L.04 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 197,250.00
B BAHAN
Batu kali m3 1.200 465,000.00 558,000.00
Sement Portland kg 163.000 1,340.00 218,420.00
Pasir Pasang m3 0.520 100,000.00 52,000.00
JUMLAH TENAGA BAHAN 828,420.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 2.025 75,000.00 151,875.00
Tukang Batu L.02 OH 0.675 90,000.00 60,750.00
Kepala Tukang L.03 OH 0.068 110,000.00 7,425.00
Mandor L.04 OH 0.101 120,000.00 12,150.00
JUMLAH TENAGA KERJA 232,200.00
B BAHAN
Batu bata bh 726.000 550.00 399,300.00
Sement Portland kg 170.022 1,340.00 227,829.48
Pasir Pasang m3 0.470 100,000.00 46,956.00
JUMLAH TENAGA BAHAN 674,085.48
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PONDASI
4. Pemasangan 1 m3 pondasi batu bata (8x8x16) cm campuran 1 SP: 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 2.025 75,000.00 151,875.00
Tukang Batu L.02 OH 0.675 90,000.00 60,750.00
Kepala Tukang L.03 OH 0.068 110,000.00 7,425.00
Mandor L.04 OH 0.101 120,000.00 12,150.00
JUMLAH TENAGA KERJA 232,200.00
B BAHAN
Batu bata bh 726.000 550.00 399,300.00
Sement Portland kg 136.998 1,340.00 183,577.32
Pasir Pasang m3 0.480 100,000.00 47,988.00
JUMLAH TENAGA BAHAN 630,865.32
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PONDASI
4.1.1. HARGA SATUAN PEKERJAAN BETON
1. Membuat 1 m3 beton mutu F'c=9,8 Mpa (K125), slump (12±2) cm, w/c=0,78
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 161,540.00
B BAHAN
Semen Portland kg 276.000 1,340.00 369,840.00
Pasir Beton kg 828.000 71.43 59,142.86
Kerikil (Maks. 30mm) kg 1012.000 351.85 356,074.07
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 799,375.93
C. PERALATAN
-
JUMLAH TENAGA ALAT -
2. Membuat 1 m3 lantai kerja beton mutu F'c=7,4 Mpa (K100) slump (3-6)cm, w/c=0,87
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 75,000.00 90,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.060 120,000.00 7,200.00
JUMLAH TENAGA KERJA 117,400.00
B BAHAN
Semen Portland kg 230.000 1,340.00 308,200.00
Pasir Beton kg 893.000 71.43 63,785.71
Kerikil (Maks. 30mm) kg 1027.000 351.85 361,351.85
Air Liter 200.000 66.60 13,320.00
JUMLAH TENAGA BAHAN 746,657.57
C. PERALATAN
-
JUMLAH TENAGA ALAT -
3. Membuat 1 m3 beton mutu F'c=14,5 Mpa (K175), slump (12±2) cm, w/c=0,66
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 161,540.00
B BAHAN
Semen Portland kg 326.000 1,340.00 436,840.00
Pasir Beton kg 760.000 71.43 54,285.71
Kerikil (Maks. 30mm) kg 1029.000 351.85 362,055.56
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 867,500.27
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
F. Harga Satuan Pekerjaan (D+E) 1,183,396.31
4. Membuat 1 m3 beton mutu F'c=19,3 Mpa (K225), slump (12±2) cm, w/c=0,58
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 161,540.00
B BAHAN
Semen Portland kg 371.000 1,340.00 497,140.00
Pasir Beton kg 698.000 71.43 49,857.14
Kerikil (Maks. 30mm) kg 1047.000 351.85 368,388.89
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 929,705.03
C. PERALATAN
-
JUMLAH TENAGA ALAT -
5. Membuat 1 m3 beton mutu F'c=21,7 Mpa (K250), slump (12±2) cm, w/c=0,56
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 161,540.00
B BAHAN
Semen Portland kg 384.000 1,340.00 514,560.00
Pasir Beton kg 692.000 71.43 49,428.57
Kerikil (Maks. 30mm) kg 1039.000 351.85 365,574.07
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 943,881.65
C. PERALATAN
-
JUMLAH TENAGA ALAT -
6. Membuat 1 m3 beton mutu F'c=26,4 Mpa (K300), slump (12±2) cm, w/c=0,52
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 161,540.00
B BAHAN
Semen Portland kg 413.000 1,340.00 553,420.00
Pasir Beton kg 681.000 71.43 48,642.86
Kerikil (Maks. 30mm) kg 1021.000 351.85 359,240.74
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 975,622.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
7. Membuat 1 m3 beton mutu F'c=31,2 Mpa (K350), slump (12±2) cm, w/c=0,48
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 2.100 75,000.00 157,500.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA 205,450.00
B BAHAN
Semen Portland kg 448.000 1,340.00 600,320.00
Pasir Beton kg 667.000 71.43 47,642.86
Kerikil (Maks. 30mm) kg 1000.000 351.85 351,851.85
Air Liter 215.000 66.60 14,319.00
JUMLAH TENAGA BAHAN 1,014,133.71
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.520 75,000.00 39,000.00
Tukang Kayu L.02 OH 0.260 90,000.00 23,400.00
Kepala Tukang L.03 OH 0.026 110,000.00 2,860.00
Mandor L.04 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 68,380.00
B BAHAN
Kayu m3 0.040 1,600,000.00 64,000.00
Paku 5-10 cm kg 0.300 18,000.00 5,400.00
Minyak bekesting Liter 0.100 11,125.00 1,112.50
JUMLAH TENAGA BAHAN 70,512.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
A. TENAGA
Pekerja L.01 OH 0.660 75,000.00 49,500.00
Tukang Kayu L.02 OH 0.330 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 86,790.00
B BAHAN
Kayu m3 0.040 1,600,000.00 64,000.00
Paku 5-12 cm kg 0.400 18,000.00 7,200.00
Minyak bekesting Liter 0.200 11,125.00 2,225.00
Balok m3 0.018 1,600,000.00 28,800.00
Plywood tebal 9 mm Lbr 0.350 110,000.00 38,500.00
Dolken Kayu Ø8-10cm p.4m Batang 2.000 8,000.00 16,000.00
JUMLAH TENAGA BAHAN 156,725.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
E. Overhead & Profit 15% X D 40,607.25
F. Harga Satuan Pekerjaan (D+E) 311,322.25
BETON
JUMLAH TENAGA BAHAN 2,723,200.94
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
21. Membuat 1 m3 balok beton bertulang (200 kg besi + bekesting)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 6.350 75,000.00 476,250.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Tukang Kayu L.02 OH 1.650 90,000.00 148,500.00
Tukang Besi L.02 OH 1.400 90,000.00 126,000.00
Kepala Tukang L.03 OH 0.333 110,000.00 36,630.00
Mandor L.04 OH 0.318 120,000.00 38,160.00
JUMLAH TENAGA KERJA 850,290.00
B BAHAN
Kayu kelas m3 0.320 1,600,000.00 512,000.00
Paku 5-12 cm kg 3.200 18,000.00 57,600.00
Minyak bekesting Liter 1.600 11,125.00 17,800.00
Besi beton polos kg 210.000 9,157.21 1,923,014.59
Kawat beton kg 3.000 18,000.00 54,000.00
Sement Portland kg 336.000 1,340.00 450,240.00
Pasir Beton m3 0.540 100,000.00 54,000.00
