You are on page 1of 57

G.R. No.

131442 July 10, 2003 The mooring facility would serve as the temporary docking site of NAPOCOR's power barge,
which, due to turbulent waters at its former mooring site in Calapan, Oriental Mindoro, required
BANGUS FRY FISHERFOLK, DIWATA MAGBUHOS, ANGELITA BINAY, ELMA GARCIA, relocation to a safer site like Minolo Cove. The 14.4 megawatts power barge would provide the
VIRGILIO PANGUIO, ARSENIO CASTILLO, ARIEL PANGUIO, ANTONIO PANGUIO, main source of power for the entire province of Oriental Mindoro pending the construction of a
ANTONIO BUNQUIN, GENEROSO BUNQUIN, CHARLIE DIMAYACYAC, RENATO land-based power plant in Calapan, Oriental Mindoro. The ECC for the mooring facility was
PANGUIO, ATILANO BUNQUIN, CARLOS CHAVEZ, JUAN DIMAYACYAC, FILEMON valid for two years counted from its date of issuance or until 30 June 1999. 4
BUNQUIN, MARIO MAGBUHOS, MAURO MAGBUHOS, NORA MAGBUHOS, JEOVILYN,
GENALYN and JORVAN QUIMUEL, minors, represented by their parents FELICIANA and Petitioners, claiming to be fisherfolks from Minolo, San Isidro, Puerto Galera, 5 sought
SABINO QUIMUEL, MARICAR MAGBUHOS, minor, represented by her parents reconsideration of the ECC issuance. RED Principe, however, denied petitioners' plea on 15
CARMELITA and ANTONIO MAGBUHOS, MARLO BINAY, minor, represented by his July 1997. On 21 July 1997, petitioners filed a complaint with the Regional Trial Court of Manila,
parents EFRENITA and CHARLITO BINAY, and the BANGUS, BANGUS FRY and other Branch 7, for the cancellation of the ECC and for the issuance of a writ of injunction to stop the
MARINE LIFE OF MINOLO COVE, petitioners, construction of the mooring facility. Impleaded as defendants were the following: (1)
vs. NAPOCOR, (2) RED Principe, (3) DENR Region IV Technical Director for Environment Oscar
THE HONORABLE ENRICO LANZANAS as Judge of the Regional Trial Court of Manila, Dominguez, (4) Oriental Mindoro Electric Cooperative ("ORMECO"), which is engaged in the
Branch VII, THE DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES — distribution of electricity in Oriental Mindoro, and (5) certain officials of Puerto
Region IV, represented by its Regional Executive Director and its Regional Director for Galera.6 Petitioners subsequently amended their complaint to include as additional defendants
Environment, THE NATIONAL POWER CORPORATION, ORIENTAL MINDORO the elective officials of Oriental Mindoro represented by then Governor Rodolfo G. Valencia.
ELECTRIC COOPERATIVE, PROVINCIAL GOVERNMENT OF ORIENTAL MINDORO, Petitioners further prayed for the demolition of mooring structures that respondents had already
herein represented by GOVERNOR RODOLFO VALENCIA, PUERTO GALERA MAYOR built.
GREGORIO DELGADO, VICE MAYOR ARISTEO ATIENZA, and MEMBERS OF THE
SANGGUNIANG BAYAN OF PUERTO GALERA, JUAN ASCAN, JR., RAFAEL ROMEY, On 28 July 1997, prior to the filing of the amended complaint, the trial court issued a 20-day
CENON SALCEDO, JERRY DALISAY, SIMON BALITAAN, RENATO CATAQUIS, temporary restraining order enjoining the construction of the mooring facility. However, the trial
MARCELINO BANAAG, DANIEL ENRIQUEZ, AMELYN MARCO, GABRIEL ILAGAN, court lifted the same on 6 August 1997 on NAPOCOR's manifestation that the provincial
MUNICIPAL ENGINEER RODEL RUBIO, and MUNICIPAL PLANNING and DEVELOPMENT government of Oriental Mindoro was the one undertaking the construction of the mooring
COORDINATOR WILHELMINA LINESES, respondents. facility.7

CARPIO, J.: On 28 August 1997, before filing their answers, respondents ORMECO and the provincial
officials of Oriental Mindoro moved to dismiss the complaint. These respondents claimed that
The Case petitioners failed to exhaust administrative remedies, rendering the complaint without cause of
action. They also asserted that the Manila RTC has no jurisdiction to enjoin the construction of
This is a petition for review1 of the Order2 dated 7 November 1997 of the Regional Trial Court the mooring facility in Oriental Mindoro, which lies outside the Manila RTC's territorial
of Manila, Branch 7 ("Manila RTC"), dismissing petitioners' complaint for lack of cause of action jurisdiction.
and lack of jurisdiction.
Petitioners opposed the motion on the ground that there was no need to exhaust administrative
The Facts remedies. They argued that the issuance of the ECC was in patent violation of Presidential
Decree No. 1605, 8 Sections 26 and 27 of Republic Act No. 7160,9 and the provisions of DENR
Department Administrative Order No. 96-37 ("DAO 96-37") on the documentation of ECC
On 30 June 1997, Regional Executive Director Antonio G. Principe ("RED Principe") of Region
applications. Petitioners also claimed that the implementation of the ECC was in patent
IV, Department of Environment and Natural Resources ("DENR"), issued an Environmental
Clearance Certificate ("ECC") in favor of respondent National Power Corporation violation of its terms.
("NAPOCOR"). The ECC authorized NAPOCOR to construct a temporary mooring facility in
Minolo Cove, Sitio Minolo, Barangay San Isidro, Puerto Galera, Oriental Mindoro. The In its order of 7 November 1997, the trial court granted the motion and dismissed petitioners'
Sangguniang Bayan of Puerto Galera has declared Minolo Cove, a mangrove area and complaint.
breeding ground for bangus fry, an eco-tourist zone.3
1
Hence, this petition. Furthermore, we find the issuance of the preliminary injunction directed against the
Provincial Sheriff of Negros Occidental a jurisdictional paux [sic] pas (from Black
The Ruling of the Trial Court Dictionary means jurisdictional falsity) as the Courts of First Instance now Regional
Trial Court[s], can only enforce their writs of injunction within their respective
designated territories.
The trial court's order dismissing the complaint reads in part:

After careful evaluation and analysis, this Court finds the Motion to Dismiss tenable And finally, this Court is not unmindful of the relevant and square application in the
and meritorious. case at bar of Presidential Decree No. 1818, Executive Order No. 380 dated November
27, 1989, and Circular No. 2-91 of the Supreme Court that the National Power
Corporation (NPC) is a public utility, created under special legislation, engaged in the
Petitioners have clearly failed to exhaust all administrative remedies before taking this generation and distribution of electric power and energy. The mooring site of NPC in
legal action in Court x x x. Puerto Galera, Oriental Mindoro is one of its infrastructure projects falling within the
mantle of Executive Order No. 380, November 27, 1989 x x x.
It is x x x worth mentioning that the decision of the Regional Director may still be x x x
elevated to the Office of the Secretary of the DENR to fully comply with the process of And as held by the Supreme Court in the case of National Power Corporation vs.
exhaustion of administrative remedies. And well settled is the rule in our jurisdiction Honorable Abraham P. Vera, et al., 170 SCRA 721, courts are without jurisdiction to
that before bringing an action in or resorting to the Courts of Justice, all remedies of issue injunctive writs against [the] National Power Corporation. The latter enjoys the
administrative character affecting or determinative of the controversy at that level protective mantle of P.D. 1818, (Circular No. 2-91).
should first be exhausted by the aggrieved party (Pestanas vs. Dyogi, L-25786,
February 27, 1978). And petitioners' failure to exhaust administrative remedies renders
his [sic] petition dismissible (Chia vs. Acting Collector of Customs, 177 SCRA 755). xxx xxx xxx
And a dismissal on the ground of failure to exhaust administrative remedies is
tantamount to a dismissal based on lack of cause of action (Baguiro vs. Basa, Jr., 214 Injunction in this case is not a mere ancillary [sic] writ but the main action itself together
SCRA 437; Pineda vs. CFI of Davao, 111 Phil. 643; Sarabia vs. Secretary of with the Annulment of the Environmental Clearance Certificate (ECC). Even assuming
Agriculture & Natural Resources, L-16002, May 23, 1961; Gone, et al. vs. District arguendo that the court [can] annul the ECC how can the latter enforce the same
Engineer, et. al., L-22782, August 29, 1975; Abe-Abe, et al. vs. Manta, et. al., L-4827, against the Provincial Government of Oriental Mindoro which was impleaded by the
May 31, 1979) although it does not affect the jurisdiction of the court over the subject petitioners as a necessary party together with the Oriental Mindoro Electric
matter (Mun. of La Trinidad, et al. vs. CFI of Baguio-Benguet, et al., L-33889, June 28, Cooperative and the government officials of Puerto Galera, Oriental Mindoro, whose
1983). acts and functions are being performed outside the territorial jurisdiction of this court?
x x x Indisputably, the injunction and annulment of ECC as prayed for in the petition
are inseparable x x x.
Moreover, this Court finds the Opposition of the Petitioners highly untenable and bereft
of merits that the controverted act in question is patently illegal and there was an
immediate need for judicial intervention. The conclusion, therefore, is inescapable that petitioners have failed to exhaust all the
available administrative remedies and this Court has no jurisdiction to issue the
injunctive writ prayed for in the Amended [Complaint].10
The ECC in question was issued by the Regional Office of the DENR which has
jurisdiction and authority over the same . . .. And corollary to this, the issue as to
whether or not the Minolo Cove is within the enclosed coves and waters embraced by The Issue
Puerto Galera bay and protected by Medio island is a clear question of fact which the
DENR may appropriately resolve before resorting to [the] Court[s]. The issue is whether the trial court erred in dismissing petitioners' complaint for lack of cause
action and lack of jurisdiction.
This Court is likewise aware and cognizant of its territorial jurisdiction in the
enforcement of Writ of Injunction. That truly, [a] writ of injunction can only be enforced The Ruling of the Court
within [the] territorial jurisdiction of this Court but not for acts which are being or about
to be committed outside its territorial jurisdiction. Thus, in Philippine National Bank vs. The petition has no merit.
Pineda, 197 SCRA 1, the Honorable Supreme Court ruled: "Regional Trial Courts can
only enforce their writs of injunction within their respective designated territories.
Jurisdiction of the Manila RTC over the Case the construction of the mooring facility could not proceed without a valid ECC, the validity of
the ECC remains the determinative issue in resolving petitioners' complaint.
Jurisdiction over the subject matter of a case is conferred by law. Such jurisdiction is
determined by the allegations in the complaint, irrespective of whether the plaintiff is entitled to Exhaustion of Administrative Remedies
all or some of the reliefs sought.11
The settled rule is before a party may seek the intervention of the courts, he should first avail
A perusal of the allegations in the complaint shows that petitioners' principal cause of action is of all the means afforded by administrative processes. Hence, if a remedy within the
the alleged illegality of the issuance of the ECC. The violation of laws on environmental administrative machinery is still available, with a procedure prescribed pursuant to law for an
protection and on local government participation in the implementation of environmentally administrative officer to decide the controversy, a party should first exhaust such remedy before
critical projects is an issue that involves the validity of NAPOCOR's ECC. If the ECC is void, resorting to the courts. The premature invocation of a court's intervention renders the complaint
then as a necessary consequence, NAPOCOR or the provincial government of Oriental without cause of action and dismissible on such ground.16
Mindoro could not construct the mooring facility. The subsidiary issue of non-compliance with
pertinent local ordinances in the construction of the mooring facility becomes immaterial for RED Principe of the DENR Region IV Office issued the ECC based on (1) Presidential Decree
purposes of granting petitioners' main prayer, which is the annulment of the ECC. Thus, if the No. 1586 ("PD No. 1586") and its implementing rules establishing the Environmental Impact
court has jurisdiction to determine the validity of the issuance of the ECC, then it has jurisdiction Statement System, (2) DAO 96-3717 and (3) the Procedural Manual of DAO 96-37. Section
to hear and decide petitioners' complaint. 418 of PD No. 1586 requires a proponent of an environmentally critical project, or a project
located within an environmentally critical area as declared by the President, to secure an ECC
Petitioners' complaint is one that is not capable of pecuniary estimation. It falls within the prior to the project's operation.19 NAPOCOR thus secured the ECC because the mooring
exclusive and original jurisdiction of the Regional Trial Courts under Section 19(1) of Batas facility in Minolo Cove, while not an environmentally critical project, is located within an
Pambansa Blg. 129, as amended by Republic Act No. 7691. The question of whether environmentally critical area under Presidential Proclamation No. 2146, issued on 14
petitioners should file their complaint in the Regional Trial Court of Manila or Oriental Mindoro December 1981.20
then becomes a matter of venue, to be determined by the residence of the parties. 12
The rules on administrative appeals from rulings of the DENR Regional Directors on the
Petitioners' main prayer is the annulment of the ECC. The principal respondent, DENR Region implementation of PD No. 1586 are found in Article VI of DAO 96-37, which provides:
IV, has its main office at the L & S Building, Roxas Boulevard, Manila. Regional Executive
Director Principe of the DENR Region IV, who issued the ECC, holds office there. Plainly, the SECTION 1.0. Appeal to the Office of the Secretary. — Any party aggrieved by the
principal respondent resides in Manila, which is within the territorial jurisdiction of the Manila final decision of the RED may, within 15 days from receipt of such decision, file an
RTC. Thus, petitioners filed their complaint in the proper venue. appeal with the Office of the Secretary. The decision of the Secretary shall be
immediately executory.
On the other hand, the jurisdiction of Regional Trial Courts to issue injunctive writs is limited to
acts committed or about to be committed within their judicial region. 13 Moreover, Presidential SECTION 2.0. Grounds for Appeal. — The grounds for appeal shall be limited to grave
Decree No. 1818 ("PD No. 1818") prohibited14 courts from issuing injunctive writs against abuse of discretion and serious errors in the findings of fact which would cause grave
government infrastructure projects like the mooring facility in the present case. Republic Act or irreparable injury to the aggrieved party. Frivolous appeals shall not be
No. 8975 ("RA No. 8975"), which took effect on 26 November 2000, superseded PD No. 1818 countenanced.
and delineates more clearly the coverage of the prohibition, reserves the power to issue such
writs exclusively with this Court, and provides penalties for its violation. 15 Obviously, neither the SECTION 3.0. Who May Appeal. — The proponent or any stakeholder, including but
Manila RTC nor the Oriental Mindoro RTC can issue an injunctive writ to stop the construction
not limited to, the LGUs concerned and affected communities, may file an appeal.
of the mooring facility. Only this Court can do so under PD No. 1818 and later under RA No.
8975. Thus, the question of whether the Manila RTC has jurisdiction over the complaint
considering that its injunctive writ is not enforceable in Oriental Mindoro is academic. The DENR Procedural Manual for DAO 96-37 explains these provisions thus:

Clearly, the Manila RTC has jurisdiction to determine the validity of the issuance of the ECC, Final decisions of the RED may be appealed. These decisions include those relating
although it could not issue an injunctive writ against the DENR or NAPOCOR. However, since to the issuance or non-issuance of an ECC, and the imposition of fines and penalties.
3
By inference, the decision of the Secretary on the issuance or non-issuance of the ECC commercial wharfs [sic]; commercial docking within the enclosed coves of Puerto
may also be appealed based on this provision. Resort to courts prior to availing of this Galera; the destruction of its mangrove stands; the devastation of its corals and
remedy would make the appellant's action dismissible on the ground of non-exhaustion coastline by large barges, motorboats, tugboat propellers, and any form of destruction
of administrative remedies. by other human activities are hereby prohibited.

The right to appeal must be exercised within 15 days from receipt by the aggrieved Section 2. x x x
party of such decision. Failure to file such appeal within the requisite period will result
in the finality of the RED's or Secretary's decision(s), which can no longer be disturbed. No permit for the construction of any wharf, marina, hotel, restaurants and other
commercial structures in Puerto Galera shall be issued without prior approval of the
An appeal shall not stay the effectivity of the RED's decision, unless the Secretary Office of the President upon the recommendation of the Philippine Tourism Authority.
directs otherwise. (Emphasis supplied)

The right to appeal does not prevent the aggrieved party from first resorting to the filing NAPOCOR claims that since Minolo Cove lies outside of "Puerto Galera Bay as protected by
of a motion for reconsideration with the RED, to give the RED an opportunity to re- Medio Island",24 PD No. 1605 does not apply to this case. However, petitioners assert that
evaluate his decision. (Emphasis added) Minolo Cove is one of the "enclosed coves of Puerto Galera"25 and thus protected under PD
No. 1605. This is a question of fact that the DENR Secretary should have first resolved. In any
Instead of following the foregoing procedure, petitioners bypassed the DENR Secretary and event, there is no dispute that NAPOCOR will use the mooring facility for its power barge that
immediately filed their complaint with the Manila RTC, depriving the DENR Secretary the will supply 14.4 megawatts of electricity to the entire province of Oriental Mindoro, including
opportunity to review the decision of his subordinate, RED Principe. Under the Procedural Puerto Galera. The mooring facility is obviously a government-owned public infrastructure
Manual for DAO 96-37 and applicable jurisprudence, petitioners' omission renders their intended to serve a basic need of the people of Oriental Mindoro. The mooring facility is not a
complaint dismissible for lack of cause of action.21 Consequently, the Manila RTC did not err in "commercial structure; commercial or semi-commercial wharf or commercial docking" as
dismissing petitioners' complaint for lack of cause of action. contemplated in Section 1 of PD No. 1605. Therefore, the issuance of the ECC does not violate
PD No. 1605 which applies only to commercial structures like wharves, marinas, hotels and
On the Alleged Patent Illegality of the ECC restaurants.

Sections 26 and 27 of RA No. 7160


Petitioners nevertheless contend that they are exempt from filing an appeal with the DENR
Secretary because the issuance of the ECC was in patent violation of existing laws and
regulations. These are (1) Section 1 of Presidential Decree No. 1605, as amended, (2) Sections Congress introduced Sections 26 and 27 in the Local Government Code to emphasize the
26 and 27 of Republic Act No. 7160 (Local Government Code of 1991), and (3) the provisions legislative concern "for the maintenance of a sound ecology and clean environment."26 These
of DAO 96-37 on the documentary requirements for the zoning permit and social acceptability provisions require every national government agency or government-owned and controlled
of the mooring facility. corporation to hold prior consultations with the local government unit concerned and to secure
the prior approval of its sanggunian before implementing "any project or program that may
Petitioners' contention is without merit. While the patent illegality of an act exempts a party from cause pollution, climatic change, depletion of non-renewable resources, loss of cropland,
rangeland, or forest cover and extinction of animal or plant species." Sections 26 and 27
complying with the rule on exhaustion Of administrative remedies,22 this does not apply in the
respectively provide:
present case.

Presidential Decree No. 1605 Section 26. Duty of National Government Agencies in the Maintenance of Ecological
Balance. — It shall be the duty of every national agency or government-owned or
controlled corporation authorized or involved in the planning and implementation of any
Presidential Decree No. 1605 ("PD No. 1605"),23 as amended by Presidential Decrees Nos. project or program that may cause pollution, climatic change, depletion of non-
1605-A and 1805, declares as ecologically threatened zone "the coves and waters embraced renewable resources, loss of crop land, rangeland, or forest cover and extinction of
by Puerto Galera Bay as protected by Medio Island." This decree provides in part: animal or plant species, to consult with the local government units, non-governmental
organizations, and other sectors concerned and explain the goals and objectives of the
Section 1. Any provision of law to the contrary notwithstanding, the construction of project or program, its impact upon the people and the community in terms of
marinas, hotels, restaurants, other commercial structures; commercial or semi-
environmental or ecological balance, and the measures that will be undertaken to of a locational clearance or zoning certificate. Petitioners assert that this omission renders the
prevent or minimize the adverse effects thereof. issuance of the ECC patently illegal.

Section 27. Prior Consultations Required. — No project or program shall be The contention is also without merit. While such documents are part of the submissions
implemented by government authorities unless the consultations mentioned in Section required from a project proponent, their mere absence does not render the issuance of the
. . . 26 hereof are complied with, and prior approval of the sanggunian concerned is ECC patently illegal. To justify non-exhaustion of administrative remedies due to the patent
obtained: Provided, That occupants in areas where such projects are to be illegality of the ECC, the public officer must have issued the ECC "[without any] semblance of
implemented shall not be evicted unless appropriate relocation sites have been compliance, or even an attempt to comply, with the pertinent laws; when manifestly, the officer
provided, in accordance with the provisions of the Constitution. has acted without jurisdiction or has exceeded his jurisdiction, or has committed a grave abuse
of discretion; or when his act is clearly and obviously devoid of any color of authority." 30
In Lina, Jr. v. Paño,27 the Court interpreted these provisions in this manner:
RED Principe, as chief of DENR Region IV, is the officer duly authorized under DAO 96-3731 to
Section 27 of the Code should be read in conjunction with Section 26 thereof x x x. issue ECCs for projects located within environmentally critical areas. RED Principe issued the
ECC on the recommendation of Amelia Supetran, the Director of the Environmental
Management Bureau. Thus, RED Principe acted with full authority pursuant to DENR
Thus, the projects and programs mentioned in Section 27 should be interpreted to
regulations. Moreover, the legal presumption is that he acted with the requisite authority.32 This
mean projects and programs whose effects are among those enumerated in Sections
clothes RED Principe's acts with presumptive validity and negates any claim that his actions
26 and 27, to wit, those that: (1) may cause pollution; (2) may bring about climatic
change; (3) may cause the depletion of non-renewable resources; (4) may result in are patently illegal or that he gravely abused his discretion. While petitioners may present proof
loss of crop land, rangeland, or forest cover; (5) may eradicate certain animal or plant to the contrary, they must do so before the proper administrative forum before resorting to
judicial remedies.
species; and (6) other projects or programs that may call for the eviction of a particular
group of people residing in the locality where these will be implemented.
On the Alleged Non-Compliance with the Terms of the ECC
Again, Sections 26 and 27 do not apply to this case because as petitioners admit,28 the mooring
facility itself is not environmentally critical and hence does not belong to any of the six types of Lastly, petitioners claim that they are justified in immediately seeking judicial recourse because
projects mentioned in the law. There is no statutory requirement for the NAPOCOR is guilty of violating the conditions of the ECC, which requires it to secure a separate
concerned sanggunian to approve the construction of the mooring facility. It is another matter ECC for the operation of the power barge. The ECC also mandates NAPOCOR to secure the
if the operation of the power barge is at issue. As an environmentally critical project that causes usual local government permits, like zoning and building permits, from the municipal
pollution, the operation of the power barge needs the prior approval of the government of Puerto Galera.
concerned sanggunian. However, what is before this Court is only the construction of the
mooring facility, not the operation of the power barge. Thus, the issuance of the ECC does not The contention is similarly without merit. The fact that NAPOCOR's ECC is subject to
violate Sections 26 and 27 of RA No. 7160. cancellation for non-compliance with its conditions does not justify petitioners' conduct in
ignoring the procedure prescribed in DAO 96-37 on appeals from the decision of the DENR
Documentary Requirements for ECC Applications Executive Director. Petitioners vigorously insist that NAPOCOR should comply with the
requirements of consultation and locational clearance prescribed in DAO 96-37. Ironically,
petitioners themselves refuse to abide with the procedure for filing complaints and appealing
Under DAO 96-37, an ECC applicant for a project located within an environmentally critical
decisions laid down in DAO 96-37.
area is required to submit an Initial Environment Examination, which must contain a brief
description of the environmental setting and a documentation of the consultative process
undertaken, when appropriate.29 As part of the description of the environmental setting, the DAO 96-37 provides for a separate administrative proceeding to address complaints for the
ECC applicant must submit a certificate of locational clearance or zoning certificate. cancellation of an ECC. Under Article IX of DAO 96-37, complaints to nullify an ECC must
undergo an administrative investigation, after which the hearing officer will submit his report to
the EMB Director or the Regional Executive Director, who will then render his decision. The
Petitioners further contend that NAPOCOR, in applying for the ECC, did not submit to the
aggrieved party may file an appeal to the DENR Secretary, who has authority to issue cease
DENR Region IV Office the documents proving the holding of consultations and the issuance
and desist orders. Article IX also classifies the types of violations covered under DAO 96-37,
5
including projects operating without an ECC or violating the conditions of the ECC. This is the (a) The zero release assumption, which was designed for the limited purpose of individual
applicable procedure to address petitioners' complaint on NAPOCOR's alleged violations and licensing decisions and which is but a single figure in Table S-3, is within the bounds of
not the filing of the instant case in court. reasoned decisionmaking required by the APA. The NRC, in its statement announcing the final
Table S-3 rule, summarized the major uncertainties of long-term storage of nuclear wastes,
A Final Word noted that the probability of intrusion was small, and found the evidence "tentative but
favorable" that an appropriate storage site
The Court commends petitioners for their courageous efforts to safeguard and maintain the
ecological balance of Minolo Cove. This Court recognizes the utmost importance of protecting Page 462 U. S. 88
the environment.33 Indeed, we have called for the vigorous prosecution of violators of
environmental laws.34 Legal actions to achieve this end, however, must be done in accordance could be found. Table S-3 refers interested persons to staff studies that discuss the
with established rules of procedure that were intended, in the first place, to achieve orderly and uncertainties in greater detail. In these circumstances, the NRC complied with NEPA's
efficient administration of justice. requirements of consideration and disclosure of the environmental impacts of its licensing
decisions. It is not the task of this Court to determine what decision it would have reached if it
WHEREFORE, we DENY the petition for lack of merit. had been the NRC. The Court's only task is to determine whether the NRC had considered the
relevant factors and articulated a rational connection between the facts found and the choice
made. Under this standard, the zero release assumption, within the context of Table S-3 as a
SO ORDERED.
whole, was not arbitrary or capricious. Pp. 462 U. S. 97-106.
U.S. Supreme Court Baltimore G. & E. Co. v. NRDC, 462 U.S. 87 (1983)
Baltimore Gas & Electric Co. v. Natural Resources Defense Council, Inc. (b) It is inappropriate to cast doubt on the licensing proceedings simply because of a minor
No. 82-524 Argued April 19, 1983 ambiguity in the language of an earlier rule as to whether licensing boards were required to
Decided June 6, 1983462 U.S. 87 462 U.S. 87 consider health effects, socioeconomic effects, or cumulative impacts, where there is no
CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR evidence that this ambiguity prevented any party from making as full a presentation as desired
THE DISTRICT OF COLUMBIA CIRCUIT or ever affected the decision to license a plant. Pp. 462 U.S. 106-108.

Syllabus 222 U.S.App.D.C. 9, 685 F.2d 459, reversed.

Section 102(2)(C) of the National Environmental Policy Act (NEPA) requires federal agencies O'CONNOR, J., delivered the opinion of the Court, in which all other Members joined, except
POWELL, J., who took no part in the consideration or decision of the cases.
to consider the environmental impact of any major federal action. The dispute in these cases
concerns the adoption by the Nuclear Regulatory Commission (NRC) of a series of generic
rules to evaluate the environmental effects of a nuclear powerplant's fuel cycle. In these rules, Page 462 U. S. 89
the NRC decided that licensing boards should assume, for purposes of NEPA, that the
permanent storage of certain nuclear wastes would have no significant environmental impact JUSTICE O'CONNOR delivered the opinion of the Court.
(the so-called "zero release" assumption), and thus should not affect the decision whether to
license a particular nuclear powerplant. At the heart of each rule is Table S-3, a numerical Section 102(2)(C) of the National Environmental Policy Act of 1969, 83 Stat. 853, 42 U.S.C. §
compilation of the estimated resources used and effluents released by fuel cycle activities 4332(2)(C) (NEPA), requires federal agencies to consider the environmental impact of any
supporting a year's operation of a typical light-water reactor. Challenges to the rules ultimately major federal action. [Footnote 1] As part of its generic rulemaking proceedings to evaluate the
resulted in a decision by the Court of Appeals, on a petition for review of the final version of the environmental effects of the nuclear fuel cycle for nuclear powerplants, the Nuclear
rules, that the rules were arbitrary and capricious and inconsistent with NEPA because the
NRC had not factored the consideration of uncertainties surrounding the zero release
Page 462 U. S. 90
assumption into the licensing process in such a manner that the uncertainties could potentially
affect the outcome of any decision to license a plant.
Regulatory Commission (Commission) [Footnote 2] decided that licensing boards should
assume, for purposes of NEPA, that the permanent storage of certain nuclear wastes would
Held: The NRC complied with NEPA, and its decision is not arbitrary or capricious within the
have no significant environmental impact, and thus should not affect the decision whether to
meaning of § 10(e) of the Administrative Procedure Act (APA). Pp. 462 U. S. 97-108.
license a particular nuclear powerplant. We conclude that the Commission complied with
NEPA, and that its decision is not arbitrary or capricious within the meaning of § 10(e) of the on the ground that the record on waste storage was inadequate to support the zero release
Administrative Procedure Act (APA), 5 U.S.C. § 706. [Footnote 3] assumption. Id. at 361, 547 F.2d at 658.

