Professional Documents
Culture Documents
The work Formation of New M.I Tank across Eduuleru vagu near
M.Lingapuram (V) ( h/o Gokavaram ) , Kothapalle mandal, kurnool district has
administratively sanctioned for Rs.316.86 lakhs vide Go.No. 223 dated 20-02-2004
without land cost. The G.P.R. Charities trust came forwrd volunterly to purchase
land . Some portion of land was purchased by the Trust in the year 2004-05 .This
process was stopped due to some unavoidable reasons from trust side. Hence the
work could not be taken up at that time. Now the Trust came forward to purchase
land and completed 85% of requirement.
The estimate was prepared with 2003-04 SSR. Hence the estimate is
required to recast with current SSR. Accordingly the estimate was recasted to
Rs.878.43 lakhs and submitted to the government. The Government vide memo no.
734 / MIR2 / 2012-2 dated 22-02-2012 has requested that the proposal may be
processed for obtaining approval from committee of chief Engineers to indicate
component wise increase. The increase is only due to increase in rates as per
current SSR. However a comparative statement has been prepared for obtain
approval from committee of Chief Engineers if required.
Ref : - Govt. memo no. 734 / MIR2 / 2012-2 dated 22-02-2012 received vide circle endorcement no
SE/IC/KNL/JTO-5/ F.M-16/ 89M dated 24-03-2012
*******
I submit that in the reference cited certain information was called for sanctioning
of Revised administrtive approval of " Formation of New M.I.Tank across Edduleru vagu near
M.Lingapuram (V), Kothapalle (M), Kurnool district". I here with submit the pera wise reply for the
remarks pointed out.
1 It was proposed that the proposal may be proceessed for obtaining approval from committee of
chief Engineers to indicate component wise increase. It is submitted that the above work was
Administratively approved for Rs.316.86 lakhs vide Go.No. 223 dated 20-02-2004 in which
estimate is prepared with 2003-04 SSR. Now the estimate is recasted with current SSR for
Rs.878.430 lakhs with out changing detailed quatities. The increase is only due to increase in
rates as per current SSR. However a comparitive statement has been submitted here with for
obtaing approval from committee of Chief Engineers if required.
2 It was requested to examine the proposal as per U.O.note No. 25/Prl.Secy.(1)/2011-2 dated 21-
09-2011 to explore the possibility to takeup under MGNREGS. In this connection it is submitted
that the work is not yet started and the nature of work is original work involving huge
machinery work.Hence could not be taken up under MGNREGS.Further the work was
scrutanizes as per U.O. note 2351/F(A1)/2011-1 dated and necessary information is furnished
in the check-list prescribed in U.O.note No. 21153-A/657/Expr.PW/11 dated 04-08-2011.
(ii) The details of land purchased by the trust was scrutinised in detail. The total land required
is 497.194 acres excluding government land of 8.422 acres. The trust has purchased and
383.04 acres and registerd in the name of District Collector i.e to the government. An extent of
34.26 acres was acquired by the Distict collector as per LA act. Balance 79.894 acres has to be
procured. The trust is negotiating with farmers to purchase. If negotiations are not possible the
land will be acquired as per LA act by the District collector. Mean while the estimate is
resubmitted to avoid delay.
The estimate along with comparitive statement and copies of documents are
submitted here with for according administrtive sanction from competent authority.
This is submitted for favour of taking further necessary action.
314.78
716.6
126165.22467
CHECK SLIP TO ACCOMPANY THE ESTIMATE FOR ADMINISTRATIVE APPROVAL
5 Liability as on :
1 Budget eligibility :
c) Balance available :
a)If the land acquisition or any other clearences are involed ,the
:
department may propose invariably for Stage-1 sanction only.
1 Prelimaniries 100000
Total 78548226
N.W:- FORMATION OF NEW M.I TANK ACROSS EDDULERU
VAGU NEAR M.LINGAPURAM VILLAGE ( GOKAVARAM ) ,
KOTHAPALLE MANDAL, KURNOOL DT.
GENERAL ABSTACT
1 Prelimaniries 100000
2 Land acquesition 20000000
4 BUILDINGS
a. Construction of Store shed (LS) 0
5 EARTH WORK
a. Formation of Bund 43815664
b. Excavation of Supply Channels ( Right & Left ) 3347798
6 Miscelleneous
a. Plantation 103000
ABSTACT ESTIMATE
Sl. Quan
Rate
Per
Description of work
N0 tity
1 sqm
space ) including bushes upto 30 cm / parthenium and
Sqm
1.10
1
other weeds including burning or disposing off the same as
directed etc., complete. PMW 1 - 1
1 cum
89.80
Cum
1 cum
185.20
Cum
3
level and profile, cost of all materials, machinery, labour,
placing the excavated rock in dump area or for formation of
service road as directed etc., complete with lead upto 1 km
and all lifts. CAW 1- 5
Cum
Cum
Rate
Per
Description of work
N0 tity
1 cum
86.20
Cum
1 cum
185.50
3346
Cum
1 cum
81.10
Cum
1 cum
86.20
Cum
1 cum
185.50
Cum
Rate
Per
Description of work
N0 tity
1 cum
185.50
7329
Cum
1 cum
206.70
1776
Cum
1830.40
and 20 cm thick 20 mm down coarse aggregate layer using
1 cum
Cum
610
1 cum
5898
Cum
1 cum
1573
Cum
Cum
1 cum
6500
Cum
Total
Sl. Quan
Rate
Per
Description of work
N0 tity
Grand Total
Rate
Per
Description of work
N0 tity
ABSTACT ESTIMATE
Sl. Quan
Rate
Per
Description of work
N0 tity
1 Cum
6760
Cum
0.00
1 labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified
thickness, breaking clods, sectioning,etc.,complete with
initial lead upto 1 km and all lifts. PMW 3 - 22
Total
Provision for Photographic charges charges / miscelleneous
2
@ 2.5%
Grand Total
Or say
Rate
Per
Description of work
N0 tity
Sub work - Formation of clay blanket in vagu portion at chainage 1400 to 1500
ABSTACT ESTIMATE
Sl. Quan
Rate
Per
Description of work
N0 tity
1 Cum
65.90
3690
Cum
1 Cum
240.70
2400
Cum
Cum
Total
Provision for Photographic charges charges / miscelleneous
4
@ 2.5%
Grand Total
Amount
26400
1809380
119454
573230
1057350
Amount
2788656
620683
858525
1422472
6367659
Amount
1359530
367099
1116544
7554748
2014856
5686548
8376550
42119684
Amount
1064
1567420
100000
27496
43815664
Superintending Engineer
Irrigation Circle,Kurnool
Amount
mp
Amount
0
0
0
1064
Superintending Engineer
Irrigation Circle,Kurnool
Amount
Amount
243171
577680
779100
1599951
-32531
1567420
Superintending Engineer
Irrigation Circle,Kurnool
N.W:- FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU
NEAR M.LINGAPURAM VILLAGE ( GOKAVARAM ) , KOTHAPALLE
MANDAL, KURNOOL DT.