Kerikil kg 0.810 475,000.00 384,750.00
Kayu kelas balok m3 0.140 1,600,000.00 224,000.00
Plywood 9 mm Lbr 2.800 110,000.00 308,000.00
Dolken Kayu Ø8-10cm p.4m Batang 16.000 8,000.00 128,000.00
JUMLAH TENAGA BAHAN 4,113,404.59
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
Tukang Kayu L.02 OH 1.300 90,000.00 117,000.00
Tukang Besi L.02 OH 1.050 90,000.00 94,500.00
Kepala Tukang L.03 OH 0.262 110,000.00 28,820.00
Mandor L.04 OH 0.265 120,000.00 31,800.00
JUMLAH TENAGA KERJA 694,370.00
B BAHAN
Kayu kelas m3 0.240 1,600,000.00 384,000.00
Paku 5-12 cm kg 3.200 18,000.00 57,600.00
Minyak bekesting Liter 1.600 11,125.00 17,800.00
Besi beton polos kg 157.500 9,157.21 1,442,260.94
Kawat beton kg 2.250 18,000.00 40,500.00
Sement Portland kg 336.000 1,340.00 450,240.00
Pasir Beton m3 0.540 100,000.00 54,000.00
Kerikil kg 0.810 475,000.00 384,750.00
Kayu kelas balok m3 0.160 1,600,000.00 256,000.00
Plywood 9 mm Lbr 2.800 110,000.00 308,000.00
Dolken Kayu Ø8-10cm p.4m Batang 24.000 8,000.00 192,000.00
JUMLAH TENAGA BAHAN 3,587,150.94
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
Kayu kelas m3 0.002 1,600,000.00 3,200.00
Paku 5-12 cm kg 0.001 18,000.00 18.00
Minyak bekesting Liter 0.100 11,125.00 1,112.50
Besi beton polos kg 3.000 9,157.21 27,471.64
Kawat beton kg 0.450 18,000.00 8,100.00
Sement Portland kg 4.000 1,340.00 5,360.00
Pasir Beton m3 0.006 100,000.00 600.00
Kerikil kg 0.009 475,000.00 4,275.00
JUMLAH TENAGA BAHAN 50,137.14
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
28. Pemasangan 1 m2 bekesting untuk balok jerambah
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.330 75,000.00 24,750.00
Tukang Kayu L.02 OH 0.165 90,000.00 14,850.00
Kepala Tukang L.03 OH 0.017 110,000.00 1,815.00
Mandor L.04 OH 0.017 120,000.00 1,980.00
JUMLAH TENAGA KERJA 43,395.00
B BAHAN
Kayu m3 0.020 1,600,000.00 32,000.00
Paku 5-12 cm kg 0.200 18,000.00 3,600.00
Minyak bekesting Liter 0.200 11,125.00 2,225.00
Balok m3 0.010 1,600,000.00 16,000.00
Papan Racuk kpg 1.050 25,000.00 26,250.00
Dolken Kayu Ø8-10cm p.4m Batang 1.000 8,000.00 8,000.00
JUMLAH TENAGA BAHAN 88,075.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
BETON
E. Overhead & Profit 15% X D 6,525.00
F. Harga Satuan Pekerjaan (D+E) 50,025.00
BETON
4.2.1. HARGA SATUAN PEKERJAAN BESI & ALUMINIUM
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 75,000.00 4,500.00
Tukang Las Konstruksi L.03 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 10,920.00
B BAHAN
Besi Profil kg 1.150 9,157.21 10,530.79
JUMLAH TENAGA BAHAN 10,530.79
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 75,000.00 4,500.00
Tukang Las Konstruksi L.03 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 10,920.00
B BAHAN
Besi Baja IWF kg 1.150 12,500.00 14,375.00
JUMLAH TENAGA BAHAN 14,375.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
4. Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 75,000.00 123,750.00
Tukang Las Biasa L.02 OH 0.275 90,000.00 24,750.00
13. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60x120cm, dinding partisi
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Besi L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 45,560.00
B BAHAN
Rangka metal hollow 40.40.2 mm m' 3.500 5,375.00 18,812.50
Assesoris (perkuatan, las dll) Ls 100%xrangka 5,375.00
JUMLAH TENAGA BAHAN 24,187.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 75,000.00 45,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 68,800.00
B BAHAN
Bata merah bh 121.000 550.00 66,550.00
Semen Portland kg 21.747 1,340.00 29,140.98
Pasir pasang m3 0.060 100,000.00 6,006.00
JUMLAH TENAGA BAHAN 101,696.98
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 75,000.00 45,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 68,800.00
B BAHAN
Bata merah bh 121.000 550.00 66,550.00
Semen Portland kg 17.523 1,340.00 23,480.82
Pasir pasang m3 0.061 100,000.00 6,138.00
JUMLAH TENAGA BAHAN 96,168.82
C. PERALATAN
-
JUMLAH TENAGA ALAT -
3. Pemasangan 1 m2 dinding bata lobang (8x8x16) cm tebal 1/2 batu campuran 1 SP:3PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 34,400.00
B BAHAN
Bata merah bh 66.000 550.00 36,300.00
Semen Portland kg 7.832 1,340.00 10,494.41
Pasir pasang m3 0.022 100,000.00 2,180.00
JUMLAH TENAGA BAHAN 48,974.41
C. PERALATAN
-
JUMLAH TENAGA ALAT -
DINDING
4. Pemasangan 1 m2 dinding bata lubang (8x8x16) cm tebal 1/2 batu campuran 1 SP:4PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 34,400.00
B BAHAN
Bata merah bh 66.000 550.00 36,300.00
Semen Portland kg 6.268 1,340.00 8,398.45
Pasir pasang m3 0.023 100,000.00 2,343.50
JUMLAH TENAGA BAHAN 47,041.95
C. PERALATAN
-
JUMLAH TENAGA ALAT -
DINDING
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 34,400.00
B BAHAN
Rooster keramik 20x20cm bh 25.000 36,500.00 912,500.00
Semen Portland kg 11.000 1,340.00 14,740.00
Pasir pasang m3 0.035 100,000.00 3,500.00
JUMLAH TENAGA BAHAN 930,740.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
DINDING
4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,450.00
B BAHAN
Semen Portland kg 7.776 1,340.00 10,419.84
Pasir pasang m3 0.023 100,000.00 2,300.00
JUMLAH TENAGA BAHAN 12,719.84
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.260 75,000.00 19,500.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 41,260.00
B BAHAN
Semen Portland kg 10.368 1,340.00 13,893.12
Pasir pasang m3 0.031 100,000.00 3,100.00
JUMLAH TENAGA BAHAN 16,993.12
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,450.00
B BAHAN
Semen Portland kg 6.240 1,340.00 8,361.60
Pasir pasang m3 0.024 100,000.00 2,400.00
JUMLAH TENAGA BAHAN 10,761.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PLESTERAN
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.260 75,000.00 19,500.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 41,260.00
B BAHAN
Semen Portland kg 8.320 1,340.00 11,148.80
Pasir pasang m3 0.032 100,000.00 3,200.00
JUMLAH TENAGA BAHAN 14,348.80
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Batu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.008 110,000.00 880.00
Mandor L.04 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 19,840.00
B BAHAN