I In Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.
S. 519 (1978), this Court unanimously reversed the Court of Appeals' decision that the
The environmental impact of operating a light-water nuclear powerplant [Footnote 4]includes Commission had used inadequate procedures, finding that the Commission had done all that
the effects of off-site activities necessary to provide fuel for the plant ("front end" activities), and was required by NEPA and the APA and determining that courts generally lack the authority to
of off-site activities necessary to dispose of the highly toxic and long-lived nuclear wastes impose "hybrid" procedures greater than those contemplated by the governing statutes. We
generated by the plant ("back end" activities). The dispute in these cases concerns remanded for review of whether the original rule was adequately supported by the
administrative record, specifically
Page 462 U. S. 91
Page 462 U. S. 93
the Commission's adoption of a series of generic rules to evaluate the environmental effects of
a nuclear powerplant's fuel cycle. At the heart of each rule is Table S-3, a numerical compilation stating that the court was free to agree or disagree with Judge Tamm's conclusion that the rule
of the estimated resources used and effluents released by fuel cycle activities supporting a pertaining to the "back end" of the fuel cycle was arbitrary and capricious within the meaning
year's operation of a typical light-water reactor. [Footnote 5] The three versions of Table S-3 of § 10(e) of the APA, 5 U.S.C. § 706. Id. at 536, n. 14.
contained similar numerical values, although the supporting documentation has been amplified
during the course of the proceedings. While Vermont Yankee was pending in this Court, the Commission proposed a new "interim"
rulemaking proceeding to determine whether to adopt a revised Table S-3. The proposal
The Commission first adopted Table S-3 in 1974, after extensive informal rulemaking explicitly acknowledged that the risks from long-term repository failure were uncertain, but
proceedings. 39 Fed.Reg. 14188 et seq. (1974). This "original" rule, as it later came to be suggested that research should resolve most of those uncertainties in the near future. 41
described, declared that in environmental reports and impact statements for individual licensing Fed.Reg. 45850-45851 (1976). After further proceedings, the Commission promulgated the
proceedings the environmental costs of the fuel cycle "shall be as set forth" in Table S-3, and interim rule in March 1977. Table S-3 now explicitly stated that solidified high-level and
that "[n]o further discussion of such environmental effects shall be required." Id. at 14191. transuranic wastes would remain buried in a federal repository, and therefore would have no
[Footnote 6] The original Table S-3 contained no numerical entry for the long-term effect on the environment. 42 Fed.Reg. 13807 (1977). Like its predecessor, the interim rule
stated that "[n]o further discussion of such environmental effects shall be required." Id. at
13806. The NRDC petitioned for review of the interim rule, challenging the zero release
Page 462 U. S. 92
assumption and faulting the Table S-3 rule for failing to consider the health, cumulative, and
socioeconomic effects of the fuel cycle activities. The Court of Appeals stayed proceedings
environmental effects of storing solidified transuranic and high-level wastes, [Footnote 7] while awaiting this Court's decision in Vermont Yankee. In April, 1978, the Commission
because the Commission staff believed that technology would be developed to isolate the amended the interim rule to clarify that health effects were not covered by Table S-3 and could
wastes from the environment. The Commission and the parties have later termed this be litigated in individual licensing proceedings. 43 Fed.Reg. 15613 et seq. (1978).
assumption of complete repository integrity as the "zero release" assumption: the
reasonableness of this assumption is at the core of the present controversy.
In 1979, following further hearings, the Commission adopted the "final" Table S-3 rule. 44
Fed.Reg. 45362 et seq. (1979). Like the amended interim rule, the final rule expressly stated
The Natural Resources Defense Council (NRDC), a respondent in the present cases, that Table S-3 should be supplemented in individual proceedings by evidence about the health,
challenged the original rule and a license issued under the rule to the Vermont Yankee Nuclear socioeconomic, and cumulative aspects of fuel cycle activities. The Commission also continued
Power Corp. The Court of Appeals for the District of Columbia Circuit affirmed Table S-3's to adhere to the zero release
treatment of the "front end" of the fuel cycle, but vacated and remanded the portion of the rule
relating to the "back end" because of perceived inadequacies in the rulemaking
procedures. Natural Resources Defense Council, Inc. v. NRC, 178 U.S.App.D.C. 336, 547 Page 462 U. S. 94
F.2d 633 (1976). Judge Tamm disagreed that the procedures were inadequate, but concurred

7
assumption that the solidified waste would not escape and harm the environment once the action. If the zero release assumption is taken as a finding that long-term storage poses no
repository was sealed. It acknowledged that this assumption was uncertain because of the significant environmental
remote possibility that water might enter the repository, dissolve the radioactive materials, and
transport them to the biosphere. Nevertheless, the Commission predicted that a bedded-salt Page 462 U. S. 96
repository would maintain its integrity, and found the evidence "tentative but favorable" that an
appropriate site would be found. Id. at 45368. The Commission ultimately determined that any
risk, which the court acknowledged may not have been the Commission's intent, it found that
undue optimism in the assumption of appropriate selection and perfect performance of the
the assumption represents a self-evident error in judgment, and is thus arbitrary and capricious.
repository is offset by the cautious assumption, reflected in other parts of the Table, that all As the evidence in the record reveals and the Commission itself acknowledged, the zero
radioactive gases in the spent fuel would escape during the initial 6- to 20-year period that the release assumption is surrounded with uncertainty.
repository remained open, ibid., and thus did not significantly reduce the overall conservatism
of Table S-3. Id. at 45369.
Alternatively, reasoned the Court of Appeals, the zero release assumption could be
characterized as a decisionmaking device whereby the Commission, rather than individual
The Commission rejected the option of expressing the uncertainties in Table S-3 or permitting licensing boards, would have sole responsibility for considering the risk that long-lived wastes
licensing boards, in performing the NEPA analysis for individual nuclear plants, to consider will not be disposed of with complete success. The court recognized that the Commission could
those uncertainties. It saw no advantage in reassessing the significance of the uncertainties in
use generic rulemaking to evaluate environmental costs common to all licensing decisions.
individual licensing proceedings:
Indeed, the Commission could use generic rulemaking to balance generic costs and benefits
to produce a generic "net value." These generic evaluations could then be considered together
"In view of the uncertainties noted regarding waste disposal, the question then arises whether with case-specific costs and benefits in individual proceedings. The key requirement of NEPA,
these uncertainties can or should be reflected explicitly in the fuel cycle rule. The Commission however, is that the agency consider and disclose the actual environmental effects in a manner
has concluded that the rule should not be so modified. On the individual reactor licensing level, that will ensure that the overall process, including both the generic rulemaking and the
where the proceedings deal with fuel cycle issues only peripherally, the Commission sees no individual proceedings, brings those effects to bear on decisions to take particular actions that
advantage in having licensing boards repeatedly weigh for themselves the effect of significantly affect the environment. The Court of Appeals concluded that the zero release
uncertainties on the selection of fuel cycle impacts for use in cost-benefit balancing. This is a assumption was not in accordance with this NEPA requirement, because the assumption
generic question properly dealt with in the rulemaking as part of choosing what impact values prevented the uncertainties -- which were not found to be insignificant or outweighed by other
should go into the fuel cycle rule. The Commission concludes, having generic benefits -- from affecting any individual licensing decision. Alternatively, by requiring
that the licensing decision ignore factors that are relevant under NEPA, the zero release
Page 462 U. S. 95 assumption is a clear error in judgment, and thus arbitrary and capricious.

noted that uncertainties exist, that, for the limited purpose of the fuel cycle rule, it is reasonable We granted certiorari. 459 U.S. 1034 (1982). We reverse.
to base impacts on the assumption which the Commission believes the probabilities
favor, i.e., that bedded-salt repository sites can be found which will provide effective isolation Page 462 U. S. 97
of radioactive waste from the biosphere."
II
Id. at 45369.
We are acutely aware that the extent to which this Nation should rely on nuclear power as a
The NRDC and respondent State of New York petitioned for review of the final rule. The Court source of energy is an important and sensitive issue. Much of the debate focuses on whether
of Appeals consolidated these petitions for all purposes with the pending challenges to the development of nuclear generation facilities should proceed in the face of uncertainties about
initial and interim rules. [Footnote 8] By a divided panel, [Footnote 9] the court concluded that their long-term effects on the environment. Resolution of these fundamental policy questions
the Table S-3 rules were arbitrary and capricious and inconsistent with NEPA because the lies, however, with Congress and the agencies to which Congress has delegated authority, as
Commission had not factored the consideration of uncertainties surrounding the zero release well as with state legislatures and, ultimately, the populace as a whole. Congress has assigned
assumption into the licensing process in such a manner that the uncertainties could potentially the courts only the limited, albeit important, task of reviewing agency action to determine
affect the outcome of any decision to license a particular plant. Natural Resources Defense whether the agency conformed with controlling statutes. As we emphasized in our earlier
Council, Inc. v. NRC, 222 U.S.App.D.C. 9, 685 F.2d 459 (1982). The court first reasoned that encounter with these very proceedings,
NEPA requires an agency to consider all significant environmental risks from its proposed
"[a]dministrative decisions should be set aside in this context, as in every other, only for the Commission's Statement of Consideration announcing the final Table S-3 rule shows that
substantial procedural or substantive reasons as mandated by statute . . . , not simply because it has digested this mass of material and disclosed all substantial risks. 44 Fed.Reg. 45367-
the court is unhappy with the result reached." 45369 (1979). The Statement summarizes the major uncertainty of long-term storage in
bedded-salt repositories, which is that water could infiltrate the repository as a result of such
Vermont Yankee, 435 U.S. at 435 U. S. 558. diverse factors as geologic faulting, a meteor strike, or accidental or deliberate intrusion by
man. The Commission noted that the probability of intrusion was small, and that the plasticity
of salt would tend to heal some types of intrusions. The Commission also found the evidence
The controlling statute at issue here is NEPA. NEPA has twin aims. First, it "places upon an
agency the obligation to consider every significant aspect of the environmental impact of a "tentative but favorable" that an appropriate site could be found. Table S-3 refers interested
proposed action." Vermont Yankee, supra, at 435 U. S. 553. Second, it ensures that the persons to staff studies that discuss the uncertainties in greater detail. [Footnote 12] Given this
record
agency will inform the public that it has indeed considered environmental concerns in its
decisionmaking process. Weinberger v. Catholic Action of Hawaii/Peace Education
Project, 454 U. S. 139, 454 U. S. 143 (1981). Congress in enacting NEPA, however, did not Page 462 U. S. 100
require agencies to elevate environmental concerns over other appropriate
considerations. See Stryckers' Bay Neighborhood Council v. Karlen, 444 U. S. 223, 444 U. S. and the Commission's statement, it simply cannot be said that the Commission ignored or failed
227 (1980) (per curiam). Rather, it required only that the agency take a "hard look" at the to disclose the uncertainties surrounding its zero release assumption.
environmental consequences before taking a major action. See Kleppe v. Sierra Club, 427 U.
S. 390, 427 U. S. 410, n. 21 (1976). The role of the courts is simply to ensure that the Congress did not enact NEPA, of course, so that an agency would contemplate the
environmental impact of an action as an abstract exercise. Rather, Congress intended that the
Page 462 U. S. 98 "hard look" be incorporated as part of the agency's process of deciding whether to pursue a
particular federal action. It was on this ground that the Court of Appeals faulted the
agency has adequately considered and disclosed the environmental impact of its actions, and Commission's action, for failing to allow the uncertainties potentially to "tip the balance" in a
that its decision is not arbitrary or capricious. See generally Citizens to Preserve Overton Park, particular licensing decision. As a general proposition, we can agree with the Court of Appeals'
Inc. v. Volpe, 401 U. S. 402, 401 U. S. 415-417 (1971). determination that an agency must allow all significant environmental risks to be factored into
the decision whether to undertake a proposed action. We think, however, that the Court of
Appeals erred in concluding that the Commission had not complied with this standard.
In its Table S-3 rule here, the Commission has determined that the probabilities favor the zero
release assumption, because the Nation is likely to develop methods to store the wastes with
no leakage to the environment. The NRDC did not challenge, and the Court of Appeals did not As Vermont Yankee made clear, NEPA does not require agencies to adopt any particular
decide, the reasonableness of this determination, 222 U.S.App.D.C. at 28, n. 96, 685 F.2d at internal decisionmaking structure. Here, the agency has chosen to evaluate generically
478, n. 96, and no party seriously challenges it here. The Commission recognized, however,
that the geological, chemical, physical, and other data it relied on in making this prediction were Page 462 U. S. 101
based, in part, on assumptions which involve substantial uncertainties. Again, no one suggests
that the uncertainties are trivial or the potential effects insignificant if time proves the zero the environmental impact of the fuel cycle and inform individual licensing boards, through the
release assumption to have been seriously wrong. After confronting the issue, though, the Table S-3 rule, of its evaluation. The generic method chosen by the agency is clearly an
Commission has determined that the uncertainties concerning the development of nuclear appropriate method of conducting the "hard look" required by NEPA. See Vermont
waste storage facilities are not sufficient to affect the outcome of any individual licensing Yankee, 435 U.S. at 435 U. S. 535, n. 13. The environmental effects of much of the fuel cycle
decision. [Footnote 10] are not plant-specific, for any plant, regardless of its particular attributes, will create additional
wastes that must be stored in a common long-term repository. Administrative efficiency and
It is clear that the Commission, in making this determination, has made the careful consistency of decision are both furthered by a generic determination of these effects without
consideration and disclosure required by NEPA. The sheer volume of proceedings before the needless repetition of the litigation in individual proceedings, which are subject to review by the
Commission is impressive. [Footnote 11] Of far greater importance, Commission in any event. See generally Ecology Action v. AEC, 492 F.2d 998, 1002, n. 5
(CA2 1974) (Friendly, J.) (quoting Administrative Conference Proposed Recommendation 73-
Page 462 U. S. 99 6).

9
The Court of Appeals recognized that the Commission has discretion to evaluate generically Third, a reviewing court must remember that the Commission is making predictions, within its
the environmental effects of the fuel cycle and require that these values be "plugged into" area of special expertise, at the frontiers of science. When examining this kind of scientific
individual licensing decisions. The court concluded that the Commission nevertheless violated determination, as opposed to simple findings of fact, a reviewing court must generally be at its
NEPA by failing to factor the uncertainty surrounding long-term storage into Table S-3 and most deferential. See, e.g., Industrial Union Dept. v. American Petroleum Institute, 448 U. S.
precluding individual licensing decisionmakers from considering it. 607, 448 U. S. 656 (1980) (plurality opinion); id.at 448 U. S. 705-706 (MARSHALL, J.,
dissenting).
The Commission's decision to affix a zero value to the environmental impact of long-term
storage would violate NEPA, however, only if the Commission acted arbitrarily and capriciously Page 462 U. S. 104
in deciding generically that the uncertainty was insufficient to affect any individual licensing
decision. In assessing whether the Commission's decision is arbitrary and capricious, it is With these three guides in mind, we find the Commission's zero release assumption to be within
crucial to place the zero release assumption in context. Three factors are particularly important. the bounds of reasoned decisionmaking required by the APA. We have already noted that the
First is the Commission's repeated emphasis that the zero release assumption -- and, indeed, Commission's Statement of Consideration detailed several areas of uncertainty, and discussed
all of the Table S-3 rule -- was made for a limited purpose. The Commission expressly noted why they were insubstantial for purposes of an individual licensing decision. The Table S-3 rule
its intention to supplement the rule with an explanatory narrative. [Footnote 13] also refers to the staff reports, public documents that contain a more expanded discussion of
the uncertainties involved in concluding that long-term storage will have no environmental
Page 462 U. S. 102 effects. These staff reports recognize that rigorous verification of long-term risks for waste
repositories is not possible, but suggest that data and extrapolation of past experience allow
It also emphasized that the purpose of the rule was not to evaluate or select the most effective the Commission to identify events that could produce repository failure, estimate the probability
long-term waste disposal technology or develop site selection criteria. A separate an of those events, and calculate the resulting consequences. NUREG-0116 at 4-86. [Footnote
comprehensive series of programs has been undertaken to serve these broader purposes. 18] The Commission staff also modeled the consequences of repository failure by tracing the
[Footnote 14] In the proceedings before us, the Commission's staff did not attempt to evaluate flow of contaminated water, and found them to be insignificant. Id. at 4-89 through 4-94.
the environmental effects of all possible methods of disposing of waste. Rather, it chose to Ultimately, the staff concluded that
analyze intensively the most probable long-term waste disposal method -- burial in a bedded-
salt repository several hundred meters below ground -- and then "estimate its impacts "[t]he radiotoxic hazard index analyses and the modeling studies that have been done indicate
conservatively, based on the best available information and analysis." 44 Fed.Reg. 45363 that consequences of all but the most improbable events will be small.
(1979). [Footnote 15] The zero release assumption cannot be evaluated in isolation. Rather, it
must be assessed in relation to the limited purpose for which the Commission made the Page 462 U. S. 105
assumption.
Risks (probabilities times consequences) inherent in the long-term for geological disposal will
Second, the Commission emphasized that the zero release assumption is but a single figure therefore also be small."
in an entire Table, which the
Id. at 2-11.
Page 462 U. S. 103
We also find significant the separate views of Commissioners Bradford and Gilinsky. These
Commission expressly designed as a risk-averse estimate of the environmental impact of the Commissioners expressed dissatisfaction with the zero release assumption, and yet
fuel cycle. It noted that Table S-3 assumed that the fuel storage canisters and the fuel rod emphasized the limited purpose of the assumption and the overall conservatism of Table S-3.
cladding would be corroded before a repository is closed, and that all volatile materials in the Commissioner Bradford characterized the bedded-salt repository as a responsible working
fuel would escape to the environment. [Footnote 16] Given that assumption, and the assumption for NEPA purposes, and concurred in the zero release figure because it does not
improbability that materials would escape after sealing, the Commission determined that the appear to affect Table S-3's overall conservatism. 44 Fed.Reg. 45372 (1979). Commissioner
overall Table represented a conservative (i.e., inflated) statement of environmental impacts. It Gilinsky was more critical of the entire Table, stating that the Commission should confront
is not unreasonable for the Commission to counteract the uncertainties in post-sealing releases directly whether it should license any nuclear reactors in light of the problems of waste disposal,
by balancing them with an overestimate of pre-sealing releases. [Footnote 17] A reviewing rather than hide an affirmative conclusion to this issue behind a table of numbers. He
court should not magnify a single line item beyond its significance as only part of a larger Table. emphasized that the "waste confidence proceeding," see n 14, supra, should provide the
Commission an appropriate vehicle for a thorough evaluation of the problems involved in the
Government's commitment to a waste disposal solution. For the limited purpose of individual
licensing proceedings, however, Commissioner Gilinsky found it "virtually inconceivable" that Page 462 U. S. 107
the Table should affect the decision whether to license, and characterized as "naive" the notion
that the fuel cycle effluents could tip the balance in some cases and not in others. 44 Fed.Reg. impact of a proposed action. See Metropolitan Edison Co. v. People Against Nuclear
45374 (1979). Energy, 460 U. S. 766(1983); Kleppe v. Sierra Club, 427 U.S. at 427 U. S. 410; 40 CFR §§
1508.7, 1508.8 (1982). We find no basis, however, for the Court of Appeals' conclusion that
In sum, we think that the zero release assumption -- a policy judgment concerning one line in the Commission ever precluded a licensing board from considering these effects.
a conservative Table designed for the limited purpose of individual licensing decisions -- is
within the bounds of reasoned decisionmaking. It is not our task to determine what decision It is true, as the Commission pointed out in explaining why it modified the language in the earlier
we, as Commissioners, would have reached. Our only task is to determine whether the rules, that the original Table S-3 rule "at least initially was apparently interpreted as cutting off"
Commission has considered the relevant factors and articulated a rational connection between discussion of the effects of effluent releases. 44 Fed.Reg. 45364 (1979). But even the notice
the facts found and the choice made. Bowman Transportation, Inc. v. accompanying the earlier versions stated that the Table was "to be used as a basis
for evaluating the environmental effects in a cost-benefit analysis for a reactor," 39 Fed.Reg.
Page 462 U. S. 106 14190 (1974) (emphasis added), suggesting that individual licensing boards were to assess
the consequences of effluent releases. And when, operating under the initial rule, the Atomic
Arkansas-Best Freight System, Inc., 419 U. S. 281, 419 U. S. 285-286 (1974); Citizens to Safety and Licensing Appeal Board suggested the desirability of discussing health effects for
Preserve Overton Park, Inc. v. Volpe, 401 U. S. 402 (1971). Under this standard, we think the comparing nuclear with coal plants, In re Tennessee Valley Authority (Hartsville Nuclear Plant
Commission's zero release assumption, within the context of Table S-3 as a whole, was not Units), 5 N.R.C. 92, 103, n. 52 (1977), the Commission staff was allowed to introduce evidence
arbitrary and capricious. of public health consequences. Cf. In re Public Service Company of Indiana (Marble Hill
Nuclear Generating Station), 7 N.R.C. 179, 187 (1978).
III
Respondents have pointed to no case where evidence concerning health or other
As we have noted, n 5, supra, Table S-3 describes effluents and other impacts in technical consequences of the data in Table S-3 was excluded from licensing proceedings. We think our
admonition in Vermont Yankee applies with equal force here:
terms. The Table does not convert that description into tangible effects on human health or
other environmental variables. The original and interim rules declared that
"[W]hile it is true that NEPA places upon an agency the obligation to consider every significant
aspect of the environmental impact of a proposed action, it is still incumbent upon intervenors
"the contribution of the environmental effects of . . . fuel cycle activities . . . shall be as set forth
who wish to participate to structure their participation so that it is meaningful, so that it alerts
in the following Table S-3 [and] [n]o further discussion of such environmental effects shall be
required." the agency to the intervenors' position and contentions."

435 U.S. at 435 U. S. 553.


39 Fed.Reg. 14191 (1974); 42 Fed.Reg. 13806 (1977). Since the Table does not specifically
mention health effects, socioeconomic impacts, or cumulative impacts, this declaration does
not clearly require or preclude their discussion. The Commission later amended the interim rule Page 462 U. S. 108
to clarify that health effects were not covered by Table S-3 and could be litigated in individual
licensing proceedings. In the final rule, the Commission expressly required licensing boards to In short, we find it totally inappropriate to cast doubt on licensing proceedings simply because
consider the socioeconomic and cumulative effects in addition to the health effects of the of a minor ambiguity in the language of the earlier rule under which the environmental impact
releases projected in the Table. 44 Fed.Reg. 45371 (1979). [Footnote 19] statement was made, when there is no evidence that this ambiguity prevented any party from
making as full a presentation as desired, or ever affected the decision to license the plant.
The Court of Appeals held that the original and interim rules violated NEPA by precluding
licensing boards from considering the health, socioeconomic, and cumulative effects of the IV
environmental impacts stated in technical terms. As does the Commission, we agree with the
Court of Appeals that NEPA requires an EIS to disclose the significant health, socioeconomic, For the foregoing reasons, the judgment of the Court of Appeals for the District of Columbia
and cumulative consequences of the environmental Circuit is
11
Reversed. [Footnote 2]

JUSTICE POWELL took no part in the consideration or decision of these cases. The original Table S-3 rule was promulgated by the Atomic Energy Commission (AEC).
Congress abolished the AEC in the Energy Reorganization Act of 1974, 42 U.S.C. § 5801 et
Page 462 U. S. 109 seq., and transferred its licensing and regulatory functions to the Nuclear Regulatory
Commission (NRC). The interim and final rules were promulgated by the NRC. This opinion
APPENDIX TO THE OPINION OF THE COURT will use the term "Commission" to refer to both the NRC and the predecessor AEC.

Table S-3 -- Table of Uranium Fuel Cycle Environmental Data[1] [Footnote 3]

[Normalized to model LWR annuel fuel requirement [WASH-1248] Title 5 U.S.C. § 706 states in part:

or reference reactor year [NUREG-0116]] "The reviewing court shall -- "

[Table omitted] "(2) hold unlawful and set aside agency action, findings, and conclusions found to be -- "

* Together with No. 82-545, United States Nuclear Regulatory Commission et al. v. Natural "(A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law."
Resources Defense Council, Inc., et al.; and No. 82-551, Commonwealth Edison Co. et al. v.
Natural Resources Defense Council, Inc., et al., also on certiorari to the same court. [Footnote 4]

[Footnote 1] A light-water nuclear powerplant is one that uses ordinary water (H^20), as opposed to heavy
water (D^20), to remove the heat generated in the nuclear core. See Van Nostrand's Scientific
Encyclopedia 1998, 2008 (D. Considine & G. Considine eds., 6th ed.1983). The bulk of the
Section 102(2)(C) provides:
reactors in the United States are light-water nuclear reactors. NRC Ann. Rep. Appendix 6
(1980).
"The Congress authorizes and directs that, to the fullest extent possible . . . (2) all agencies of
the Federal Government shall -- "
[Footnote 5]
****
For example, the tabulated impacts include the acres of land committed to fuel cycle activities,
the amount of water discharged by such activities, fossil fuel consumption, and chemical and
"(c) include in every recommendation or report on proposals for legislation and other major radiological effluents (measured in curies), all normalized to the annual fuel requirement for a
Federal actions significantly affecting the quality of the human environment, a detailed model 1,000 megawatt light-water reactor. See Table S-3, reprinted in the
statement by the responsible official on -- " Appendix, infra [omitted].

"(i) the environmental impact of the proposed action," [Footnote 6]

"(ii) any adverse environmental effects which cannot be avoided should the proposal be Under the Atomic Energy Act of 1954, 68 Stat. 919, as amended, 42 U.S.C. § 2011 et seq., a
implemented, [and]" utility seeking to construct and operate a nuclear powerplant must obtain a separate permit or
license at both the construction and the operation stage of the project. After the Commission's
**** staff has examined the application for a construction license, which includes a review of
possible environmental effects as required by NEPA, a three-member Atomic Safety and
"(v) any irreversible and irretrievable commitments of resources which would be involved in the Licensing Board conducts a public adjudicatory hearing and reaches a decision which can be
proposed action should it be implemented." appealed to the Atomic Safety and Licensing Appeal Board and, in the Commission's
discretion, to the Commission itself. The final agency decision may be appealed to the courts
of appeals. A similar procedure occurs when the utility applies for an operating license, except The record includes more than 1,100 pages of prepared direct testimony, two rounds of
that a hearing need be held only in contested cases. See Vermont Yankee Nuclear Power questions by participants and several hundred pages of responses, 1,200 pages of oral
Corp. v. Natural Resources Defense Council, Inc., 435 U. S. 519, 435 U. S. 526-527 (1978). hearings, participants' rebuttal testimony, concluding statements, the 137-page report of the
hearing board, further written statements from participants, and oral argument before the
[Footnote 7] Commission. The Commission staff has prepared three studies of the environmental effects of
the fuel cycle: Environmental Survey of the Uranium Fuel Cycle, WASH-1248 (Apr.1974);
Environmental Survey of the Reprocessing and Waste Management Portions of the LWR Fuel
High-level wastes, which are highly radioactive, are produced in liquid form when spent fuel is
reprocessed. Transuranic wastes, which are also highly toxic, are nuclides heavier than Cycle, NUREG-0116 (Supp. I to WASH-1248) (Oct.1976) (hereinafter cited as NUREG-0116);
uranium that are produced in the reactor fuel. See Natural Resources Defense Council, Inc. v. and Public Comments and Task Force Responses Regarding the Environmental Survey of the
NRC, 222 U.S.App.D.C. 9, 16, n. 11, 685 F.2d 459, 466, n. 11 (1982). Reprocessing and Waste Management Portions of the LWR Fuel Cycle, NUREG-0216 (Supp.
2 to WASH-1248) (Mar.1977).
[Footnote 8]
[Footnote 12]
In Vermont Yankee, we indicated that the Court of Appeals could consider any additions made
We are reviewing here only the Table S-3 rulemaking proceedings, and do not have before us
to the record by the Commission, and could consolidate review of the initial review with review
an individual EIS that incorporates Table S-3. It is clear that the Statement of Consideration
of later rules. 435 U.S. at 435 U. S. 537, n. 14. Consistent with this direction, the parties
supporting the Table S-3 rule adequately discloses the environmental uncertainties considered
stipulated that all three versions of the rule could be reviewed on the basis of the whole
record. See 222 U.S.App.D.C. at 21, n. 39, 685 F.2d at 471, n. 39. by the Commission. However, Table S-3 itself refers to other documents, but gives only brief
descriptions of the environmental effects it encapsulates. There is some concern with an EIS
that relies too heavily on separate documents, rather than addressing the concerns directly.
[Footnote 9] Although we do not decide whether they have binding effect on an independent agency such
as the Commission, it is worth noting that the guidelines from the Council on Environmental
Judge Bazelon wrote the opinion for the court. Judge Wilkey joined the section of the opinion Quality in effect during these proceedings required that
that rejected New York's argument that the waste disposal technology assumed for calculation
of certain effluent release values was economically infeasible. That issue is not before us. "care should be taken to ensure that the statement remains an essentially self-contained
Judge Wilkey filed a dissenting opinion on the issues that are under review here. Judge instrument, capable of being understood by the reader without the need for undue cross
Edwards of the Court of Appeals for the Sixth Circuit, sitting by designation, joined these reference."
sections of Judge Bazelon's opinion, and also filed a separate opinion concurring in part and
dissenting on the economic infeasibility issue.
38 Fed.Reg. 20554 (1973), 40 CFR § 1500.8(b) (1974). The present regulations state that
incorporation by reference is permissible if it will not "imped[e] agency and public review of the
[Footnote 10] action. The incorporated material shall be cited in the statement and its content briefly
described." 40 CFR § 1502.21 (1982). The Court of Appeals noted that NEPA "requires an
As the Court of Appeals recognized, 222 U.S.App.D.C. at 31, n. 118, 685 F.2d at 481, n. 118, agency to do more than to scatter its evaluation of environmental damage among various public
the Commission became increasingly candid in acknowledging the uncertainties underlying documents," 222 U.S.App.D.C. at 34, 685 F.2d at 484, but declined to find that the incorporation
permanent waste disposal. Because all three versions of Table S-3 use the same zero release of other documents by reference would invalidate an EIS that used Table S-3 to describe the
assumption, and the parties stipulated that the entire record be used in reviewing all three environmental impact of the fuel cycle. The parties here do not treat this insufficient disclosure
versions, see n 8, supra, we need review only the propriety of the final Table S-3 rule. We argument as a separate argument and, like the Court of Appeals, we decline to strike down the
leave for another day any general concern with an agency whose initial Environmental Impact rule on this ground. We do not deny the value of an EIS that can be understood without
Statement (EIS) is insufficient but who later adequately supplements its consideration and extensive cross-reference. The staff documents referred to in Table S-3 are public documents,
disclosure of the environmental impact of its action. however, and we note that the Commission has proposed an explanatory narrative to
accompany Table S-3, which would be included in an individual EIS, that may alleviate some
[Footnote 11] of the concerns of incorporation. See n 13, infra.

13
[Footnote 13] [Footnote 18]

In March 1981, the Commission submitted a version of the explanatory narrative for public For example, using this approach, the staff estimated that a meteor the size necessary to
comment as a proposed amendment to the final fuel cycle rule. 46 Fed.Reg. 15154 (1981). damage a repository would hit a given square kilometer of the earth's surface only once every
The Commission has not yet adopted a final narrative. 50 trillion years, and that geologic faulting through the Delaware Basin in southeast New
Mexico (assuming that were the site of the repository) would occur once in 25 billion years.
[Footnote 14] NUREG-0116 at 4-87. The staff determined that a surface burst of a 50 megaton nuclear
weapon, far larger than any currently deployed, would not breach the repository. Ibid. The staff
In response to Minnesota v. NRC, 195 U.S.App.D.C. 234, 602 F.2d 412 (1979), the also recognized the possibility that heat generated by the waste would damage the repository,
but suggested this problem could be alleviated by decreasing the density of the stored waste.
Commission has initiated a "waste confidence" proceeding to consider the most recent
In recognition that this suggestion would increase the size of the repository, the Commission
evidence regarding the likelihood that nuclear waste can be safely disposed of and when that,
amended Table S-3 to reflect the greater acreage required under these assumptions. See 44
or some other off-site storage solution, can be accomplished. 44 Fed.Reg. 61372 et
seq. (1979). See id. at 45363. The recently enacted Nuclear Waste Policy Act of 1982, Pub.L. Fed.Reg. 45369 (1979).
97-425, 96 Stat. 2201, 42 U.S.C. § 10101 et seq. (1982 ed.), has set up a schedule for
identifying site locations and a funding mechanism for development of permanent waste [Footnote 19]
repositories. The Environmental Protection Agency has also proposed standards for future
waste repositories, 47 Fed.Reg. 58196 et seq. (1982). Of course, just as the Commission has discretion to evaluate generically aspects of the
environmental impact of the fuel cycle, it has discretion to have other aspects of the issue
[Footnote 15] decided in individual licensing decisions.