Sub work - Construction of H.C.Weir
ABSTACT ESTIMATE
Sl. Quant
Rate
Per
Description of work Amount
N0 ity
1 cum
65.90
3550
Cum
1 cum
229.00
1600
Cum
3 58249
placing the excavated stuff neatly in specified dump area or
disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m. CCDW 1 - 5
Cum
5682.53
1 cum
Cum
5 3114026
labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
5430.53
1 cum
Cum
6 1618298
asphalt mortar etc., complete with initial lead upto 50 m
and all lifts. ( Cement content : 300 kg / cum ) If water is to
be brought from other place add only lead charges @ 500
ltr / cum. to the data (Cement content: 330 kg / cum with
use of super plasticiser(0.4% by wt. of cement), CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2 - 26
1 Sqm
408.88
pitching including cost of all materials,labour,hand
Sqm
7 452324
packing,finishing etc.,complete ( rubble stones : 0.33
cum/sqm) CAW 8 - 4
8 6953
packing, finishing etc., complete ( rubble stones : 0.275
cum/sqm) CAW 8 - 2
Total 15365974
ABSTACT ESTIMATE
Sl. Quant
Rate
Per
Description of work Amount
N0 ity
1 cum
89.80
Cum
1 cum
121.50
2300
Cum
Cum
5.80
1 cum
95.30
Cum
5 2592800
packing, finishing etc., complete ( rubble stones : 0.275
cum/sqm) CAW 8 - 2
Total 11403263
Provision for Photographic charges charges / miscelleneous
6 171977
@ 2.5%
Rate
Per
Description of work Amount
N0 ity
1 cum
341.9
65.90
Cum
1 cum
229.00
Cum
Cum
5682.53
1 cum
115.5
Cum
6006.43
structure works including cost of all materials, machinery,
1 cum
Cum
14.4
1 kg
Kg
6 46857
required,tying with 1.25 mm dia soft annealed steel wire,
including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts. CCDW 2 - 1
Cum
LS
### 100000
2
Total 1288262
Provision for Photographic charges charges / miscelleneous
11 0
@ 2.5%
ABSTACT ESTIMATE
Sl. Quant
Rate
Per
Description of work Amount
N0 ity
1 cum
89.80
6879
Cum
2 85172
required level and profile, cost of all materials, machinery,
labour, placing the excavated soft rock neatly in dump area
or for formation of service road as directed etc., complete
with lead upto 1 km and all lifts. CAW 1 - 3
Cum
1 cum
1260
Cum
5.80
4 labour, all operations such as compacting to density 7308
control of not less than 90 percent or as stipulated using
2T roller etc., complete with initial lead upto 1 km and all
lifts. PMW 3- 24
1 cum
95.30
4535
Cum
Total 1361492
171162 233474
Provision towards construction of pipe barrel for vagu
1 No
Nos
6 233474
1
1 No
Nos
72596
1 No
Nos
statement )
1 No
Nos
statement )
58800
10 470400
8
11 233328
4
12 86197
1
statement )
28469
13 28469
1
statement )
FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU NEAR
M.LINGAPURAM VILLAGE ( GOKAVARAM ) , KOTHAPALLE
MANDAL, KURNOOL DT.
for canal, seating of embankment, filter drains / catch water drains etc.,
including dressing bed and sides to required level and profile, cost of all
materials, machinery, labour, placing the excavated soil neatly in dump
area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts. CAW -1-1
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1750.50
Fuel / Energy charges Hour 8.00 816.80
2 Tippers 5 cum capacity 6 Nos Hour 48.00 456.20
Fuel / Energy charges Hour 48.00 280.70
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Shovel Hour 8.00 187.20
2 Crew for Tipper Hour 48.00 140.40
3 work inspector Day 1.00 335.00
4 mazdoor Day 30.00 280.00
Total cost of Labour Rs:
labour component/unit qty 14.30
Add contractor's profit and overhead charges 0.14 2.00
labour component/unit qty (including contractor's profi16.30
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 925.00 cum Rs:
Rate cum (A+B+C+D)/925 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1750.50
Fuel / Energy charges Hour 8.00 816.80
2 Tippers 5 cum capacity 5 Nos Hour 40.00 456.20
Fuel / Energy charges Hour 40.00 280.70
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Shovel Hour 8.00 187.20
2 Crew for Tipper Hour 40.00 140.40
3 work inspector Day 1.00 335.00
4 Crowbarman Day 11.00 320.00
5 mazdoor Day 22.00 280.00
Total cost of Labour Rs:
labour component/unit qty 21.40
Add contractor's profit and overhead charges 0.14 3.00
labour component/unit qty (including contractor's profi24.40
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 630.00 cum Rs:
Rate cum (A+B+C+D)/630 Rs.
including boulders above 0.6 m upto 1.2 m dia. For canals, seating of
embankment, filter drain / catch water drains etc., including dressing bed
and sides to required level and profile, cost of all materials, machinery,
labour, placing the excavated rock in dump area or for formation of service
road as directed etc., complete with lead upto 1 km and all lifts. CAW 1- 5
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1750.50
Fuel / Energy charges Hour 8.00 816.80
2 Tippers 5 cum capacity 5 Nos. Hour 40.00 456.20
Fuel / Energy charges Hour 40.00 280.70
3 Air compressor 8.5 cmm ( diesel ) Hour 12.00 282.90
Fuel / Energy charges Hour 12.00 835.30
4 Jack hammers 3 Nos. Hour 39.00 20.50
Fuel / Energy charges Hour 39.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Shovel Hour 8.00 187.20
2 Crew for Tipper Hour 40.00 140.40
3 Crew for Air compressor Hour 12.00 167.20
4 Crew for Jack hammer Hour 39.00 261.30
5 work inspector Day 1.00 335.00
6 Blaster Day 1.00 400.00
7 Helper blaster Day 1.00 320.00
8 Crowbarman Day 16.00 320.00
9 Stone breaker Day 16.00 320.00
10 mazdoor Day 32.00 280.00
Total cost of Labour Rs:
labour component/unit qty 39.30
Add contractor's profit and overhead charges 0.14 5.50
labour component/unit qty (including contractor's profi44.80
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 805.00 cum Rs:
Rate cum (A+B+C+D)/805 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer 90 hp Hour 3.40 1753.10
Fuel / Energy charges Hour 3.40 571.40
2 Shovel 0.5 cum Hour 8.00 1028.90
Fuel / Energy charges Hour 8.00 445.50
3 Tippers 5 cum Hour 32.00 456.20
Fuel / Energy charges Hour 32.00 280.70
4 Pump 5 hp ( diesel ) Hour 2.00 10.40
Fuel / Energy charges Hour 2.00 74.30
5 Water tanker 8000 ltr Hour 4.00 411.00
Fuel / Energy charges Hour 4.00 280.70
6 Vibratory pad foot roller 8 tonne Hour 4.17 1367.10
Fuel / Energy charges Hour 4.17 965.30
7 Sundries LS 5.00 41.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Dozer Hour 3.40 187.20
2 Crew for Shovel Hour 8.00 187.20
3 Crew for Tipper Hour 32.00 140.40
4 Crew for Pump Hour 2.00 87.40
5 Crew for Water tanker Hour 4.00 140.40
6 Crew for Roller Hour 4.00 209.00
7 work inspector Day 4.17 335.00
8 mazdoor Day 4.00 280.00
Total cost of Labour Rs:
labour component/unit qty 20.60
Add contractor's profit and overhead charges 0.14 2.90
labour component/unit qty (including contractor's profi23.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 412.80 cum Rs:
Rate cum (A+B+C+D)/412.80 Rs.
Add segniorage charges of soil
Total cost for
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer Hour 6.06 1753.10
Fuel / Energy charges Hour 6.06 571.40
2 Shovel 0.50 cum capacity Hour 8.00 1028.90
Fuel / Energy charges Hour 8.00 445.50
3 Tippers 5.00 cum capacity 6 Nos. Hour 48.00 456.20
Fuel / Energy charges Hour 48.00 280.70
4 Pump 5 hp ( diesel ) Hour 3.00 10.40
Fuel / Energy charges Hour 3.00 74.30
5 Water tanker 8000 ltr Hour 6.00 411.00
Fuel / Energy charges Hour 6.00 280.70
6 Vibratory pad foot roller 8 tonne Hour 7.53 1367.10
Fuel / Energy charges Hour 7.53 965.30
7 Sundries LS 2.00 41.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Dozer Hour 6.06 187.20
2 Crew for Shovel Hour 8.00 187.20
3 Crew for Tipper Hour 48.00 140.40
4 Crew for Pump Hour 3.00 87.40
5 Crew for Water tanker Hour 6.00 140.40
6 Crew for Roller Hour 7.53 209.00
7 work inspector Day 2.00 335.00
8 mazdoor Day 4.00 280.00
Total cost of Labour Rs:
labour component/unit qty 16.20
Add contractor's profit and overhead charges 0.14 2.30
labour component/unit qty (including contractor's profi18.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 677.28 cum Rs:
Rate cum (A+B+C+D)/678.2 Rs.