Semen Portland kg 5.184 1,340.00 6,946.56
Pasir pasang m3 0.026 100,000.00 2,600.00
JUMLAH TENAGA BAHAN 9,546.56
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.080 75,000.00 6,000.00
Tukang Batu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 110,000.00 4,400.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 46,880.00
B BAHAN
Semen Portland kg 0.500 1,340.00 670.00
Pasir pasang m3 0.013 100,000.00 1,300.00
JUMLAH TENAGA BAHAN 1,970.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
PLESTERAN
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 34,400.00
B BAHAN
Semen Portland kg 4.320 1,340.00 5,788.80
Pasir pasang m3 0.006 100,000.00 600.00
JUMLAH TENAGA BAHAN 6,388.80
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang Batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,450.00
B BAHAN
Semen Portland kg 6.340 1,340.00 8,495.60
Pasir pasang m3 0.012 100,000.00 1,200.00
JUMLAH TENAGA BAHAN 9,695.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
9. Pemasangan 1 m2 acian
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 26,300.00
B BAHAN
Semen Portland kg 3.250 1,340.00 4,355.00
JUMLAH TENAGA BAHAN 4,355.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PLESTERAN
4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 11,610.00
B BAHAN
Soda api bh 0.050 40,000.00 2,000.00
JUMLAH TENAGA BAHAN 2,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
2. 1 m2 Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 75,000.00 5,250.00
Tukang cat L.02 OH 0.009 90,000.00 810.00
Kepala tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 7,080.00
B BAHAN
Cat menie kg 0.200 34,000.00 6,800.00
Plamur kg 0.150 38,500.00 5,775.00
Cat dasar kg 0.170 31,000.00 5,270.00
Cat penutup kg 0.260 52,000.00 13,520.00
Kuas bh 0.010 5,000.00 50.00
Pengencer kg 0.030 25,000.00 750.00
Amplas Lbr 0.200 5,000.00 1,000.00
JUMLAH TENAGA BAHAN 33,165.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.040 75,000.00 3,000.00
Tukang cat L.02 OH 0.063 90,000.00 5,670.00
Kepala tukang L.03 OH 0.063 110,000.00 6,930.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 15,960.00
B BAHAN
Teak oil L 0.360 57,500.00 20,700.00
JUMLAH TENAGA BAHAN 20,700.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
CAT
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.040 75,000.00 3,000.00
Tukang cat L.02 OH 0.060 90,000.00 5,400.00
Kepala tukang L.03 OH 0.016 110,000.00 1,760.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 10,520.00
B BAHAN
Politur L 0.150 38,500.00 5,775.00
Politur jadi L 0.372 76,500.00 28,458.00
Amplas Lbr 2.000 5,000.00 10,000.00
JUMLAH TENAGA BAHAN 44,233.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 8,220.00
B BAHAN
Residu atau ter L 0.350 4,500.00 1,575.00
JUMLAH TENAGA BAHAN 1,575.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.160 75,000.00 12,000.00
Tukang cat L.02 OH 0.160 90,000.00 14,400.00
Kepala tukang L.03 OH 0.016 110,000.00 1,760.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 28,520.00
B BAHAN
Vernis L 0.150 46,500.00 6,975.00
Dempul Kg 0.050 7,200.00 360.00
Ampelas Lbr 0.100 5,000.00 500.00
JUMLAH TENAGA BAHAN 7,835.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
7. Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 75,000.00 1,500.00
Tukang cat L.02 OH 0.063 90,000.00 5,670.00
CAT
Kepala tukang L.03 OH 0.0063 110,000.00 693.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 8,223.00
B BAHAN
Plamir L 0.100 6,000.00 600.00
Cat dasar Kg 0.100 25,000.00 2,500.00
Cat penutup ex. Vinilex kg 0.260 21,200.00 5,512.00
JUMLAH TENAGA BAHAN 8,612.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 75,000.00 2,100.00
Tukang cat L.02 OH 0.042 90,000.00 3,780.00
Kepala tukang L.03 OH 0.0042 110,000.00 462.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 6,702.00
B BAHAN
Cat dasar Kg 0.120 25,000.00 3,000.00
Cat penutup ex. Vinilex Lbr 0.180 21,200.00 3,816.00
JUMLAH TENAGA BAHAN 6,816.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
9. Pemasangan 1 m2 wallpaper
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 75,000.00 1,500.00
Tukang cat L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.0200 110,000.00 2,200.00
Mandor L.04 OH 0.003 120,000.00 300.00
JUMLAH TENAGA KERJA 22,000.00
B BAHAN
Wallpaper m2 1.200 40,333.00 48,399.60
Lem Kg 0.200 45,000.00 9,000.00
JUMLAH TENAGA BAHAN 57,399.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 75,000.00 4,500.00
Tukang cat L.02 OH 0.060 90,000.00 5,400.00
Kepala tukang L.03 OH 0.0120 110,000.00 1,320.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 11,580.00
CAT
B BAHAN
Menie besi kg 0.100 34,000.00 3,400.00
Kuas bh 0.010 5,000.00 50.00
JUMLAH TENAGA BAHAN 3,450.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
11. Pengecatam 1 m2 permukaan baja galvanis secara manual sisitem 1 lapis cat
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 75,000.00 4,500.00
Tukang cat L.02 OH 0.060 90,000.00 5,400.00
Kepala tukang L.03 OH 0.0120 110,000.00 1,320.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 11,580.00
B BAHAN
Cat kg 0.300 53,000.00 15,900.00
Kuas bh 0.010 5,000.00 50.00
Pengencer L 0.010 25,000.00 250.00
JUMLAH TENAGA BAHAN 16,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
12. Pengecatan 1 m2 tembok baru untuk exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 75,000.00 1,500.00
Tukang cat L.02 OH 0.063 90,000.00 5,670.00
Kepala tukang L.03 OH 0.0063 110,000.00 693.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 8,223.00
B BAHAN
Plamir L 0.100 6,000.00 600.00
Cat dasar Kg 0.100 25,000.00 2,500.00
Cat penutup ex. Dulux L 0.260 90,000.00 23,400.00
JUMLAH TENAGA BAHAN 26,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 75,000.00 2,100.00
Tukang cat L.02 OH 0.042 90,000.00 3,780.00
Kepala tukang L.03 OH 0.0042 110,000.00 462.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 6,702.00
B BAHAN
Cat penutup ex. Vinilex Lbr 0.180 21,200.00 3,816.00
CAT
JUMLAH TENAGA BAHAN 3,816.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
CAT
4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Granite tile bh 3.050 60,000.00 183,000.00
Semen Portland kg 8.190 1,340.00 10,974.60