For example, Table S-3 assumes that plutonium will not be recycled. The Commission noted Calvert Cliffs' Coordinating Committee, Inc., et al., Petitioners, v. United States Atomic Energy
that, in response to a Presidential directive, it had terminated separate proceedings concerning Commission and United States of America, Respondents,baltimore Gas and Electric Company,
the possibility of recycling plutonium in mixed oxide fuel. 44 Fed.Reg. 45369, n. 28 (1979). See Intervenor.calvert Cliffs' Coordinating Committee, Inc., et al., Petitioners, v. United States
In re Mixed Oxide Fuel, 6 N.R.C. 861 (1977); In re Mixed Oxide Fuel, 7 N.R.C. 711 (1978). Atomic Energy Commission and United States of America, Respondents, 449 F.2d 1109 (D.C.
Cir. 1971)
[Footnote 16]
U.S. Court of Appeals for the District of Columbia Circuit - 449 F.2d 1109 (D.C. Cir. 1971)
The Commission also increased the overall conservatism of the Table by overestimating the Argued April 16, 1971 Decided July 23, 1971
amount of fuel consumed by a reactor, underestimating the amount of electricity produced, and
then underestimating the efficiency of filters and other protective devices. See Conclusions
and Recommendations of the Hearing Board Regarding the Environmental Effects of the
Uranium Fuel Cycle, Docket No. Rm 50-3, App. to Pet. for Cert. in No. 82-524, pp. 282a-293a.
Additionally, Table S-3, which analyzes both a uranium-recycle and no-recycle system,
conservatively lists, for each effluent, the highest of the two releases that would be expected
COPYRIGHT MATERIAL OMITTED Mr. Anthony Z. Roisman, Washington, D. C., with whom
under each cycle. 41 Fed.Reg. 45849, 45850 (1976).
Messrs. Myron M. Cherry, Chicago, Ill., and Lewis Drain, Grand Rapids, Mich., were on the
brief, for petitioners.
[Footnote 17]

The Court of Appeals recognized that the Commission could weigh certain generic costs and
benefits of reactors against each other to produce a generic "net value" to be used in individual
licensing proceedings. 222 U.S.App.D.C. at 32, 685 F.2d at 482. We see no reason why the
Commission does not have equal discretion to evaluate certain environmental costs together Mr. Marcus A. Rowden, Solicitor, Atomic Energy Commission, with whom Messrs. Howard K.
to produce a generic net cost. Shapar, Asst. Gen. Counsel, Licensing and Regulation, Atomic Energy Commission, and
Edmund Clark, Atty., Department of Justice, were on the brief, for respondents. Mr. William C.
Parler, Atty., Atomic Energy Commission, also entered an appearance for respondent Atomic * We begin our analysis with an examination of NEPA's structure and approach and of the
Energy Commission. Atomic Energy Commission rules which are said to conflict with the requirements of the Act.
The relevant portion of NEPA is Title I, consisting of five sections. 3 Section 101 sets forth the
Mr. George F. Trowbridge, Washington, D. C., with whom Mr. Jay E. Silberg, Washington, D.
Act's basic substantive policy: that the federal government "use all practicable means and
C., was on the brief, for intervenor in No. 24,839.
measures" to protect environmental values. Congress did not establish environmental
Messrs. George D. Gibson and Arnold H. Quint, Washington, D. C., filed a brief on behalf of protection as an exclusive goal; rather, it desired a reordering of priorities, so that
Duke Power Company et al. as amici curiae in No. 24,871. environmental costs and benefits will assume their proper place along with other
considerations. In Section 101(b), imposing an explicit duty on federal officials, the Act provides
Mr. Roy B. Snapp, Washington, D. C., filed a brief on behalf of Arkansas Power and Light
that "it is the continuing responsibility of the Federal Government to use all practicable means,
Company as amicus curiae in No. 24,871. consistent with other essential considerations of national policy," to avoid environmental
Messrs. Arvin E. Upton, Leonard M. Trosten and Henry V. Nickel, Washington, D. C., filed a degradation, preserve "historic, cultural, and natural" resources, and promote "the widest range
brief on behalf of Consolidated Edison Company as amicus curiae in No. 24,871. of beneficial uses of the environment without * * * undesirable and unintended consequences."
Mr. Jerome E. Sharfman, Washington, D. C., filed a brief on behalf of Consumers Power Thus the general substantive policy of the Act is a flexible one. It leaves room for a responsible
Company as amicus curiae in No. 24,871. exercise of discretion and may not require particular substantive results in particular
problematic instances. However, the Act also contains very important "procedural" provisions
Messrs. H. Edward Dunkelberger, Jr., Christopher M. Little and Peter M. Phillipes, Washington, — provisions which are designed to see that all federal agencies do in fact exercise the
D. C., filed a brief on behalf of Indiana and Michigan Electric Company and Portland General substantive discretion given them. These provisions are not highly flexible. Indeed, they
Electric Company as amici curiae in No. 24,871. establish a strict standard of compliance.
Before WRIGHT, TAMM and ROBINSON, Circuit Judges. NEPA, first of all, makes environmental protection a part of the mandate of every federal agency
These cases are only the beginning of what promises to become a flood of new litigation — and department. The Atomic Energy Commission, for example, had continually asserted, prior
litigation seeking judicial assistance in protecting our natural environment. Several recently to NEPA, that it had no statutory authority to concern itself with the adverse environmental
enacted statutes attest to the commitment of the Government to control, at long last, the effects of its actions.4 Now, however, its hands are no longer tied. It is not only permitted, but
destructive engine of material "progress."1 But it remains to be seen whether the promise of compelled, to take environmental values into account. Perhaps the greatest importance of
this legislation will become a reality. Therein lies the judicial role. In these cases, we must for NEPA is to require the Atomic Energy Commission and other agencies
the first time interpret the broadest and perhaps most important of the recent statutes: the to consider environmental issues just as they consider other matters within their mandates.
National Environmental Policy Act of 1969 (NEPA).2 We must assess claims that one of the This compulsion is most plainly stated in Section 102. There, "Congress authorizes and directs
agencies charged with its administration has failed to live up to the congressional mandate. that, to the fullest extent possible: (1) the policies, regulations, and public laws of the United
Our duty, in short, is to see that important legislative purposes, heralded in the halls of States shall be interpreted and administered in accordance with the policies set forth in this Act
Congress, are not lost or misdirected in the vast hallways of the federal bureaucracy. * * *." Congress also "authorizes and directs" that "(2) all agencies of the Federal Government
shall" follow certain rigorous procedures in considering environmental values.5 Senator
NEPA, like so much other reform legislation of the last 40 years, is cast in terms of a general Jackson, NEPA's principal sponsor, stated that " [n]o agency will [now] be able to maintain that
mandate and broad delegation of authority to new and old administrative agencies. It takes the it has no mandate or no requirement to consider the environmental consequences of its
major step of requiring all federal agencies to consider values of environmental preservation in actions."6 He characterized the requirements of Section 102 as "action-forcing" and stated that
their spheres of activity, and it prescribes certain procedural measures to ensure that those " [o]therwise, these lofty declarations [in Section 101] are nothing more than that."7
values are in fact fully respected. Petitioners argue that rules recently adopted by the Atomic
Energy Commission to govern consideration of environmental matters fail to satisfy the rigor The sort of consideration of environmental values which NEPA compels is clarified in Section
demanded by NEPA. The Commission, on the other hand, contends that the vagueness of the 102(2) (A) and (B). In general, all agencies must use a "systematic, interdisciplinary approach"
NEPA mandate and delegation leaves much room for discretion and that the rules challenged to environmental planning and evaluation "in decisionmaking which may have an impact on
by petitioners fall well within the broad scope of the Act. We find the policies embodied in NEPA man's environment." In order to include all possible environmental factors in the decisional
to be a good deal clearer and more demanding than does the Commission. We conclude that equation, agencies must "identify and develop methods and procedures * * * which will insure
the Commission's procedural rules do not comply with the congressional policy. Hence we that presently unquantified environmental amenities and values may be given appropriate
remand these cases for further rule making. consideration in decisionmaking along with economic and technical
considerations."8 "Environmental amenities" will often be in conflict with "economic and

15
technical considerations." To "consider" the former "along with" the latter must involve a Thus the Section 102 duties are not inherently flexible. They must be complied with to the fullest
balancing process. In some instances environmental costs may outweigh economic and extent, unless there is a clear conflict of statutory authority.12 Considerations of administrative
technical benefits and in other instances they may not. But NEPA mandates a rather finely difficulty, delay or economic cost will not suffice to strip the section of its fundamental
tuned and "systematic" balancing analysis in each instance.9 importance.
To ensure that the balancing analysis is carried out and given full effect, Section 102(2) (C) We conclude, then, that Section 102 of NEPA mandates a particular sort of careful and
requires that responsible officials of all agencies prepare a "detailed statement" covering the informed decisionmaking process and creates judicially enforceable duties. The reviewing
impact of particular actions on the environment, the environmental costs which might be courts probably cannot reverse a substantive decision on its merits, under Section 101, unless
avoided, and alternative measures which might alter the cost-benefit equation. The apparent it be shown that the actual balance of costs and benefits that was struck was arbitrary or clearly
purpose of the "detailed statement" is to aid in the agencies' own decision making process and gave insufficient weight to environmental values. But if the decision was reached procedurally
to advise other interested agencies and the public of the environmental consequences of without individualized consideration and balancing of environmental factors — conducted fully
planned federal action. Beyond the "detailed statement," Section 102(2) (D) requires all and in good faith — it is the responsibility of the courts to reverse. As one District Court has
agencies specifically to "study, develop, and describe appropriate alternatives to recommended said of Section 102 requirements: "It is hard to imagine a clearer or stronger mandate to the
courses of action in any proposal which involves unresolved conflicts concerning alternative Courts."13
uses of available resources." This requirement, like the "detailed statement" requirement,
In the cases before us now, we do not have to review a particular decision by the Atomic Energy
seeks to ensure that each agency decision maker has before him and takes into proper account
Commission granting a construction permit or an operating license. Rather, we must review
all possible approaches to a particular project (including total abandonment of the project)
the Commission's recently promulgated rules which govern consideration of environmental
which would alter the environmental impact and the cost-benefit balance. Only in that fashion
values in all such individual decisions.14 The rules were devised strictly in order to comply with
is it likely that the most intelligent, optimally beneficial decision will ultimately be made.
the NEPA procedural requirements — but petitioners argue that they fall far short of the
Moreover, by compelling a formal "detailed statement" and a description of alternatives, NEPA
congressional mandate.
provides evidence that the mandated decision making process has in fact taken place and,
most importantly, allows those removed from the initial process to evaluate and balance the The period of the rules' gestation does not indicate overenthusiasm on the Commission's part.
factors on their own. NEPA went into effect on January 1, 1970. On April 2, 1970 — three months later — the
Commission issued its first, short policy statement on implementation of the Act's procedural
Of course, all of these Section 102 duties are qualified by the phrase "to the fullest extent
provisions.15 After another span of two months, the Commission published a notice of
possible." We must stress as forcefully as possible that this language does not provide an
proposed rule making in the Federal Register.16 Petitioners submitted substantial comments
escape hatch for footdragging agencies; it does not make NEPA's procedural requirements
critical of the proposed rules. Finally, on December 3, 1970, the Commission terminated its
somehow "discretionary." Congress did not intend the Act to be such a paper tiger. Indeed, the
long rule making proceeding by issuing a formal amendment, labelled Appendix D, to its
requirement of environmental consideration "to the fullest extent possible" sets a high standard
governing regulations.17 Appendix D is a somewhat revised version of the earlier proposal and,
for the agencies, a standard which must be rigorously enforced by the reviewing courts.
at last, commits the Commission to consider environmental impact in its decision making
Unlike the substantive duties of Section 101(b), which require agencies to "use all practicable process.
means consistent with other essential considerations," the procedural duties of Section 102
The procedure for environmental study and consideration set up by the Appendix D rules is as
must be fulfilled to the "fullest extent possible."10 This contrast, in itself, is revealing. But the
follows: Each applicant for an initial construction permit must submit to the Commission his
dispositive factor in our interpretation is the expressed views of the Senate and House
own "environmental report," presenting his assessment of the environmental impact of the
conferees who wrote the "fullest extent possible" language into NEPA. They stated: 11
planned facility and possible alternatives which would alter the impact. When construction is
"* * * The purpose of the new language is to make it clear that each agency of the Federal completed and the applicant applies for a license to operate the new facility, he must again
Government shall comply with the directives set out in * * * [Section 102(2)] unless the existing submit an "environmental report" noting any factors which have changed since the original
law applicable to such agency's operations expressly prohibits or makes full compliance with report. At each stage, the Commission's regulatory staff must take the applicant's report and
one of the directives impossible. * * * Thus, it is the intent of the conferees that the provision prepare its own "detailed statement" of environmental costs, benefits and alternatives. The
`to the fullest extent possible' shall not be used by any Federal agency as a means of avoiding statement will then be circulated to other interested and responsible agencies and made
compliance with the directives set out in section 102. Rather, the language in section 102 is available to the public. After comments are received from those sources, the staff must prepare
intended to assure that all agencies of the Federal Government shall comply with the directives a final "detailed statement" and make a final recommendation on the application for a
set out in said section `to the fullest extent possible' under their statutory authorizations and construction permit or operating license.
that no agency shall utilize an excessively narrow construction of its existing statutory
Up to this point in the Appendix D rules petitioners have raised no challenge. However, they do
authorizations to avoid compliance."
attack four other, specific parts of the rules which, they say, violate the requirements of Section
102 of NEPA. Each of these parts in some way limits full consideration and individualized
balancing of environmental values in the Commission's decision making process. (1) Although more than physical proximity — mandating no more than the physical act of passing certain
environmental factors must be considered by the agency's regulatory staff under the rules, such folders and papers, unopened, to reviewing officials along with other folders and papers? What
factors need not be considered by the hearing board conducting an independent review of staff possible purpose could there be in requiring the "detailed statement" to be before hearing
recommendations, unless affirmatively raised by outside parties or staff members. (2) Another boards, if the boards are free to ignore entirely the contents of the statement? NEPA was meant
part of the procedural rules prohibits any such party from raising nonradiological environmental to do more than regulate the flow of papers in the federal bureaucracy. The word "accompany"
issues at any hearing if the notice for that hearing appeared in the Federal Register before in Section 102(2) (C) must not be read so narrowly as to make the Act ludicrous. It must, rather,
March 4, 1971. (3) Moreover, the hearing board is prohibited from conducting an independent be read to indicate a congressional intent that environmental factors, as compiled in the
evaluation and balancing of certain environmental factors if other responsible agencies have "detailed statement," be considered through agency review processes.19
already certified that their own environmental standards are satisfied by the proposed federal
Beyond Section 102(2) (C), NEPA requires that agencies consider the environmental impact
action. (4) Finally, the Commission's rules provide that when a construction permit for a facility
of their actions "to the fullest extent possible." The Act is addressed to agencies as a whole,
has been issued before NEPA compliance was required and when an operating license has
not only to their professional staffs. Compliance to the "fullest" possible extent would seem to
yet to be issued, the agency will not formally consider environmental factors or require
demand that environmental issues be considered at every important stage in the decision
modifications in the proposed facility until the time of the issuance of the operating license.
making process concerning a particular action — at every stage where an overall balancing of
Each of these parts of the Commission's rules will be described at greater length and evaluated
environmental and nonenvironmental factors is appropriate and where alterations might be
under NEPA in the following sections of this opinion.
made in the proposed action to minimize environmental costs. Of course, consideration which
is entirely duplicative is not necessarily required. But independent review of staff proposals by
II hearing boards is hardly a duplicative function. A truly independent review provides a crucial
NEPA makes only one specific reference to consideration of environmental values in agency check on the staff's recommendations. The Commission's hearing boards automatically
review processes. Section 102(2) (C) provides that copies of the staff's "detailed statement" consider nonenvironmental factors, even though they have been previously studied by the staff.
and comments thereon "shall accompany the proposal through the existing agency review Clearly, the review process is an appropriate stage at which to balance conflicting factors
processes." The Atomic Energy Commission's rules may seem in technical compliance with against one another. And, just as clearly, it provides an important opportunity to reject or
the letter of that provision. They state: significantly modify the staff's recommended action. Environmental factors, therefore, should
not be singled out and excluded, at this stage, from the proper balance of values envisioned
"12. If any party to a proceeding * * * raises any [environmental] issue * * * the Applicant's by NEPA.
Environmental Report and the Detailed Statement will be offered in evidence. The atomic safety
and licensing board will make findings of fact on, and resolve, the matters in controversy among The Commission's regulations provide that in an uncontested proceeding the hearing board
the parties with regard to those issues. Depending on the resolution of those issues, the permit shall on its own "determine whether the application and the record of the proceeding contain
or license may be granted, denied, or appropriately conditioned to protect environmental sufficient information, and the review of the application by the Commission's regulatory staff
values. has been adequate, to support affirmative findings on" various nonenvironmental
factors.20 NEPA requires at least as much automatic consideration of environmental factors.
"13. When no party to a proceeding * * * raises any [environmental] issue * * * such issues will In uncontested hearings, the board need not necessarily go over the same ground covered in
not be considered by the atomic safety and licensing board. Under such circumstances, the "detailed statement." But it must at least examine the statement carefully to determine
although the Applicant's Environmental Report, comments thereon, and the Detailed Statement whether "the review * * * by the Commission's regulatory staff has been adequate." And it must
will accompany the application through the Commission's review processes, they will not be independently consider the final balance among conflicting factors that is struck in the staff's
received in evidence, and the Commission's responsibilities under the National Environmental recommendation.
Policy Act of 1969 will be carried out in toto outside the hearing process."18
The rationale of the Commission's limitation of environmental issues to hearings in which
The question here is whether the Commission is correct in thinking that its NEPA parties affirmatively raise those issues may have been one of economy. It may have been
responsibilities may "be carried out in toto outside the hearing process" — whether it is enough supposed that, whenever there are serious environmental costs overlooked or uncorrected by
that environmental data and evaluations merely "accompany" an application through the review the staff, some party will intervene to bring those costs to the hearing board's attention. Of
process, but receive no consideration whatever from the hearing board. course, independent review of the "detailed statement" and independent balancing of factors
We believe that the Commission's crabbed interpretation of NEPA makes a mockery of the Act. in an uncontested hearing will take some time. If it is done properly, it will take a significant
What possible purpose could there be in the Section 102 (2) (C) requirement (that the "detailed amount of time. But all of the NEPA procedures take time. Such administrative costs are not
statement" accompany proposals through agency review processes) if "accompany" means no enough to undercut the Act's requirement that environmental protection be considered "to the

17
fullest extent possible," see text at page 1114, supra. It is, moreover, unrealistic to assume that The Commission, however, cannot justify its time lag under these Section 103 provisions.
there will always be an intervenor with the information, energy and money required to challenge Indeed, it has not attempted to do so; only intervenors have raised the argument. Section 103
a staff recommendation which ignores environmental costs. NEPA establishes environmental could support a substantial delay only by an agency which in fact discovered an insuperable
protection as an integral part of the Atomic Energy Commission's basic mandate. The primary barrier to compliance with the Act and required time to formulate and propose the needed
responsibility for fulfilling that mandate lies with the Commission. Its responsibility is not simply reformative measures. The actual review of existing statutory authority and regulations cannot
to sit back, like an umpire, and resolve adversary contentions at the hearing stage. Rather, it be a particularly lengthy process for experienced counsel of a federal agency. Of course, the
must itself take the initiative of considering environmental values at every distinctive and Atomic Energy Commission discovered no obstacle to NEPA implementation. Although it did
comprehensive stage of the process beyond the staff's evaluation and recommendation.21 not report its conclusion to the President until October 2, 1970, that nine-month delay (January
to October) cannot justify so long a period of noncompliance with the Act. It certainly cannot
III justify a further delay of compliance until March 4, 1971.

Congress passed the final version of NEPA in late 1969, and the Act went into full effect on No doubt the process formulating procedural rules to implement NEPA takes some time.
January 1, 1970. Yet the Atomic Energy Commission's rules prohibit any consideration of Congress cannot have expected that federal agencies would immediately begin considering
environmental issues by its hearing boards at proceedings officially noticed before March 4, environmental issues on January 1, 1970. But the effective date of the Act does set a time for
1971.22 This is 14 months after the effective date of NEPA. And the hearings affected may go agencies to begin adopting rules and it demands that they strive, "to the fullest extent possible,"
on for as much as a year longer until final action is taken. The result is that major federal actions to be prompt in the process. The Atomic Energy Commission has failed in this
having a significant environmental impact may be taken by the Commission, without full NEPA regard.26 Consideration of environmental issues in the agency review process, for example, is
compliance, more than two years after the Act's effective date. In view of the importance of quite clearly compelled by the Act.27 The Commission cannot justify its 11-month delay in
environmental consideration during the agency review process, see Part II supra, such a time adopting rules on this point as part of a difficult, discretionary effort to decide whether or not its
lag is shocking. hearing boards should deal with environmental questions at all.

The Commission explained that its very long time lag was intended "to provide an orderly period Even if the long delay had been necessary, however, the Commission would not be relieved of
of transition in the conduct of the Commission's regulatory proceedings and to avoid all NEPA responsibility to hold public hearings on the environmental consequences of actions
unreasonable delays in the construction and operation of nuclear power plants urgently needed taken between January 1, 1970 and final adoption of the rules. Although the Act's effective date
to meet the national requirements for electric power."23 Before this court, it has claimed may not require instant compliance, it must at least require that NEPA procedures, once
authority for its action, arguing that "the statute did not lay down detailed guidelines and established, be applied to consider prompt alterations in the plans or operations of facilities
inflexible timetables for its implementation; and we find in it no bar to agency provisions which approved without compliance.28 Yet the Commission's rules contain no such provision. Indeed,
are designed to accommodate transitional implementation problems."24 they do not even apply to the hearings still being conducted at the time of their adoption on
December 3, 1970 — or, for that matter, to hearings initiated in the following three months. The
Again, the Commission's approach to statutory interpretation is strange indeed — so strange delayed compliance date of March 4, 1971, then, cannot be justified by the Commission's long
that it seems to reveal a rather thoroughgoing reluctance to meet the NEPA procedural drawn out rule making process.
obligations in the agency review process, the stage at which deliberation is most open to public
examination and subject to the participation of public intervenors. The Act, it is true, lacks an Strangely, the Commission has principally relied on more pragmatic arguments. It seems an
"inflexible timetable" for its implementation. But it does have a clear effective date, consistently unfortunate affliction of large organizations to resist new procedures and to envision massive
enforced by reviewing courts up to now. Every federal court having faced the issues has held roadblocks to their adoption. Hence the Commission's talk of the need for an "orderly transition"
that the procedural requirements of NEPA must be met in order to uphold federal action taken to the NEPA procedures. It is difficult to credit the Commission's argument that several months
after January 1, 1970.25 The absence of a "timetable" for compliance has never been held were needed to work the consideration of environmental values into its review process. Before
sufficient, in itself, to put off the date on which a congressional mandate takes effect. The the enactment of NEPA, the Commission already had regulations requiring that hearings
absence of a "timetable," rather, indicates that compliance is required forthwith. include health, safety and radiological matters.29 The introduction of environmental matters
cannot have presented a radically unsettling problem. And, in any event, the obvious sense of
The only part of the Act which even implies that implementation may be subject, in some cases, urgency on the part of Congress should make clear that a transition, however "orderly," must
to some significant delay is Section 103. There, Congress provided that all agencies must proceed at a pace faster than a funeral procession.
review "their present statutory authority, administrative regulations, and current policies and
procedures for the purpose of determining whether there are any deficiencies or In the end, the Commission's long delay seems based upon what it believes to be a pressing
inconsistencies therein which prohibit full compliance" with NEPA. Agencies finding some such national power crisis. Inclusion of environmental issues in pre-March 4, 1971 hearings might
insuperable difficulty are obliged to "propose to the President not later than July 1, 1971, such have held up the licensing of some power plants for a time. But the very purpose of NEPA was
measures as may be necessary to bring their authority and policies into conformity with the to tell federal agencies that environmental protection is as much a part of their responsibility as
intent, purposes, and procedures set forth in this Act." is protection and promotion of the industries they regulate. Whether or not the spectre of a
national power crisis is as real as the Commission apparently believes, it must not be used to Certification by another agency that its own environmental standards are satisfied involves an
create a blackout of environmental consideration in the agency review process. NEPA compels entirely different kind of judgment. Such agencies, without overall responsibility for the
a case-by-case examination and balancing of discrete factors. Perhaps there may be cases in particular federal action in question, attend only to one aspect of the problem: the magnitude
which the need for rapid licensing of a particular facility would justify a strict time limit on a of certain environmental costs. They simply determine whether those costs exceed an
hearing board's review of environmental issues; but a blanket banning of such issues until allowable amount. Their certification does not mean that they found no environmental damage
March 4, 1971 is impermissible under NEPA. whatever. In fact, there may be significant environmental damage (e. g., water pollution), but
not quite enough to violate applicable (e. g., water quality) standards. Certifying agencies do
IV not attempt to weigh that damage against the opposing benefits. Thus the balancing analysis
remains to be done. It may be that the environmental costs, though passing prescribed
The sweep of NEPA is extraordinarily broad, compelling consideration of any and all types of standards, are nonetheless great enough to outweigh the particular economic and technical
environmental impact of federal action. However, the Atomic Energy Commission's rules benefits involved in the planned action. The only agency in a position to make such a judgment
specifically exclude from full consideration a wide variety of environmental issues. First, they is the agency with overall responsibility for the proposed federal action — the agency to which
provide that no party may raise and the Commission may not independently examine any NEPA is specifically directed.
problem of water quality — perhaps the most significant impact of nuclear power plants. Rather,
the Commission indicates that it will defer totally to water quality standards devised and The Atomic Energy Commission, abdicating entirely to other agencies' certifications, neglects
administered by state agencies and approved by the federal government under the Federal the mandated balancing analysis. Concerned members of the public are thereby precluded
Water Pollution Control Act.30 Secondly, the rules provide for similar abdication of NEPA from raising a wide range of environmental issues in order to affect particular Commission
authority to the standards of other agencies: decisions. And the special purpose of NEPA is subverted.

"With respect to those aspects of environmental quality for which environmental quality Arguing before this court, the Commission has made much of the special environmental
standards and requirements have been established by authorized Federal, State, and regional expertise of the agencies which set environmental standards. NEPA did not overlook this
agencies, proof that the applicant is equipped to observe and agrees to observe such standards consideration. Indeed, the Act is quite explicit in describing the attention which is to be given to
and requirements will be considered a satisfactory showing that there will not be a significant, the views and standards of other agencies. Section 102 (2) (C) provides:
adverse effect on the environment. Certification by the appropriate agency that there is "Prior to making any detailed statement, the responsible Federal official shall consult with and
reasonable assurance that the applicant for the permit or license will observe such standards obtain the comments of any Federal agency which has jurisdiction by law or special expertise
and requirements will be considered dispositive for this purpose."31 with respect to any environmental impact involved. Copies of such statement and the
The most the Commission will do is include a condition in all construction permits and operating comments and views of the appropriate Federal, State, and local agencies, which are
licenses requiring compliance with the water quality or other standards set by such authorized to develop and enforce environmental standards, shall be made available to the
agencies.32 The upshot is that the NEPA procedures, viewed by the Commission as President, the Council on Environmental Quality and to the public * * *."
superfluous, will wither away in disuse, applied only to those environmental issues wholly Thus the Congress was surely cognizant of federal, state and local agencies "authorized to
unregulated by any other federal, state or regional body. develop and enforce environmental standards." But it provided, in Section 102(2) (C), only for
We believe the Commission's rule is in fundamental conflict with the basic purpose of the Act. full consultation. It most certainly did not authorize a total abdication to those agencies. Nor did
NEPA mandates a case-by-case balancing judgment on the part of federal agencies. In each it grant a license to disregard the main body of NEPA obligations.
individual case, the particular economic and technical benefits of planned action must be Of course, federal agencies such as the Atomic Energy Commission may have specific duties,
assessed and then weighed against the environmental costs; alternatives must be considered under acts other than NEPA, to obey particular environmental standards. Section 104 of NEPA
which would affect the balance of values. See text at page 1113 supra. The magnitude of makes clear that such duties are not to be ignored:
possible benefits and possible costs may lie anywhere on a broad spectrum. Much will depend
on the particular magnitudes involved in particular cases. In some cases, the benefits will be "Nothing in Section 102 or 103 shall in any way affect the specific statutory obligations of any
great enough to justify a certain quantum of environmental costs; in other cases, they will not Federal agency (1) to comply with criteria or standards of environmental quality, (2) to
be so great and the proposed action may have to be abandoned or significantly altered so as coordinate or consult with any other Federal or State agency, or (3) to act, or refrain from acting
to bring the benefits and costs into a proper balance. The point of the individualized balancing contingent upon the recommendations or certification of any other Federal or State agency."
analysis is to ensure that, with possible alterations, the optimally beneficial action is finally On its face, Section 104 seems quite unextraordinary, intended only to see that the general
taken. procedural reforms achieved in NEPA do not wipe out the more specific environmental controls