Add segniorage charges for soil
Rate cum Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer 90 hp Hour 6.06 1256.70
Fuel / Energy charges Hour 6.06 476.10
2 Shovel 0.50 cum capacity Hour 8.00 697.70
Fuel / Energy charges Hour 8.00 371.30
3 Tippers 5.00 cum capacity 4 Nos. Hour 48.00 351.30
Fuel / Energy charges Hour 48.00 233.90
4 Vibratory pad foot roller 8 tonne Hour 6.16 912.50
Fuel / Energy charges Hour 6.16 804.40
5 Sundries LS 2.00 33
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Dozer Hour 6.06 148.20
2 Crew for Shovel Hour 8.00 148.20
3 Crew for Tipper Hour 48.00 111.20
4 Crew for Roller Hour 6.16 170.00
5 work inspector Day 2.00 275.00
6 mazdoor Day 4.00 215.00
Total cost of Labour Rs:
labour component/unit qty 14.60
Add contractor's profit and overhead charges 0.14 2.00
labour component/unit qty (including contractor's profi16.60
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 677.28 cum Rs:
Rate cum (A+B+C+D)/677.28 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer 90 hp Hour 3.60 1753.10
Fuel / Energy charges Hour 3.60 571.40
2 Pump 5 hp ( diesel ) Hour 3.00 10.40
Fuel / Energy charges Hour 3.00 74.30
3 Water tanker 8000 ltr Hour 5.00 411.00
Fuel / Energy charges Hour 5.00 280.70
4 Vibratory pad foot roller 8 tonne Hour 7.30 1367.10
Fuel / Energy charges Hour 7.30 965.30
5 Sundries LS 2.00 33
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Dozer Hour 3.60 187.20
2 Crew for Pump Hour 3.00 87.40
3 Crew for Water tanker Hour 5.00 140.40
4 Crew for Roller Hour 7.30 209.00
5 work inspector Day 1.00 335.00
6 mazdoor Day 4.00 280.00
Total cost of Labour Rs:
labour component/unit qty 6.10
Add contractor's profit and overhead charges 0.14 0.90
labour component/unit qty (including contractor's profi7.00
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 600 cum Rs:
Rate cum (A+B+C+D)/600 Rs.
Add segniorage charges for soil
Rate cum Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer 90 hp Hour 3.60 1753.10
Fuel / Energy charges Hour 3.60 571.40
2 Pump 5 hp ( diesel ) Hour 3.00 10.40
Fuel / Energy charges Hour 3.00 74.30
3 Water tanker 8000 ltr Hour 5.00 411.00
Fuel / Energy charges Hour 5.00 280.70
4 Vibratory pad foot roller 8 tonne Hour 6.1 1367.10
Fuel / Energy charges Hour 6.1 965.30
5 Sundries LS 5.00 41.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Dozer Hour 3.60 187.20
2 Crew for Pump Hour 3.00 87.40
3 Crew for Water tanker Hour 5.00 140.40
4 Crew for Roller Hour 6.1 209.00
5 work inspector Day 2.00 335.00
6 mazdoor Day 4.00 280.00
Total cost of Labour Rs:
labour component/unit qty 6.20
Add contractor's profit and overhead charges 0.14 0.90
labour component/unit qty (including contractor's profi7.10
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 600 cum Rs:
Rate cum (A+B+C+D)/600 Rs.
Add segniorage charges for soil
Rate cum Rs.
Providing and laying 25 cm thick sand blanket below embankment
IRR-CAW-
5-3 A
including cost of all materials, machinery, labour, spreading to specified
thickness etc., complete with initial lead upto 50 m and all lifts. CAW 5 - 3
-A
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 mazdoor Day 20.00 215.00
Total cost of Labour Rs:
labour component/unit qty 10.80
Add contractor's profit and overhead charges 0.14 1.50
labour component/unit qty (including contractor's profi12.30
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 100 Cum Rs:
Rate sqm (A+B+C+D)/100 Rs.
Providing and constructing dry rubble rock-toe using rubble and stone
IRR- CAW -
chips from approved source including cost of all materials, machinery,
5- 4
labour, hand packing rubble and stone chips, finishing top and sides to
required slopes etc., complete with initial lead upto 50 m and all lifts. CAW
- 5- 4
DATA RATE ANALYSIS UNIT : 100.00
A. MATERIALS:
Sl No particulars Unit Quantity Rate
in Rs.
1 Rubble cum 100.00 280.00
2 Stone chips cum 15.00 330.00
3 Sundries LS 2.00 41.00
Seionorage charges for stone chips
(included in the material rates)
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 1.00 335.00
2 Mason Class-II Day 7.00 320.00
3 mazdoor Day 19.00 280.00
Total cost of Labour Rs:
labour component/unit qty 61.80
Add contractor's profit and overhead charges 0.14 8.70
labour component/unit qty (including contractor's profi70.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 100.00 cum Rs:
Add lead charges Qty Rate
1 Rubble 100 711.10
2 Stone chips 15 711.10
Total
Add lead charges
1 Rubble 100 50
2 Stone chips 15 50
Total
Total cost including conveyance
Rate cum Rs.
IRR-CAW - 5-8
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 1.00 335.00
2 mazdoor Day 36.00 280.00
Total cost of Labour Rs:
labour component/unit qty 80.20
Add contractor's profit and overhead charges 0.14 525.70
labour component/unit qty (including contractor's profi605.90
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 100.00 cum Rs:
Rate cum (A+B+C+D)/100.0 Rs.
Add lead charges
1 Sand un screened 60 860.00
IRR-CAW
Sl. Rate
Particulars Unit Quantity
No in Rs.
Sl. Rate
Particulars Unit Quantity
No in Rs.
0 0
1 Nil
0 0
Total hire charges of Machinery Rs.
C. LABOUR :
Sl. Rate
Particulars Unit Quantity
No in Rs.
1 Mason Class II Day 5.50 260.00
2 Mazdoor Day 24.75 215.00
Total Cost of Labour Rs.
labour component/unit qty 67.50
Add contractor's profit and overhead charges 0.14 9.50
labour component/unit qty (including contractor's profi77.00
ABSTRACT :
A. Cost of Material including seignorage charges Rs.
B. Hire Charges of Machinery Rs.
C. Cost of Labour Rs.
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 100.0 Sqm. Rs:
Rate Sqm. (A+B+C+D)/100.0 Rs.
B.MACHINERY :
Rate
Sl No Description Unit Quantity
in Rs
C.LABOUR :
Rate
Sl No Description Unit Quantity
in Rs
ABSTRACT
A.Cost of Materials including ryolty charges Rs:
B. Hire charges of Machinery Rs:
C.Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on
14% Rs:
(A+B+C)
Total cost for 100.00 sqm Rs:
Rate sqm (A+B+C+D)/100.0 Rs.
Add lead charges Qty Rate
1 Rubble 33 711.10
2 Stone chips 0 711.10
Total
Add lead charges
1 Rubble 33 50
2 Stone chips 0 50
Total
Total cost including conveyance
Rate per sqm Rs.
Rate per cum
Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing the excavated stuff neatly in specified dump area or disposing off
the same as directed etc., complete with initial lead upto 50 m and initial
lift upto 3 m. CCDW 1 - 1
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 NIL 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 0.25 275.00
2 mazdoor Day 6.00 215.00
Total cost of Labour Rs:
labour component/unit qty 135.9
Add contractor's profit and overhead charges 0.14 19.02
labour component/unit qty (including contractor's profi 154.90
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+ 14.00% Rs:
Total cost for 10.00 cum Rs:
Rate cum (A+B+C+D)/10.0 Rs.
IRR-CCDW-1-2
b)Machinery
Sl No Description Unit Quantity Rate
in Rs.
Hydraulic excavator 1.0 cum bucket
1 hour 6.00 1180.70
capacity
Fuel/ Energy charges hour 6.00 680.60
crew for excavator hour 6.00 148.20
Total in Rs.
labour component/unit qty 50.20
Add contractor's profit and overhead charges 0.14 7.00
labour component/unit qty (including contractor's profi57.20
Abstract
a) Labour Rs
b) Machinery Rs
c) Material Rs
Total Rs
D. Add for contractor's profit and overheads on (A+ 14.00% Rs:
Total cost for 240.00 cum Rs:
Rate cum (A+B+C+D)/240.0 Rs.
IRR-CCDW -1-
Excavation in ordnary rock (including HDR) without blasting including
boulders above 0.3 m upto 0.60 m dia.for foundations of canal cross
drainage and other appurtenant structures and placing the excavated
3
stuff neatly in specified dump area or disposing off the same as directed
etc., complete with initial lead upto 50 m and initial lift upto 3 m. CCDW -
1-3
DATA: RATE ANALYSIS UNIT : 10.00
A. MATERIALS:
Sl No Particulars Unit Quantity Rate
in Rs.