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.620 12,000.00 19,440.00
JUMLAH TENAGA BAHAN 217,914.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Granite tile bh 1.716 137,500.00 235,950.00
Semen Portland kg 8.190 1,340.00 10,974.60
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.620 12,000.00 19,440.00
JUMLAH TENAGA BAHAN 270,864.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Keramik 30x30 (putih) bh 11.870 4,545.45 53,954.55
Semen Portland kg 10.000 1,340.00 13,400.00
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.500 12,000.00 18,000.00
JUMLAH TENAGA BAHAN 89,854.55
C. PERALATAN
-
JUMLAH TENAGA ALAT -
LANTAI
15% E. Overhead & Profit 15% X D 18,426.68
F. Harga Satuan Pekerjaan (D+E) 141,271.23
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Keramik 40x40 (putih) bh 6.630 8,666.67 57,460.00
Semen Portland kg 10.000 1,340.00 13,400.00
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.500 12,000.00 18,000.00
JUMLAH TENAGA BAHAN 93,360.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.270 75,000.00 20,250.00
Tukang Batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.014 110,000.00 1,540.00
Mandor L.04 OH 0.014 120,000.00 1,680.00
JUMLAH TENAGA KERJA 35,620.00
B BAHAN
Keramik 20x20 (KM/WC) bh 26.500 2,257.20 59,815.80
Semen Portland kg 10.400 1,340.00 13,936.00
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.620 12,000.00 19,440.00
JUMLAH TENAGA BAHAN 97,691.80
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Keramik 30x30 warna bh 11.870 5,090.91 60,429.09
Semen Portland kg 10.000 1,340.00 13,400.00
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.500 12,000.00 18,000.00
JUMLAH TENAGA BAHAN 96,329.09
C. PERALATAN
-
JUMLAH TENAGA ALAT -
LANTAI
D. Jumlah (A+B+C) 129,319.09
15% E. Overhead & Profit 15% X D 19,397.86
F. Harga Satuan Pekerjaan (D+E) 148,716.95
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Batu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 32,990.00
B BAHAN
Keramik 40x40 warna bh 6.630 10,540.00 69,880.20
Semen Portland kg 10.000 1,340.00 13,400.00
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 1.500 12,000.00 18,000.00
JUMLAH TENAGA BAHAN 105,780.20
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 75,000.00 6,750.00
Tukang Batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 19,300.00
B BAHAN
Plint keramik bh 3.530 1,696.97 5,990.30
Semen Portland kg 1.140 1,340.00 1,527.60
Pasir pasang kg 0.003 100,000.00 300.00
Semen warna kg 0.050 12,000.00 600.00
JUMLAH TENAGA BAHAN 8,417.90
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 75,000.00 6,750.00
Tukang Batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 19,300.00
B BAHAN
Plint keramik bh 2.650 2,635.00 6,982.75
Semen Portland kg 1.140 1,340.00 1,527.60
Pasir pasang kg 0.003 100,000.00 300.00
Semen warna kg 0.050 12,000.00 600.00
JUMLAH TENAGA BAHAN 9,410.35
C. PERALATAN
LANTAI
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 75,000.00 6,750.00
Tukang Batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 19,300.00
B BAHAN
Plint granite tile bh 1.760 10,000.00 17,600.00
Semen Portland kg 1.140 1,340.00 1,527.60
Pasir pasang kg 0.003 100,000.00 300.00
Semen warna kg 0.050 12,000.00 600.00
JUMLAH TENAGA BAHAN 20,027.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 75,000.00 6,750.00
Tukang Batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 19,300.00
B BAHAN
Plint granite tile bh 1.325 17,187.50 22,773.44
Semen Portland kg 1.140 1,340.00 1,527.60
Pasir pasang kg 0.003 100,000.00 300.00
Semen warna kg 0.050 12,000.00 600.00
JUMLAH TENAGA BAHAN 25,201.04
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 75,000.00 52,500.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 92,050.00
B BAHAN
Marmer bh 1.060 1,500,000.00 1,590,000.00
Semen Portland kg 8.190 1,340.00 10,974.60
Pasir pasang kg 0.045 100,000.00 4,500.00
Semen warna kg 0.650 12,000.00 7,800.00
LANTAI
JUMLAH TENAGA BAHAN 1,613,274.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.170 75,000.00 12,750.00
Tukang Batu L.02 OH 0.170 90,000.00 15,300.00
Kepala Tukang L.03 OH 0.017 110,000.00 1,870.00
Mandor L.04 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 31,000.00
B BAHAN
Karpet tebal 6 mm m2 1.050 81,250.00 85,312.50
Lem kg 0.350 45,000.00 15,750.00
JUMLAH TENAGA BAHAN 101,062.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 75,000.00 52,500.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 92,050.00
B BAHAN
Vinyl kayu m2 1.050 177,060.00 185,913.00
Lem kg 0.600 45,000.00 27,000.00
JUMLAH TENAGA BAHAN 212,913.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.1875 75,000.00 14,062.50
Tukang Batu L.02 OH 0.3750 90,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 110,000.00 4,950.00
Mandor L.04 OH 0.0188 120,000.00 2,256.00
JUMLAH TENAGA KERJA 55,018.50
B BAHAN
Keramik 20x25 warna bh 22.000 2,536.50 55,803.00
Semen Portland kg 9.300 1,340.00 12,462.00
Pasir pasang kg 0.018 100,000.00 1,800.00
Semen warna kg 1.940 12,000.00 23,280.00
JUMLAH TENAGA BAHAN 93,345.00
C. PERALATAN
LANTAI
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.1875 75,000.00 14,062.50
Tukang Batu L.02 OH 0.3750 90,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 110,000.00 4,950.00
Mandor L.04 OH 0.0188 120,000.00 2,256.00
JUMLAH TENAGA KERJA 55,018.50
B BAHAN
Keramik 20x25 putih bh 22.000 2,400.00 52,800.00
Semen Portland kg 9.300 1,340.00 12,462.00
Pasir pasang kg 0.018 100,000.00 1,800.00
Semen warna kg 1.940 12,000.00 23,280.00
JUMLAH TENAGA BAHAN 90,342.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.300 75,000.00 97,500.00
Tukang Batu L.02 OH 0.650 90,000.00 58,500.00
Kepala Tukang L.03 OH 0.065 110,000.00 7,150.00
Mandor L.04 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 167,350.00
B BAHAN
Marmer m2 1.060 1,500,000.00 1,590,000.00
Semen Portland kg 12.440 1,340.00 16,669.60
Pasir pasang kg 0.025 100,000.00 2,500.00
Semen warna kg 0.650 12,000.00 7,800.00
Paku 12 cm kg 3.030 18,000.00 54,540.00
JUMLAH TENAGA BAHAN 1,671,509.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 75,000.00 52,500.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 92,050.00