19
imposed by other statutes. Ironically, however, the Commission argues that Section 104 in fact statements indicate that Section 104 was the product of a compromise intended to eliminate
allows other statutes to wipe out NEPA. any conflict between the two bills then in the Senate. The overriding purpose was to prevent
NEPA from eclipsing obedience to more specific standards under WQIA. Senator Muskie,
Since the Commission places great reliance on Section 104 to support its abdication to
distrustful of "self-policing by Federal agencies which pollute or license pollution," was
standard setting agencies, we should first note the section's obvious limitation. It deals only
particularly concerned that NEPA not undercut the independent role of standard setting
with deference to such agencies which is compelled by "specific statutory obligations." The
agencies.36 Most of his and Senator Jackson's comments stop short of suggesting that NEPA
Commission has brought to our attention one "specific statutory obligation": the Water Quality
would have no application in water quality matters; their goal was to protect WQIA, not to
Improvement Act of 1970 (WQIA).33 That Act prohibits federal licensing bodies, such as the
undercut NEPA. Our interpretation of Section 104 is perfectly consistent with that purpose.
Atomic Energy Commission, from issuing licenses for facilities which pollute "the navigable
waters of the United States" unless they receive a certification from the appropriate agency that Yet the statements of the two Senators occasionally indicate they were willing to go farther, to
compliance with applicable water quality standards is reasonably assured. Thus Section 104 permit agencies such as the Atomic Energy Commission to forego at least some NEPA
applies in some fashion to consideration of water quality matters. But it definitely cannot support procedures in consideration of water quality. Senator Jackson, for example, said, "The
— indeed, it is not even relevant to — the Commission's wholesale abdication to the standards compromise worked out between the bills provides that the licensing agency will not have to
and certifications of any and all federal, state and local agencies dealing with matters other make a detailed statement on water quality if the State or other appropriate agency has made
than water quality. a certification pursuant to [WQIA]."37 Perhaps Senator Jackson would have required some
consideration and balancing of environmental costs — despite the lack of a formal detailed
As to water quality, Section 104 and WQIA clearly require obedience to standards set by other
statement — but he did not spell out his views. No Senator, other than Senators Jackson and
agencies. But obedience does not imply total abdication. Certainly, the language of Section
Muskie, addressed himself specifically to the problem during floor discussion. Nor did any
104 does not authorize an abdication. It does not suggest that other "specific statutory
member of the House of Representatives.38 The section-by-section analysis of NEPA
obligations" will entirely replace NEPA. Rather, it ensures that three sorts of "obligations" will
submitted to the Senate clearly stated the overriding purpose of Section 104: that "no agency
not be undermined by NEPA: (1) the obligation to "comply" with certain standards, (2) the
may substitute the procedures outlined in this Act for more restrictive and specific procedures
obligation to "coordinate" or "consult" with certain agencies, and (3) the obligation to "act, or
established by law governing its activities."39 The report does not suggest there that NEPA
refrain from acting contingent upon" a certification from certain agencies. WQIA imposes the
procedures should be entirely abandoned, but rather that they should not be "substituted" for
third sort of obligation. It makes the granting of a license by the Commission "contingent upon"
more specific standards. In one rather cryptic sentence, the analysis does muddy the waters
a water quality certification. But it does not require the Commission to grant a license once a
somewhat, stating that " [i]t is the intention that where there is no more effective procedure
certification has been issued. It does not preclude the Commission from demanding water
already established, the procedure of this act will be followed." 40 Notably, however, the
pollution controls from its licensees which are more strict than those demanded by the
sentence does not state that in the presence of "more effective procedures" the NEPA
applicable water quality standards of the certifying agency.34 It is very important to understand
procedure will be abandoned entirely. It seems purposefully vague, quite possibly meaning that
these facts about WQIA. For all that Section 104 of NEPA does is to reaffirm other "specific
obedience to the certifications of standard setting agencies must alter, by supplementing,
statutory obligations." Unless those obligations are plainly mutually exclusive with the
the normal "procedure of this act."
requirements of NEPA, the specific mandate of NEPA must remain in force. In other words,
Section 104 can operate to relieve an agency of its NEPA duties only if other "specific statutory This rather meager legislative history, in our view, cannot radically transform the purport of the
obligations" clearly preclude performance of those duties. plain words of Section 104. Had the Senate sponsors fully intended to allow a total abdication
of NEPA responsibilities in water quality matters — rather than a supplementing of them by
Obedience to water quality certifications under WQIA is not mutually exclusive with the NEPA
strict obedience to the specific standards of WQIA — the language of Section 104 could easily
procedures. It does not preclude performance of the NEPA duties. Water quality certifications
have been changed. As the Supreme Court often has said, the legislative history of a statute
essentially establish a minimum condition for the granting of a license. But they need not end
(particularly such relatively meager and vague history as we have here) cannot radically affect
the matter. The Commission can then go on to perform the very different operation of balancing
its interpretation if the language of the statute is clear. See, e. g., Packard Motor Car Co. v.
the overall benefits and costs of a particular proposed project, and consider alterations (above
NLRB, 330 U.S. 485, 67 S. Ct. 789, 91 L. Ed. 1040 (1947); Kuehner v. Irving Trust Co., 299
and beyond the applicable water quality standards) which would further reduce environmental
U.S. 445, 57 S. Ct. 298, 81 L. Ed. 340 (1937); Fairport, Painesville & Eastern R. Co. v.
damage. Because the Commission can still conduct the NEPA balancing analysis, consistent
Meredith, 292 U.S. 589, 54 S. Ct. 826, 78 L. Ed. 1446 (1934); Wilbur v. United States ex rel.
with WQIA, Section 104 does not exempt it from doing so. And it, therefore, must conduct the
Vindicator Consolidated Gold Mining Co., 284 U.S. 231, 52 S. Ct. 113, 76 L. Ed. 261 (1931).
obligatory analysis under the prescribed procedures.
In a recent case interpreting a veterans' act, the Court set down the principle which must govern
We believe the above result follows from the plain language of Section 104 of NEPA and WQIA. our approach to the case before us:
However, the Commission argues that we should delve beneath the plain language and adopt
"Having concluded that the provisions of § 1 are clear and unequivocal on their face, we find
a significantly different interpretation. It relies entirely upon certain statements made by Senator
no need to resort to the legislative history of the Act. Since the State has placed such heavy
Jackson and Senator Muskie, the sponsors of NEPA and WQIA respectively. 35 Those
reliance upon that history, however, we do deem it appropriate to point out that this history is
at best inconclusive. It is true, as the State points out, that Representative Rankin, as Chairman them. Once again, the Commission seems to believe that the mere drafting and filing of papers
of the Committee handling the bill on the floor of the House, expressed his view during the is enough to satisfy NEPA.
course of discussion of the bill on the floor that the 1941 Act would not apply to [the sort of case
The Commission appears to recognize the severe limitation which its rules impose on
in question] * * *. But such statements, even when they stand alone, have never been regarded
environmental protection. Yet it argues that full NEPA consideration of alternatives and
as sufficiently compelling to justify deviation from the plain language of a statute. * * *" United
independent action would cause too much delay at the pre-operating license stage. It justifies
States v. Oregon, 366 U.S. 643, 648, 81 S. Ct. 1278, 1281, 6 L. Ed. 2d 575 (1961). (Footnotes
its rules as the most that is "practicable, in the light of environmental needs and `other essential
omitted.) It is, after all, the plain language of the statute which all the members of both houses
considerations of national policy'."42 It cites, in particular, the "national power crisis" as a
of Congress must approve or disapprove. The courts should not allow that language to be
consideration of national policy militating against delay in construction of nuclear power
significantly undercut. In cases such as this one, the most we should do to interpret clear
facilities.
statutory wording is to see that the overriding purpose behind the wording supports its plain
meaning. We have done that here. And we conclude that Section 104 of NEPA does not permit The Commission relies upon the flexible NEPA mandate to "use all practicable means
the sort of total abdication of responsibility practiced by the Atomic Energy Commission. consistent with other essential considerations of national policy." As we have previously pointed
out, however, that mandate applies only to the substantive guidelines set forth in Section 101
V of the Act. See page 1114 supra. The procedural duties, the duties to give full consideration to
environmental protection, are subject to a much more strict standard of compliance. By now,
Petitioners' final attack is on the Commission's rules governing a particular set of nuclear the applicable principle should be absolutely clear. NEPA requires that an agency must — to
facilities: those for which construction permits were granted without consideration of the fullest extent possible under its other statutory obligations — consider alternatives to its
environmental issues, but for which operating licenses have yet to be issued. These facilities, actions which would reduce environmental damage. That principle establishes that
still in varying stages of construction, include the one of most immediate concern to one of the consideration of environmental matters must be more than a pro forma ritual. Clearly, it is
petitioners: the Calvert Cliffs nuclear power plant on Chesapeake Bay in Maryland. pointless to "consider" environmental costs without also seriously considering action to avoid
The Commission's rules recognize that the granting of a construction permit before NEPA's them. Such a full exercise of substantive discretion is required at every important, appropriate
effective date does not justify bland inattention to environmental consequences until the and nonduplicative stage of an agency's proceedings. See text at page 1114 supra.
operating license proceedings, perhaps far in the future. The rules require that measures be The special importance of the pre-operating license stage is not difficult to fathom. In cases
taken now for environmental protection. Specifically, the Commission has provided for three where environmental costs were not considered in granting a construction permit, it is very
such measures during the pre-operating license stage. First, it has required that a condition be likely that the planned facility will include some features which do significant damage to the
added to all construction permits, "whenever issued," which would oblige the holders of the environment and which could not have survived a rigorous balancing of costs and benefits. At
permits to observe all applicable environmental standards imposed by federal or state law. the later operating license proceedings, this environmental damage will have to be fully
Second, it has required permit holders to submit their own environmental report on the facility considered. But by that time the situation will have changed radically. Once a facility has been
under construction. And third, it has initiated procedures for the drafting of its staff's "detailed completely constructed, the economic cost of any alteration may be very great. In the language
environmental statement" in advance of operating license proceedings. 41 of NEPA, there is likely to be an "irreversible and irretrievable commitment of resources," which
The one thing the Commission has refused to do is take any independent action based upon will inevitably restrict the Commission's options. Either the licensee will have to undergo a major
the material in the environmental reports and "detailed statements." Whatever environmental expense in making alterations in a completed facility or the environmental harm will have to be
damage the reports and statements may reveal, the Commission will allow construction to tolerated. It is all too probable that the latter result would come to pass.
proceed on the original plans. It will not even consider requiring alterations in those plans By refusing to consider requirement of alterations until construction is completed, the
(beyond compliance with external standards which would be binding in any event), though the Commission may effectively foreclose the environmental protection desired by Congress. It
"detailed statements" must contain an analysis of possible alternatives and may suggest may also foreclose rigorous consideration of environmental factors at the eventual operating
relatively inexpensive but highly beneficial changes. Moreover, the Commission has, as a license proceedings. If "irreversible and irretrievable commitment [s] of resources" have already
blanket policy, refused to consider the possibility of temporarily halting construction in particular been made, the license hearing (and any public intervention therein) may become a hollow
cases pending a full study of a facility's environmental impact. It has also refused to weigh the exercise. This hardly amounts to consideration of environmental values "to the fullest extent
pros and cons of "backfitting" for particular facilities (alteration of already constructed portions possible."
of the facilities in order to incorporate new technological developments designed to protect the
environment). Thus reports and statements will be produced, but nothing will be done with A full NEPA consideration of alterations in the original plans of a facility, then, is both important
and appropriate well before the operating license proceedings. It is not duplicative if

21
environmental issues were not considered in granting the construction permit. And it need not TITLE I
be duplicated, absent new information or new developments, at the operating license stage. In
order that the pre-operating license review be as effective as possible, the Commission should DECLARATION OF NATIONAL ENVIRONMENTAL POLICY
consider very seriously the requirement of a temporary halt in construction pending its review
and the "backfitting" of technological innovations. For no action which might minimize Sec. 101. (a) The Congress, recognizing the profound impact of man's activity on the
environmental damage may be dismissed out of hand. Of course, final operation of the facility interrelations of all components of the natural environment, particularly the profound influences
may be delayed thereby. But some delay is inherent whenever the NEPA consideration is of population growth, high-density urbanization, industrial expansion, resource exploitation,
conducted — whether before or at the license proceedings. It is far more consistent with the and new and expanding technological advances and recognizing further the critical importance
purposes of the Act to delay operation at a stage where real environmental protection may of restoring and maintaining environmental quality to the overall welfare and development of
come about than at a stage where corrective action may be so costly as to be impossible. man, declares that it is the continuing policy of the Federal Government, in co-operation with
State and local governments, and other concerned public and private organizations, to use all
Thus we conclude that the Commission must go farther than it has in its present rules. It must practicable means and measures, including financial and technical assistance, in a manner
consider action, as well as file reports and papers, at the pre-operating license stage. As the calculated to foster and promote the general welfare, to create and maintain conditions under
Commission candidly admits, such consideration does not amount to a retroactive application which man and nature can exist in productive harmony, and fulfill the social, economic, and
of NEPA. Although the projects in question may have been commenced and initially approved other requirements of present and future generations of Americans.
before January 1, 1970, the Act clearly applies to them since they must still pass muster before
going into full operation.43 All we demand is that the environmental review be as full and fruitful (b) In order to carry out the policy set forth in this Act, it is the continuing responsibility of the
as possible. Federal Government to use all practicable means, consistent with other essential
considerations of national policy, to improve and coordinate Federal plans, functions,
programs, and resources to the end that the Nation may —
VI
(1) fulfill the responsibilities of each generation as trustee of the environment for succeeding
We hold that, in the four respects detailed above, the Commission must revise its rules
generations;
governing consideration of environmental issues. We do not impose a harsh burden on the
Commission. For we require only an exercise of substantive discretion which will protect the (2) assure for all Americans safe, healthful, productive, and esthetically and culturally pleasing
environment "to the fullest extent possible." No less is required if the grand congressional surroundings;
purposes underlying NEPA are to become a reality.
(3) attain the widest range of beneficial uses of the environment without degradation, risk to
Remanded for proceedings consistent with this opinion. health or safety, or other undesirable and unintended consequences;
(4) preserve important historic, cultural, and natural aspects of our national heritage, and
APPENDIX maintain, wherever possible, an environment which supports diversity and variety of individual
choice;
Public Law 91-190 91st Congress, S. 1075 January 1, 1970 An Act
(5) achieve a balance between population and resource use which will permit high standards
To establish a national policy for the environment, to provide for the establishment of a Council of living and a wide sharing of life's amenities; and
on Environmental Quality, and for other purposes.
(6) enhance the quality of renewable resources and approach the maximum attainable
Be it enacted by the Senate and House of Representatives of the United States of America in recycling of depletable resources.
Congress assembled, That this Act may be cited as the "National Environmental Policy Act of
1969." (c) The Congress recognizes that each person should enjoy a healthful environment and that
each person has a responsibility to contribute to the preservation and enhancement of the
environment.
PURPOSE
Sec. 102. The Congress authorizes and directs that, to the fullest extent possible: (1) the
Sec. 2. The purposes of this Act are: To declare a national policy which will encourage
policies, regulations, and public laws of the United States shall be interpreted and administered
productive and enjoyable harmony between man and his environment; to promote efforts which
in accordance with the policies set forth in this Act, and (2) all agencies of the Federal
will prevent or eliminate damage to the environment and biosphere and stimulate the health Government shall —
and welfare of man; to enrich the understanding of the ecological systems and natural
resources important to the Nation; and to establish a Council on Environmental Quality. (A) utilize a systematic, interdisciplinary approach which will insure the integrated use of the
natural and social sciences and the environmental design arts in planning and in
decisionmaking which may have an impact on man's environment;
(B) identify and develop methods and procedures, in consultation with the Council on whether there are any deficiencies or inconsistencies therein which prohibit full compliance with
Environmental Quality established by title II of this Act, which will insure that presently the purposes and provisions of this Act and shall propose to the President not later than July
unquantified environmental amenities and values may be given appropriate consideration in 1, 1971, such measures as may be necessary to bring their authority and policies into
decisionmaking along with economic and technical considerations; conformity with the intent, purposes, and procedures set forth in this Act.
(C) include in every recommendation or report on proposals for legislation and other major Sec. 104. Nothing in Section 102 or 103 shall in any way affect the specific statutory obligations
Federal actions significantly affecting the quality of the human environment, a detailed of any Federal agency (1) to comply with criteria or standards of environmental quality, (2) to
statement by the responsible official on — coordinate or consult with any other Federal or State agency, or (3) to act, or refrain from acting
contingent upon the recommendations or certification of any other Federal or State agency.
(i) the environmental impact of the proposed action,
Sec. 105. The policies and goals set forth in this Act are supplementary to those set forth in
(ii) any adverse environmental effects which cannot be avoided should the proposal be
existing authorizations of Federal agencies.
implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of man's environment and the maintenance U.S. Supreme Court
and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be involved in the Strycker's Bay Neighborhood Council v. Karlen, 444 U.S. 223 (1980)
proposed action should it be implemented.
Strycker's Bay Neighborhood Council, Inc. v. Karlen No. 79-168
Prior to making any detailed statement, the responsible Federal official shall consult with and
obtain the comments of any Federal agency which has jurisdiction by law or special expertise
with respect to any environmental impact involved. Copies of such statement and the Decided January 7, 1980444 U.S. 223ast|>* 444 U.S. 223
comments and views of the appropriate Federal, State, and local agencies, which are
authorized to develop and enforce environmental standards, shall be made available to the CERTIORARI TO THE UNITED STATES COURT OF APPEALS
President, the Council on Environmental Quality and to the public as provided by section 552
of title 5, United States Code, and shall accompany the proposal through the existing agency FOR THE SECOND CIRCUIT
review processes;
(D) study, develop, and describe appropriate alternatives to recommended courses of action in Syllabus
any proposal which involves unresolved conflicts concerning alternative uses of available
resources; Held: The Court of Appeals erred in concluding that, when the Department of Housing and
(E) recognize the worldwide and long-range character of environmental problems and, where Urban Development (HUD) considered alternative sites before redesignating a proposed site
consistent with the foreign policy of the United States, lend appropriate support to initiatives, for middle-income housing as one for low-income housing it should have given determinative
resolutions, and programs designed to maximize international cooperation in anticipating and weight to environmental factors such as crowding low-income housing into a concentrated area
preventing a decline in the quality of mankind's world environment; and should not have considered the delay that would occur in developing an alternative site as
an overriding factor. Once an agency has made a decision subject to the procedural
(F) make available to States, counties, municipalities, institutions, and individuals, advice and requirements of the National Environmental Policy Act of 1969, the only role for a court is to
information useful in restoring, maintaining, and enhancing the quality of the environment; insure that the agency has considered the environmental consequences; it cannot interject
(G) initiate and utilize ecological information in the planning and development of resource- itself within the area of discretion of the executive as to the choice of the action to be taken.
oriented projects; and Here, there is no doubt that HUD considered the environmental consequences of its decision
to re-designate the proposed site for low-income housing, and the Act requires no more.
(H) assist the Council on Environmental Quality established by title II of this Act.
Sec. 103. All agencies of the Federal Government shall review their present statutory authority, Certiorari granted; 590 F.2d 39, reversed.
administrative regulations, and current policies and procedures for the purpose of determining

23
PER CURIAM. "study, develop, and describe appropriate alternatives to recommended courses of action in
any proposal which involves unresolved conflicts concerning alternative uses of available
The protracted nature of this litigation is perhaps best illustrated by the identity of the original resources."
federal defendant, "George Romney, Secretary of the Department of Housing and Urban
Development." At the center of this dispute is the site of a proposed low-income housing project 42 U.S.C. § 4332(2)(E). See 523 F.2d at 995. According to the Court of Appeals, any
to be constructed on Manhattan's Upper West Side. In 1962, the New York City Planning consideration by HUD of alternatives to placing low-income housing on the site "was either
Commission (Commission), acting in conjunction with the United States Department of Housing highly limited or nonexistent." Id. at 94. Citing the "background of urban environmental factors"
and Urban Development (HUD), began formulating a behind HUD's decision, the Court of Appeals remanded the case, requiring HUD to prepare a
"statement of possible alternatives, the consequences thereof and the facts and reasons for
Page 444 U. S. 224 and against. . . ." Ibid. The statement was not to reflect "HUD's concept or the Housing
Authority's views as to how these agencies would choose to resolve the city's low income group
housing situation," but rather was to explain
plan for the renewal of 20 square blocks known as the "West Side Urban Renewal Area"
(WSURA) through a joint effort on the part of private parties and various government agencies.
As originally written, the plan called for a mix of 70% middle-income housing and 30% low- "how, within the framework of the Plan, its objective of economic integration can best be
income housing and designated the site at issue here as the location of one of the middle- achieved with a minimum of adverse environmental impact."
income projects. In 1969, after substantial progress toward completion of the plan, local
agencies in New York determined that the number of low-income units proposed for WSURA Ibid. The Court of Appeals believed that, given such an assessment of alternatives, "the
would be insufficient to satisfy an increased need for such units. In response to this shortage, agencies with the cooperation of the interested parties should be able to arrive at an equitable
the Commission amended the plan to designate the site as the future location of a high-rise solution." Id. at 95.
building containing 160 units of low-income housing. HUD approved this amendment in
December, 1972. On remand, HUD prepared a lengthy report entitled Special Environmental Clearance (1977).
After marshaling the data, the report asserted that,
Meanwhile, in October, 1971, the Trinity Episcopal School Corp. (Trinity), which had
participated in the plan by building a combination school and middle-income housing "while the choice of Site 30 for development as a 100 percent low-income project has raised
development at a nearby location, sued in the United States District Court for the Southern
District of New York to enjoin the Commission and HUD from constructing low-income housing
Page 444 U. S. 226
on the site. The present respondents, Roland N. Karlen, Alvin C. Hudgins, and the Committee
of Neighbors To Insure a Normal Urban Environment (CONTINUE), intervened as plaintiffs,
while petitioner Strycker's Bay Neighborhood Council, Inc., intervened as a defendant. valid questions about the potential social environmental impacts involved, the problems
associated with the impact on social fabric and community structures are not considered so
serious as to require that this component be rated as unacceptable."
The District Court entered judgment in favor of petitioners. See Trinity Episcopal School Corp.
v. Romney, 387 F. Supp. 1044 (1974). It concluded, inter alia, that petitioners had not violated
the National Environmental Policy Act of 1969 (NEPA), 83 Stat. 852, 42 U.S.C. § 4321 et seq. Special Environmental Clearance Report 42. The last portion of the report incorporated a study
wherein the Commission evaluated nine alternative locations for the project, and found none
of them acceptable. While HUD's report conceded that this study may not have considered all
On respondents' appeal, the Second Circuit affirmed all but the District Court's treatment of the
possible alternatives, it credited the Commission's conclusion that any relocation of the units
NEPA claim. See Trinity Episcopal School Corp. v. Romney, 523 F.2d 88
would entail an unacceptable delay of two years or more. According to HUD,

Page 444 U. S. 225


"[m]easured against the environmental costs associated with the minimum two-year delay, the
benefits seem insufficient to justify a mandated substitution of sites."
(1975). While the Court of Appeals agreed with the District Court that HUD was not required to
prepare a full-scale environmental impact statement under § 102(2)(C) of NEPA, 42 U.S.C. § Id. at 54.
4332(2)(C), it held hat HUD had not complied with § 102(2)(E), [Footnote 1] which requires an
agency to
After soliciting the parties' comments on HUD's report, the District Court again entered
judgment in favor of petitioners. See Trinity Episcopal School Corp. v. Harris, 445 F. Supp.
204 (1978). The court was "impressed with HUD's analysis as being thorough and In the present litigation, there is no doubt that HUD considered the environmental
exhaustive," id. at 209-210, and found that "HUD's consideration of the alternatives was neither consequences of its decision to redesignate the proposed site for low-income housing. NEPA
arbitrary nor capricious"; on the contrary, "[i]t was done in good faith and in full accordance with requires no more. The petitions for certiorari are granted, and the judgment of the Court of
the law." Id. at 220. Appeals is therefore

On appal, the Second Circuit vacated and remanded again. Karlen v. Harris, 590 F.2d 39 Reversed.
(1978). The appellate court focused upon that part of HUD's report where the agency
considered and rejected alternative sites, and in particular upon HUD's reliance on the delay * Together with No. 79-181, City of New York v. Karlen et al.; and No. 79-184, Secretary of
such a relocation would entail. The Court of Appeals purported to recognize that its role in Housing and Urban Development v. Karlen et al., also on petitions for certiorari to the same
reviewing HUD's decision was defined by the Administrative Procedure Act (APA), 5 U.S.C. § court.
706(2)(A), which provides that agency actions should be set aside if found to be "arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law. . . ." Additionally,
[Footnote 1]

Page 444 U. S. 227


At the time of the Court of Appeals' decision, this section was numbered 102(2)(D) and was
codified at 42 U.S.C. § 4332(2)(D) (1970 ed.). Congress redesignated it two weeks
however, the Court of Appeals looked to "[t]he provisions of NEPA" for "the substantive later. See Act of Aug. 9, 1975, Pub.L. 94-83, 89 Stat. 424.
standards necessary to review the merits of agency decisions. . . ." 590 F.2d at 43. The Court
of Appeals conceded that HUD had "given consideration' to alternatives" to redesignating the
[Footnote 2]
site. Id. at 44. Nevertheless, the court believed that "`consideration' is not an end in
itself." Ibid. Concentrating on HUD's finding that development of an alternative location would
entail an unacceptable delay, the appellate court held that such delay could not be "an If we could agree with the dissent that the Court of Appeals held that HUD had acted "arbitrarily"
overriding factor" in HUD's decision to proceed with the development. Ibid. According to the in redesignating the site for low-income housing, we might also agree that plenary review is
court, when HUD considers such projects, "environmental factors, such as crowding low- warranted. But the District Court expressly concluded that HUD had not acted arbitrarily or
income housing into a concentrated area, should be given determinative weight." Ibid. The capriciously, and our reading of the opinion of the Court of Appeals satisfies us that it did not
Court of Appeals therefore remanded the case to the District Court, instructing HUD to attack overturn that finding. Instead, the appellate court required HUD to elevate environmental
the shortage of low-income housing in a manner that would avoid the "concentration" of such concerns over other, admittedly legitimate, considerations. Neither NEPA nor the APA provides
housing on Site 30. Id. at 45. In Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U. S. any support for such a reordering of priorities by a reviewing court.
519, 435 U. S. 558 (1978), we stated that NEPA, while establishing "significant substantive
goals for the Nation," imposes upon agencies duties that are "essentially procedural." As we MR. JUSTICE MARSHALL, dissenting.
stressed in that case, NEPA was designed "to insure a fully informed and well considered
decision," but not necessarily "a decision the judges of the Court of Appeals or of this Court The issue raised by these cases is far more difficult than the per curiam opinion suggests. The
would have reached had they been members of the decisionmaking unit of the Court of Appeals held that the Secretary of Housing and Urban Development (HUD) had acted
agency." Ibid. Vermont Yankee cuts sharply against the Court of Appeals' conclusion that an arbitrarily in concluding that prevention of a delay in the construction process justified the
agency, in selecting a course of action, must elevate environmental concerns over other selection of a housing site which could produce adverse social environmental effects, including
appropriate considerations. On the contrary, once an agency has made a decision subject to racial and economic concentration. Today the majority responds that,
NEPA's procedural requirements, the only role for a court is to insure that the agency has
considered the environmental consequences; it cannot " 'interject itself within the area of "once an agency has made a decision subject to NEPA's procedural requirements, the only
discretion of the executive as to the choice of the action to role for a court is to insure that the agency has considered the environmental consequences,"

Page 444 U. S. 228 and that, in this litigation,

be taken.'" Kleppe v. Sierra Club, 427 U. S. 390, 427 U. S. 410, n. 21 (1976). See also FPC "there is no doubt that HUD considered the environmental consequences of its decision to
v. Transcontinental Gas Pipe Line Corp., 423 U. S. 326 (1976). [Footnote 2] redesignate the proposed site for low-income housing. NEPA requires no more."
25
The majority finds support for this conclusion in the closing paragraph integration. The environmental "impact . . . on social fabric and community structures" was
given a B rating in the report, indicating that, from this perspective, the project is "questionable"
Page 444 U. S. 229 and ameliorative measures are "mandated." The report lists 10 ameliorative measures
necessary to make the project acceptable. The report also discusses two alternatives, Sites 9
of our decision in Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U. S. 519, 435 U. S. and 41, both of which are the appropriate size for the project and require "only minimal"
amounts of relocation and clearance. Concerning Site 9, the report explicitly concludes that
558 (1978).
"[f]rom the standpoint of social environmental impact, this location would be superior to Site 30
for the development of low-rent public housing." The sole reason for rejecting the
Vermont Yankee does not stand for the broad proposition that the majority advances today. environmentally superior site was the fact that, if the location were shifted to Site 9, there would
The relevant passage in that opinion was meant to be only a "further observation of some be a projected delay of two years in the construction of the housing.
relevance to this case," id. at 435 U. S. 557. That "observation" was a response to this Court's
perception that the Court of Appeals in that case was attempting, "under the guise of judicial
The issue before the Court of Appeals, therefore, was whether HUD was free under NEPA to
review of agency action," to assert its own policy judgment as to the desirability of developing
nuclear energy as an energy source for this Nation, a judgment which is properly left to reject an alternative acknowledged to be environmentally preferable solely on the ground that
Congress. Id. at 435 U. S. 558. The Court of Appeals had remanded the case to the agency any change in sites would cause delay. This was hardly a "peripheral issue" in the case.
Whether NEPA, which sets forth "significant substantive goals," Vermont Yankee Nuclear
because of "a single alleged oversight on a peripheral issue, urged by parties who never fully
Power Corp. v. NRDC, supra at 435 U. S. 558, permits a projected 2-year time difference to
cooperated or indeed raised the issue below," ibid. It was in this context that the Court
be controlling over environmental superiority is by no means clear. Resolution of the issue,
remarked that "NEPA does set forth significant substantive goals for the Nation, but its mandate
to the agencies is essentially procedural." Ibid.(emphasis supplied). Accordingly, however, is certainly within the normal scope of review of agency action to determine if it is
arbitrary,
"[a]dministrative decisions should be set aside in this context, as in every other, only for
substantial procedural or substantive reasons as mandated by statute," Page 444 U. S. 231

ibid. (emphasis supplied). Thus, Vermont Yankee does not stand for the proposition that a capricious, or an abuse of discretion.* The question whether HUD can make delay the
court reviewing agency action under NEPA is limited solely to the factual issue of whether the paramount concern over environmental superiority is essentially a restatement of the question
whether HUD in considering the environmental consequences of its proposed action gave
agency "considered" environmental consequences. The agency's decision must still be set
those consequences a "hard look," which is exactly the proper question for the reviewing court
aside if it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with
to ask. Kleppe v. Sierra Club, supra at 427 U. S. 410, n. 21.
law," 5 U.S.C. § 706(2)(A), and the reviewing court must still insure that the agency "has taken
a hard look' at environmental consequences," Kleppe v. Sierra Club,427 U. S. 390, 427 U. S.
410, n. 21 (1976). The issue of whether the Secretary's decision was arbitrary or capricious is sufficiently difficult
and important to merit plenary consideration in this Court. Further, I do not subscribe to the
Court's apparent suggestion that Vermont Yankee limits the reviewing court to the essentially
In the present case, the Court of Appeals did not "substitute its judgment for that of the agency
as to the environmental consequences of its actions," ibid., for HUD, in its mindless task of determining whether an agency "considered" environmental factors even if
that agency may have effectively decided to ignore those factors in reaching its conclusion.
Indeed, I cannot believe that the Court would adhere to that position in a different factual setting.
Page 444 U. S. 230 Our cases establish that the "arbitrary or capricious" standard prescribes a "searching and
careful" judicial inquiry designed to ensure that the agency has not exercised its discretion in
Special Environmental Clearance Report, acknowledged the adverse environmental an unreasonable manner. Citizens To Preserve Overton Park, Inc. v. Volpe, 401 U. S.
consequences of its proposed action: 402, 401 U. S. 416 (1971). Believing that today's summary reversal represents a departure
from that principle, I respectfully dissent.
"the choice of Site 30 for development as a 100 percent low-income project has raised valid
questions about the potential social environmental impacts involved." It is apparent to me that this is not the type of case for a summary disposition. We should at
least have a plenary hearing.
These valid questions arise from the fact that 68% of all public housing units would be sited on
only one cross-town axis in this area of New York City. As the Court of Appeals observed, the * The Secretary concedes that, if an agency gave little or no weight to environmental values,
resulting high concentration of low-income housing would hardly further racial and economic its decision might be arbitrary or capricious. Pet. for Cert. in No. 7184, p. 15, n. 16.
FIRST DIVISION [G.R. No. 148622. September 12, 2002.] favor of respondent upon submission of the required documents.

REPUBLIC OF THE PHILIPPINES, represented by HON. HEHERSON T. ALVAREZ, in his The Regional Trial Court rendered judgment in favor of respondent, the dispositive portion of
capacity as Secretary of the DEPARTMENT OF ENVIRONMENT AND NATURAL which reads as follows:chanrob1es virtual 1aw library
RESOURCES (DENR), CLARENCE L. BAGUILAT, in his capacity as the Regional
Executive Director of DENR-Region XI and ENGR. BIENVENIDO L. LIPAYON, in his WHEREFORE, finding the petition to be meritorious, judgment granting the writ of mandamus
capacity as the Regional Director of the DENR-ENVIRONMENTAL MANAGEMENT and injunction is hereby rendered in favor of the petitioner City of Davao and against
BUREAU (DENR-EMB), Region XI, Petitioners, respondents Department of Environment and Natural Resources and the other respondents
v. THE CITY OF DAVAO, represented by BENJAMIN C. DE GUZMAN, City by:chanrob1es virtual 1aw library
Mayor, Respondent.
1) directing the respondents to issue in favor of the petitioner City of Davao a Certificate of
DECISION Non-Coverage, pursuant to Presidential Decree No. 1586 and related laws, in connection with
the construction by the City of Davao of the Artica Sports Dome;

YNARES-SANTIAGO, J.: 2) making the preliminary injunction issued on December 12, 2000 permanent. Costs de oficio.
SO ORDERED.

Before us is a petition for review 1 on certiorari assailing the decision 2 dated May 28, 2001 of The trial court ratiocinated that there is nothing in PD 1586, in relation to PD 1151 and Letter
the Regional Trial Court of Davao City, Branch 33, which granted the writ of mandamus and of Instruction No. 1179 (prescribing guidelines for compliance with the EIA system), which
injunction in favor of respondent, the City of Davao, and against petitioner, the Republic, requires local government units (LGUs) to comply with the EIS law. Only agencies and
represented by the Department of Environment and Natural Resources (DENR). The trial court instrumentalities of the national government, including government owned or controlled
also directed petitioner to issue a Certificate of Non-Coverage in favor corporations, as well as private corporations, firms and entities are mandated to go through the
of Respondent.chanrob1es virtua1 1aw 1ibrary EIA process for their proposed projects which have significant effect on the quality of the
environment. A local government unit, not being an agency or instrumentality of the National
The antecedent facts of the case are as follows:chanrob1es virtual 1aw library Government, is deemed excluded under the principle of expressio unius est exclusio alterius.