1 NIL 0.00 0.00
0.00 0.00
Total cost of Materials Rs:
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 NIL 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crowbarman Day 1.25 260.00
2 Stone breaker Day 1.25 260.00
3 work inspector Day 0.25 275.00
4 mazdoor Day 6.00 215.00
Total cost of Labour Rs:
labour component/unit qty 200.90
Add contractor's profit and overhead charges 0.14 28.10
labour component/unit qty (including contractor's profi229.00
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+ 14.00% Rs:
Total cost for 10.00 cum Rs:
Rate cum (A+B+C+D)/10.0 Rs.
IRR-CCDW-1-4
Excavation in ordnary rock without blasting for foundations of canal
cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as
directed etc., complete with initial lead upto 50 m and initial lift upto 3
m.CCDW - 1-4
b) Machinery
Sl No Description Unit Quantity Rate
in Rs.
Hydraulic excavator 1.0 cum bucket
1.0 hour 6.00 1180.70
capacity
Fuel/ Energy charges hour 6.00 680.60
crew for excavator hour 6.00 148.20
Total in Rs.
labour component/unit qty 67.00
Add contractor's profit and overhead charges 0.14 9.40
labour component/unit qty (including contractor's profi76.40
Abstract
a) Labour Rs
b) Machinery Rs
c) Material Rs
Total Rs
D. Add for contractor's profit and overheads on
14.00% Rs:
(A+B+C)
Total cost for 180.00 cum Rs:
Rate cum (A+B+C+D)/180.0 Rs.
IRR-CCDW-1-
dump area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m. CCDW 1 - 5
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Air compressor 8.5 cmm ( diesel ) Hour 3.00 210.40
Fuel / Energy charges Hour 3.00 696.10
2 Jack hammers 2 Nos. Hour 6.00 13.50
Fuel / Energy charges Hour 6.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Air compressor Hour 3.00 136.00
2 Crew for Jack hammer Hour 6.00 212.60
3 work inspector Day 1.00 275.00
4 Blaster Day 0.50 310.00
5 Helper blaster Day 0.50 260.00
6 Crowbarman Day 6.00 260.00
7 Stone breaker Day 3.00 260.00
8 mazdoor Day 51.00 215.00
Total cost of Labour Rs:
labour component/unit qty 155.50
Add contractor's profit and overhead charges 0.14 21.80
labour component/unit qty (including contractor's profi177.30
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+ 14.00% Rs:
Total cost for 100.00 cum Rs:
Rate cum (A+B+C+D)/100.0 Rs.
IRR-CCDW-1-8
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel
anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed
rock and remaining length embedded in concrete / masonry including cost
of all materials, machinery, labour, drilling and cleaning hole, driving
anchor rod, grouting hole with thick cement slurry etc., complete with
initial lead upto 50 m and all lifts. CCDW 1 - 8
RATE ANALYSIS UNIT : 10.00
A. MATERIALS:
Sl No Particulars Unit Quantity Rate
in Rs.
1 Cement for grouting kg 5.00 5.50
2 25 mm dia steel kg 101.00 41.00
3 Use rate of 32 mm dia drill rod Rm 12.50 22.00
Reconditioning charges @ 10%
4 Use rate of air hose Hour 2.00 8.13
Total cost of Materials Rs:
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Air compressor 8.5 cmm ( diesel ) Hour 1.00 210.40
Fuel / Energy charges Hour 1.00 696.10
2 Jack hammer 2 Nos Hour 2.00 13.50
Fuel / Energy charges Hour 2.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Air compressor Hour 1.00 136.00
2 Crew for Jack hammer Hour 2.00 212.60
3 Mason Class-II Day 0.50 260.00
4 Bar bender Day 0.50 300.00
5 work inspector Day 0.50 275.00
6 mazdoor Day 1.00 215.00
Total cost of Labour Rs:
labour component/unit qty 119.40
Add contractor's profit and overhead charges 0.14 16.70
labour component/unit qty (including contractor's profi136.10
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+ 14.00% Rs:
Total cost for 10.00 Nos. Rs:
Rate each (A+B+C+D)/10.0 Rs.
IRR-CCDW-2-1
Providing, fabricating and placing in position reinforcement steel bars for
RCC works including cleaning, straightening, cutting, bending, hooking,
lapping, welding wherever required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials, machinery, labour etc., complete
with initial lead upto 50 and all lifts. CCDW 2 - 1
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 1.00 275.00
2 Bar bender Day 6.00 300.00
3 mazdoor Day 11.00 215.00
Total cost of Labour Rs:
labour component/unit qty 4.40
Add contractor's profit and overhead charges 0.14 0.60
labour component/unit qty (including contractor's profi5.00
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for ### kg Rs:
Rate kg (A+B+C+D)/1000.0Rs.
Providing and laying insitu vibrated M-15 ( 28 days cube compressive
IRR-CCDW-2-3
strength not less than 15 N /sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for foundation filling
including cost of all materials, machinery, labour, formwork, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts. (Cement content:
260 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) CCDW 2 - 3
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Water tanker 8000 ltr Hour 1.00 285.80
Fuel / Energy charges Hour 1.00 233.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Water tanker Hour 1.00 106.30
4 Crew for Needle vibrator Hour 8.00 102.00
5 work inspector Day 1.00 275.00
6 Mason Class-I Day 1.00 285.00
7 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 3.00 215.00
for conveying concrete Day 15.38 215.00
for cleaning/ washing/ curing Day 1.00 215.00
8 Labour cost for shuttering sqm 15.38 55.65
Labour cost for scaffolding @ 10%
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.38 cum Rs:
Rate cum (A+B+C+D)/15.38 Rs.
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
IRR-CCDW-2-5
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Water tanker 8000 ltr Hour 1.00 285.80
Fuel / Energy charges Hour 1.00 233.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Water tanker Hour 1.00 106.30
4 Crew for Vibrator Hour 8.00 102.00
5 Mason Class-I Day 1.00 285.00
6 work inspector Day 1.00 275.00
7 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 3.00 215.00
for conveying concrete Day 16.36 215.00
8 for cleaning/ washing/ curing Day 1.00 215.00
9 Labour cost for shuttering sqm 16.36 55.65
Total cost of Labour Rs:
labour component/unit qty 682.41
Add contractor's profit and overhead charges 0.14 95.54
labour component/unit qty (including contractor's profi777.95
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 16.36 cum Rs:
Rate cum (A+B+C+D)/16.36 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Water tanker 8000 ltr Hour 1.00 285.80
Fuel / Energy charges Hour 1.00 233.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Water tanker Hour 1.00 106.30
4 Crew for Vibrator Hour 8.00 102.00
5 Mason Class-I Day 1.00 285.00
6 work inspector Day 1.00 275.00
7 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying including lifting Day 4.00 215.00
for conveying concrete Day 15.00 215.00
for cleaning/ washing/ curing Day 1.00 215.00
8 Labour cost for shuttering sqm 15.00 55.65
Labour cost for scaffolding @ 25%
labour component/unit qty 13.91
Add contractor's profit and overhead charges 0.14 1.95
labour component/unit qty (including contractor's profi15.86
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.00 cum Rs:
Rate cum (A+B+C+D)/15 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Water tanker 8000 ltr Hour 1.00 285.80
Fuel / Energy charges Hour 1.00 233.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Water tanker Hour 1.00 106.30
4 Crew for Vibrator Hour 8.00 102.00
5 Mason Class-I Day 1.00 285.00
6 work inspector Day 1.00 275.00
7 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying including lifting Day 4.00 215.00
for conveying concrete Day 15.76 215.00
for cleaning/ washing/ curing Day 1.00 215.00
8 Labour cost for shuttering sqm 31.52 55.65
Labour cost for scaffolding @ 25%
labour component/unit qty 27.83
Add contractor's profit and overhead charges 0.14 3.90
labour component/unit qty (including contractor's profi31.72
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.76 cum Rs:
Rate cum (A+B+C+D)/15 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Water tanker 8000 ltr Hour 1.00 285.80
Fuel / Energy charges Hour 1.00 233.90
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Water tanker Hour 1.00 106.30
4 Crew for Vibrator Hour 8.00 102.00
5 Mason Class-I Day 1.00 285.00
6 work inspector Day 1.00 275.00
7 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 4.00 215.00
for conveying concrete Day 15.71 215.00
for cleaning/ washing/ curing Day 1.00 215.00
8 Labour cost for shuttering sqm 31.42 55.65
Labour cost for scaffolding @ 25%
Total cost of Labour Rs:
labour component/unit qty 796.60
Add contractor's profit and overhead charges 0.14 111.50
labour component/unit qty (including contractor's profi908.10
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.71 cum Rs:
Rate cum (A+B+C+D)/15.71 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Needle vibrator Hour 8.00 102.00
4 Mason Class-I Day 1.00 285.00
5 work inspector Day 1.00 275.00
6 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 5.00 215.00
for conveying concrete Day 16.36 215.00
for cleaning/ washing/ curing Day 1.00 215.00
7 Labour cost for shuttering sqm 44.99 55.65
Labour cost for scaffolding @ 30%
Total cost of Labour Rs:
labour component/unit qty 845.50
Add contractor's profit and overhead charges 0.14 118.40
labour component/unit qty (including contractor's profi963.90
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 16.36 cum Rs:
Rate cum (A+B+C+D)/16.36 Rs.
