Professional Documents
Culture Documents
PMU-PMKSY-WAPCOS Limited
E. PHYSICAL PROGRESS SHEET
PMU-PMKSY-WAPCOS Limited
(ii) PHYSICAL PROGRESS SHEET (CADWM-Structural Interventions)
(Rs. in Cr., CCA ha)
Whether
Target Progress Percent Progress
on Track
During 2018- During
Sr. No. Major Component
Completion Upto 19 Upto 2018-19
Quantity Total Total
Date (3/18) upto Dec, (3/18) upto
2018 Dec, 2018
1 2 3 4 5 6 7 8 9 10 11
1 OFD works
i Irrigation Field
Channels (ha)
ii Micro-irrigation
iii Piped distribution
network
Total for OFD works
2 Construction of Field
drains
3 Correction of System
deficiency
4 Land Leveling
5 Reclamation of water
logged areas
PMU-PMKSY-WAPCOS Limited
(iii) PHYSICAL PROGRESS SHEET (CADWM-Non-Structural Interventions) (Area in Th.ha.)
Total WUAs Planned- 12 Progress
Sr.No. Upto 03/2018 During 2018-19 as on Cumulative as on Infrastructural Grant Functional Grant
Nos. Area Nos. Area Nos. Area Nos. Nos. Area
1 Formed
2 Registered
3 System handed over
PMU-PMKSY-WAPCOS Limited
(ii) FINANCIAL PROGRESS SHEET (CADWM)
State Share
CA
released Expenditure
released
through during
Total Cost as per MoU during
CA Released As per Budget 2018-19 NABARD 2018-19
dated: 23/02/2018 2018-19
Sr. No. during 2018- from 1/4/18
upto Dec,
19 upto Dec, upto Dec, 2018
2018
2018
Central State Upto Cumulative Central State Total
Cost 2016-17 2017-18
Assistance Share 3/16 upto 3/18 Assistance Share Budget
1
PMU-PMKSY-WAPCOS Limited
PMU-PMKSY-WAPCOS Limited