On August 11, 2000, respondent filed an application for a Certificate of Non-Coverage (CNC) The trial court also declared, based on the certifications of the DENR-Community Environment
for its proposed project, the Davao City Artica Sports Dome, with the Environmental and Natural Resources Office (CENRO)-West, and the data gathered from the Philippine
Management Bureau (EMB), Region XI. Attached to the application were the required Institute of Volcanology and Seismology (PHIVOLCS), that the site for the Artica Sports Dome
documents for its issuance, namely, a) detailed location map of the project site; b) brief project was not within an environmentally critical area. Neither was the project an environmentally
description; and c) a certification from the City Planning and Development Office that the project critical one. It therefore becomes mandatory for the DENR, through the EMB Region XI, to
is not located in an environmentally critical area (ECA). The EMB Region XI denied the approve respondent’s application for CNC after it has satisfied all the requirements for its
application after finding that the proposed project was within an environmentally critical area issuance. Accordingly, petitioner can be compelled by a writ of mandamus to issue the CNC, if
and ruled that, pursuant to Section 2, Presidential Decree No. 1586, otherwise known as the it refuses to do so.
Environmental Impact Statement System, in relation to Section 4 of Presidential Decree No.
1151, also known as the Philippine Environment Policy, the City of Davao must undergo the Petitioner filed a motion for reconsideration, however, the same was denied. Hence, the instant
environmental impact assessment (EIA) process to secure an Environmental Compliance petition for review.
Certificate (ECC), before it can proceed with the construction of its project.
With the supervening change of administration, respondent, in lieu of a comment, filed a
Believing that it was entitled to a Certificate of Non-Coverage, respondent filed a petition for manifestation expressing its agreement with petitioner that, indeed, it needs to secure an ECC
mandamus and injunction with the Regional Trial Court of Davao, docketed as Civil Case No. for its proposed project. It thus rendered the instant petition moot and academic. However, for
28, 133-2000. It alleged that its proposed project was neither an environmentally critical project the guidance of the implementors of the EIS law and pursuant to our symbolic function to
nor within an environmentally critical area; thus it was outside the scope of the EIS system. educate the bench and bar, 4 we are inclined to address the issue raised in this petition.
Hence, it was the ministerial duty of the DENR, through the EMB-Region XI, to issue a CNC in
27
Section 15 of Republic Act 7160, 5 otherwise known as the Local Government Code, defines Environmental Compliance Certificate issued by the President or his duly authorized
a local government unit as a body politic and corporate endowed with powers to be exercised representative." 13 The Civil Code defines a person as either natural or juridical. The state and
by it in conformity with law. As such, it performs dual functions, governmental and proprietary. its political subdivisions, i.e., the local government units 14 are juridical persons. 15
Governmental functions are those that concern the health, safety and the advancement of the Undoubtedly therefore, local government units are not excluded from the coverage of PD 1586.
public good or welfare as affecting the public generally. 6 Proprietary functions are those that
seek to obtain special corporate benefits or earn pecuniary profit and intended for private Lastly, very clear in Section 1 of PD 1586 that said law intends to implement the policy of the
advantage and benefit. 7 When exercising governmental powers and performing governmental state to achieve a balance between socio-economic development and environmental
duties, an LGU is an agency of the national government. 8 When engaged in corporate protection, which are the twin goals of sustainable development. The above-quoted first
activities, it acts as an agent of the community in the administration of local affairs. 9 paragraph of the Whereas clause stresses that this can only be possible if we adopt a
comprehensive and integrated environmental protection program where all the sectors of the
Found in Section 16 of the Local Government Code is the duty of the LGUs to promote the community are involved, i.e., the government and the private sectors. The local government
people’s right to a balanced ecology. 10 Pursuant to this, an LGU, like the City of Davao, can units, as part of the machinery of the government, cannot therefore be deemed as outside the
not claim exemption from the coverage of PD 1586. As a body politic endowed with scope of the EIS system.
governmental functions, an LGU has the duty to ensure the quality of the environment, which The foregoing arguments, however, presuppose that a project, for which an Environmental
is the very same objective of PD 1586.chanrob1es virtua1 1aw 1ibrary Compliance Certificate is necessary, is environmentally critical or within an environmentally
critical area. In the case at bar, respondent has sufficiently shown that the Artica Sports Dome
Further, it is a rule of statutory construction that every part of a statute must be interpreted with will not have a significant negative environmental impact because it is not an environmentally
reference to the context, i.e., that every part must be considered with other parts, and kept critical project and it is not located in an environmentally critical area. In support of this
subservient to the general intent of the enactment. 11 The trial court, in declaring local contention, respondent submitted the following:chanrob1es virtual 1aw library
government units as exempt from the coverage of the EIS law, failed to relate Section 2 of PD
1586 12 to the following provisions of the same law:chanrob1es virtual 1aw library 1. Certification from the City Planning and Development Office that the project is not located in
an environmentally critical area;
WHEREAS, the pursuit of a comprehensive and integrated environmental protection program
necessitates the establishment and institutionalization of a system whereby the exigencies of 2. Certification from the Community Environment and Natural Resources Office (CENRO-West)
socio-economic undertakings can be reconciled with the requirements of environmental quality; that the project area is within the 18-30% slope, is outside the scope of the NIPAS (R.A. 7586),
. . . and not within a declared watershed area; and

Section 1. Policy. — It is hereby declared the policy of the State to attain and maintain a rational 3. Certification from PHILVOCS that the project site is thirty-seven (37) kilometers southeast of
and orderly balance between socio-economic growth and environmental protection. the southernmost extension of the Davao River Fault and forty-five (45) kilometers west of the
Eastern Mindanao Fault; and is outside the required minimum buffer zone of five (5) meters
x x x from a fault zone.

The trial court, after a consideration of the evidence, found that the Artica Sports Dome is not
Section 4. Presidential Proclamation of Environmentally Critical Areas and Projects. — The within an environmentally critical area. Neither is it an environmentally critical project. It is
President of the Philippines may, on his own initiative or upon recommendation of the National axiomatic that factual findings of the trial court, when fully supported by the evidence on record,
Environmental Protection Council, by proclamation declare certain projects, undertakings or are binding upon this Court and will not be disturbed on appeal. 17 This Court is not a trier of
areas in the country as environmentally critical. No person, partnership or corporation shall facts. 18
undertake or operate any such declared environmentally critical project or area without first
securing an Environmental Compliance Certificate issued by the President or his duly There are exceptional instances when this Court may disregard factual findings of the trial
authorized representative. For the proper management of said critical project or area, the court, namely: a) when the conclusion is a finding grounded entirely on speculations, surmises,
President may by his proclamation reorganize such government offices, agencies, institutions, or conjectures; b) when the inference made is manifestly mistaken, absurd, or impossible; c)
corporations or instrumentalities including the realignment of government personnel, and their where there is a grave abuse of discretion; d) when the judgment is based on a
specific functions and responsibilities. misapprehension of facts; e) when the findings of fact are conflicting; f) when the Court of
Appeals, in making its findings, went beyond the issues of the case and the same are contrary
Section 4 of PD 1586 clearly states that "no person, partnership or corporation shall undertake to the admissions of both appellant and appellee; g) when the findings of the Court of Appeals
or operate any such declared environmentally critical project or area without first securing an are contrary to those of the trial court; h) when the findings of fact are conclusions without
citation of specific evidence on which they are based; i) when the finding of fact of the Court of the Environmental Impact Statement System, shall be by Presidential Proclamation, in
Appeals is premised on the supposed absence of evidence but is contradicted by the evidence accordance with Section 4 of PD 1586 quoted above.
on record; and j) when the Court of Appeals manifestly overlooked certain relevant facts not
disputed by the parties and which, if properly considered, would justify a different conclusion. Pursuant thereto, Proclamation No. 2146 was issued on December 14, 1981, proclaiming the
19 None of these exceptions, however, obtain in this case. following areas and types of projects as environmentally critical and within the scope of the
Environmental Impact Statement System established under PD 1586:chanrob1es virtual 1aw
The Environmental Impact Statement System, which ensures environmental protection and library
regulates certain government activities affecting the environment, was established by
Presidential Decree No. 1586. Section 2 thereof states:chanrob1es virtual 1aw library A. Environmentally Critical Projects
I. Heavy Industries
There is hereby established an Environmental Impact Statement System founded and based a. Non-ferrous metal industries
on the environmental impact statement required under Section 4 of Presidential Decree No. b. Iron and steel mills
1151, of all agencies and instrumentalities of the national government, including government- c. Petroleum and petro-chemical industries including oil and gas
owned or controlled corporations, as well as private corporations, firms and entities, for every d. Smelting plants
proposed project and undertaking which significantly affect the quality of the environment. II. Resource Extractive Industries
a. Major mining and quarrying project
Section 4 of PD 1151, on the other hand, provides:chanrob1es virtual 1aw library b. Forestry projects
1. Logging
Environmental Impact Statements. — Pursuant to the above enunciated policies and goals, all 2. Major wood processing projects
agencies and instrumentalities of the national government, including government-owned or 3. Introduction of fauna (exotic-animals) in public/private forests
controlled corporations, as well as private corporations, firms and entities shall prepare, file and 4. Forest occupancy
include in every action, project or undertaking which significantly affects the quality of the 5. Extraction of mangrove products
environment a detailed statement on — 6. Grazing
c. Fishery Projects
(a) the environmental impact of the proposed action, project or undertaking 1. Dikes for/and fishpond development projects
III. Infrastructure Projects
(b) any adverse environmental effect which cannot be avoided should the proposal be a. Major dams
implemented b. Major power plants (fossil-fueled, nuclear fueled, hydroelectric or geothermal)
c. Major reclamation projects
(c) alternative to the proposed action d. Major roads and bridges
B. Environmentally Critical Areas
(d) a determination that the short-term uses of the resources of the environment are consistent 1. All areas declared by law as national parks, watershed reserves, wildlife preserves and
with the maintenance and enhancement of the long-term productivity of the same; and sanctuaries;
2. Areas set aside as aesthetic potential tourist spots;
(e) whenever a proposal involves the use of depletable or nonrenewable resources, a finding 3. Areas which constitute the habitat for any endangered or threatened species of indigenous
must be made that such use and commitment are warranted. Philippine Wildlife (flora and fauna);
4. Areas of unique historic, archaeological, or scientific interests;
Before an environmental impact statement is issued by a lead agency, all agencies having 5. Areas which are traditionally occupied by cultural communities or tribes;
jurisdiction over, or special expertise on, the subject matter involved shall comment on the draft 6. Areas frequently visited and/or hard-hit by natural calamities (geologic hazards, floods,
environmental impact statement made by the lead agency within thirty (30) days from receipt typhoons, volcanic activity, etc.);
of the same. 7. Areas with critical slopes;
8. Areas classified as prime agricultural lands;
Under Article II, Section 1, of the Rules and Regulations Implementing PD 1586, the declaration 9. Recharged areas of aquifers;
of certain projects or areas as environmentally critical, and which shall fall within the scope of 10. Water bodies characterized by one or any combination of the following conditions;
29
a. tapped for domestic purposes G.R. No. 160932 January 14, 2013
b. within the controlled and/or protected areas declared by appropriate authorities
c. which support wildlife and fishery activities SPECIAL PEOPLE, INC. FOUNDATION, REPRESENTED BY ITS CHAIRMAN, ROBERTO
11. Mangrove areas characterized by one or any combination of the following conditions: P. CERICOS, Petitioner,
a. with primary pristine and dense young growth; vs.
b. adjoining mouth of major river systems; NESTOR M. CANDA, BIENVENIDO LIPA YON, JULIAN D. AMADOR, BOHOL PROVINCIAL
c. near or adjacent to traditional productive fry or fishing grounds; CHIEF, REGIONAL DIRECTOR, AND NATIONAL DIRECTOR, RESPECTIVELY,
d. which act as natural buffers against shore erosion, strong winds and storm floods; ENVIRONMENTAL MANAGEMENT BUREAU, DEPARTMENT OF ENVIRONMENT AND
e. on which people are dependent for their livelihood. NATURAL RESOURCES, AND THE SECRETARY OF THE DEPARTMENT OF
12. Coral reefs, characterized by one or any combinations of the following conditions: ENVIRONMENT AND NATURAL RESOURCES, ALL SUED IN BOTH THEIR OFFICIAL AND
a. with 50% and above live coralline cover; PRIVATE CAPACITIES, Respondents.
b. spawning and nursery grounds for fish;
c. which act as natural breakwater of coastlines.
DECISION
In this connection, Section 5 of PD 1586 expressly states:

Environmentally Non-Critical Projects. — All other projects, undertakings and areas not BERSAMIN, J.:
declared by the President as environmentally critical shall be considered as non-critical and
shall not be required to submit an environmental impact statement. The National Environmental The peremptory writ of mandamus is an extraordinary remedy that is issued only in extreme
Protection Council, thru the Ministry of Human Settlements may however require non-critical necessity, and the ordinary course of procedure is powerless to afford an adequate and speedy
projects and undertakings to provide additional environmental safeguards as it may deem relief to one who has a clear legal right to the performance of the act to be compelled.
necessary.
Antecedents
The Artica Sports Dome in Langub does not come close to any of the projects or areas
enumerated above. Neither is it analogous to any of them. It is clear, therefore, that the said The petitioner was a proponent of a water-resource development and utilization project in
project is not classified as environmentally critical, or within an environmentally critical area. Barangay Jimilia-an in the Municipality of Loboc, Bohol that would involve the tapping and
Consequently, the DENR has no choice but to issue the Certificate of Non-Coverage. It purifying of water from the Loboc River, and the distribution of the purified water to the residents
becomes its ministerial duty, the performance of which can be compelled by writ of mandamus, of Loboc and six other municipalities. The petitioner applied for a Certificate of Non-Coverage
such as that issued by the trial court in the case at bar.chanrob1es virtua1 1aw 1ibrary (CNC) with the Environmental Management Bureau (EMB) of the Department of Environment
and Natural Resources (DENR), Region 7, seeking to be exempt from the requirement of the
WHEREFORE, in view of the foregoing, the instant petition is DENIED. The decision of the Environmental Compliance Certificate (ECC) under Section 4 of Presidential Decree No. 1586
Regional Trial Court of Davao City, Branch 33, in Civil Case No. 28,133-2000, granting the writ on the following justifications, to wit:
of mandamus and directing the Department of Environment and Natural Resources to issue in
favor of the City of Davao a Certificate of Non-Coverage, pursuant to Presidential Decree No.
1) The whole project simply involves tapping of water from the Loboc River, filtering
1586 and related laws, in connection with the construction of the Artica Sports Dome, is
and purifying it, and distributing the same to the consumers in the covered towns;
AFFIRMED.

SO ORDERED. 2) From the source to the filtration plant, then to the purifier stations, then finally to the
consumers’ households, water flows through steel pipes;
Davide, Jr., C.J., Vitug and Carpio, JJ., concur.
3) The filtration and purifying process employs the latest technology—
"electrocatalytic"—internationally accepted for safety and environment friendliness;

4) No waste is generated, as the electrocatalytic process dissolves all impurities in the


water;
5) The project involves no destruction [n]or harm to the environment. On the other 3.1. Philippine Atmospheric Geophysical and Astronomical Services
hand, it is environment friendly.1 Administration (PAGASA) that the area is not frequently visited or hard-hit by
typhoons. This shall refer to all areas where typhoon signal no. 3 not hoisted
Upon evaluating the nature and magnitude of the environmental impact of the project, for at least twice a year during the last five (5) years prior to the year of
respondent Nestor M. Canda, then Chief of EMB in Bohol, rendered his findings in a letter reckoning. Years to be considered shall be from January 1995 to December
dated December 4, 2001, as follows: 2001.

1) The project is located within a critical area; hence, Initial Environmental Examination 3.2. Philippine Institute of Volcanology and Seismology (PHIVOLCS) that the
is required. area was not subjected to an earthquake of at least intensity VII in the Rossi-
Forel scale or its equivalent and hit by tsunamis during the period of 1638 until
the year 2001.
2) The project is socially and politically sensitive therefore proof of social acceptability
should be established. Proper indorsement from the Protected Area Management
Bureau or PAMB should be secured.2 (Emphasis supplied) 3.3. PHIVOLCS that the area was not subjected to earthquakes of at least
intensity VII in the Rossi-Forel scale or its equivalent during the period of 1949
until the year 2001.
On January 11, 2002, the petitioner appealed Canda’s findings to respondent EMB Region 7
Director Bienvenido L. Lipayon (RD Lipayon), claiming that it should also be issued a CNC
because the project was no different from the Loboc-Loay waterworks project of the 3.4. PAGASA that the area is not storm surge-prone.
Department of Public Works and Highways (DPWH) that had recently been issued a CNC. 3
3.5. Mines and Geosciences Bureau Region 7 (MGB 7) that the area is not
On April 3, 2002, RD Lipayon notified the petitioner that its documents substantially complied located along fault lines or within fault zones and not located in critical slope.
with the procedural aspects of the EMB’s review, and that the application was assigned EMB-
DENR-7 Control No. CNC-02-080 for easy reference in case of follow-up and submission of 3.6. City Mayor and/or City Engineers Office that the area is not flood prone.
additional requirements.4
3.7. Network of Protected Areas for Agriculture (NPAA) of the Bureau of Soils
Later on, RD Lipayon informed the petitioner that an Initial Environmental Examination and Water Management (BSWM) that the area is not classified as Prime
document was required for the project due to its significant impact in the area. 5 Agricultural Land.

On August 26, 2002, RD Lipayon required the petitioner to submit the following documents to 4. Certification from the Provincial Tourism Office or its equivalent office that areas in
enable the EMB to determine whether the project was within an environmentally critical area your project are not set-aside as aesthetic potential tourist spot.
or not, to wit:
5. Certification from the National Water Resources Board (NWRB) that areas within
1. Certification from DENR, Provincial Environment and Natural Resources Office your project are not recharged areas of aquifer.
(PENRO) that it is not within areas declared by law as national parks, watershed
reserves, wildlife preservation area, sanctuaries and not within the purview of Republic 6. Certification from DENR regional Office and/or Environmental Management Bureau
Act No. 7586 or the National Integrated Protected Areas System (NIPAS) Act, and 7 (EMB 7) that Loboc River is not characterized by one or any combination of the
other issuances including international commitments and declarations; following conditions:

2. Certification from the DENR Regional Office/ PENRO [that] the areas within the a. Tapped for domestic purposes;
project do not constitute the habitat for any endangered or threatened species or
indigenous wildlife (Flora and Fauna). b. With controlled and/or protected areas declared by appropriate authorities;
and
3. Certification from the following:
31
c. Which support wildlife and fishery activities. Therefore, we reiterate our previous stand that your project is covered by the EIS System
pursuant to P.D. 1586, the Environmental Impact Statement Law.11
A Certificate of Non-Coverage will duly be issued to your foundation once all the above
mentioned required certifications are complied with. On March 27, 2003, the petitioner filed a petition for mandamus and damages in the Regional
Trial Court (RTC) in Loay, Bohol,12 alleging that it was now entitled to a CNC as a matter of
Projects that are covered by P.D. 1586 or the Environmental Impact System (EIS) Law should right after having complied with the certification requirements; and that the EMB had earlier
not start unless the Project Proponent should secure an Environmental Compliance Certificate issued a CNC to the DPWH for a similar waterworks project in the same area.
(ECC), otherwise penalties shall be imposed.6 (Emphases supplied)
In the decision dated November 18, 2003,13 the RTC dismissed the petition for mandamus
On January 28, 2003, the petitioner submitted eight certifications, 7 including the certification upon the following considerations, namely: (1) PHIVOLCS certified that the project site had
issued by the Philippine Institute of Volcanology and Seismology (PHIVOLCS), as follows: been subjected to an Intensity VII earthquake in 1990; (2) the CNC issued by the EMB to a
similar waterworks project of the DPWH in the same area was only for the construction of a
That the project area, Loboc, Bohol was subjected to an earthquake of Intensity VII in the unit spring box intake and pump house, and the DENR issued a cease and desist order relative
to the DPWH’s additional project to put up a water filtration plant therein; (3) the determination
adapted Rossi-Forel scale of I-IX last February 8, 1990. The magnitude of the earthquake is
of whether an area was environmentally critical was a task that pertained to the EMB; (4) the
6.8 and the highest intensity reported was VIII, based on the Rossi-Forel Intensity Scale. During
assignment of a control number by the EMB to the petitioner’s application did not mean that
the said earthquake, the PMI Academy Building collapsed while minor cracks were sustained
the application was as good as approved; (5) the RTC would not interfere with the primary
by the municipal hall, public school, town church and some other houses in the town. There
were reports that immediately after the earthquake, the force of the incoming waves from the prerogative of the EMB to review the merits of the petitioner’s application for the CNC; and (6)
sea caused Alijuan River in the town of Duero to flow inland. The report also states that the there was already a pending appeal lodged with the DENR Secretary.
waves affected 10-50 meters of the coastal beach of the towns of Jagna, Duero, Guindulman,
Garcia Hernandez and Valencia.8 (Emphases supplied) Hence, this appeal brought directly to the Court via petition for review on certiorari.

The petitioner failed to secure a certification from the Regional Office of the Mines and Issues
Geosciences Bureau (RO-MGB) to the effect that the project area was not located along a fault
line/fault zone or a critical slope because RO-MGB did not have the data and expertise to The petitioner submits the following issues:
render such finding, and thus had to forward the petitioner’s request to the MGB Central Office. 9
A. WHETHER OR NOT, AFTER PETITIONER’S DUE COMPLIANCE WITH THE
Upon the MGB’s advice, the petitioner sought and obtained the required certification from REQUIREMENTS MANDATED BY RESPONDENTS FOR THE ISSUANCE OF THE
PHIVOLCS, but the certification did not state whether the project area was within a critical CERTIFICATE OF NON-COVERAGE (CNC) APPLIED FOR BY PETITIONER, IT IS
slope. Instead, the certification stated that the project site was approximately 18 kilometers NOW THE RIPENED DUTY OF RESPONDENTS, THROUGH RESPONDENT EMB
west of the East Bohol Fault.10 REGIONAL DIRECTOR, TO ISSUE SAID DOCUMENT IN FAVOR OF PETITIONER;

Given the tenor of the certification from PHIVOLCS, RD Lipayon’s letter dated February 4, 2003 B. WHETHER OR NOT PETITIONER HAS EXHAUSTED AVAILABLE
declared that the project was within an environmentally critical area, and that the petitioner was ADMINISTRATIVE REMEDIES THROUGH AN APPEAL TO RESPONDENT DENR
not entitled to the CNC, viz: SECRETARY WHO HAS SAT ON SAID APPEAL UP TO THE PRESENT;

After thorough review of your submitted certifications, it was found out that the area was C. WHETHER OR NOT PETITIONER IS ENTITLED TO RECOVER DAMAGES FROM
subjected to an earthquake of Intensity VII in the adapted Rossi-Forel scale wherein the RESPONDENTS IN THEIR PERSONAL CAPACITY.14
magnitude of the earthquake is 6.8 with the highest intensity reported of VIII and you fail to
support certification that the project area is not within critical slope. And based on the Water The petitioner insists that RD Lipayon already exercised his discretion by finding that the
Usage and Classification per Department Order (DAO) 34 Series of 1990, subject river system application substantially complied with the procedural aspects for review and by assigning
was officially classified as Class B intended for swimming and bathing purposes. Moreover, Control No. CNC-02-080 to its application; that after the petitioner complied with the
one component of your project involves opening of roadway connected to the barangay road. requirements enumerated in the August 26, 2002 letter of RD Lipayon, the EMB became duty-
bound to issue the CNC to the petitioner; that the EMB issued a CNC to a similar project of the
DPWH in the same area; that it filed an appeal with the DENR Secretary, but the appeal
remained unresolved; and that it brought the petition for mandamus precisely as a speedier judgment is based on a misapprehension of facts; (e) when the findings of facts are conflicting;
recourse. (f) when in making its findings the Court of Appeals or the trial court went beyond the issues of
the case, or its findings are contrary to the admissions of both the appellant and the appellee;
In their comment, RD Lipayon and Canda aver that the act complained of against them involved (g) when the findings are contrary to the trial court; (h) when the findings are conclusions
an exercise of discretion that could not be compelled by mandamus; that the petitioner’s without citation of specific evidence on which they are based; (i) when the facts set forth in the
proposed project was located within an environmentally critical area, and the activities to be petition as well as in the petitioner’s main and reply briefs are not disputed by the respondent;
done were so significant that they would create massive earth movement and environmental (j) when the findings of fact are premised on the supposed absence of evidence and
degradation; that the petitioner violated the rule against forum shopping; and that the petitioner contradicted by the evidence on record; and (k) when the Court of Appeals or the trial court
had no cause of action against them for failure to exhaust administrative remedies. manifestly overlooked certain relevant facts not disputed by the parties, which, if properly
considered, would justify a different conclusion.15 However, none of the aforementioned
exceptions applies herein.
On his part, the DENR Secretary, through the Solicitor General, contends that the petition
raises questions of fact that are not proper in a petition for review; that the petitioner should
have appealed to the CA under Rule 41 of the Rules of Court; that the grant or denial of a CNC 2.
application is discretionary and cannot be compelled by mandamus; and that the petitioner
failed to exhaust administrative remedies. Mandamus was an improper remedy for petitioner

Accordingly, the Court is called upon to resolve, firstly, whether the appeal directly to this Court We dismiss the present recourse because the petitioner failed to exhaust the available
from the RTC was proper, and, secondly, whether the petition for mandamus was the correct administrative remedies, and because it failed to show that it was legally entitled to demand
recourse. the performance of the act by the respondents.

Ruling It is axiomatic, to begin with, that a party who seeks the intervention of a court of law upon an
administrative concern should first avail himself of all the remedies afforded by administrative
The petition for review is denied for its lack of merit. processes. The issues that an administrative agency is authorized to decide should not be
summarily taken away from it and submitted to a court of law without first giving the agency the
opportunity to dispose of the issues upon due deliberation.16 The court of law must allow the
1.
administrative agency to carry out its functions and discharge its responsibilities within the
specialized areas of its competence.17 This rests on the theory that the administrative authority
Petitioner’s appeal is improper under Rule 45, Rules of Court is in a better position to resolve questions addressed to its particular expertise, and that errors
committed by subordinates in their resolution may be rectified by their superiors if given a
This appeal by certiorari is being taken under Rule 45, Rules of Court, whose Section 1 chance to do so.18
expressly requires that the petition shall raise only questions of law which must be distinctly set
forth. Yet, the petitioner hereby raises a question of fact whose resolution is decisive in this The records show that the petitioner failed to exhaust the available administrative remedies. At
appeal. That issue of fact concerns whether or not the petitioner established that its project was the time RD Lipayon denied the petitioner’s application for the CNC, Administrative Order No.
not located in an environmentally critical area. For this reason, the Court is constrained to deny 42 dated November 2, 200219 had just vested the authority to grant or deny applications for the
due course to the petition for review. ECC in the Director and Regional Directors of the EMB. Notwithstanding the lack of a specific
implementing guideline to what office the ruling of the EMB Regional Director was to be
It is a settled rule, indeed, that in the exercise of our power of review, the Court is not a trier of appealed, the petitioner could have been easily guided in that regard by the Administrative
facts and does not normally undertake the re-examination of the evidence presented by the Code of 1987, which provides that the Director of a line bureau, such as the EMB, 20 shall have
contending parties during the trial of the case. The Court relies on the findings of fact of the supervision and control over all division and other units, including regional offices, under the
Court of Appeals or of the trial court, and accepts such findings as conclusive and binding bureau.21 Verily, supervision and control include the power to "review, approve, reverse or
unless any of the following exceptions obtains, namely: (a) when the findings are grounded modify acts and decisions of subordinate officials or units."22 Accordingly, the petitioner should
entirely on speculation, surmises or conjectures; (b) when the inference made is manifestly have appealed the EMB Regional Director’s decision to the EMB Director, who exercised
mistaken, absurd or impossible; (c) when there is grave abuse of discretion; (d) when the supervision and control over the former.
33
It is relevant to mention that the DENR later promulgated Administrative Order No. 2003-3023 in No. 1586 pursuant to Section 4 of P.D. No. 1151 (Philippine Environmental Policy) that required
order to define where appeals should be taken, providing as follows: all entities to submit an EIS for projects that would have a significant effect on the environment,
thus:
Section 6. Appeal
Section 4. Environmental Impact Statements. – Pursuant to the above enunciated policies and
Any party aggrieved by the final decision on the ECC/CNC applications may, within 15 days goals, all agencies and instrumentalities of the national government, including government-
from receipt of such decision, file an appeal on the following grounds: owned or controlled corporations, as well as private corporations, firms and entities shall
prepare, file and include in every action, project or undertaking which significantly affects the
quality of the environment a detailed statement on–
a. Grave abuse of discretion on the part of the deciding authority, or

(a) the environmental impact of the proposed action, project or undertaking


b. Serious errors in the review findings.