down size approved, clean, hard, graded aggregates with placing and
sinking plums of size 150 to 80 mm upto 15 percent for gravity type
retaining walls / piers / abutments etc., including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete with
initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with
use of super plasticiser(0.4% by wt. of cement), CA : 0.765cum, Blending
Ratio of CA--50:30:20, FA : 0.34 cum, CCDW 2 - 21
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20
Fuel / Energy charges Hour 8.00 18.60
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Needle vibrator Hour 8.00 102.00
4 Mason Class-I Day 1.00 285.00
5 work inspector Day 1.00 275.00
6 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 5.00 215.00
for placing plums Day 2.00 215.00
for conveying concrete Day 15.38 215.00
for conveying plums Day 2.00 215.00
for cleaning/ washing/ curing Day 1.00 215.00
7 Labour for shuttering sqm 49.75 55.65
Labour for scaffolding @ 30%
Total cost of Labour Rs:
labour component/unit qty 819.56
Add contractor's profit and overhead charges 0.14 114.74
labour component/unit qty (including contractor's profi934.30
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 18.09 cum Rs:
Rate cum (A+B+C+D)/18.09 Rs.
Providing and laying insitu vibrated M-20 ( 28 days cube compressive
IRR-CCDW-2-24
strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for deck slab & kerb
including cost of all materials,machinery, labour, formwork, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum ) (Cement content: 330 kg / cum with
use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending
Ratio of CA--65:35, FA : 0.45 cum) CCDW 2 - 24
DATA: RATE ANALYSIS UNIT : 15.76
A. MATERIALS:
Sl No Particulars Unit Quantity Rate
in Rs.
1 Cement for mix kg 5200.80 5.50
Cement for incidentals @ 5 kg / cum kg 78.80 5.50
2 Coarse aggregate 20-10 mm cum 8.20 2151.10
Coarse aggregate 10 mm below cum 4.41 1831.10
3 Fine aggregate cum 7.09 1245.00
4 Super Plasticizer kg 20.80 54
5 Use rate of shuttering for 30 uses sqm 39.40 242.86
Scaffolding @ of shuttering 250%
6 Sundries LS 1.00 33
Add seignorage charges on CA @ (Included in materia Rs:
Add seignorage charges on FA @ (Included in materia Rs:
Total cost of Materials Rs:
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Needle vibrator Hour 8.00 102.00
4 Mason Class-I Day 2.00 285.00
5 work inspector Day 1.00 275.00
6 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 4.00 215.00
for conveying concrete Day 15.76 215.00
for cleaning/ washing/ curing Day 1.00 215.00
7 Labour cost for shuttering sqm 39.40 55.65
Labour cost for scaffolding @ 250%
Total cost of Labour Rs:
labour component/unit qty 1154.36
Add contractor's profit and overhead charges 0.14 161.61
labour component/unit qty (including contractor's profi1315.97
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.76 cum Rs:
Rate cum (A+B+C+D)/15.76 Rs.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Needle vibrator Hour 8.00 102.00
4 Mason Class-I Day 1.00 285.00
5 work inspector Day 1.00 275.00
6 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 3.00 215.00
for conveying concrete Day 15.76 215.00
for cleaning/ washing/ curing Day 1.00 215.00
7 Labour cost for shuttering sqm 78.80 55.65
Labour cost for scaffolding @ 50%
Total cost of Labour Rs:
labour component/unit qty 1053.07
Add contractor's profit and overhead charges 0.14 147.43
labour component/unit qty (including contractor's profi1200.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.76 cum Rs:
Rate cum (A+B+C+D)/15.76 Rs.
Providing and laying insitu M- 20 ( 28 days cube compressive strength not
less than 20 N / sqmm ) grade cement concrete using 20 mm down size
IRR-CCDW-2-26 approved, clean, hard, graded aggregates for wearing coat including cost of
all materials, machinery, labour, formwork,cleaning, batching, mixing,
placing in position in alternate panels, levelling, compacting, finishing,
curing, packing joints with asphalt mortar etc., complete with initial lead
upto 50 m and all lifts. ( Cement content : 300 kg / cum ) If water is to be
brought from other place add only lead charges @ 500 ltr / cum. to the
data (Cement content: 330 kg / cum with use of super plasticiser(0.4% by
wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2 - 26
DATA: RATE ANALYSIS UNIT : 15.76
A. MATERIALS:
Sl No Particulars Unit Quantity Rate
in Rs.
1 Cement for mix kg 5200.80 5.50
Cement for incidentals @ 5 kg / cum kg 78.80 5.50
2 Coarse aggregate 20-10 mm cum 8.20 2151.10
Coarse aggregate 10 mm below cum 4.41 1831.10
3 Fine aggregate cum 7.09 1245.00
4 Super Plasticizer kg 20.80 54
5 Use rate of shuttering sqm 7.88 197.64
6 Sundries ( asphalt mortar etc ) LS 5.00 33
Add seignorage charges on CA @ (Included in materia Rs:
Add seignorage charges on FA @ (Included in materia Rs:
Total cost of Materials Rs:
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80
Fuel / Energy charges Hour 8.00 61.90
2 5 hp pump ( diesel ) Hour 0.50 8.40
Fuel / Energy charges Hour 0.50 61.90
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00
Fuel / Energy charges Hour 8.00 12.40
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 141.70
2 Crew for Pump Hour 0.50 71.10
3 Crew for Needle vibrator Hour 8.00 102.00
4 Mason Class-I Day 2.00 285.00
5 work inspector Day 1.00 275.00
6 mazdoor
for batching materials Day 11.00 215.00
for loading mortar pans Day 4.00 215.00
for laying Day 4.00 215.00
for conveying concrete Day 15.76 215.00
for cleaning/ washing/ curing Day 2.00 215.00
7 Labour cost for shuttering sqm 7.88 55.65
Total cost of Labour Rs:
labour component/unit qty 708.89
Add contractor's profit and overhead charges 0.14 99.24
labour component/unit qty (including contractor's profi808.13
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 15.76 cum Rs:
Rate cum (A+B+C+D)/15.76 Rs.
IRR-CCDW-
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
( Manual mixing) 0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Mason Cl- I Day 15.00 285.00
2 work inspector Day 1.00 275.00
3 mazdoor Day 25.00 215.00
Total cost of Labour Rs:
labour component/unit qty 99.30
Add contractor's profit and overhead charges 0.14 13.90
labour component/unit qty (including contractor's profi113.20
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 100 sqm Rs:
Rate sqm (A+B+C+D)/100.0 Rs.
IRR-CCDW-6-3
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes
in CM 1 : 2 proportion by volume including cost of all materials ( excluding
pipes and collars ), machinery, labour, aligning, packing joints with hemp,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn :
0.22kg/joint) CCDW 6 - 3
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nill 0.00 0.00
( Manual mixing ) 0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Mason Cl- II Day 2.50 260.00
2 work inspector Day 1.00 275.00
3 mazdoor Day 4.00 215.00
Total cost of Labour Rs:
labour component/unit qty 178.50
Add contractor's profit and overhead charges 0.14 25.00
labour component/unit qty (including contractor's profi203.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 10.00 Joints Rs:
Rate joint (A+B+C+D)/10.0 Rs.