B BAHAN
Batu candi / andesit m2 1.100 155,000.00 170,500.00
Semen Portland kg 11.750 1,340.00 15,745.00
Pasir pasang kg 0.035 100,000.00 3,500.00
LANTAI
JUMLAH TENAGA BAHAN 189,745.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 75,000.00 52,500.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 92,050.00
B BAHAN
Batu tempel m2 1.100 95,000.00 104,500.00
Semen Portland kg 11.750 1,340.00 15,745.00
Pasir pasang kg 0.035 100,000.00 3,500.00
JUMLAH TENAGA BAHAN 123,745.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 75,000.00 26,250.00
Tukang Batu L.02 OH 0.175 90,000.00 15,750.00
Kepala Tukang L.03 OH 0.017 110,000.00 1,870.00
Mandor L.04 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 44,110.00
B BAHAN
Wallpaper m 2.200 20,166.50 44,366.30
Lem kg 0.250 45,000.00 11,250.00
JUMLAH TENAGA BAHAN 55,616.30
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.120 75,000.00 9,000.00
Tukang Batu L.02 OH 0.120 90,000.00 10,800.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Floor harderner kg 3.000 7,500.00 22,500.00
JUMLAH TENAGA BAHAN 22,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
LANTAI
D. Jumlah (A+B+C) 44,340.00
15% E. Overhead & Profit 15% X D 6,651.00
F. Harga Satuan Pekerjaan (D+E) 50,991.00
LANTAI
4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.030 75,000.00 2,250.00
Tukang Kayu L.02 OH 0.070 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.007 110,000.00 770.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 9,800.00
B BAHAN
Asbes semen m2 1.100 22,569.44 24,826.39
Paku tripleks kg 0.010 25,000.00 250.00
JUMLAH TENAGA BAHAN 25,076.39
C. PERALATAN
-
JUMLAH TENAGA ALAT -
2. Pemasangan 1 m2 langit-langit plywood ukuran (120 x 240) cm (tebal 3 mm, 4 mm, 6 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 18,200.00
B BAHAN
Plywood 4mm Lembar 0.375 65,000.00 24,375.00
Paku tripleks kg 0.030 25,000.00 750.00
JUMLAH TENAGA BAHAN 25,125.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Batu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 13,150.00
B BAHAN
Gypsum board Lembar 0.364 60,000.00 21,840.00
Paku skrup kg 0.110 40,000.00 4,400.00
Cornis kg 0.300 3,750.00 1,125.00
Lakban gypsum roll 0.070 15,000.00 1,050.00
JUMLAH TENAGA BAHAN 28,415.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PLAFOND
4. Pemasangan 1 m' list langit-langit kayu profil
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 75,000.00 3,750.00
Tukang Batu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,160.00
B BAHAN
List kayu profil m 1.050 4,473.68 4,697.37
Paku kg 0.010 18,000.00 180.00
JUMLAH TENAGA BAHAN 4,877.37
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 75,000.00 3,750.00
Tukang Batu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,160.00
B BAHAN
List gypsum sedang m 1.050 10,000.00 10,500.00
Paku skrup kg 0.010 40,000.00 400.00
Cornis kg 0.100 3,750.00 375.00
JUMLAH TENAGA BAHAN 11,275.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Batu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 13,150.00
B BAHAN
Kalsiboard Lembar 0.364 59,000.00 21,476.00
Paku skrup kg 0.110 40,000.00 4,400.00
Cornis kg 0.300 3,750.00 1,125.00
Lakban gypsum roll 0.070 15,000.00 1,050.00
JUMLAH TENAGA BAHAN 28,051.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
PLAFOND
4.5.1 HARGA SATUAN PEKERJAAN PENUTUP ATAP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.140 75,000.00 10,500.00
Tukang Kayu L.02 OH 0.067 90,000.00 6,030.00
Kepala Tukang L.03 OH 0.007 110,000.00 770.00
Mandor L.04 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 18,140.00
B BAHAN
Rooflight 2,1m x 11,8m m2 1.050 90,799.03 95,338.98
Paku kg 0.050 25,000.00 1,250.00
JUMLAH TENAGA BAHAN 96,588.98
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.1400 75,000.00 10,500.00
Tukang Kayu L.02 OH 0.0700 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.0070 110,000.00 770.00
Mandor L.04 OH 0.0070 120,000.00 840.00
JUMLAH TENAGA KERJA 18,410.00
B BAHAN
Asbes gelombang Lbr 0.800 55,000.00 44,000.00
Paku pancing 6x23 kg 0.120 25,000.00 3,000.00
JUMLAH TENAGA BAHAN 47,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.084 75,000.00 6,300.00
Tukang Kayu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 19,460.00
B BAHAN
Nok asbes Lbr 1.000 45,000.00 45,000.00
Paku seng kg 0.040 25,000.00 1,000.00
JUMLAH TENAGA BAHAN 46,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
ATAP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 26,300.00
B BAHAN
Genteng keramik ex. Kanmuri Bh 14.000 10,735.00 150,290.00
Paku biasa 2"-5" kg 0.030 18,000.00 540.00
JUMLAH TENAGA BAHAN 150,830.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 25,220.00
B BAHAN
Genteng metal ex. Sakura Bh 1.620 32,500.00 52,650.00
Paku biasa 1/2"-1" kg 0.200 18,000.00 3,600.00
JUMLAH TENAGA BAHAN 56,250.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.400 75,000.00 30,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.020 120,000.00 2,400.00
JUMLAH TENAGA KERJA 52,600.00
B BAHAN
Nok genteng beton Bh 3.900 25,000.00 97,500.00
Paku biasa 1/2"-1" kg 0.050 18,000.00 900.00
Semen PC kg 10.800 1,340.00 14,472.00
Pasir pasang m3 0.032 100,000.00 3,200.00
Semen warna kg 1.000 12,000.00 12,000.00
JUMLAH TENAGA BAHAN 128,072.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
ATAP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 75,000.00 18,750.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 35,460.00
B BAHAN
Nok genteng metal Bh 1.100 23,000.00 25,300.00
Paku biasa 1/2"-1" kg 0.050 18,000.00 900.00
JUMLAH TENAGA BAHAN 26,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.120 75,000.00 9,000.00
Tukang Kayu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 15,780.00
B BAHAN
Atap seng gelombang Lbr 0.913 31,000.00 28,303.00
Paku biasa 1/2"-1" kg 0.020 18,000.00 360.00
JUMLAH TENAGA BAHAN 28,663.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.070 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.007 110,000.00 770.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 19,040.00
B BAHAN
Seng plat 3"x6" Bh 0.300 14,000.00 4,200.00
Paku biasa 1/2"-1" kg 0.040 18,000.00 720.00