(b) any adverse environmental effect which cannot be avoided should the proposal be
The DENR may adopt alternative conflict/dispute resolution procedures as a means to settle
implemented
grievances between proponents and aggrieved parties to avert unnecessary legal action.
Frivolous appeals shall not be countenanced.
(c) alternative to the proposed action
The proponent or any stakeholder may file an appeal to the following:
(d) a determination that the short-term uses of the resources of the environment are
1âwphi1 consistent with the maintenance and enhancement of the long-term productivity of the
same; and
Deciding Authority Where to file the appeal
(e) whenever a proposal involves the use of depletable or non-renewable resources, a
EMB Regional Office Director Office of the EMB Director
finding must be made that such use and commitment are warranted.
EMB Central Office Director Office of the DENR Secretary
xxxx
DENR Secretary Office of the President
P.D. No. 1586 exempted from the requirement of an EIS the projects and areas not declared
by the President of the Philippines as environmentally critical, 27 thus:
Moreover, the petitioner states in its pleadings that it had a pending appeal with the DENR
Secretary.1âwphi1 However, the records reveal that the subject of the appeal of the petitioner
was an undated resolution of the DENR Regional Director, Region VII, denying its application Section 5. Environmentally Non-Critical Projects. - All other projects, undertakings and areas
for the CNC,24 not the decision of RD Lipayon. Nonetheless, even assuming that the pending not declared by the Presidents as environmentally critical shall be considered as non-critical
appeal with the DENR Secretary had related to RD Lipayon’s decision, the petitioner should and shall not be required to submit an environmental impact statement. The National
still have waited for the DENR Secretary to resolve the appeal in line with the principle of Environmental Protection Council, thru the Ministry of Human Settlements may however
exhaustion of administrative remedies. Its failure to do so rendered its resort to mandamus in require non-critical projects and undertakings to provide additional environmental safeguards
the RTC premature. The omission is fatal, because mandamus is a remedy only when there is as it may deem necessary.
no appeal, nor any plain, speedy and adequate remedy in the ordinary course of law. 25
On December 14, 1981, the President issued Proclamation No. 2146 declaring areas and types
Another reason for denying due course to this review is that the petitioner did not establish that of projects as environmentally critical and within the scope of the EIS System, as follows:
the grant of its application for the CNC was a purely ministerial in nature on the part of RD
Lipayon. Hence, mandamus was not a proper remedy. A. Environmentally Critical Projects

The CNC is a certification issued by the EMB certifying that a project is not covered by the I. Heavy Industries
Environmental Impact Statement System (EIS System) and that the project proponent is not
required to secure an ECC. 26 The EIS System was established by Presidential Decree (P.D.) a. Non-ferrous metal industries
b. Iron and steel mills 1. All areas declared by law as national parks, watershed reserves, wildlife
preserves and sanctuaries;
c. Petroleum and petro-chemical industries including oil and gas
2. Areas set aside as aesthetic potential tourist spots;
d. Smelting plants
3. Areas which constitute the habitat for any endangered or threatened species
II. Resource Extractive Industries of indigenous Philippine Wildlife (flora and fauna);

a. Major mining and quarrying projects 4. Areas of unique historic, archaeological, or scientific interests;

b. Forestry projects 5. Areas which are traditionally occupied by cultural communities or tribes;

1. Logging 6. Areas frequently visited and/or hard-hit by natural calamities (geologic


hazards, floods, typhoons, volcanic activity, etc.);
2. Major wood processing projects
7. Areas with critical slopes;
3. Introduction of fauna (exotic-animals) in public/private forests
8. Areas classified as prime agricultural lands;
4. Forest occupancy
9. Recharged areas of aquifers;
5. Extraction of mangrove products
10. Water bodies characterized by one or any combination of the following
6. Grazing conditions;

a. tapped for domestic purposes


c. Fishery Projects

1. Dikes for fishpond development projects b. within the controlled and/or protected areas declared by appropriate
authorities
III. Infrastructure Projects
c. which support wildlife and fishery activities
a. Major dams
11. Mangrove areas characterized by one or any combination of the following
conditions:
b. Major power plants (fossil-fueled, nuclear fueled, hydroelectric or
geothermal)
a. with primary pristine and dense young growth;
c. Major reclamation projects
b. adjoining mouth of major river systems;
d. Major roads and bridges.
c. near or adjacent to traditional productive fry or fishing grounds;
B. Environmentally Critical Areas
35
d. which act as natural buffers against shore erosion, strong winds and calamities." Clearly, the petitioner failed to establish that it had the legal right to be issued the
storm floods; CNC applied for, warranting the denial of its application.

e. on which people are dependent for their livelihood. It is not amiss for us to observe, therefore, that the petitioner grossly misunderstood the nature
of the remedy of mandamus. To avoid similar misunderstanding of the remedy hereafter, a
12. Coral reef, characterized by one or any combination of the following short exposition on the nature and office of the remedy is now appropriate.
conditions:
The writ of mandamus is of very ancient and obscure origin. It is believed that the writ was
a. with 50% and above live coralline cover; originally part of the class of writs or mandates issued by the English sovereign to direct his
subjects to perform a particular act or duty.28 The earliest writs were in the form of letters
missive, and were mere personal commands. The command was a law in itself, from which
b. spawning and nursery grounds for fish;
there was no appeal. The writ of mandamus was not only declaratory of a duty under an existing
law, but was a law in itself that imposed the duty, the performance of which it
c. which act as natural breakwater of coastlines. commanded.29 The King was considered as the fountain and source of justice, and when the
law did not afford a remedy by the regular forms of proceedings, the prerogative powers of the
Projects not included in the foregoing enumeration were considered non-critical to the sovereign were invoked in aid of the ordinary powers of the courts.30
environment and were entitled to the CNC.
A judicial writ of mandamus, issued in the King’s name out of the court of King’s Bench that
The foregoing considerations indicate that the grant or denial of an application for ECC/CNC is had a general supervisory power over all inferior jurisdictions and officers, gradually supplanted
not an act that is purely ministerial in nature, but one that involves the exercise of judgment the old personal command of the sovereign.31 The court of King’s Bench, acting as the general
and discretion by the EMB Director or Regional Director, who must determine whether the guardian of public rights and in the exercise of its authority to grant the writ, rendered the writ
project or project area is classified as critical to the environment based on the documents to be of mandamus the suppletory means of substantial justice in every case where there was no
submitted by the applicant. other specific legal remedy for a legal right, and ensured that all official duties were fulfilled
whenever the subject-matter was properly within its control.32 Early on, the writ of mandamus
The petitioner maintains that RD Lipayon already exercised his discretion in its case when he was particularly used to compel public authorities to return the petitioners to public offices from
made his finding that the application substantially complied with the procedural requirements which they had been unlawfully removed.33
for review. As such, he was then obliged to issue the CNC once the petitioner had submitted
the required certifications. Mandamus was, therefore, originally a purely prerogative writ emanating from the King himself,
superintending the police and preserving the peace within the realm.34 It was allowed only in
The petitioner errs on two grounds. cases affecting the sovereign, or the interest of the public at large.35 The writ of mandamus
grew out of the necessity to compel the inferior courts to exercise judicial and ministerial powers
Firstly, RD Lipayon had not yet fully exercised his discretion with regard to the CNC application invested in them by restraining their excesses, preventing their negligence and restraining their
when he made his finding. It is clear that his finding referred to the "procedural requirements denial of justice.36
for review" only. He had still to decide on the substantive aspect of the application, that is,
whether the project and the project area were considered critical to the environment. In fact, Over time, the writ of mandamus has been stripped of its highly prerogative features and has
this was the reason why RD Lipayon required the petitioner to submit certifications from the been assimilated to the nature of an ordinary remedy. Nonetheless, the writ has remained to
various government agencies concerned. Surely, the required certifications were not mere be an extraordinary remedy in the sense that it is only issued in extraordinary cases and where
formalities, because they would serve as the bases for his decision on whether to grant or deny the usual and ordinary modes of proceeding and forms of remedy are powerless to afford
the application. redress to a party aggrieved, and where without its aid there would be a failure of justice. 37

Secondly, there is no sufficient showing that the petitioner satisfactorily complied with the The writ of mandamus has also retained an important feature that sets it apart from the other
requirement to submit the needed certifications. For one, it submitted no certification to the remedial writs, i.e., that it is used merely to compel action and to coerce the performance of a
effect that the project site was not within a critical slope. Also, the PHIVOLCS’s certification pre-existing duty.38 In fact, a doctrine well-embedded in our jurisprudence is that mandamus
showed that the project site had experienced an Intensity VII earthquake in 1990, a fact that will issue only when the petitioner has a clear legal right to the performance of the act sought
sufficed to place the site in the category of "areas frequently visited and/or hard-hit by natural to be compelled and the respondent has an imperative duty to perform the same.39 The
petitioner bears the burden to show that there is such a clear legal right to the performance of Nature of the Case
the act, and a corresponding compelling duty on the part of the respondent to perform the act.40
This is an original petition for the issuance of an Environmental Protection Order in the nature
A key principle to be observed in dealing with petitions for mandamus is that such extraordinary of a continuing mandamus under A.M. No. 09-6-8-SC, otherwise known as the Rules of
remedy lies to compel the performance of duties that are purely ministerial in nature, not those Procedure for Environmental Cases, promulgated on April 29, 2010.
that are discretionary.41 A purely ministerial act or duty is one that an officer or tribunal performs
in a given state of facts, in a prescribed manner, in obedience to the mandate of a legal The Parties
authority, without regard to or the exercise of its own judgment upon the propriety or impropriety
of the act done. The duty is ministerial only when its discharge requires neither the exercise of
Petitioner Boracay Foundation, Inc. (petitioner) is a duly registered, non-stock domestic
official discretion or judgment.42
corporation. Its primary purpose is "to foster a united, concerted and environment-conscious
development of Boracay Island, thereby preserving and maintaining its culture, natural beauty
The petitioner's disregard of the foregoing fundamental requisites for mandamus rendered its and ecological balance, marking the island as the crown jewel of Philippine tourism, a prime
petition in the RTC untenable and devoid of merit. tourist destination in Asia and the whole world."1 It counts among its members at least sixty (60)
owners and representatives of resorts, hotels, restaurants, and similar institutions; at least five
WHEREFORE, the Court DENIES the petition for review on certiorari; and ORDERS the community organizations; and several environmentally-conscious residents and advocates.2
petitioner to pay the costs of suit.
Respondent Province of Aklan (respondent Province) is a political subdivision of the
SO ORDERED. government created pursuant to Republic Act No. 1414, represented by Honorable Carlito S.
Marquez, the Provincial Governor (Governor Marquez).

Respondent Philippine Reclamation Authority (respondent PRA), formerly called the Public
Estates Authority (PEA), is a government entity created by Presidential Decree No.
1084,3 which states that one of the purposes for which respondent PRA was created was to
G.R. No. 196870 June 26, 2012 reclaim land, including foreshore and submerged areas. PEA eventually became the lead
agency primarily responsible for all reclamation projects in the country under Executive Order
No. 525, series of 1979. In June 2006, the President of the Philippines issued Executive Order
BORACAY FOUNDATION, INC., Petitioner, No. 543, delegating the power "to approve reclamation projects to PRA through its governing
vs. Board, subject to compliance with existing laws and rules and further subject to the condition
THE PROVINCE OF AKLAN, REPRESENTED BY GOVERNOR CARLITO S. MARQUEZ, that reclamation contracts to be executed with any person or entity (must) go through public
THE PHILIPPINE RECLAMATION AUTHORITY, AND THE DENR-EMB (REGION bidding."4
VI), Respondents.
Respondent Department of Environment and Natural Resources – Environmental Management
DECISION Bureau (DENR-EMB), Regional Office VI (respondent DENR-EMB RVI), is the government
agency in the Western Visayas Region authorized to issue environmental compliance
LEONARDO-DE CASTRO, J.: certificates regarding projects that require the environment’s protection and management in
the region.5
In resolving this controversy, the Court took into consideration that all the parties involved share
common goals in pursuit of certain primordial State policies and principles that are enshrined Summary of Antecedent Facts
in the Constitution and pertinent laws, such as the protection of the environment, the
empowerment of the local government units, the promotion of tourism, and the encouragement Boracay Island (Boracay), a tropical paradise located in the Western Visayas region of the
of the participation of the private sector. The Court seeks to reconcile the respective roles, Philippines and one of the country’s most popular tourist destinations, was declared a tourist
duties and responsibilities of the petitioner and respondents in achieving these shared goals zone and marine reserve in 1973 under Presidential Proclamation No. 1801. 6 The island
within the context of our Constitution, laws and regulations.
37
comprises the barangays of Manoc-manoc, Balabag, and Yapak, all within the municipality of consultations with the Sangguniang Barangay of Caticlan regarding the proposed foreshore
Malay, in the province of Aklan.7 lease, which failure the Sanggunian considered as an act of bad faith on the part of respondent
Province.15
Petitioner describes Boracay as follows:
On November 20, 2008, the Sangguniang Panlalawigan of respondent Province approved
Boracay is well-known for its distinctive powdery white-sand beaches which are the product of Resolution No. 2008-369,16 formally authorizing Governor Marquez to enter into negotiations
the unique ecosystem dynamics of the area. The island itself is known to come from the uplifted towards the possibility of effecting self-liquidating and income-producing development and
remnants of an ancient reef platform. Its beaches, the sandy land strip between the water and livelihood projects to be financed through bonds, debentures, securities, collaterals, notes or
the area currently occupied by numerous establishments, is the primary draw for domestic and other obligations as provided under Section 299 of the Local Government Code, with the
international tourists for its color, texture and other unique characteristics. Needless to state, it following priority projects: (a) renovation/rehabilitation of the Caticlan/Cagban Passenger
is the premier domestic and international tourist destination in the Philippines.8 Terminal Buildings and Jetty Ports; and (b) reclamation of a portion of Caticlan foreshore for
commercial purposes.17 This step was taken as respondent Province’s existing jetty port and
More than a decade ago, respondent Province built the Caticlan Jetty Port and Passenger passenger terminal was funded through bond flotation, which was successfully redeemed and
Terminal at Barangay Caticlan to be the main gateway to Boracay. It also built the paid ahead of the target date. This was allegedly cited as one of the LGU’s Best Practices
wherein respondent Province was given the appropriate commendation.18
corresponding Cagban Jetty Port and Passenger Terminal to be the receiving end for tourists
in Boracay. Respondent Province operates both ports "to provide structural facilities suited for
locals, tourists and guests and to provide safety and security measures."9 Respondent Province included the proposed expansion of the port facilities at Barangay
Caticlan in its 2009 Annual Investment Plan,19 envisioned as its project site the area adjacent
In 2005, Boracay 2010 Summit was held and participated in by representatives from national to the existing jetty port, and identified additional areas along the coastline of Barangay Caticlan
as the site for future project expansion.20
government agencies, local government units (LGUs), and the private sector. Petitioner was
one of the organizers and participants thereto. The Summit aimed "to re-establish a common
vision of all stakeholders to ensure the conservation, restoration, and preservation of Boracay Governor Marquez sent a letter to respondent PRA on March 12, 200921 expressing the interest
Island" and "to develop an action plan that [would allow] all sectors to work in concert among of respondent Province to reclaim about 2.64 hectares of land along the foreshores of Barangay
and with each other for the long term benefit and sustainability of the island and the Caticlan, Municipality of Malay, Province of Aklan.
community."10 The Summit yielded a Terminal Report11 stating that the participants had shared
their dream of having world-class land, water and air infrastructure, as well as given their Sometime in April 2009, respondent Province entered into an agreement with the Financial
observations that government support was lacking, infrastructure was poor, and, more Advisor/Consultant that won in the bidding process held a month before, to conduct the
importantly, the influx of tourists to Boracay was increasing. The Report showed that there was necessary feasibility study of the proposed project for the Renovation/Rehabilitation of the
a need to expand the port facilities at Caticlan due to congestion in the holding area of the Caticlan Passenger Terminal Building and Jetty Port, Enhancement and Recovery of Old
existing port, caused by inadequate facilities, thus tourists suffered long queues while waiting Caticlan Coastline, and Reclamation of a Portion of Foreshore for Commercial Purposes (the
for the boat ride going to the island.12 Marina Project), in Malay, Aklan.22

Respondent Province claimed that tourist arrivals to Boracay reached approximately 649,559 Subsequently, on May 7, 2009, the Sangguniang Panlalawigan of respondent Province issued
in 2009 and 779,666 in 2010, and this was expected to reach a record of 1 million tourist arrivals Resolution No. 2009–110,23 which authorized Governor Marquez to file an application to
in the years to come. Thus, respondent Province conceptualized the expansion of the port reclaim the 2.64 hectares of foreshore area in Caticlan, Malay, Aklan with respondent PRA.
facilities at Barangay Caticlan.13
Sometime in July 2009, the Financial Advisor/Consultant came up with a feasibility study which
The Sangguniang Barangay of Caticlan, Malay Municipality, issued Resolution No. 13, s. focused on the land reclamation of 2.64 hectares by way of beach enhancement and recovery
200814 on April 25, 2008 stating that it had learned that respondent Province had filed an of the old Caticlan coastline for the rehabilitation and expansion of the existing jetty port, and
application with the DENR for a foreshore lease of areas along the shorelines of Barangay for its future plans – the construction of commercial building and wellness center. The financial
Caticlan, and manifesting its strong opposition to said application, as the proposed foreshore component of the said study was Two Hundred Sixty Million Pesos (₱260,000,000.00). Its
lease practically covered almost all the coastlines of said barangay, thereby technically suggested financing scheme was bond flotation. 24
diminishing its territorial jurisdiction, once granted, and depriving its constituents of their
statutory right of preference in the development and utilization of the natural resources within Meanwhile, the Sangguniang Bayan of the Municipality of Malay expressed its strong
its jurisdiction. The resolution further stated that respondent Province did not conduct any opposition to the intended foreshore lease application, through Resolution No. 044, 25 approved
on July 22, 2009, manifesting therein that respondent Province’s foreshore lease application In his letter dated October 22, 2009 addressed to respondent PRA, Governor Marquez wrote:
was for business enterprise purposes for its benefit, at the expense of the local government of
Malay, which by statutory provisions was the rightful entity "to develop, utilize and reap benefits With our substantial compliance with the requirements under Administrative Order No. 2007-2
from the natural resources found within its jurisdiction." 26 relative to our request to PRA for approval of the reclamation of the [proposed Beach Zone
Restoration and Protection Marine Development in Barangays Caticlan and Manoc-Manoc]
In August 2009, a Preliminary Geohazard Assessment27 for the enhancement/expansion of the and as a result of our discussion during the [meeting with the respondent PRA on October 12,
existing Caticlan Jetty Port and Passenger Terminal through beach zone restoration and 2009], may we respectfully submit a revised Reclamation Project Description embodying
Protective Marina Developments in Caticlan, Malay, Aklan was completed. certain revisions/changes in the size and location of the areas to be reclaimed. x x x.

Thereafter, Governor Marquez submitted an Environmental Performance Report and On another note, we are pleased to inform your Office that the bond flotation we have secured
Monitoring Program (EPRMP)28 to DENR-EMB RVI, which he had attached to his letter29 dated with the Local Government Unit Guarantee Corporation (LGUGC) has been finally approved
September 19, 2009, as an initial step for securing an Environmental Compliance Certificate last October 14, 2009. This will pave the way for the implementation of said project. Briefly, the
(ECC). The letter reads in part: Province has been recognized by the Bureau of Local Government Finance (BLGF) for its
capability to meet its loan obligations. x x x.
With the project expected to start its construction implementation next month, the province
hereby assures your good office that it will give preferential attention to and shall comply with With the continued increase of tourists coming to Boracay through Caticlan, the Province is
whatever comments that you may have on this EPRMP.30 (Emphasis added.) venturing into such development project with the end in view of protection and/or restoring
certain segments of the shoreline in Barangays Caticlan (Caticlan side) and Manoc-manoc
Respondent Province was then authorized to issue "Caticlan Super Marina Bonds" for the (Boracay side) which, as reported by experts, has been experiencing tremendous coastal
purpose of funding the renovation of the Caticlan Jetty Port and Passenger Terminal Building, erosion.
and the reclamation of a portion of the foreshore lease area for commercial purposes in Malay,
Aklan through Provincial Ordinance No. 2009-013, approved on September 10, 2009. The said For the project to be self-liquidating, however, we will be developing the reclaimed land for
ordinance authorized Governor Marquez to negotiate, sign and execute agreements in relation commercial and tourism-related facilities and for other complementary uses.35 (Emphasis ours.)
to the issuance of the Caticlan Super Marina Bonds in the amount not exceeding
₱260,000,000.00.31 Then, on November 19, 2009, the Sangguniang Panlalawigan enacted Resolution No. 2009-
29936 authorizing Governor Marquez to enter into a Memorandum of Agreement (MOA) with
Subsequently, the Sangguniang Panlalawigan of the Province of Aklan issued Provincial respondent PRA in the implementation of the Beach Zone Restoration and Protection Marina
Ordinance No. 2009-01532 on October 1, 2009, amending Provincial Ordinance No. 2009-013, Development Project, which shall reclaim a total of 40 hectares in the areas adjacent to the
authorizing the bond flotation of the Province of Aklan through Governor Marquez to fund the jetty ports at Barangay Caticlan and Barangay Manoc-manoc. The Sangguniang Panlalawigan
Marina Project and appropriate the entire proceeds of said bonds for the project, and further approved the terms and conditions of the necessary agreements for the implementation of the
authorizing Governor Marquez to negotiate, sign and execute contracts or agreements bond flotation of respondent Province to fund the renovation/rehabilitation of the existing jetty
pertinent to the transaction.33 port by way of enhancement and recovery of the Old Caticlan shoreline through reclamation of
an area of 2.64 hectares in the amount of ₱260,000,000.00 on December 1, 2009. 37
Within the same month of October 2009, respondent Province deliberated on the possible
expansion from its original proposed reclamation area of 2.64 hectares to forty (40) hectares in Respondent Province gave an initial presentation of the project with consultation to the
order to maximize the utilization of its resources and as a response to the findings of the Sangguniang Bayan of Malay38 on December 9, 2009.
Preliminary Geohazard Assessment study which showed that the recession and retreat of the
shoreline caused by coastal erosion and scouring should be the first major concern in the Respondent PRA approved the reclamation project on April 20, 2010 in its Resolution No. 4094
project site and nearby coastal area. The study likewise indicated the vulnerability of the coastal and authorized its General Manager/Chief Executive Officer (CEO) to enter into a MOA with
zone within the proposed project site and the nearby coastal area due to the effects of sea level respondent Province for the implementation of the reclamation project.39
rise and climate change which will greatly affect the social, economic, and environmental
situation of Caticlan and nearby Malay coastal communities.34

39
On April 27, 2010, DENR-EMB RVI issued to respondent Province ECC-R6-1003-096-7100 In Resolution No. 046, Series of 2010, adopted on June 23, 2010, the Malay Municipality
(the questioned ECC) for Phase 1 of the Reclamation Project to the extent of 2.64 hectares to reiterated its strong opposition to respondent Province’s project and denied its request for a
be done along the Caticlan side beside the existing jetty port. 40 favorable endorsement of the Marina Project.51

On May 17, 2010, respondent Province entered into a MOA41 with respondent PRA. Under The Malay Municipality subsequently issued Resolution No. 016, Series of 2010, adopted on
Article III, the Project was described therein as follows: August 3, 2010, to request respondent PRA "not to grant reclamation permit and notice to
proceed to the Marina Project of the [respondent] Provincial Government of Aklan located at
The proposed Aklan Beach Zone Restoration and Protection Marina Development Project Caticlan, Malay, Aklan."52
involves the reclamation and development of approximately forty (40) hectares of foreshore
and offshore areas of the Municipality of Malay x x x. In a letter53 dated October 12, 2010, petitioner informed respondent PRA of its opposition to
the reclamation project, primarily for the reason that, based on the opinion of Dr. Porfirio M.
The land use development of the reclamation project shall be for commercial, recreational and Aliño, an expert from the University of the Philippines Marine Science Institute (UPMSI), which
institutional and other applicable uses.42 (Emphases supplied.) he rendered based on the documents submitted by respondent Province to obtain the ECC, a
full EIA study is required to assess the reclamation project’s likelihood of rendering critical and
lasting effect on Boracay considering the proximity in distance, geographical location, current
It was at this point that respondent Province deemed it necessary to conduct a series of what
and wind direction, and many other environmental considerations in the area. Petitioner noted
it calls "information-education campaigns," which provided the venue for interaction and
that said documents had failed to deal with coastal erosion concerns in Boracay. It also noted
dialogue with the public, particularly the Barangay and Municipal officials of the Municipality of
Malay, the residents of Barangay Caticlan and Boracay, the stakeholders, and the non- that respondent Province failed to comply with certain mandatory provisions of the Local
governmental organizations (NGOs). The details of the campaign are summarized as follows 43 : Government Code, particularly, those requiring the project proponent to conduct consultations
with stakeholders.
a. June 17, 2010 at Casa Pilar Beach Resort, Boracay Island, Malay, Aklan;44
Petitioner likewise transmitted its Resolution No. 001, Series of 2010, registering its opposition
to the reclamation project to respondent Province, respondent PRA, respondent DENR-EMB,
b. July 28, 2010 at Caticlan Jetty Port and Passenger Terminal;45 the National Economic Development Authority Region VI, the Malay Municipality, and other
concerned entities.54
c. July 31, 2010 at Barangay Caticlan Plaza;46
Petitioner alleges that despite the Malay Municipality’s denial of respondent Province’s request
d. September 15, 2010 at the Office of the Provincial Governor with Municipal Mayor for a favorable endorsement, as well as the strong opposition manifested both by Barangay
of Malay – Mayor John P. Yap;47 Caticlan and petitioner as an NGO, respondent Province still continued with the implementation
of the Reclamation Project.55
e. October 12, 2010 at the Office of the Provincial Governor with the Provincial
Development Council Executive Committee;48 and On July 26, 2010, the Sangguniang Panlalawigan of respondent Province set aside Resolution
No. 046, s. 2010, of the Municipality of Malay and manifested its support for the implementation
f. October 29, 2010 at the Office of the Provincial Governor with Officials of LGU-Malay of the aforesaid project through its Resolution No. 2010-022.56
and Petitioner.49
On July 27, 2010, the MOA was confirmed by respondent PRA Board of Directors under its
Petitioner claims that during the "public consultation meeting" belatedly called by respondent Resolution No. 4130. Respondent PRA wrote to respondent Province on October 19, 2010,
Province on June 17, 2010, respondent Province presented the Reclamation Project and only informing the latter to proceed with the reclamation and development of phase 1 of site 1 of its
then detailed the actions that it had already undertaken, particularly: the issuance of the proposed project. Respondent PRA attached to said letter its Evaluation Report dated October
Caticlan Super Marina Bonds; the execution of the MOA with respondent PRA; the alleged 18, 2010.57
conduct of an Environmental Impact Assessment (EIA) study for the reclamation project; and
the expansion of the project to forty (40) hectares from 2.64 hectares. 50 Petitioner likewise received a copy of respondent PRA’s letter dated October 19, 2010, which
authorized respondent Province to proceed with phase 1 of the reclamation project, subject to
compliance with the requirements of its Evaluation Report. The reclamation project was
described as:
"[A] seafront development involving reclamation of an aggregate area of more or less, forty (40) During the First Quarter Regular Meeting of the Regional Development Council, Region VI
hectares in two (2) separate sites both in Malay Municipality, Aklan Province. Site 1 is in Brgy. (RDC-VI) on April 16, 2011, it approved and supported the subject project (covering 2.64
Caticlan with a total area of 36.82 hectares and Site 2 in Brgy. Manoc-Manoc, Boracay Island hectares) through RDC-VI Resolution No. VI-26, series of 2011.65
with a total area of 3.18 hectares. Sites 1 and 2 are on the opposite sides of Tabon Strait, about
1,200 meters apart. x x x." 58 (Emphases added.) Subsequently, Mr. Abriam sent a letter to Governor Marquez dated April 25, 2011 stating that
the study conducted by the UPMSI confirms that the water flow across the Caticlan-Boracay
The Sangguniang Panlalawigan of Aklan, through Resolution No. 2010-034,59 addressed the channel is primarily tide-driven, therefore, the marine scientists believe that the 2.64-hectare
apprehensions of petitioner embodied in its Resolution No. 001, s. 2010, and supported the project of respondent Province would not significantly affect the flow in the channel and would
implementation of the project. Said resolution stated that the apprehensions of petitioner with unlikely impact the Boracay beaches. Based on this, PCCI-Boracay stated that it was not
regard to the economic, social and political negative impacts of the projects were mere opposing the 2.64-hectare Caticlan reclamation project on environmental grounds.66
perceptions and generalities and were not anchored on definite scientific, social and political
studies. On June 1, 2011, petitioner filed the instant Petition for Environmental Protection
Order/Issuance of the Writ of Continuing Mandamus. On June 7, 2011, this Court issued a
In the meantime, a study was commissioned by the Philippine Chamber of Commerce and Temporary Environmental Protection Order (TEPO) and ordered the respondents to file their
Industry-Boracay (PCCI-Boracay), funded by the Department of Tourism (DOT) with the respective comments to the petition.67
assistance of, among others, petitioner. The study was conducted in November 2010 by
several marine biologists/experts from the Marine Environmental Resources Foundation After receiving a copy of the TEPO on June 9, 2011, respondent Province immediately issued
(MERF) of the UPMSI. The study was intended to determine the potential impact of a an order to the Provincial Engineering Office and the concerned contractor to cease and desist
reclamation project in the hydrodynamics of the strait and on the coastal erosion patterns in from conducting any construction activities until further orders from this Court.
the southern coast of Boracay Island and along the coast of Caticlan.60
The petition is premised on the following grounds:
After noting the objections of the respective LGUs of Caticlan and Malay, as well as the
apprehensions of petitioner, respondent Province issued a notice to the contractor on I.
December 1, 2010 to commence with the construction of the project.61
The respondent Province, proponent of the reclamation project, failed to comply with relevant
On April 4, 2011, the Sangguniang Panlalawigan of Aklan, through its Committee on
rules and regulations in the acquisition of an ECC.
Cooperatives, Food, Agriculture, and Environmental Protection and the Committee on Tourism,
Trade, Industry and Commerce, conducted a joint committee hearing wherein the study
undertaken by the MERF-UPMSI was discussed.62 In attendance were Mr. Ariel Abriam, A. The reclamation project is co-located within environmentally critical areas requiring
President of PCCI-Boracay, representatives from the Provincial Government, and Dr. Cesar the performance of a full, or programmatic, environmental impact assessment.
Villanoy, a professor from the UPMSI. Dr. Villanoy said that the subject project, consisting of
2.64 hectares, would only have insignificant effect on the hydrodynamics of the strait traversing B. Respondent Province failed to obtain the favorable endorsement of the LGU
the coastline of Barangay Caticlan and Boracay, hence, there was a distant possibility that it concerned.
would affect the Boracay coastline, which includes the famous white-sand beach of the
island.63 C. Respondent Province failed to conduct the required consultation procedures as
required by the Local Government Code.
Thus, on April 6, 2011, the Sangguniang Panlalawigan of Aklan enacted Resolution No. 2011-
06564 noting the report on the survey of the channel between Caticlan and Boracay conducted D. Respondent Province failed to perform a full environmental impact assessment as
by the UPMSI in relation to the effects of the ongoing reclamation to Boracay beaches, and required by law and relevant regulations.
stating that Dr. Villanoy had admitted that nowhere in their study was it pointed out that there
would be an adverse effect on the white-sand beach of Boracay.

41
II. that respondent Province’s choice of classification was designed to avoid a comprehensive
impact assessment of the reclamation project.
The reclamation of land bordering the strait between Caticlan and Boracay shall adversely
affect the frail ecological balance of the area.68 Petitioner further contends that respondent DENR-EMB RVI willfully and deliberately
disregarded its duty to ensure that the environment is protected from harmful developmental
Petitioner objects to respondent Province’s classification of the reclamation project as single projects because it allegedly performed only a cursory and superficial review of the documents
instead of co-located, as "non-environmentally critical," and as a mere "rehabilitation" of the submitted by the respondent Province for an ECC, failing to note that all the information and
existing jetty port. Petitioner points out that the reclamation project is on two sites (which are data used by respondent Province in its application for the ECC were all dated and not current,
situated on the opposite sides of Tabon Strait, about 1,200 meters apart): as data was gathered in the late 1990s for the ECC issued in 1999 for the first jetty port. Thus,
petitioner alleges that respondent DENR-EMB RVI ignored the environmental impact to
Boracay, which involves changes in the structure of the coastline that could contribute to the
 36.82 hectares – Site 1, in Bgy. Caticlan
changes in the characteristics of the sand in the beaches of both Caticlan and Boracay.
 3.18 hectares – Site 2, in Manoc-manoc, Boracay Island69
Petitioner insists that reclamation of land at the Caticlan side will unavoidably adversely affect
Phase 1, which was started in December 2010 without the necessary permits, 70 is located on
the Boracay side and notes that the declared objective of the reclamation project is for the
the Caticlan side of a narrow strait separating mainland Aklan from Boracay. In the
exploitation of Boracay’s tourist trade, since the project is intended to enhance support services
implementation of the project, respondent Province obtained only an ECC to conduct Phase 1,
thereto. But, petitioner argues, the primary reason for Boracay’s popularity is its white-sand
instead of an ECC on the entire 40 hectares. Thus, petitioner argues that respondent Province
beaches which will be negatively affected by the project.
abused and exploited the Revised Procedural Manual for DENR Administrative Order No. 30,
Series of 2003 (DENR DAO 2003-30)71 relating to the acquisition of an ECC by:
Petitioner alleges that respondent PRA had required respondent Province to obtain the
favorable endorsement of the LGUs of Barangay Caticlan and Malay Municipality pursuant to
1. Declaring the reclamation project under "Group II Projects-Non-ECP
the consultation procedures as required by the Local Government Code. 75 Petitioner asserts
(environmentally critical project) in ECA (environmentally critical area) based on the
that the reclamation project is in violation not only of laws on EIS but also of the Local
type and size of the area," and
Government Code as respondent Province failed to enter into proper consultations with the
concerned LGUs. In fact, the Liga ng mga Barangay-Malay Chapter also expressed strong
2. Failing to declare the reclamation project as a co-located project application which opposition against the project.76
would have required the Province to submit a Programmatic Environmental Impact
Statement (PEIS)72 or Programmatic Environmental [Performance] Report
Petitioner cites Sections 26 and 27 of the Local Government Code, which require consultations
Management Plan (PE[P]RMP).73 (Emphases ours.)
if the project or program may cause pollution, climactic change, depletion of non-renewable
resources, etc. According to petitioner, respondent Province ignored the LGUs’ opposition
Petitioner further alleges that the Revised Procedural Manual (on which the classification above expressed as early as 2008. Not only that, respondent Province belatedly called for public
is based, which merely requires an Environmental Impact Statement [EIS] for Group II projects) "consultation meetings" on June 17 and July 28, 2010, after an ECC had already been issued
is patently ultra vires, and respondent DENR-EMB RVI committed grave abuse of discretion and the MOA between respondents PRA and Province had already been executed. As the
because the laws on EIS, namely, Presidential Decree Nos. 1151 and 1586, as well as petitioner saw it, these were not consultations but mere "project presentations."
Presidential Proclamation No. 2146, clearly indicate that projects in environmentally critical
areas are to be immediately considered environmentally critical. Petitioner complains that
Petitioner claims that respondent Province, aided and abetted by respondents PRA and DENR-
respondent Province applied for an ECC only for Phase 1; hence, unlawfully
EMB, ignored the spirit and letter of the Revised Procedural Manual, intended to implement the
various regulations governing the Environmental Impact Assessments (EIAs) to ensure that
evading the requirement that co-located projects74 within Environmentally Critical Areas (ECAs) developmental projects are in line with sustainable development of natural resources. The
must submit a PEIS and/or a PEPRMP. project was conceptualized without considering alternatives.