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-6-5
Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes
in CM 1 : 2 proportion by volume including cost of all materials ( excluding
pipes and collars ), machinery, labour, aligning, packing joints with hemp,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 39.60 kg / joint, FA : 0.039cum/joint, Hemp Yarn :
0.31kg/joint) CCDW 6 - 5
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nill 0.00 0.00
( Manual mixing ) 0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Mason Cl- II Day 3.00 260.00
2 work inspector Day 1.00 275.00
3 mazdoor Day 5.00 215.00
Total cost of Labour Rs:
labour component/unit qty 178.50
Add contractor's profit and overhead charges 0.14 25.00
labour component/unit qty (including contractor's profi203.50
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 10.00 Joints Rs:
Rate joint (A+B+C+D)/10.0 Rs.
Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
IRR-CCDW-7-2
Providing and filling murrum / gravely soil ( CNS soil ) for foundation or
around pipes including breaking clods, spreading in layers of 10 to 15 cm,
watering, compaction by earth masters to achieve density control of not
less than 95 percent etc., complete with lead upto 50 m and all lifts.
CCDW 7 -2
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Cartman with double bullock cart Day 0.50 305.00
2 work inspector Day 0.50 275.00
3 mazdoor Day 6.00 215.00
Total cost of Labour Rs:
labour component/unit qty 158.00
Add contractor's profit and overhead charges 0.14 22.12
labour component/unit qty (including contractor's profi180.1
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 10.00 cum Rs:
Rate cum (A+B+C+D)/10.0 Rs.
Providing and fixing one line dressed 111x35x25 cm thick IRC standard
IRR-CCDW-7-4
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 NIL 0.00 0.00
( Manual mixing ) 0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Mason Cl- II Day 1.00 260.00
2 work inspector Day 1.00 275.00
3 mazdoor Day 1.00 215.00
4 Painter Cl- I Day 1.00 300.00
Total cost of Labour Rs:
labour component/unit qty 262.50
Add contractor's profit and overhead charges 0.14 36.80
labour component/unit qty (including contractor's profi299.30
ABSTRACT:
A. Cost of Materials including seignorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 4.00 Nos. Rs:
Rate No. (A+B+C+D)/4.0 Rs.
IRR-PMW-1-1
Clearing thin jungle growth ( more than 50 percent open space ) including
bushes upto 30 cm / parthenium and other weeds including burning or
disposing off the same as directed etc., complete. PMW 1 - 1
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overhead 14.00% Rs:
Total cost for 1000 sqm Rs:
Rate sqm (A+B+C+D)/1000.0Rs.
IRR-PMW-3-22
ABSTRACT:
A. Cost of Materials including seigniorage charges Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D.Add for contractor's profit and overheads on
14% Rs.
(A+B+C)
Total cost for 807.00 Rs:
Rate per cum (A+B+C+D)/807 Rs:
IRR-PMW-3-
cum
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
14004.00
6534.40
21897.60
13473.60
55909.60
Amount
in Rs.
1497.60
6739.20
335.00
8400.00
16971.80
0.00
55909.60
16971.80
72881.40
10203.396
83084.80
89.80
cum
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
14004.00
6534.40
18248.00
11228.00
50014.40
Amount
in Rs.
1497.60
5616.00
335.00
3520.00
6160.00
17128.60
0.00
50014.40
17128.60
67143.00
9400.02
76543.02
121.50
cum
Amount
in Rs.
6004.00
600.40
250.56
11270.00
108.00
2795.00
5720.00
205.00
26952.96
Amount
in Rs.
14004.00
6534.40
18248.00
11228.00
3394.80
10023.60
799.50
0.00
64232.30
Amount
in Rs.
1497.60
5616.00
2006.40
10190.70
335.00
400.00
320.00
5120.00
5120.00
8960.00
39565.70
26952.96
64232.30
39565.70
130750.96
18305.1344
149056.09
185.20
cum
Amount
in Rs.
0.00
0.00
0.00
0.00
Amount
in Rs.
5960.54
1942.76
8231.20
3564.00
14598.40
8982.40
20.80
148.60
1644.00
1122.80
5700.81
4025.30
205.00
56146.61
Amount
in Rs.
636.48
1497.60
4492.80
174.80
561.60
836.00
1396.95
1120.00
10716.23
0.00
56146.61
10716.23
66862.84
9360.7976
76223.64
184.70
22.00
206.70
Amount
in Rs.
0.00
0.00
0.00
0.00
Amount
in Rs.
10623.79
3462.68
8231.20
3564.00
21897.60
13473.60
31.20
222.90
2466.00
1684.20
10294.26
7268.71
82.00
83302.14
Amount
in Rs.
1134.43
1497.60
6739.20
262.20
842.40
1573.77
670.00
1120.00
13839.60
0.00
83302.14
13839.60
97141.74
13599.8436
110741.58
163.50
22.00
185.50
cum
Amount
in Rs.
0.00
0.00
14900.16
14900.16
Amount
in Rs.
7615.60
2885.17
5581.60
2970.40
16862.40
11227.20
5621.00
4955.10
66.00
57784.47
Amount
in Rs.
898.09
1185.60
5337.60
1047.20
550.00
860.00
9878.49
14900.16
57784.47
9878.49
82563.12
11558.8368
94121.96
139.00
cum
Amount
in Rs.
0.00
0.00
0.00
0.00
Amount
in Rs.
6311.16
2057.04
31.20
222.90
2055.00
1403.50
9979.83
7046.69
66.00
29173.32
Amount
in Rs.
673.92
262.20
702.00
1525.70
335.00
1120.00
4618.82
0.00
29173.32
4618.82
33792.14
4730.8996
38523.04
64.20
22.00
86.20
cum
Amount
in Rs.
0.00
0.00
0.00
0.00
Amount
in Rs.
6311.16
2057.04
31.20
222.90
2055.00
1403.50
8284.63
5849.72
205.00
26420.15
Amount
in Rs.
673.92
262.20
702.00
1266.54
670.00
1120.00
4694.66
0.00
26420.15
4694.66
31114.81
4356.0734
35470.88
59.10
22.00
81.10
blanket below embankment
abour, spreading to specified
o 50 m and all lifts. CAW 5 - 3
Cum
Amount
in Rs.
114500.00
0.00
114500.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
4300.00
4300.00
114500.00
0.00
4300.00
118800.00
16632
135432.00
1354.30
k-toe using rubble and stone
of all materials, machinery,
ps, finishing top and sides to
d upto 50 m and all lifts. CAW
cum
Amount
in Rs.
28000.00
4950.00
82.00
0.00
0.00
33032.00
Amount
in Rs.
0.00
Amount
in Rs.
335.00
2240.00
5320.00
7895.00
33032.00
0.00
7895.00
40927.00
5729.78
46656.78
Amount
71110.00
10666.50
81776.50
5000.00
750.00
5750.00
134183.28
1341.80
cum
Amount
in Rs.
23100.00
34500.00
8300.00
0.00
0.00
65900.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
335.00
10080.00
10415.00
65900.00
0.00
10415.00
76315.0
10684.1
86999.10
870.00
51600.00
Sqm.
Amount in
Rs.
27255.25
0
27255.25
Amount in
Rs.
Amount in
Rs.
1430.00
5321.25
6751.25
27255.25
0
6751.25
34006.50
4760.91
38767.41
387.70
26.20
413.90
Amount
in Rs
9240.00
9240.00
Amount
in Rs
0.00
Amount
in Rs
2112.00
8316.00
10428.00
9240.00
0.00
10428.00
19668.00
2753.52
22421.52
224.20
Amount
23466.30
0.00
23466.30
1650.00
0.00
1650.00
47537.82
475.40
1584.67
26.20
er day.
cum
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
68.75
1290.00
1358.75
0.00
0.00
1358.75
1358.75
190.225
1548.98
154.90
Amount
in Rs.
88.00
1720.00
1808.00
Amount
in Rs.