JUMLAH TENAGA BAHAN 4,920.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
ATAP
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.080 110,000.00 8,800.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,520.00
B BAHAN
alkan t. 0,35 Lbr 1.050 55,000.00 57,750.00
Paku hak panj.15 cm kg 0.020 25,000.00 500.00
JUMLAH TENAGA BAHAN 58,250.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.100 110,000.00 11,000.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 33,500.00
B BAHAN
Nok standar 40x18 Bh 1.200 25,666.67 30,800.00
Paku hak panj.15 cm kg 0.040 25,000.00 1,000.00
JUMLAH TENAGA BAHAN 31,800.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 17,260.00
B BAHAN
Aluminium foil woven m2 1.050 10,710.42 11,245.94
JUMLAH TENAGA BAHAN 11,245.94
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.140 75,000.00 10,500.00
Tukang Kayu L.02 OH 0.070 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.007 110,000.00 770.00
Mandor L.04 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 18,410.00
B BAHAN
ATAP
Atam bitumen ex. Onduline Lbr 0.600 128,500.00 77,100.00
Paku bh 10.000 1,100.00 11,000.00
JUMLAH TENAGA BAHAN 88,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.084 75,000.00 6,300.00
Tukang Kayu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 19,460.00
B BAHAN
Nok bitumen ex. Onduline bh 1.100 75,000.00 82,500.00
Paku bh 8.000 1,100.00 8,800.00
JUMLAH TENAGA BAHAN 91,300.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.080 110,000.00 8,800.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,520.00
B BAHAN
Zincalujme t.0,35 Lbr 1.050 63,500.00 66,675.00
Paku hak panj.15 cm kg 0.020 25,000.00 500.00
JUMLAH TENAGA BAHAN 67,175.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.100 110,000.00 11,000.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 33,500.00
B BAHAN
Nok zincalume m 1.200 25,666.67 30,800.00
Paku kg 0.040 25,000.00 1,000.00
JUMLAH TENAGA BAHAN 31,800.00
C. PERALATAN
ATAP
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.080 110,000.00 8,800.00
Mandor L.04 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,520.00
B BAHAN
Zincalujme t.0,22 Lbr 1.050 52,000.00 54,600.00
Paku hak panj.15 cm kg 0.020 25,000.00 500.00
JUMLAH TENAGA BAHAN 55,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 26,300.00
B BAHAN
Genteng ex. Lokal Bh 17.500 1,000.00 17,500.00
Paku biasa 2"-5" kg 0.030 18,000.00 540.00
JUMLAH TENAGA BAHAN 18,040.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.400 75,000.00 30,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.020 120,000.00 2,400.00
JUMLAH TENAGA KERJA 52,600.00
B BAHAN
Nok genteng Bh 3.500 1,500.00 5,250.00
Paku biasa 1/2"-1" kg 0.050 18,000.00 900.00
Semen PC kg 10.800 1,340.00 14,472.00
Pasir pasang m3 0.032 100,000.00 3,200.00
Semen warna kg 1.000 12,000.00 12,000.00
JUMLAH TENAGA BAHAN 35,822.00
C. PERALATAN
-
ATAP
JUMLAH TENAGA ALAT -
ATAP
1. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 6.700 75,000.00 502,500.00
Tukang Kayu L.02 OH 20.100 90,000.00 1,809,000.00
Kepala Tukang L.03 OH 2.010 110,000.00 221,100.00
Mandor L.04 OH 0.335 120,000.00 40,200.00
JUMLAH TENAGA KERJA 2,572,800.00
B BAHAN
Balok kayu klas II m3 1.100 5,800,000.00 502,500.00
Besi strip tebal 5mm kg 15.000 12,500.00 1,809,000.00
Paku 12 cm kg 3.000 18,000.00 221,100.00
JUMLAH TENAGA BAHAN 2,532,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 18,200.00
B BAHAN
Kaso 5x7 cm m3 0.014 3,800,000.00 53,200.00
Reng 2x3 cm m3 0.036 3,800,000.00 136,800.00
Paku 5 dan 10 cm kg 0.250 18,000.00 4,500.00
JUMLAH TENAGA BAHAN 194,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.030 110,000.00 3,300.00
Mandor L.04 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 50,550.00
B BAHAN
Kaso 5x7 cm m3 0.0154 3,800,000.00 58,520.00
Paku kg 0.200 18,000.00 3,600.00
JUMLAH TENAGA BAHAN 62,120.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
KAYU
10. Pemasangan 1 m2 rangka langit-langit (60x60) cm, III
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang Kayu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.030 110,000.00 3,300.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 46,500.00
B BAHAN
Kaso 5x7 cm m3 0.0163 3,800,000.00 61,940.00
Paku kg 0.250 18,000.00 4,500.00
JUMLAH TENAGA BAHAN 66,440.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 28,300.00
B BAHAN
Papan kayu klas II m3 0.0108 5,500,000.00 59,400.00
Paku kg 0.100 18,000.00 1,800.00
JUMLAH TENAGA BAHAN 61,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 28,300.00
B BAHAN
Papan kayu klas II m3 0.0110 5,500,000.00 60,500.00
Paku kg 0.050 18,000.00 900.00
JUMLAH TENAGA BAHAN 61,400.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
KAYU
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 75,000.00 11,250.00
Tukang Kayu L.02 OH 0.450 90,000.00 40,500.00
Kepala Tukang L.03 OH 0.045 110,000.00 4,950.00
Mandor L.04 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 57,660.00
B BAHAN
Balok kayu klas III m3 0.0280 3,800,000.00 106,400.00
Paku kg 0.150 18,000.00 2,700.00
JUMLAH TENAGA BAHAN 109,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
14. Pemasangan 1 m2 rangka dinding pemisah plywood rangkap, rangka kayu kelas III
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 75,000.00 2,100.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.860 110,000.00 94,600.00
Mandor L.04 OH 0.560 120,000.00 67,200.00
JUMLAH TENAGA KERJA 177,400.00
B BAHAN
Balok kayu klas III, 6x12 m3 0.0280 3,800,000.00 106,400.00
Paku kg 0.1500 18,000.00 2,700.00
Plywood 4 mm, 120x240 Lembar 0.8600 65,000.00 55,900.00
Lem kayu kg 0.560 13,000.00 7,280.00
JUMLAH TENAGA BAHAN 172,280.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 75,000.00 45,000.00
Tukang Kayu L.02 OH 1.800 90,000.00 162,000.00
Kepala Tukang L.03 OH 0.180 110,000.00 19,800.00
Mandor L.04 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 230,400.00
B BAHAN
Papan kayu klas II m3 0.0070 5,500,000.00 38,500.00
Paku kg 0.1000 18,000.00 1,800.00
Paku skrup kg 0.1500 18,000.00 2,700.00
JUMLAH TENAGA BAHAN 43,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
KAYU