Petitioner argues that respondent Province fraudulently classified and misrepresented the Further, as to its allegation that respondent Province failed to perform a full EIA, petitioner
project as a Non-ECP in an ECA, and as a single project instead of a co-located one. The argues that while it is true that as of now, only the Caticlan side has been issued an ECC, the
impact assessment allegedly performed gives a patently erroneous and wrongly-premised entire project involves the Boracay side, which should have been considered a co-located
appraisal of the possible environmental impact of the reclamation project. Petitioner contends project. Petitioner claims that any project involving Boracay requires a full EIA since it is an
ECA. Phase 1 of the project will affect Boracay and Caticlan as they are separated only by a Respondent Province argues that the instant petition is anchored on a wrong premise that
narrow strait; thus, it should be considered an ECP. Therefore, the ECC and permit issued results to petitioner’s unfounded fears and baseless apprehensions. It is respondent Province’s
must be invalidated and cancelled. contention that its 2.64-hectare reclamation project is considered as a "stand alone project,"
separate and independent from the approved area of 40 hectares. Thus, petitioner should have
Petitioner contends that a study shows that the flow of the water through a narrower channel observed the difference between the "future development plan" of respondent Province from
due to the reclamation project will likely divert sand transport off the southwest part of Boracay, its "actual project" being undertaken.83
whereas the characteristic coast of the Caticlan side of the strait indicate stronger sediment
transport.77 The white-sand beaches of Boracay and its surrounding marine environment Respondent Province clearly does not dispute the fact that it revised its original application to
depend upon the natural flow of the adjacent waters. respondent PRA from 2.64 hectares to 40 hectares. However, it claims that such revision is
part of its future plan, and implementation thereof is "still subject to availability of funds,
Regarding its claim that the reclamation of land bordering the strait between Caticlan and independent scientific environmental study, separate application of ECC and notice to proceed
Boracay shall adversely affect the frail ecological balance of the area, petitioner submits that to be issued by respondent PRA."84
while the study conducted by the MERF-UPMSI only considers the impact of the reclamation
project on the land, it is undeniable that it will also adversely affect the already frail ecological Respondent Province goes on to claim that "[p]etitioner’s version of the Caticlan jetty port
balance of the area. The effect of the project would have been properly assessed if the proper expansion project is a bigger project which is still at the conceptualization stage. Although this
EIA had been performed prior to any implementation of the project. project was described in the Notice to Proceed issued by respondent PRA to have two phases,
36.82 hectares in Caticlan and 3.18 hectares in Boracay [Island,] it is totally different from the
According to petitioner, respondent Province’s intended purposes do not prevail over its duty [ongoing] Caticlan jetty port expansion project."85
and obligation to protect the environment. Petitioner believes that rehabilitation of the Jetty Port
may be done through other means. Respondent Province says that the Accomplishment Report86 of its Engineering Office would
attest that the actual project consists of 2.64 hectares only, as originally planned and
In its Comment78 dated June 21, 2011, respondent Province claimed that application for conceptualized, which was even reduced to 2.2 hectares due to some construction and design
reclamation of 40 hectares is advantageous to the Provincial Government considering that its modifications.
filing fee would only cost Php20,000.00 plus Value Added Tax (VAT) which is also the minimum
fee as prescribed under Section 4.2 of Administrative Order No. 2007-2.79 Thus, respondent Province alleges that from its standpoint, its capability to reclaim is limited to
2.64 hectares only, based on respondent PRA’s Evaluation Report 87 dated October 18, 2010,
Respondent Province considers the instant petition to be premature; thus, it must necessarily which was in turn the basis of the issuance of the Notice to Proceed dated October 19, 2010,
fail for lack of cause of action due to the failure of petitioner to fully exhaust the available because the project’s financial component is ₱260,000,000.00 only. Said Evaluation Report
administrative remedies even before seeking judicial relief. According to respondent Province, indicates that the implementation of the other phases of the project including site 2, which
the petition primarily assailed the decision of respondent DENR-EMB RVI in granting the ECC consists of the other portions of the 40-hectare area that includes a portion in Boracay, is still
for the subject project consisting of 2.64 hectares and sought the cancellation of the ECC for within the 10-year period and will depend largely on the availability of funds of respondent
alleged failure of respondent Province to submit proper documentation as required for its Province.88
issuance. Hence, the grounds relied upon by petitioner can be addressed within the confines
of administrative processes provided by law. So, even if respondent PRA approved an area that would total up to 40 hectares, it was divided
into phases in order to determine the period of its implementation. Each phase was separate
Respondent Province believes that under Section 5.4.3 of DENR Administrative Order No. and independent because the source of funds was also separate. The required documents and
2003-30 (DAO 2003-30),80 the issuance of an ECC81 is an official decision of DENR-EMB RVI requirements were also specific for each phase. The entire approved area of 40 hectares could
on the application of a project proponent.82 It cites Section 6 of DENR DAO 2003-30, which be implemented within a period of 10 years but this would depend solely on the availability of
provides for a remedy available to the party aggrieved by the final decision on the proponent’s funds.89
ECC applications.
As far as respondent Province understands it, additional reclamations not covered by the ECC,
which only approved 2.64 hectares, should undergo another EIA. If respondent Province

43
intends to commence the construction on the other component of the 40 hectares, then it Thus, respondent Province concludes that petitioner’s allegation of this being a "co-located
agrees that it is mandated to secure a new ECC. 90 project" is premature if not baseless as the bigger reclamation project is still on the
conceptualization stage. Both respondents PRA and Province are yet to complete studies and
Respondent Province admits that it dreamt of a 40-hectare project, even if it had originally feasibility studies to embark on another project.
planned and was at present only financially equipped and legally compliant to undertake 2.64
hectares of the project, and only as an expansion of its old jetty port. 91 Respondent Province claims that an ocular survey of the reclamation project revealed that it
had worked within the limits of the ECC.92
Respondent Province claims that it has complied with all the necessary requirements for
securing an ECC. On the issue that the reclamation project is within an ECA requiring the With regard to petitioner’s allegation that respondent Province failed to get the favorable
performance of a full or programmatic EIA, respondent Province reiterates that the idea of endorsement of the concerned LGUs in violation of the Local Government Code, respondent
expanding the area to 40 hectares is only a future plan. It only secured an ECC for 2.64 Province contends that consultation vis-à-vis the favorable endorsement from the concerned
hectares, based on the limits of its funding and authority. From the beginning, its intention was LGUs as contemplated under the Local Government Code are merely tools to seek advice and
to rehabilitate and expand the existing jetty port terminal to accommodate an increasing not a power clothed upon the LGUs to unilaterally approve or disapprove any government
projected traffic. The subject project is specifically classified under DENR DAO 2003-30 on its projects. Furthermore, such endorsement is not necessary for projects falling under Category
Project Grouping Matrix for Determination of EIA Report Type considered as Minor B2 unless required by the DENR-EMB RVI, under Section 5.3 of DENR DAO 2003-30.
Reclamation Projects falling under Group II – Non ECP in an ECA. Whether 2.64 or 40 hectares
in area, the subject project falls within this classification. Moreover, DENR Memorandum Circular No. 08-2007 no longer requires the issuance of
permits and certifications as a pre-requisite for the issuance of an ECC. Respondent Province
Consequently, respondent Province claims that petitioner erred in considering the ongoing claims to have conducted consultative activities with LGUs in connection with Sections 26 and
reclamation project at Caticlan, Malay, Aklan, as co-located within an ECA. 27 of the Local Government Code. The vehement and staunch objections of both the
Sangguniang Barangay of Caticlan and the Sangguniang Bayan of Malay, according to
Respondent Province, likewise argues that the 2.64-hectare project is not a component of the respondent Province, were not rooted on its perceived impact upon the people and the
approved 40-hectare area as it is originally planned for the expansion site of the existing community in terms of environmental or ecological balance, but due to an alleged conflict with
Caticlan jetty port. At present, it has no definite conceptual construction plan of the said portion their "principal position to develop, utilize and reap benefits from the natural resources found
in Boracay and it has no financial allocation to initiate any project on the said Boracay portion. within its jurisdiction."93 Respondent Province argues that these concerns are not within the
purview of the Local Government Code. Furthermore, the Preliminary Geohazard Assessment
Report and EPRMP as well as Sangguniang Panlalawigan Resolution Nos. 2010-022 and
Furthermore, respondent Province contends that the present project is located in Caticlan while
the alleged component that falls within an ECA is in Boracay. Considering its geographical 2010-034 should address any environmental issue they may raise.
location, the two sites cannot be considered as a contiguous area for the reason that it is
separated by a body of water – a strait that traverses between the mainland Panay wherein Respondent Province posits that the spirit and intent of Sections 26 and 27 of the Local
Caticlan is located and Boracay. Hence, it is erroneous to consider the two sites as a co-located Government Code is to create an avenue for parties, the proponent and the LGU concerned,
project within an ECA. Being a "stand alone project" and an expansion of the existing jetty port, to come up with a tool in harmonizing its views and concerns about the project. The duty to
respondent DENR-EMB RVI had required respondent Province to perform an EPRMP to consult does not automatically require adherence to the opinions during the consultation
secure an ECC as sanctioned by Item No. 8(b), page 7 of DENR DAO 2003-30. process. It is allegedly not within the provisions to give the full authority to the LGU concerned
to unilaterally approve or disapprove the project in the guise of requiring the proponent of
securing its favorable endorsement. In this case, petitioner is calling a halt to the project without
Respondent Province contends that even if, granting for the sake of argument, it had
providing an alternative resolution to harmonize its position and that of respondent Province.
erroneously categorized its project as Non-ECP in an ECA, this was not a final determination.
Respondent DENR-EMB RVI, which was the administrator of the EIS system, had the final
decision on this matter. Under DENR DAO 2003-30, an application for ECC, even for a Respondent Province claims that the EPRMP94 would reveal that:
Category B2 project where an EPRMP is conducted, shall be subjected to a review process.
Respondent DENR-EMB RVI had the authority to deny said application. Its Regional Director [T]he area fronting the project site is practically composed of sand. Dead coral communities
could either issue an ECC for the project or deny the application. He may also require a more may be found along the vicinity. Thus, fish life at the project site is quite scarce due to the
comprehensive EIA study. The Regional Director issued the ECC based on the EPRMP absence of marine support systems like the sea grass beds and coral reefs.
submitted by respondent Province and after the same went through the EIA review process.
x x x [T]here is no coral cover at the existing Caticlan jetty port. [From] the deepest point of jetty 4. The respondent Province’s IRA, regular income, and/or such other revenues or
to the shallowest point, there was no more coral patch and the substrate is sandy. It is of public funds, as may be permitted by law, are being used as security for the payment of the
knowledge that the said foreshore area is being utilized by the residents ever since as berthing said loan used for the project’s construction.
or anchorage site of their motorized banca. There will be no possibility of any coral development
therein because of its continuous utilization. Likewise, the activity of the strait that traverses 5. The inability of the subject project to earn revenues as projected upon completion
between the main land Caticlan and Boracay Island would also be a factor of the coral will compel the Province to shoulder the full amount of the obligation, starting from year
development. Corals [may] only be formed within the area if there is scientific human 2012.
intervention, which is absent up to the present.
6. Respondent province is mandated to assign its IRA, regular income and/or such
In light of the foregoing premise, it casts serious doubt on petitioner’s allegations pertaining to other revenues or funds as permitted by law; if project is stopped, detriment of the
the environmental effects of Respondent-LGU’s 2.64 hectares reclamation project. The alleged public welfare and its constituents.96
environmental impact of the subject project to the beaches of Boracay Island remains
unconfirmed. Petitioner had unsuccessfully proven that the project would cause imminent, As to the second ground for the dissolution of the TEPO, respondent Province argues:
grave and irreparable injury to the community.95
1. Non-compliance with the guidelines of the ECC may result to environmental hazards
Respondent Province prayed for the dissolution of the TEPO, claiming that the rules provide
most especially that reclaimed land if not properly secured may be eroded into the sea.
that the TEPO may be dissolved if it appears after hearing that its issuance or continuance
would cause irreparable damage to the party or person enjoined, while the applicant may be
fully compensated for such damages as he may suffer and subject to the posting of a sufficient 2. The construction has accomplished 65.26 percent of the project. The embankment
bond by the party or person enjoined. Respondent Province contends that the TEPO would that was deposited on the project has no proper concrete wave protection that might
cause irreparable damage in two aspects: be washed out in the event that a strong typhoon or big waves may occur affecting the
strait and the properties along the project site. It is already the rainy season and there
is a big possibility of typhoon occurrence.
a. Financial dislocation and probable bankruptcy; and
3. If said incident occurs, the aggregates of the embankment that had been washed
b. Grave and imminent danger to safety and health of inhabitants of immediate area,
out might be transferred to the adjoining properties which could affect its natural
including tourists and passengers serviced by the jetty port, brought about by the
environmental state.
abrupt cessation of development works.
4. It might result to the total alteration of the physical landscape of the area attributing
As regards financial dislocation, the arguments of respondent Province are summarized below:
to environmental disturbance.

1. This project is financed by bonds which the respondent Province had issued to its 5. The lack of proper concrete wave protection or revetment would cause the total
creditors as the financing scheme in funding the present project is by way of credit erosion of the embankment that has been dumped on the accomplished area. 97
financing through bond flotation.
Respondent Province claims that petitioner will not stand to suffer immediate, grave and
2. The funds are financed by a Guarantee Bank – getting payment from bonds, being
irreparable injury or damage from the ongoing project. The petitioner’s perceived fear of
sold to investors, which in turn would be paid by the income that the project would environmental destruction brought about by its erroneous appreciation of available data is
realize or incur upon its completion. unfounded and does not translate into a matter of extreme urgency. Thus, under the Rules of
Procedure on Environmental Cases, the TEPO may be dissolved.
3. While the project is under construction, respondent Province is appropriating a
portion of its Internal Revenue Allotment (IRA) budget from the 20% development fund
Respondent PRA filed its Comment98 on June 22, 2011. It alleges that on June 24, 2006,
to defray the interest and principal amortization due to the Guarantee Bank. Executive Order No. 543 delegated the power "to approve reclamation projects to respondent
PRA through its governing Board, subject to compliance with existing laws and rules and further
45
subject to the condition that reclamation contracts to be executed with any person or entity (d) Drainage plan vis-a-vis the land-form approved by DPWH Regional Office to include
(must) go through public bidding." a cost effective and efficient drainage system as may be required based on the results
of the studies;
Section 4 of respondent PRA’s Administrative Order No. 2007-2 provides for the approval
process and procedures for various reclamation projects to be undertaken. Respondent PRA (e) Detailed project cost estimates and quantity take-off per items of work of the
prepared an Evaluation Report on November 5, 200999 regarding Aklan’s proposal to increase rawland reclamation components, e.g. reclamation containment structures and soil
its project to 40 hectares. consolidation;

Respondent PRA contends that it was only after respondent Province had complied with the (f) Organizational chart of the construction arm, manning table, equipment schedule
requirements under the law that respondent PRA, through its Board of Directors, approved the for the project; and,
proposed project under its Board Resolution No. 4094.100 In the same Resolution, respondent
PRA Board authorized the General Manager/CEO to execute a MOA with the Aklan provincial (g) Project timetable (PERT/CPM) for the entire project construction period. 104
government to implement the reclamation project under certain conditions.
In fact, respondent PRA further required respondent Province under Article IV (B)(24) of the
The issue for respondent PRA was whether or not it approved the respondent Province’s 2.64- MOA to strictly comply with all conditions of the DENR-EMB-issued ECC "and/or comply with
hectare reclamation project proposal in willful disregard of alleged "numerous irregularities" as pertinent local and international commitments of the Republic of the Philippines to ensure
claimed by petitioner.101 environmental protection."105

Respondent PRA claims that its approval of the Aklan Reclamation Project was in accordance In its August 11, 2010 letter,106 respondent PRA referred for respondent Province’s appropriate
with law and its rules. Indeed, it issued the notice to proceed only after Aklan had complied with action petitioner’s Resolution 001, series of 2010 and Resolution 46, series of 2010, of the
all the requirements imposed by existing laws and regulations. It further contends that the 40 Sangguniang Bayan of Malay. Governor Marquez wrote respondent PRA 107 on September 16,
hectares involved in this project remains a plan insofar as respondent PRA is concerned. What 2010 informing it that respondent Province had already met with the different officials of Malay,
has been approved for reclamation by respondent PRA thus far is only the 2.64-hectare furnishing respondent PRA with the copies of the minutes of such meetings/presentations.
reclamation project. Respondent PRA reiterates that it approved this reclamation project after Governor Marquez also assured respondent PRA that it had complied with the consultation
extensively reviewing the legal, technical, financial, environmental, and operational aspects of requirements as far as Malay was concerned.
the proposed reclamation.102
Respondent PRA claims that in evaluating respondent Province’s project and in issuing the
One of the conditions that respondent PRA Board imposed before approving the Aklan project necessary NTP for Phase 1 of Site 1 (2.64 hectares) of the Caticlan Jetty Port expansion and
was that no reclamation work could be started until respondent PRA has approved the detailed modernization, respondent PRA gave considerable weight to all pertinent issuances, especially
engineering plans/methodology, design and specifications of the reclamation. Part of the the ECC issued by DENR-EMB RVI.108 Respondent PRA stresses that its earlier approval of
required submissions to respondent PRA includes the drainage design as approved by the the 40-hectare reclamation project under its Resolution No. 4094, series of 2010, still requires
Public Works Department and the ECC as issued by the DENR, all of which the Aklan a second level of compliance requirements from the proponent. Respondent Province could
government must submit to respondent PRA before starting any reclamation works. 103 Under not possibly begin its reclamation works since respondent PRA had yet to issue an NTP in its
Article IV(B)(3) of the MOA between respondent PRA and Aklan, the latter is required to submit, favor.
apart from the ECC, the following requirements for respondent PRA’s review and approval, as
basis for the issuance of a Notice to Proceed (NTP) for Reclamation Works:
Respondent PRA alleges that prior to the issuance of the NTP to respondent Province for
Phase 1 of Site 1, it required the submission of the following pre-construction documents:
(a) Land-form plan with technical description of the metes and bounds of the same
land-form;
(a) Land-Form Plan (with technical description);

(b) Final master development and land use plan for the project;
(b) Site Development Plan/Land Use Plan including,

(c) Detailed engineering studies, detailed engineering design, plans and specification
(i) sewer and drainage systems and
for reclamation works, reclamation plans and methodology, plans for the sources of fill
materials;
(ii) waste water treatment; as contained in the EPRMP on March 19, 2010, which were the bases in granting ECC No. R6-
1003-096-7100 (amended) on April 27, 2010 for the expansion of Caticlan Jetty Port and
(c) Engineering Studies and Engineering Design; Passenger Terminal, covering 2.64 hectares.114

(d) Reclamation Methodology; Respondent DENR-EMB RVI claims that the issues raised by the LGUs of Caticlan and Malay
had been considered by the DENR-Provincial Environment and Natural Resources Office
(e) Sources of Fill Materials, and, (PENRO), Aklan in the issuance of the Order115 dated January 26, 2010, disregarding the claim
of the Municipality of Malay, Aklan of a portion of the foreshore land in Caticlan covered by the
application of the Province of Aklan; and another Order of Rejection dated February 5, 2010 of
(f) The ECC.109 the two foreshore applications, namely FLA No. 060412-43A and FLA No. 060412-43B, of the
Province of Aklan.116
Respondent PRA claims that it was only after the evaluation of the above submissions that it
issued to respondent Province the NTP, limited to the 2.64-hectare reclamation project. Respondent DENR-EMB RVI contends that the supporting documents attached to the EPRMP
Respondent PRA even emphasized in its evaluation report that should respondent Province for the issuance of an ECC were merely for the expansion and modernization of the old jetty
pursue the other phases of its project, it would still require the submission of an ECC for each port in Barangay Caticlan covering 2.64 hectares, and not the 40-hectare reclamation project
succeeding phases before the start of any reclamation works.110 in Barangay Caticlan and Boracay. The previous letter of respondent Province dated October
14, 2009 addressed to DENR-EMB RVI Regional Executive Director, would show that the
Respondent PRA, being the national government’s arm in regulating and coordinating all reclamation project will cover approximately 2.6 hectares.117 This application for ECC was not
reclamation projects in the Philippines – a mandate conferred by law – manifests that it is officially accepted due to lack of requirements or documents.
incumbent upon it, in the exercise of its regulatory functions, to diligently evaluate, based on its
technical competencies, all reclamation projects submitted to it for approval. Once the Although petitioner insists that the project involves 40 hectares in two sites, respondent DENR-
reclamation project’s requirements set forth by law and related rules have been complied with, EMB RVI looked at the documents submitted by respondent Province and saw that the subject
respondent PRA is mandated to approve the same. Respondent PRA claims, "[w]ith all the area covered by the ECC application and subsequently granted with ECC-R6-1003-096-7100
foregoing rigorous and detailed requirements submitted and complied with by Aklan, and the consists only of 2.64 hectares; hence, respondent DENR-EMB RVI could not comment on the
attendant careful and meticulous technical and legal evaluation by respondent PRA, it cannot excess area.118
be argued that the reclamation permit it issued to Aklan is ‘founded upon numerous
irregularities;’ as recklessly and baselessly imputed by BFI." 111
Respondent DENR-EMB RVI admits that as regards the classification of the 2.64-hectare
reclamation project under "Non ECP in ECA," this does not fall within the definition of a co-
In its Comment112 dated July 1, 2011, respondent DENR-EMB RVI asserts that its act of issuing located project because the subject project is merely an expansion of the old Caticlan Jetty
the ECC certifies that the project had undergone the proper EIA process by assessing, among Port, which had a previously issued ECC (ECC No. 0699-1012-171 on October 12, 1999).
others, the direct and indirect impact of the project on the biophysical and human environment Thus, only an EPRMP, not a PEIS or PEPRMP, is required. 119
and ensuring that these impacts are addressed by appropriate environmental protection and
enhancement measures, pursuant to Presidential Decree No. 1586, the Revised Procedural
Manual for DENR DAO 2003-30, and the existing rules and regulations.113 Respondent Province submitted to respondent DENR-EMB RVI the following documents
contained in the EPRMP:
Respondent DENR-EMB RVI stresses that the declaration in 1978 of several islands, which
a. The Observations on the Floor Bottom and its Marine Resources at the Proposed
includes Boracay as tourist zone and marine reserve under Proclamation No. 1801, has no
relevance to the expansion project of Caticlan Jetty Port and Passenger Terminal for the very Jetty Ports at Caticlan and Manok-manok, Boracay, Aklan, conducted in 1999 by the
reason that the project is not located in the Island of Boracay, being located in Barangay Bureau of Fisheries Aquatic Resources (BFAR) Central Office, particularly in Caticlan
site, and
Caticlan, Malay, which is not a part of mainland Panay. It admits that the site of the subject jetty
port falls within the ECA under Proclamation No. 2146 (1981), being within the category of a
water body. This was why respondent Province had faithfully secured an ECC pursuant to the b. The Study conducted by Dr. Ricarte S. Javelosa, Ph. D, Mines and Geosciences
Revised Procedural Manual for DENR DAO 2003-30 by submitting the necessary documents Bureau (MGB), Central Office and Engr. Roger Esto, Provincial Planning and

47
Development Office (PPDO), Aklan in 2009 entitled "Preliminary Geo-hazard Confirming this in a letter dated 12 August 2011,126 Governor Marquez informed respondent
Assessment for the Enhancement of the Existing Caticlan Jetty Port Terminal through PRA that the Province of Aklan is no longer "pursuing the implementation of the succeeding
Beach Zone Restoration and Protective Marina Development in Malay, Aklan." phases of the project with a total area of 37.4 hectares for our inability to comply with Article IV
B.2 (3) of the MOA; hence, the existing MOA will cover only the project area of 2.64 hectares."
Respondent DENR-EMB RVI claims that the above two scientific studies were enough for it to
arrive at a best professional judgment to issue an amended ECC for the Aklan Marina Project In his reply-letter dated August 22, 2011,127 [respondent] PRA General Manager informed
covering 2.64 hectares.120 Furthermore, to confirm that the 2.64-hectare reclamation has no Governor Marquez that the [respondent] PRA Board of Directors has given [respondent] PRA
significant negative impact with the surrounding environment particularly in Boracay, a more the authority to confirm the position of the Province of Aklan that the "Aklan Beach Zone
recent study was conducted, and respondent DENR-EMB RVI alleges that "[i]t is very important Restoration and Protection Marine Development Project will now be confined to the reclamation
to highlight that the input data in the [MERF- UPMSI] study utilized the [40-hectare] reclamation and development of the 2.64 hectares, more or less.
and [200-meter] width seaward using the tidal and wave modelling."121 The study showed that
the reclamation of 2.64 hectares had no effect to the hydrodynamics of the strait between It is undisputed from the start that the coverage of the Project is in fact limited to 2.64 hectares,
Barangay Caticlan and Boracay. as evidenced by the NTP issued by respondent PRA. The recent exchange of correspondence
between respondents Province of Aklan and [respondent] PRA further confirms the intent of
Respondent DENR-EMB RVI affirms that no permits and/or clearances from National the parties all along. Hence, the Project subject of the petition, without doubt, covers only 2.64
Government Agencies (NGAs) and LGUs are required pursuant to the DENR Memorandum and not 40 hectares as feared. This completely changes the extent of the Project and,
Circular No. 2007-08, entitled "Simplifying the Requirements of ECC or CNC Applications;" that consequently, moots the issues and fears expressed by the petitioner. 128 (Emphasis supplied.)
the EPRMP was evaluated and processed based on the Revised Procedural Manual for DENR
DAO 2003-30 which resulted to the issuance of ECC-R6-1003-096-7100; and that the ECC is Based on the above contentions, respondent Province prays that the petition be dismissed as
not a permit per se but a planning tool for LGUs to consider in its decision whether or not to no further justiciable controversy exists since the feared adverse effect to Boracay Island’s
issue a local permit.122 ecology had become academic all together.129

Respondent DENR-EMB RVI concludes that in filing this case, petitioner had bypassed and The Court heard the parties’ oral arguments on September 13, 2011 and gave the latter twenty
deprived the DENR Secretary of the opportunity to review and/or reverse the decision of his (20) days thereafter to file their respective memoranda.
subordinate office, EMB RVI pursuant to the Revised Procedural Manual for DENR DAO 2003-
30. There is no "extreme urgency that necessitates the granting of Mandamus or issuance of
Respondent Province filed another Manifestation and Motion,130 which the Court received on
TEPO that put to balance between the life and death of the petitioner or present grave or
April 2, 2012 stating that:
irreparable damage to environment."123
1. it had submitted the required documents and studies to respondent DENR-EMB RVI
After receiving the above Comments from all the respondents, the Court set the case for oral
before an ECC was issued in its favor;
arguments on September 13, 2011.
2. it had substantially complied with the requirements provided under PRA
Meanwhile, on September 8, 2011, respondent Province filed a Manifestation and Administrative Order 2007-2, which compliance caused respondent PRA’s Board to
Motion124 praying for the dismissal of the petition, as the province was no longer pursuing the
approve the reclamation project; and
implementation of the succeeding phases of the project due to its inability to comply with Article
IV B.2(3) of the MOA; hence, the issues and fears expressed by petitioner had become moot.
Respondent Province alleges that the petition is "premised on a serious misappreciation of the 3. it had conducted a series of "consultative [presentations]" relative to the reclamation
real extent of the contested reclamation project" as certainly the ECC covered only a total of project before the LGU of Malay Municipality, the Barangay Officials of Caticlan, and
2,691 square meters located in Barangay Caticlan, Malay, Aklan; and although the MOA spoke stakeholders of Boracay Island.
of 40 hectares, respondent Province’s submission of documents to respondent PRA pertaining
to said area was but the first of a two-step process of approval. Respondent Province claims Respondent Province further manifested that the Barangay Council of Caticlan, Malay, Aklan
that its failure to comply with the documentary requirements of respondent PRA within the enacted on February 13, 2012 Resolution No. 003, series of 2012, entitled "Resolution
period provided, or 120 working days from the effectivity of the MOA, indicated its waiver to Favorably Endorsing the 2.6 Hectares Reclamation/MARINA Project of the Aklan Provincial
pursue the remainder of the project.125 Respondent Province further manifested: Government at Caticlan Coastline"131 and that the Sangguniang Bayan of the Municipality of
Malay, Aklan enacted Resolution No. 020, series of 2012, entitled "Resolution Endorsing the
2.6 Hectares Reclamation Project of the Provincial Government of Aklan Located at Barangay On the issue of whether or not the Petition should be dismissed for having been rendered moot
Caticlan, Malay, Aklan."132 and academic

Respondent Province claims that its compliance with the requirements of respondents DENR- Respondent Province claims in its Manifestation and Motion filed on April 2, 2012 that with the
EMB RVI and PRA that led to the approval of the reclamation project by the said government alleged favorable endorsement of the reclamation project by the Sangguniang Barangay of
agencies, as well as the recent enactments of the Barangay Council of Caticlan and the Caticlan and the Sangguniang Bayan of the Municipality of Malay, all the issues raised by
Sangguniang Bayan of the Municipality of Malay favorably endorsing the said project, had petitioner had already been addressed, and this petition should be dismissed for being moot
"categorically addressed all the issues raised by the Petitioner in its Petition dated June 1, and academic.
2011." Respondent Province prays as follows:
On the contrary, a close reading of the two LGUs’ respective resolutions would reveal that they
WHEREFORE, premises considered, it is most respectfully prayed of this Honorable Court that are not sufficient to render the petition moot and academic, as there are explicit conditions
after due proceedings, the following be rendered: imposed that must be complied with by respondent Province. In Resolution No. 003, series of
2012, of the Sangguniang Barangay of Caticlan it is stated that "any vertical structures to be
1. The Temporary Environmental Protection Order (TEPO) it issued on June 7, 2011 constructed shall be subject for barangay endorsement."133 Clearly, what the barangay
be lifted/dissolved. endorsed was the reclamation only, and not the entire project that includes the construction of
a commercial building and wellness center, and other tourism-related facilities. Petitioner’s
objections, as may be recalled, pertain not only to the reclamation per se, but also to the
2. The instant petition be dismissed for being moot and academic.
building to be constructed and the entire project’s perceived ill effects to the surrounding
environment.
3. Respondent Province of Aklan prays for such other reliefs that are just and equitable
under the premises. (Emphases in the original.)
Resolution No. 020, series of 2012, of the Sangguniang Bayan of Malay134 is even more
specific. It reads in part:
ISSUES
WHEREAS, noble it seems the reclamation project to the effect that it will generate scores of
The Court will now resolve the following issues: benefits for the Local Government of Malay in terms of income and employment for its
constituents, but the fact cannot be denied that the project will take its toll on the environment
I. Whether or not the petition should be dismissed for having been rendered moot and especially on the nearby fragile island of Boracay and the fact also remains that the project will
academic eventually displace the local transportation operators/cooperatives;

II. Whether or not the petition is premature because petitioner failed to exhaust WHEREAS, considering the sensitivity of the project, this Honorable Body through the
administrative remedies before filing this case Committee where this matter was referred conducted several consultations/committee
hearings with concerned departments and the private sector specifically Boracay Foundation,
III. Whether or not respondent Province failed to perform a full EIA as required by laws Inc. and they are one in its belief that this Local Government Unit has never been against
and regulations based on the scope and classification of the project development so long as compliance with the law and proper procedures have been observed
and that paramount consideration have been given to the environment lest we disturb the
IV. Whether or not respondent Province complied with all the requirements under the balance of nature to the end that progress will be brought to naught;
pertinent laws and regulations
WHEREAS, time and again, to ensure a healthy intergovernmental relations, this August Body
V. Whether or not there was proper, timely, and sufficient public consultation for the requires no less than transparency and faithful commitment from the Provincial Government of
project Aklan in the process of going through these improvements in the Municipality because it once
fell prey to infidelities in matters of governance;
DISCUSSION

49
WHEREAS, as a condition for the grant of this endorsement and to address all issues and Any party aggrieved by the final decision on the ECC / CNC applications may, within 15 days
concerns, this Honorable Council necessitates a sincere commitment from the Provincial from receipt of such decision, file an appeal on the following grounds:
Government of Aklan to the end that:
a. Grave abuse of discretion on the part of the deciding authority, or
1. To allocate an office space to LGU-Malay within the building in the reclaimed area;
b. Serious errors in the review findings.
2. To convene the Cagban and Caticlan Jetty Port Management Board before the
resumption of the reclamation project; The DENR may adopt alternative conflict/dispute resolution procedures as a means to settle
grievances between proponents and aggrieved parties to avert unnecessary legal action.
3. That the reclamation project shall be limited only to 2.6 hectares in Barangay Frivolous appeals shall not be countenanced.
Caticlan and not beyond;
The proponent or any stakeholder may file an appeal to the following:
4. That the local transportation operators/cooperatives will not be displaced; and
Deciding Authority Where to file the appeal
5. The Provincial Government of Aklan conduct a simultaneous comprehensive study
on the environmental impact of the reclamation project especially during Habagat and EMB Regional Office Director Office of the EMB Director
Amihan seasons and put in place as early as possible mitigating measures on the
effect of the project to the environment. EMB Central Office Director Office of the DENR Secretary

WHEREAS, having presented these stipulations, failure to comply herewith will leave this DENR Secretary Office of the President
August Body no choice but to revoke this endorsement, hence faithful compliance of the
commitment of the Provincial Government is highly appealed for[.] 135 (Emphases added.)
(Emphases supplied.)