7084.20
4083.60
889.20
12057.00
1808.00
12057.00
0.00
13865.00
1941.1
15806.10
65.90
R) without blasting including
r foundations of canal cross
s and placing the excavated
osing off the same as directed
d initial lift upto 3 m. CCDW -
cum
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
325.00
325.00
68.75
1290.00
2008.75
0.00
0.00
2008.75
2008.75
281.225
2289.98
229.00
ng for foundations of canal
structures and placing the
a or disposing off the same as
o 50 m and initial lift upto 3
cum
Amount
in Rs.
66.00
1290.00
1356.00
Amount
in Rs.
7084.20
4083.60
889.20
12057.00
1356.00
12057.00
0.00
13413.00
1877.82
15290.82
84.90
cum
Amount
in Rs.
717.75
71.78
0.98
1080.00
319.00
560.00
16.50
2766.01
Amount
in Rs.
631.20
2088.30
81.00
0.00
2800.50
Amount
in Rs.
408.00
1275.60
275.00
155.00
130.00
1560.00
780.00
10965.00
15548.60
2766.01
2800.50
15548.60
21115.11
2956.1147
24071.22
240.70
ng cold twisted deformed steel
32 mm dia hole drilled in bed
crete / masonry including cost
g and cleaning hole, driving
nt slurry etc., complete with
-8
Nos.
Amount
in Rs.
27.50
4141.00
275.00
27.50
16.25
4487.25
Amount
in Rs.
210.40
696.10
27.00
0.00
933.50
Amount
in Rs.
136.00
425.20
130.00
150.00
137.50
215.00
1193.70
4487.25
933.50
1193.70
6614.45
926.02
7540.47
754.00
kg
Amount
in Rs.
43050.00
440.00
99.00
43589.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
275.00
1800.00
2365.00
4440.00
43589.00
0.00
4440.00
48029.00
6724.06
54753.06
54.80
( 28 days cube compressive
cement concrete using 40 mm
gregates for foundation filling
labour, formwork, cleaning,
ng, vibrating, finishing, curing
and all lifts. (Cement content:
(0.4% by wt. of cement), CA :
A : 0.40 cum) CCDW 2 - 3
cum
Amount
in Rs.
21993.40
253.77
14472.50
8932.66
5069.22
7659.24
863.74
3039.75
303.98
16.50
0.00
0.00
62604.76
Amount
in Rs.
358.40
495.20
4.20
30.95
285.80
233.90
48.00
99.20
1555.65
Amount
in Rs.
1133.60
35.55
106.30
816.00
275.00
285.00
2365.00
860.00
645.00
3306.70
215.00
855.90
85.59
10984.64
62604.76
1555.65
10984.64
75145.05
10520.307
85665.36
5569.90
cum
Amount
in Rs.
19795.60
269.94
15394.68
9501.84
5392.22
8147.28
777.43
3233.44
323.34
16.50
0.00
0.00
62852.27
Amount
in Rs.
358.40
495.20
4.20
30.95
285.80
233.90
48.00
99.20
1555.65
Amount
in Rs.
1133.60
35.55
106.30
816.00
285.00
275.00
2365.00
860.00
645.00
3517.40
215.00
910.43
11164.28
62852.27
1555.65
11164.28
75572.20
10580.1086
86152.31
5266.00
cum
Amount
in Rs.
26400.00
412.50
14114.93
8711.96
4943.97
7470.00
1036.80
5929.29
1482.32
16.50
0.00
0.00
70518.27
Amount
in Rs.
358.40
495.20
4.20
30.95
285.80
233.90
48.00
99.20
1555.65
Amount
in Rs.
1133.60
35.55
106.30
816.00
285.00
275.00
2365.00
860.00
860.00
3225.00
215.00
834.75
208.69
11219.89
70518.27
1555.65
11219.89
83293.81
11661.1334
94954.94
6330.30
cum
Amount
in Rs.
28604.40
433.40
17628.69
8080.28
8829.54
1123.20
6229.70
1557.43
16.50
0.00
0.00
72503.14
Amount
in Rs.
358.40
495.20
4.20
30.95
285.80
233.90
48.00
99.20
1555.65
Amount
in Rs.
1133.60
35.55
106.30
816.00
285.00
275.00
2365.00
860.00
860.00
3388.40
215.00
1754.09
438.52
12532.46
72503.14
1555.65
12532.46
86591.25
12122.7747
98714.02
6263.60
cum
Amount
in Rs.
24193.40
432.03
17572.77
8054.64
8801.53
950.14
6209.94
1552.49
16.50
0.00
0.00
67783.44
Amount
in Rs.
358.40
495.20
4.20
30.95
285.80
233.90
48.00
99.20
1555.65
Amount
in Rs.
1133.60
35.55
106.30
816.00
285.00
275.00
2365.00
860.00
860.00
3377.65
215.00
1748.52
437.13
12514.75
67783.44
1555.65
12514.75
81853.84
11459.5369
93313.37
5939.70
cum
Amount
in Rs.
19795.60
449.90
15394.68
9501.84
5392.22
8147.28
777.43
9336.55
2800.97
0.00
0.00
71596.47
Amount
in Rs.
358.40
495.20
4.20
30.95
48.00
99.20
1035.95
Amount
in Rs.
1133.60
35.55
816.00
285.00
275.00
2365.00
860.00
1075.00
3517.40
215.00
2503.69
751.11
13832.35
71596.47
1035.95
13832.35
86464.76
12105.0667
98569.83
6025.10
cum
Amount
in Rs.
25868.70
397.98
14469.21
8930.63
5068.06
4708.37
7657.50
1015.93
9832.24
2949.67
0.00
0.00
80898.29
Amount
in Rs.
358.40
495.20
4.20
30.95
49.60
148.80
1087.15
Amount
in Rs.
1133.60
35.55
816.00
285.00
275.00
2365.00
860.00
1075.00
430.00
3306.70
430.00
215.00
2768.45
830.54
14825.84
80898.29
1087.15
14825.84
96811.28
13553.58
110364.86
6100.90
( 28 days cube compressive
cement concrete using 20 mm
gregates for deck slab & kerb
abour, formwork, scaffolding,
position, levelling, vibrating,
lead upto 50 m and all lifts.
t content: 330 kg / cum with
ent), CA : 0.80cum, Blending
- 24
cum
Amount
in Rs.
28604.40
433.40
17628.69
8080.28
8829.54
1123.37
9568.57
23921.43
33.00
0.00
0.00
98222.68
Amount
in Rs.
358.40
495.20
4.20
30.95
48.00
99.20
1035.95
Amount
in Rs.
1133.60
35.55
816.00
570.00
275.00
2365.00
860.00
860.00
3388.40
215.00
2192.61
5481.53
18192.69
98222.68
1035.95
18192.69
117451.32
16443.18
133894.50
8495.80
cum
Amount
in Rs.
28604.40
433.40
17628.69
8080.28
8829.54
1123.37
15574.26
7787.13
33.00
0.00
0.00
88094.07
Amount
in Rs.
358.40
495.20
4.20
30.95
48.00
99.20
1035.95
Amount
in Rs.
1133.60
35.55
816.00
285.00
275.00
2365.00
860.00
645.00
3388.40
215.00
4385.22
2192.61
16596.38
88094.07
1035.95
16596.38
105726.40
14801.7
120528.10
7647.70
cube compressive strength not
crete using 20 mm down size
wearing coat including cost of
k,cleaning, batching, mixing,
elling, compacting, finishing,
etc., complete with initial lead
00 kg / cum ) If water is to be
rges @ 500 ltr / cum. to the
se of super plasticiser(0.4% by
o of CA--65:35, FA : 0.45 cum)
cum
Amount
in Rs.
28604.40
433.40
17628.69
8080.28
8829.54
1123.37
1557.43
165.00
0.00
0.00
66422.11
Amount
in Rs.
358.40
495.20
4.20
30.95
48.00
99.20
1035.95
Amount
in Rs.
1133.60
35.55
816.00
570.00
275.00
2365.00
860.00
860.00
3388.40
430.00
438.52
11172.07
66422.11
1035.95
11172.07
78630.13
11008.22
89638.35
5687.70
sqm
Amount
in Rs.
4334.00
2739.00
7073.00
176.83
7249.83
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
4275.00
275.00
5375.00
9925.00
7249.83
0.00
9925.00
17174.83
2404.4755
19579.30
195.80
Joints
Amount
in Rs.