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.025 75,000.00 1,875.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.008 110,000.00 880.00
Mandor L.04 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 9,625.00
B BAHAN
Plywod 4 mm m3 0.4000 65,000.00 26,000.00
Paku 1' dan 2,5' kg 0.0500 18,000.00 900.00
JUMLAH TENAGA BAHAN 26,900.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 75,000.00 7,500.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 28,300.00
B BAHAN
Kalsiplank btg 0.3500 46,000.00 16,100.00
Paku kg 0.100 18,000.00 1,800.00
JUMLAH TENAGA BAHAN 17,900.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
KAYU
4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 51,850.00
B BAHAN
Kunci tanam biasa bh 1.000 133,000.00 133,000.00
JUMLAH TENAGA BAHAN 133,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 51,850.00
B BAHAN
Handle bh 1.000 150,000.00 150,000.00
Isi Silinder bh 1.000 100,000.00 100,000.00
JUMLAH TENAGA BAHAN 250,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.005 75,000.00 375.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 51,235.00
B BAHAN
Kunci bulat ex. SES bh 1.000 125,000.00 125,000.00
JUMLAH TENAGA BAHAN 125,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.0005 120,000.00 60.00
JUMLAH TENAGA KERJA 10,910.00
B BAHAN
Engsel 3" biasa bh 1.000 7,500.00 7,500.00
JUMLAH TENAGA BAHAN 7,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 75,000.00 1,125.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.0080 120,000.00 960.00
JUMLAH TENAGA KERJA 17,235.00
B BAHAN
Spring knip stainless stell bh 1.000 16,000.00 16,000.00
JUMLAH TENAGA BAHAN 16,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 75,000.00 1,125.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 75,000.00 3,750.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 54,610.00
B BAHAN
Door closer kw 2 bh 1.000 251,000.00 251,000.00
JUMLAH TENAGA BAHAN 251,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 75,000.00 1,500.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.0010 120,000.00 120.00
JUMLAH TENAGA KERJA 21,820.00
B BAHAN
Kunci slot stainless stell bh 1.000 17,500.00 17,500.00
JUMLAH TENAGA BAHAN 17,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 75,000.00 3,750.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 54,610.00
B BAHAN
Door handle bh 1.000 125,000.00 125,000.00
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 11,450.00
B BAHAN
Door stop bh 1.000 18,000.00 18,000.00
JUMLAH TENAGA BAHAN 18,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 75,000.00 1,125.00
Tukang Kaca L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 16,371.00
B BAHAN
Kaca tebal 5 mm m2 1.100 95,000.00 104,500.00
Sealent bh 0.050 25,000.00 1,250.00
JUMLAH TENAGA BAHAN 104,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.017 75,000.00 1,275.00
Tukang Kayu L.02 OH 0.170 90,000.00 15,300.00
Kepala Tukang L.03 OH 0.017 110,000.00 1,870.00
Mandor L.04 OH 0.0009 120,000.00 108.00
JUMLAH TENAGA KERJA 18,553.00
B BAHAN
Kaca tebal 8 mm m2 1.100 200,000.00 220,000.00
Sealent bh 0.070 25,000.00 1,750.00
JUMLAH TENAGA BAHAN 220,000.00
C. PERALATAN
-
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.025 75,000.00 1,875.00
Tukang Kayu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.00
Mandor L.04 OH 0.0013 120,000.00 156.00
JUMLAH TENAGA KERJA 27,281.00
B BAHAN
Kaca tebal 12 mm m2 1.100 450,000.00 495,000.00
Sealent bh 0.070 25,000.00 1,750.00
JUMLAH TENAGA BAHAN 495,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.075 75,000.00 5,625.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.0040 120,000.00 480.00
JUMLAH TENAGA KERJA 21,255.00
B BAHAN
Kaca patri 5 mm m2 1.100 2,000,000.00 2,200,000.00
Sealent bh 0.050 25,000.00 1,250.00
JUMLAH TENAGA BAHAN 2,200,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 3.300 75,000.00 247,500.00
Tukang batu L.02 OH 1.100 90,000.00 99,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.160 120,000.00 19,200.00
JUMLAH TENAGA KERJA 366,800.00
B BAHAN
Closed duduk ex. AmStand unit 1.000 1,250,000.00 1,250,000.00
Perlengkapan Ls 6%xclosed 75,000.00
JUMLAH TENAGA BAHAN 1,325,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.000 75,000.00 75,000.00
Tukang batu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.150 110,000.00 16,500.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 124,500.00
B BAHAN
Closed jongkok ex. Toto unit 1.000 225,000.00 225,000.00
Semen Portland kg 6.000 1,340.00 8,040.00
Pasir pasang m3 0.010 100,000.00 1,000.00
Batu bata bh 7.000 550.00 3,850.00
JUMLAH TENAGA BAHAN 237,890.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.000 75,000.00 75,000.00
Tukang batu L.02 OH 1.000 90,000.00 90,000.00
Kepala Tukang L.03 OH 0.100 110,000.00 11,000.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 182,000.00
B BAHAN
Urinoir ex. Amstand unit 1.000 1,550,000.00 1,550,000.00
Semen Portland kg 6.000 1,340.00 8,040.00
Pasir pasang m3 0.010 100,000.00 1,000.00
Perlengkapan 30%xurinoir 465,000.00
JUMLAH TENAGA BAHAN 2,024,040.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 75,000.00 90,000.00
Tukang batu L.02 OH 1.450 90,000.00 130,500.00
Kepala Tukang L.03 OH 0.150 110,000.00 16,500.00
Mandor L.04 OH 0.060 120,000.00 7,200.00
JUMLAH TENAGA KERJA 244,200.00
B BAHAN
Wastafel unit 1.000 550,000.00 550,000.00
Semen Portland kg 6.000 1,340.00 8,040.00
Pasir pasang m3 0.010 100,000.00 1,000.00
SANITASI
Perlengkapan 12 x wastafel 412,500.00
JUMLAH TENAGA BAHAN 971,540.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.075 75,000.00 5,625.00
Tukang batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 110,000.00 8,250.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 81,735.00
B BAHAN
Bathube unit 1.000 3,800,000.00 3,800,000.00
Perlengkapan % 20.000 760,000.00
JUMLAH TENAGA BAHAN 4,560,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 75,000.00 22,500.00
Tukang batu L.02 OH 0.450 90,000.00 40,500.00
Kepala Tukang L.03 OH 0.045 110,000.00 4,950.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 69,750.00
B BAHAN
Bak fibreglass unit 1.000 395,000.00 395,000.00
Perlengkapan Ls 12%xbak 47,400.00