The Sangguniang Bayan of Malay obviously imposed explicit conditions for respondent
Respondents argue that since there is an administrative appeal provided for, then petitioner is
Province to comply with on pain of revocation of its endorsement of the project, including the
duty bound to observe the same and may not be granted recourse to the regular courts for its
need to conduct a comprehensive study on the environmental impact of the reclamation project,
failure to do so.
which is the heart of the petition before us. Therefore, the contents of the two resolutions
submitted by respondent Province do not support its conclusion that the subsequent favorable
endorsement of the LGUs had already addressed all the issues raised and rendered the instant We do not agree with respondents’ appreciation of the applicability of the rule on exhaustion of
petition moot and academic. administrative remedies in this case. We are reminded of our ruling in Pagara v. Court of
Appeals,136 which summarized our earlier decisions on the procedural requirement of
exhaustion of administrative remedies, to wit:
On the issue of failure to exhaust administrative remedies
The rule regarding exhaustion of administrative remedies is not a hard and fast rule. It is not
Respondents, in essence, argue that the present petition should be dismissed for petitioner’s
applicable (1) where the question in dispute is purely a legal one, or (2) where the controverted
failure to exhaust administrative remedies and even to observe the hierarchy of courts.
act is patently illegal or was performed without jurisdiction or in excess of jurisdiction; or (3)
Furthermore, as the petition questions the issuance of the ECC and the NTP, this involves
where the respondent is a department secretary, whose acts as an alter ego of the President
factual and technical verification, which are more properly within the expertise of the concerned
bear the implied or assumed approval of the latter, unless actually disapproved by him, or (4)
government agencies.
where there are circumstances indicating the urgency of judicial intervention, - Gonzales vs.
Hechanova, L-21897, October 22, 1963, 9 SCRA 230; Abaya vs. Villegas, L-25641, December
Respondents anchor their argument on Section 6, Article II of DENR DAO 2003-30, which 17, 1966, 18 SCRA; Mitra vs. Subido, L-21691, September 15, 1967, 21 SCRA 127.
provides:
Said principle may also be disregarded when it does not provide a plain, speedy and adequate
Section 6. Appeal remedy, (Cipriano vs. Marcelino, 43 SCRA 291), when there is no due process observed
(Villanos vs. Subido, 45 SCRA 299), or where the protestant has no other recourse (Sta. Maria This point is emphasized in the availability of the remedy of the writ of mandamus, which allows
vs. Lopez, 31 SCRA 637).137 (Emphases supplied.) for the enforcement of the conduct of the tasks to which the writ pertains: the performance of a
legal duty.142 (Emphases added.)
As petitioner correctly pointed out, the appeal provided for under Section 6 of DENR DAO 2003-
30 is only applicable, based on the first sentence thereof, if the person or entity charged with The writ of continuing mandamus "permits the court to retain jurisdiction after judgment in order
the duty to exhaust the administrative remedy of appeal to the appropriate government agency to ensure the successful implementation of the reliefs mandated under the court’s decision"
has been a party or has been made a party in the proceedings wherein the decision to be and, in order to do this, "the court may compel the submission of compliance reports from the
appealed was rendered. It has been established by the facts that petitioner was never made a respondent government agencies as well as avail of other means to monitor compliance with
party to the proceedings before respondent DENR-EMB RVI. Petitioner was only informed that its decision."143
the project had already been approved after the ECC was already granted.138 Not being a party
to the said proceedings, it does not appear that petitioner was officially furnished a copy of the According to petitioner, respondent Province acted pursuant to a MOA with respondent PRA
decision, from which the 15-day period to appeal should be reckoned, and which would warrant that was conditioned upon, among others, a properly-secured ECC from respondent DENR-
the application of Section 6, Article II of DENR DAO 2003-30. EMB RVI. For this reason, petitioner seeks to compel respondent Province to comply with
certain environmental laws, rules, and procedures that it claims were either circumvented or
Although petitioner was not a party to the proceedings where the decision to issue an ECC was ignored. Hence, we find that the petition was appropriately filed with this Court under Rule 8,
rendered, it stands to be aggrieved by the decision,139 because it claims that the reclamation of Section 1, A.M. No. 09-6-8-SC, which reads:
land on the Caticlan side would unavoidably adversely affect the Boracay side, where
petitioner’s members own establishments engaged in the tourism trade. As noted earlier, SECTION 1. Petition for continuing mandamus.—When any agency or instrumentality of the
petitioner contends that the declared objective of the reclamation project is to exploit Boracay’s government or officer thereof unlawfully neglects the performance of an act which the law
tourism trade because the project is intended to enhance support services thereto; however, specifically enjoins as a duty resulting from an office, trust or station in connection with the
this objective would not be achieved since the white-sand beaches for which Boracay is famous enforcement or violation of an environmental law rule or regulation or a right therein, or
might be negatively affected by the project. Petitioner’s conclusion is that respondent Province, unlawfully excludes another from the use or enjoyment of such right and there is no other plain,
aided and abetted by respondents PRA and DENR-EMB RVI, ignored the spirit and letter of speedy and adequate remedy in the ordinary course of law, the person aggrieved thereby may
our environmental laws, and should thus be compelled to perform their duties under said laws. file a verified petition in the proper court, alleging the facts with certainty, attaching thereto
supporting evidence, specifying that the petition concerns an environmental law, rule or
The new Rules of Procedure for Environmental Cases, A.M. No. 09-6-8-SC, provides a relief regulation, and praying that judgment be rendered commanding the respondent to do an act or
for petitioner under the writ of continuing mandamus, which is a special civil action that may be series of acts until the judgment is fully satisfied, and to pay damages sustained by the
availed of "to compel the performance of an act specifically enjoined by law" 140 and which petitioner by reason of the malicious neglect to perform the duties of the respondent, under the
provides for the issuance of a TEPO "as an auxiliary remedy prior to the issuance of the writ law, rules or regulations. The petition shall also contain a sworn certification of non-forum
itself."141 The Rationale of the said Rules explains the writ in this wise: shopping.

Environmental law highlights the shift in the focal-point from the initiation of regulation by SECTION 2. Where to file the petition.—The petition shall be filed with the Regional Trial Court
Congress to the implementation of regulatory programs by the appropriate government exercising jurisdiction over the territory where the actionable neglect or omission occurred or
agencies. with the Court of Appeals or the Supreme Court.

Thus, a government agency’s inaction, if any, has serious implications on the future of Petitioner had three options where to file this case under the rule: the Regional Trial Court
environmental law enforcement. Private individuals, to the extent that they seek to change the exercising jurisdiction over the territory where the actionable neglect or omission occurred, the
scope of the regulatory process, will have to rely on such agencies to take the initial incentives, Court of Appeals, or this Court.
which may require a judicial component. Accordingly, questions regarding the propriety of an
agency’s action or inaction will need to be analyzed. Petitioner had no other plain, speedy, or adequate remedy in the ordinary course of law to
determine the questions of unique national and local importance raised here that pertain to
laws and rules for environmental protection, thus it was justified in coming to this Court.

51
Having resolved the procedural issue, we now move to the substantive issues. 2. Its classification of the reclamation project as a single instead of a co-located project;

On the issues of whether, based on the scope and classification of the project, a full EIA is 3. The lack of prior public consultations and approval of local government agencies;
required by laws and regulations, and whether respondent Province complied with all the and
requirements under the pertinent laws and regulations
4. The lack of comprehensive studies regarding the impact of the reclamation project
Petitioner’s arguments on this issue hinges upon its claim that the reclamation project is to the environment.
misclassified as a single project when in fact it is co-located. Petitioner also questions the
classification made by respondent Province that the reclamation project is merely an expansion The above issues as raised put in question the sufficiency of the evaluation of the project by
of the existing jetty port, when the project descriptions embodied in the different documents respondent DENR-EMB RVI.
filed by respondent Province describe commercial establishments to be built, among others, to
raise revenues for the LGU; thus, it should have been classified as a new project. Petitioner Nature of the project
likewise cries foul to the manner by which respondent Province allegedly circumvented the
documentary requirements of the DENR-EMB RVI by the act of connecting the reclamation
project with its previous project in 1999 and claiming that the new project is a mere expansion The first question must be answered by respondent DENR-EMB RVI as the agency with the
of the previous one. expertise and authority to state whether this is a new project, subject to the more rigorous
environmental impact study requested by petitioner, or it is a mere expansion of the existing
jetty port facility.
As previously discussed, respondent Province filed a Manifestation and Motion stating that the
ECC issued by respondent DENR-EMB RVI covered an area of 2,691 square meters in
Caticlan, and its application for reclamation of 40 hectares with respondent PRA was The second issue refers to the classification of the project by respondent Province, approved
conditioned on its submission of specific documents within 120 days. Respondent Province by respondent DENR-EMB RVI, as single instead of co-located. Under the Revised Procedural
claims that its failure to comply with said condition indicated its waiver to pursue the succeeding Manual, the "Summary List of Additional Non-Environmentally-Critical Project (NECP) Types
phases of the reclamation project and that the subject matter of this case had thus been limited in ECAs Classified under Group II" (Table I-2) lists "buildings, storage facilities and other
to 2.64 hectares. Respondent PRA, for its part, declared through its General Manager that the structures" as a separate item from "transport terminal facilities." This creates the question of
"Aklan Beach Zone Restoration and Protection Marine Development Project will now be whether this project should be considered as consisting of more than one type of activity, and
confined to the reclamation and development of the 2.64 hectares, more or less."144 should more properly be classified as "co-located," under the following definition from the same
Manual, which reads:
The Court notes such manifestation of respondent Province. Assuming, however, that the area
involved in the subject reclamation project has been limited to 2.64 hectares, this case has not f) Group IV (Co-located Projects in either ECA or NECA): A co-located project is a group of
become moot and academic, as alleged by respondents, because the Court still has to check single projects, under one or more proponents/locators, which are located in a contiguous area
whether respondents had complied with all applicable environmental laws, rules, and and managed by one administrator, who is also the ECC applicant. The co-located project may
regulations pertaining to the actual reclamation project. be an economic zone or industrial park, or a mix of projects within a catchment, watershed or
river basin, or any other geographical, political or economic unit of area. Since the location or
threshold of specific projects within the contiguous area will yet be derived from the EIA process
We recognize at this point that the DENR is the government agency vested with delegated
based on the carrying capacity of the project environment, the nature of the project is called
powers to review and evaluate all EIA reports, and to grant or deny ECCs to project
"programmatic." (Emphasis added.)
proponents.145 It is the DENR that has the duty to implement the EIS system. It appears,
however, that respondent DENR-EMB RVI’s evaluation of this reclamation project was
problematic, based on the valid questions raised by petitioner. Respondent DENR-EMB RVI should conduct a thorough and detailed evaluation of the project
to address the question of whether this could be deemed as a group of single projects (transport
terminal facility, building, etc.) in a contiguous area managed by respondent Province, or as a
Being the administrator of the EIS System, respondent DENR-EMB RVI’s submissions bear
single project.
great weight in this case. However, the following are the issues that put in question the wisdom
of respondent DENR-EMB RVI in issuing the ECC:
The third item in the above enumeration will be discussed as a separate issue.
1. Its approval of respondent Province’s classification of the project as a mere
expansion of the existing jetty port in Caticlan, instead of classifying it as a new project;
The answer to the fourth question depends on the final classification of the project under items xxxx
1 and 3 above because the type of EIA study required under the Revised Procedural Manual
depends on such classification. The succeeding phases of the project will consist of [further] reclamation, completion of the
commercial center building, bay walk commercial strip, staff building, ferry terminal, a cable car
The very definition of an EIA points to what was most likely neglected by respondent Province system and wharf marina. This will entail an additional estimated cost of ₱785 million bringing
as project proponent, and what was in turn overlooked by respondent DENR-EMB RVI, for it is the total investment requirement to about ₱1.0 billion.147 (Emphases added.)
defined as follows:
As may be gleaned from the breakdown of the 2.64 hectares as described by respondent
An [EIA] is a ‘process that involves predicting and evaluating the likely impacts of a project Province above, a significant portion of the reclaimed area would be devoted to the construction
(including cumulative impacts) on the environment during construction, commissioning, of a commercial building, and the area to be utilized for the expansion of the jetty port consists
operation and abandonment. It also includes designing appropriate preventive, mitigating and of a mere 3,000 square meters (sq. m). To be true to its definition, the EIA report submitted by
enhancement measures addressing these consequences to protect the environment and the respondent Province should at the very least predict the impact that the construction of the new
community’s welfare.146 (Emphases supplied.) buildings on the reclaimed land would have on the surrounding environment. These new
constructions and their environmental effects were not covered by the old studies that
Thus, the EIA process must have been able to predict the likely impact of the reclamation respondent Province previously submitted for the construction of the original jetty port in 1999,
project to the environment and to prevent any harm that may otherwise be caused. and which it re-submitted in its application for ECC in this alleged expansion, instead of
conducting updated and more comprehensive studies.
The project now before us involves reclamation of land that is more than five times the size of
the original reclaimed land. Furthermore, the area prior to construction merely contained a jetty Any impact on the Boracay side cannot be totally ignored, as Caticlan and Boracay are
port, whereas the proposed expansion, as described in the EPRMP submitted by respondent separated only by a narrow strait. This becomes more imperative because of the significant
Province to respondent DENR-EMB RVI involves so much more, and we quote: contributions of Boracay’s white-sand beach to the country’s tourism trade, which requires
respondent Province to proceed with utmost caution in implementing projects within its vicinity.
The expansion project will be constructed at the north side of the existing jetty port and terminal
that will have a total area of 2.64 hectares, more or less, after reclamation. The Phase 1 of the We had occasion to emphasize the duty of local government units to ensure the quality of the
project construction costing around ₱260 million includes the following: environment under Presidential Decree No. 1586 in Republic of the Philippines v. The City of
Davao,148 wherein we held:
1. Reclamation - 3,000 sq m (expansion of jetty port)
Section 15 of Republic Act 7160, otherwise known as the Local Government Code, defines a
local government unit as a body politic and corporate endowed with powers to be exercised by
2. Reclamation - 13,500 sq m (buildable area)
it in conformity with law. As such, it performs dual functions, governmental and proprietary.
Governmental functions are those that concern the health, safety and the advancement of the
3. Terminal annex building - 250 sq m public good or welfare as affecting the public generally. Proprietary functions are those that
seek to obtain special corporate benefits or earn pecuniary profit and intended for private
4. 2-storey commercial building – 2,500 sq m (1,750 sq m of leasable space) advantage and benefit. When exercising governmental powers and performing governmental
duties, an LGU is an agency of the national government. When engaged in corporate activities,
5. Health and wellness center it acts as an agent of the community in the administration of local affairs.

6. Access road - 12 m (wide) Found in Section 16 of the Local Government Code is the duty of the LGUs to promote the
people’s right to a balanced ecology. Pursuant to this, an LGU, like the City of Davao, can not
7. Parking, perimeter fences, lighting and water treatment sewerage system claim exemption from the coverage of PD 1586. As a body politic endowed with governmental
functions, an LGU has the duty to ensure the quality of the environment, which is the very same
objective of PD 1586.
8. Rehabilitation of existing jetty port and terminal

53
xxxx Section 26. Duty of National Government Agencies in the Maintenance of Ecological Balance.
- It shall be the duty of every national agency or government-owned or controlled corporation
Section 4 of PD 1586 clearly states that "no person, partnership or corporation shall undertake authorizing or involved in the planning and implementation of any project or program that may
or operate any such declared environmentally critical project or area without first securing an cause pollution, climatic change, depletion of non-renewable resources, loss of crop land,
Environmental Compliance Certificate issued by the President or his duly authorized rangeland, or forest cover, and extinction of animal or plant species, to consult with the local
representative." The Civil Code defines a person as either natural or juridical. The state and its government units, nongovernmental organizations, and other sectors concerned and explain
political subdivisions, i.e., the local government units are juridical persons. Undoubtedly the goals and objectives of the project or program, its impact upon the people and the
therefore, local government units are not excluded from the coverage of PD 1586. community in terms of environmental or ecological balance, and the measures that will be
undertaken to prevent or minimize the adverse effects thereof.
Lastly, very clear in Section 1 of PD 1586 that said law intends to implement the policy of the
state to achieve a balance between socio-economic development and environmental Section 27. Prior Consultations Required. - No project or program shall be implemented by
protection, which are the twin goals of sustainable development. The above-quoted first government authorities unless the consultations mentioned in Sections 2 (c) and 26 hereof are
paragraph of the Whereas clause stresses that this can only be possible if we adopt a complied with, and prior approval of the sanggunian concerned is obtained: Provided, That
comprehensive and integrated environmental protection program where all the sectors of the occupants in areas where such projects are to be implemented shall not be evicted unless
community are involved, i.e., the government and the private sectors. The local government appropriate relocation sites have been provided, in accordance with the provisions of the
units, as part of the machinery of the government, cannot therefore be deemed as outside the Constitution.
scope of the EIS system.149 (Emphases supplied.)
In Lina, Jr. v. Paño,150 we held that Section 27 of the Local Government Code applies only to
The Court chooses to remand these matters to respondent DENR-EMB RVI for it to make a "national programs and/or projects which are to be implemented in a particular local
proper study, and if it should find necessary, to require respondent Province to address these community"151 and that it should be read in conjunction with Section 26. We held further in this
environmental issues raised by petitioner and submit the correct EIA report as required by the manner:
project’s specifications. The Court requires respondent DENR-EMB RVI to complete its study
and submit a report within a non-extendible period of three months. Respondent DENR-EMB Thus, the projects and programs mentioned in Section 27 should be interpreted to mean
RVI should establish to the Court in said report why the ECC it issued for the subject project projects and programs whose effects are among those enumerated in Section 26 and 27, to
should not be canceled. wit, those that: (1) may cause pollution; (2) may bring about climatic change; (3) may cause
the depletion of non-renewable resources; (4) may result in loss of crop land, range-land, or
Lack of prior public consultation forest cover; (5) may eradicate certain animal or plant species from the face of the planet; and
(6) other projects or programs that may call for the eviction of a particular group of people
The Local Government Code establishes the duties of national government agencies in the residing in the locality where these will be implemented. Obviously, none of these effects will
be produced by the introduction of lotto in the province of Laguna.152 (Emphasis added.)
maintenance of ecological balance, and requires them to secure prior public consultation and
approval of local government units for the projects described therein.
During the oral arguments held on September 13, 2011, it was established that this project as
In the case before us, the national agency involved is respondent PRA. Even if the project described above falls under Section 26 because the commercial establishments to be built on
proponent is the local government of Aklan, it is respondent PRA which authorized the phase 1, as described in the EPRMP quoted above, could cause pollution as it could generate
garbage, sewage, and possible toxic fuel discharge.153
reclamation, being the exclusive agency of the government to undertake reclamation
nationwide. Hence, it was necessary for respondent Province to go through respondent PRA
and to execute a MOA, wherein respondent PRA’s authority to reclaim was delegated to Our ruling in Province of Rizal v. Executive Secretary154 is instructive:
respondent Province. Respondent DENR-EMB RVI, regional office of the DENR, is also a
national government institution which is tasked with the issuance of the ECC that is a We reiterated this doctrine in the recent case of Bangus Fry Fisherfolk v. Lanzanas, where we
prerequisite to projects covered by environmental laws such as the one at bar. held that there was no statutory requirement for the sangguniang bayan of Puerto Galera to
approve the construction of a mooring facility, as Sections 26 and 27 are inapplicable to projects
This project can be classified as a national project that affects the environmental and ecological which are not environmentally critical.
balance of local communities, and is covered by the requirements found in the Local
Government Code provisions that are quoted below: Moreover, Section 447, which enumerates the powers, duties and functions of the municipality,
grants the sangguniang bayan the power to, among other things, "enact ordinances, approve
resolutions and appropriate funds for the general welfare of the municipality and its inhabitants dissemination conducted months after the ECC had already been issued was insufficient to
pursuant to Section 16 of th(e) Code." These include: comply with this requirement under the Local Government Code. Had they been conducted
properly, the prior public consultation should have considered the ecological or environmental
(1) Approving ordinances and passing resolutions to protect the environment and concerns of the stakeholders and studied measures alternative to the project, to avoid or
impose appropriate penalties for acts which endanger the environment, such as minimize adverse environmental impact or damage. In fact, respondent Province once tried to
dynamite fishing and other forms of destructive fishing, illegal logging and smuggling obtain the favorable endorsement of the Sangguniang Bayan of Malay, but this was denied by
of logs, smuggling of natural resources products and of endangered species of flora the latter.
and fauna, slash and burn farming, and such other activities which result in pollution,
acceleration of eutrophication of rivers and lakes, or of ecological imbalance; [Section Moreover, DENR DAO 2003-30 provides:
447 (1)(vi)]
5.3 Public Hearing / Consultation Requirements
(2) Prescribing reasonable limits and restraints on the use of property within the
jurisdiction of the municipality, adopting a comprehensive land use plan for the For projects under Category A-1, the conduct of public hearing as part of the EIS review is
municipality, reclassifying land within the jurisdiction of the city, subject to the pertinent mandatory unless otherwise determined by EMB. For all other undertakings, a public hearing
provisions of this Code, enacting integrated zoning ordinances in consonance with the is not mandatory unless specifically required by EMB.
approved comprehensive land use plan, subject to existing laws, rules and regulations;
establishing fire limits or zones, particularly in populous centers; and regulating the
Proponents should initiate public consultations early in order to ensure that environmentally
construction, repair or modification of buildings within said fire limits or zones in relevant concerns of stakeholders are taken into consideration in the EIA study and the
accordance with the provisions of this Code; [Section 447 (2)(vi-ix)] formulation of the management plan. All public consultations and public hearings conducted
during the EIA process are to be documented. The public hearing/consultation Process report
(3) Approving ordinances which shall ensure the efficient and effective delivery of the shall be validated by the EMB/EMB RD and shall constitute part of the records of the EIA
basic services and facilities as provided for under Section 17 of this Code, and in process. (Emphasis supplied.)
addition to said services and facilities, …providing for the establishment, maintenance,
protection, and conservation of communal forests and watersheds, tree parks, In essence, the above-quoted rule shows that in cases requiring public consultations, the same
greenbelts, mangroves, and other similar forest development projects …and, subject
should be initiated early so that concerns of stakeholders could be taken into consideration in
to existing laws, establishing and providing for the maintenance, repair and operation
the EIA study. In this case, respondent Province had already filed its ECC application before it
of an efficient waterworks system to supply water for the inhabitants and purifying the
met with the local government units of Malay and Caticlan.
source of the water supply; regulating the construction, maintenance, repair and use
of hydrants, pumps, cisterns and reservoirs; protecting the purity and quantity of the
water supply of the municipality and, for this purpose, extending the coverage of The claim of respondent DENR-EMB RVI is that no permits and/or clearances from National
appropriate ordinances over all territory within the drainage area of said water supply Government Agencies (NGAs) and LGUs are required pursuant to the DENR Memorandum
and within one hundred (100) meters of the reservoir, conduit, canal, aqueduct, Circular No. 2007-08. However, we still find that the LGC requirements of consultation and
pumping station, or watershed used in connection with the water service; and approval apply in this case. This is because a Memorandum Circular cannot prevail over the
regulating the consumption, use or wastage of water." [Section 447 (5)(i) & (vii)] Local Government Code, which is a statute and which enjoys greater weight under our
hierarchy of laws.
Under the Local Government Code, therefore, two requisites must be met before a national
project that affects the environmental and ecological balance of local communities can be Subsequent to the information campaign of respondent Province, the Municipality of Malay and
implemented: prior consultation with the affected local communities, and prior approval of the the Liga ng mga Barangay-Malay Chapter still opposed the project. Thus, when respondent
project by the appropriate sanggunian. Absent either of these mandatory requirements, the Province commenced the implementation project, it violated Section 27 of the LGC, which
project’s implementation is illegal.155 (Emphasis added.) clearly enunciates that "[no] project or program shall be implemented by government authorities
unless the consultations mentioned in Sections 2(c) and 26 hereof are complied with, and prior
approval of the sanggunian concerned is obtained."
Based on the above, therefore, prior consultations and prior approval are required by law to
have been conducted and secured by the respondent Province. Accordingly, the information
55
The lack of prior public consultation and approval is not corrected by the subsequent Section 2. Declaration of Policy. - (a) It is hereby declared the policy of the State that the
endorsement of the reclamation project by the Sangguniang Barangay of Caticlan on February territorial and political subdivisions of the State shall enjoy genuine and meaningful local
13, 2012, and the Sangguniang Bayan of the Municipality of Malay on February 28, 2012, which autonomy to enable them to attain their fullest development as self-reliant communities and
were both undoubtedly achieved at the urging and insistence of respondent Province. As we make them more effective partners in the attainment of national goals. Toward this end, the
have established above, the respective resolutions issued by the LGUs concerned did not State shall provide for a more responsive and accountable local government structure instituted
render this petition moot and academic. through a system of decentralization whereby local government units shall be given more
powers, authority, responsibilities, and resources. The process of decentralization shall
It is clear that both petitioner and respondent Province are interested in the promotion of tourism proceed from the national government to the local government units.156 (Emphases ours.)
in Boracay and the protection of the environment, lest they kill the proverbial hen that lays the
golden egg. At the beginning of this decision, we mentioned that there are common goals of As shown by the above provisions of our laws and rules, the speedy and smooth resolution of
national significance that are very apparent from both the petitioner’s and the respondents’ these issues would benefit all the parties. Thus, respondent Province’s cooperation with
respective pleadings and memoranda. respondent DENR-EMB RVI in the Court-mandated review of the proper classification and
environmental impact of the reclamation project is of utmost importance.
The parties are evidently in accord in seeking to uphold the mandate found in Article II,
Declaration of Principles and State Policies, of the 1987 Constitution, which we quote below: WHEREFORE, premises considered, the petition is hereby PARTIALLY
GRANTED.1âwphi1 The TEPO issued by this Court is hereby converted into a writ of
SECTION 16. The State shall protect and advance the right of the people to a balanced and continuing mandamus specifically as follows:
healthful ecology in accord with the rhythm and harmony of nature.
1. Respondent Department of Environment and Natural Resources-Environmental
xxxx Management Bureau Regional Office VI shall revisit and review the following matters:

SECTION 20. The State recognizes the indispensable role of the private sector, encourages a. its classification of the reclamation project as a single instead of a co-located
private enterprise, and provides incentives to needed investments. project;

The protection of the environment in accordance with the aforesaid constitutional mandate is b. its approval of respondent Province’s classification of the project as a mere
the aim, among others, of Presidential Decree No. 1586, "Establishing an Environmental expansion of the existing jetty port in Caticlan, instead of classifying it as a new
Impact Statement System, Including Other Environmental Management Related Measures and project; and
For Other Purposes," which declared in its first Section that it is "the policy of the State to attain
and maintain a rational and orderly balance between socio-economic growth and c. the impact of the reclamation project to the environment based on new,
environmental protection." updated, and comprehensive studies, which should forthwith be ordered by
respondent DENR-EMB RVI.
The parties undoubtedly too agree as to the importance of promoting tourism, pursuant to
Section 2 of Republic Act No. 9593, or "The Tourism Act of 2009," which reads: 2. Respondent Province of Aklan shall perform the following:

SECTION 2. Declaration of Policy. – The State declares tourism as an indispensable element a. fully cooperate with respondent DENR-EMB RVI in its review of the
of the national economy and an industry of national interest and importance, which must be reclamation project proposal and submit to the latter the appropriate report and
harnessed as an engine of socioeconomic growth and cultural affirmation to generate study; and
investment, foreign exchange and employment, and to continue to mold an enhanced sense of
national pride for all Filipinos. (Emphasis ours.) b. secure approvals from local government units and hold proper consultations
with non-governmental organizations and other stakeholders and sectors
The primordial role of local government units under the Constitution and the Local Government concerned as required by Section 27 in relation to Section 26 of the Local
Code of 1991 in the subject matter of this case is also unquestionable. The Local Government Government Code.
Code of 1991 (Republic Act No. 7160) pertinently provides:
3. Respondent Philippine Reclamation Authority shall closely monitor the submission
by respondent Province of the requirements to be issued by respondent DENR-EMB
RVI in connection to the environmental concerns raised by petitioner, and shall
coordinate with respondent Province in modifying the MOA, if necessary, based on the
findings of respondent DENR-EMB RVI.

4. The petitioner Boracay Foundation, Inc. and the respondents The Province of Aklan,
represented by Governor Carlito S. Marquez, The Philippine Reclamation Authority,
and The DENR-EMB (Region VI) are mandated to submit their respective reports to
this Court regarding their compliance with the requirements set forth in this Decision
no later than three (3) months from the date of promulgation of this Decision.

5. In the meantime, the respondents, their concerned contractor/s, and/or their agents,
representatives or persons acting in their place or stead, shall immediately cease and
desist from continuing the implementation of the project covered by ECC-R6-1003-
096-7100 until further orders from this Court. For this purpose, the respondents shall
report within five (5) days to this Court the status of the project as of their receipt of this
Decision, copy furnished the petitioner.

This Decision is immediately executory.

SO ORDERED.

57

You might also like