JUMLAH TENAGA BAHAN 442,400.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.030 75,000.00 2,250.00
Tukang batu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.030 110,000.00 3,300.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 34,350.00
B BAHAN
Bak cuci piring stainless Steel unit 1.000 1,240,000.00 1,240,000.00
Waterdrain unit 1.000 25,000.00 25,000.00
JUMLAH TENAGA BAHAN 1,265,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 120,000.00 600.00
SANITASI
JUMLAH TENAGA KERJA 11,450.00
B BAHAN
Floor drain unit 1.000 125,000.00 125,000.00
JUMLAH TENAGA BAHAN 125,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.054 75,000.00 4,050.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 110,000.00 990.00
Mandor L.04 OH 0.027 120,000.00 3,240.00
JUMLAH TENAGA KERJA 16,380.00
B BAHAN
Pipa galvanis 1/2" m 1.200 20,000.00 24,000.00
Perlenglapan Ls 35%xpipa 7,000.00
JUMLAH TENAGA BAHAN 24,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 75,000.00 750.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.040 110,000.00 4,400.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 14,750.00
B BAHAN
Kran air ex. onda m 1.000 55,000.00 55,000.00
Sealtape Buah 0.025 3,000.00 75.00
JUMLAH TENAGA BAHAN 55,075.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.054 75,000.00 4,050.00
Tukang batu L.02 OH 0.090 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.009 110,000.00 990.00
Mandor L.04 OH 0.027 120,000.00 3,240.00
JUMLAH TENAGA KERJA 16,380.00
B BAHAN
Pipa galvanis 3/4" m 1.200 25,000.00 30,000.00
Perlengkapan Ls 35%xpipa 8,750.00
JUMLAH TENAGA BAHAN 30,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.036 75,000.00 2,700.00
Tukang batu L.02 OH 0.060 90,000.00 5,400.00
SANITASI
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 9,000.00
B BAHAN
Pipa PVC tipe AW 1/2" m 1.200 4,250.00 5,100.00
Perlengkapan Ls 35%xpipa 1,487.50
JUMLAH TENAGA BAHAN 5,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.036 75,000.00 2,700.00
Tukang batu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 9,000.00
B BAHAN
Pipa PVC tipe AW 3/4" m 1.200 5,500.00 6,600.00
Perlengkapan Ls 35%xpipa 1,925.00
JUMLAH TENAGA BAHAN 6,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.081 75,000.00 6,075.00
Tukang batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.0135 110,000.00 1,485.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 20,190.00
B BAHAN
Pipa PVC tipe AW 3/4" m 1.200 18,750.00 22,500.00
Perlengkapan Ls 35%xpipa 6,562.50
JUMLAH TENAGA BAHAN 22,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.081 75,000.00 6,075.00
Tukang batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.0135 110,000.00 1,485.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 20,190.00
B BAHAN
Pipa PVC tipe AW 3/4" m 1.200 29,000.00 34,800.00
Perlengkapan Ls 35%xpipa 10,150.00
JUMLAH TENAGA BAHAN 34,800.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
SANITASI
A. TENAGA
Pekerja L.01 OH 0.380 75,000.00 28,500.00
Tukang batu L.02 OH 0.190 90,000.00 17,100.00
Kepala Tukang L.03 OH 0.019 110,000.00 2,090.00
Mandor L.04 OH 0.019 120,000.00 2,280.00
JUMLAH TENAGA KERJA 49,970.00
B BAHAN
Buis beton dia. 40 bh 1.100 150,000.00 165,000.00
Batu bata m3 0.550 550.00 302.50
Semen Portland kg 10.300 1,340.00 13,802.00
Pasir pasang m3 0.061 100,000.00 6,100.00
Pasir urug m3 0.069 80,000.00 5,520.00
JUMLAH TENAGA BAHAN 165,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
SANITASI
HARGA SATUAN PEKERJAAN LAIN-LAIN
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 75,000.00 15,000.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 62,600.00
B BAHAN
Smartruss C 75.80 m 1.488 18,833.33 28,024.00
Smartruss C 75.75 m 2.232 12,666.67 28,272.00
Reng AZ 0,55mm x 6m m 5.400 6,000.00 32,400.00
Srew bh 38.000 165.00 6,270.00
Dynabolt bh 1.600 1,000.00 1,600.00
Valery Gutter Talang Jurai m 0.124 39,000.00 4,836.00
JUMLAH TENAGA BAHAN 101,402.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 75,000.00 26,250.00
Tukang L.02 OH -
Kepala Tukang L.03 OH -
Mandor L.04 OH 0.018 120,000.00 2,100.00
JUMLAH TENAGA KERJA 28,350.00
B BAHAN
Persegi panjang t. 8 cm bh 44.000 2,102.27 92,500.00
Pasir m3 0.100 80,000.00 8,000.00
JUMLAH TENAGA BAHAN 100,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 75,000.00 26,250.00
Tukang L.02 OH - -
Kepala Tukang L.03 OH - -
Mandor L.04 OH 0.018 120,000.00 2,100.00
JUMLAH TENAGA KERJA 28,350.00
B BAHAN
Persegi panjang t. 8 cm bh 44.000 2,386.36 105,000.00
Pasir m3 0.100 80,000.00 8,000.00
JUMLAH TENAGA BAHAN 113,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
TAKSIR
4. Pemasangan 1 m2 paving blok segienam t. 8 cm mutu K200
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 75,000.00 26,250.00
Tukang L.02 OH - -
Kepala Tukang L.03 OH - -
Mandor L.04 OH 0.018 120,000.00 2,100.00
JUMLAH TENAGA KERJA 28,350.00
B BAHAN
Paving blok segienam t. 8 cm bh 37.000 2,500.00 92,500.00
Pasir m3 0.100 80,000.00 8,000.00
JUMLAH TENAGA BAHAN 100,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 75,000.00 26,250.00
Tukang L.02 OH - -
Kepala Tukang L.03 OH - -
Mandor L.04 OH 0.018 120,000.00 2,100.00
JUMLAH TENAGA KERJA 28,350.00
B BAHAN
Paving blok segienam t. 8 cm bh 37.000 2,837.84 105,000.00
Pasir m3 0.100 80,000.00 8,000.00
JUMLAH TENAGA BAHAN 113,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang L.02 OH 0.1350 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.0135 110,000.00 1,485.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 14,235.00
B BAHAN
NYM 2 x 2,5 mm2 m 15.000 9,000.00 135,000.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 47,250.00
JUMLAH TENAGA BAHAN 182,250.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
TAKSIR
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH -
Tukang L.02 OH 0.1350 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.0135 110,000.00 1,485.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 14,235.00
B BAHAN
NYM 3 x 2,5 mm2 m 15.000 11,400.00 171,000.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 59,850.00
JUMLAH TENAGA BAHAN 230,850.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
15%
TAKSIR