1364.00
311.25
132.00
0.00
1807.25
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
650.00
275.00
860.00
1785.00
1807.25
0.00
1785.00
3592.25
502.915
4095.17
409.50
Joints
Amount
in Rs.
2178.00
485.55
186.00
0.00
2849.55
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
780.00
275.00
1075.00
2130.00
2849.55
0.00
2130.00
4979.55
697.137
5676.69
567.70
cum
Amount
in Rs.
1980.00
0.00
0.00
1980.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
152.50
137.50
1290.00
1580.00
1980.00
0.00
1580.00
3560.00
498.4
4058.40
405.80
Nos.
Amount
in Rs.
1360.00
418.22
322.67
183.11
249.00
550.00
184.00
132.00
0.00
0.00
0.00
3399.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
260.00
275.00
215.00
300.00
1050.00
3399.00
0.00
1050.00
4449.00
622.86
5071.86
1268.00
1000
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
167.50
840.00
1007.50
0.00
0.00
1007.50
1007.50
141.05
1148.55
1.10
cum
Amount
in Rs
0.00
0.00
17754.00
17754.00
Amount
in Rs
3393.09
1285.47
9445.60
5444.80
14052.00
9356.00
42976.96
Amount
in Rs
400.14
1185.60
4448.00
275.00
430.00
6738.74
17754.00
42976.96
6738.74
67469.70
9445.758
76915.46
95.30
Amount
in Rs
3450.00
66.00
3516.00
Amount
in Rs
137.50
430.00
567.50
0.00
3516.00
567.50
4083.50
571.69
4655.19
5.80
FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU NEAR M.LINGAPURAM VILLAGE ( GOKAVARAM ) , KOTHAPALLE MANDAL, KURNOOL
DT.
LEAD STATEMENT
1 2 3 4 5 7 8 9 10 11 12
1 Cement 1 MT At site 5
2 Sand for concrete( Unscreened) 1 CUM Paridempadu 27(a) 78 2.5 81 890.00 30 860.00
3 Sand for filling( Unscreened) 1 CUM Paridempadu 28(b) 78 2.5 81 890.00 30 860.00
1) Certifed that the leads provided for the materials are correct to the best of my knowledge
2) Certifed that the sufficent quantites of materials are available
3) The aggregate rates mentioned above are inclusive of seinorage charges Rs 50 /- per cum for stone and metal and Rs 40 /- per cum for sand, blasting charges and machine
crushing charges.
4) Certified that the rates adopted as per A.P.Revised Schedule of Rates for the year 2010 -11
N.W:- FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU NEAR M.LINGAPURAM VILLAGE (GOKAVARAM) ,
KOTHAPALLE MANDAL, KURNOOL DT.
Provision as per
1 Prelimaniries 27000 100000 73000
latest rates
Provision as per
2 Land acquesition 14650000 20000000 5350000
latest rates
3
FALLS AND WEIR 0
Due to increase in
a. Construction of H C Weir 101195 15700000 15598805
SSR rates
Due to increase in
b. Excavation of Surplus course 19135 11575240 11556105
SSR rates
c. Construction of 2 nos of Head Due to increase in
56870 #REF! #REF!
sluices SSR rates
4
BUILDINGS 0
Due to increase in
a. Formation of Bund 791750 43715664 42923914
SSR rates
Provision as per
a. Plantation 50000 103000 53000
latest rates
7 VAT @ 4% on working items Previously included
0 3346400 3346400
ecluding LA in data
8 Labour cess @ 1% on working
0 836600 836600 --
items ecluding LA
Total cost of scheme including
9 16773950 #REF! #REF!
LA charges
N.W:- FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU NEAR M.LINGAPURAM VILLAGE ( GOKAVARAM ) , KOTHAPALLE
MANDAL, KURNOOL DT.
Unit
S.N Description of work
including setting out, construction of shoring 3550 0.00 0 3550 65.90 233945 233945
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
2
Excavation in ordnary rock (including HDR)
without blasting including boulders above
0.3 m upto 0.60 m dia.for foundations of
canal cross drainage and other appurtenant
Increase in
Cum
structures and placing the excavated stuff 1600 0.00 0 1600 229.00 366400 366400
SSR rates
neatly in specified dump area or disposing
off the same as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
CCDW - 1 - 3
Page 133 of 175
Unit
S.N Description of work
3
Excavation in hard rock requiring blasting
including boulders above 0.6 m upto 1.2 m
dia. For foundations of canal cross drainage
and other appurtenant structures and placing Increase in
Cum
242 0.00 0 242 240.70 58249 58249
the excavated stuff neatly in specified dump SSR rates
area or disposing off the same as directed
etc., complete with initial lead upto 50 m and
initial lift upto 3 m. CCDW 1 - 5
Unit
S.N Description of work
5
Providing and laying insitu vibrated M-15
( 28 days cube compressive strength not less
than 15 N / sq mm ) grade cement concrete
using 20 mm down size approved, clean,
hard, graded aggregates for sub-structure /
super- structure works including cost of all
Increase in
Cum
materials, machinery, labour, formwork, 548 0.00 0 548 5682.53 3114026 3114026
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
Page 135 of 175
Unit
S.N Description of work
Unit
S.N Description of work
7
Increase in
Providing and Constructing 30 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Sqm
materials,labour,hand packing,finishing 332 0.00 0 1106.25 408.88 452324 452324
this item
etc.,complete ( rubble stones : 0.33
rate was in
cum/sqm) CAW 8 - 4
cum
8
Increase in
Providing and constructing 25 cm thick dry
SSR rates.
rubble stone pitching including cost of all Sqm Previously
materials, labour, hand packing, finishing 5 0.00 0 21.81 318.81 6953 6953
this item
etc., complete ( rubble stones : 0.275
rate was in
cum/sqm) CAW 8 - 2
cum
9
Provision for Photographic charges charges / Increase in
LS 101195 334026 232831
miscelleneous @ 2.5% SSR rates
Unit
S.N Description of work
required level and profile, cost of all 2300 0.00 0 2300 121.50 279450 279450
SSR rates
materials, machinery, labour, placing the
excavated soft rock neatly in dump area or
for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
CAW 1 - 3
Page 138 of 175
Unit
S.N Description of work
3
Providing homogeneous embankment using
soil from approved borrow area in layers of
25 to 30 cm before compaction including
cost of all materials, machinery, labour, all
Increase in
Cum
operations such as compacting to density 9590 0.00 0 9590 5.80 55622 55622
SSR rates
control of not less than 90 percent or as
stipulated using 2T roller etc., complete with
initial lead upto 1 km and all lifts. PMW 3-
24
4
Providing homogeneous embankment using
soil from approved borrow area in layers of
25 to 30 cm before compaction including
cost of all materials, machinery, labour, all
Increase in
Cum
operations such as excavation, sorting out, 14870 0.00 0 14870 95.30 1417111 1417111
SSR rates
transportation, spreading soil in layer of
specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto
1 km and all lifts. PMW 3 - 22
5 Increase in
Providing and constructing 25 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Sqm
materials, labour, hand packing, finishing 1830 0.00 0 8133 318.80 2592800 2592800
this item
etc., complete ( rubble stones : 0.275
rate was in
cum/sqm) CAW 8 - 2
cum
6
Provision for Photographic charges charges / Increase in
LS
Unit
S.N Description of work
Cum
including setting out, construction of shoring 37 0.00 0 341.9 65.90 22531 22531
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
structures and placing the excavated stuff 61 0.00 0 109.32 229.00 25034 25034
SSR rates
neatly in specified dump area or disposing
off the same as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
CCDW - 1 - 3
Page 140 of 175
Unit
S.N Description of work
Cum
26 0.00 0 66.16 4974.27 329098 329098
mixing, placing in position, levelling, SSR rates
vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) CCDW 2 - 5
Unit
S.N Description of work
Cum
scaffolding, cleaning, batching, mixing, 26 0.00 0 14.4 6006.43 86493 86493
SSR rates
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts. (Cement content:
330 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA :
0.80cum, Blending Ratio of CA--65:35, FA :
0.45 cum) CCDW 2 - 9
6
Providing, fabricating and placing in position
reinforcement steel bars for RCC works
Previously
including cleaning, straightening, cutting,
this item
bending, hooking, lapping, welding wherever
rate was
Kg
required,tying with 1.25 mm dia soft 0 0.00 0 819.9 57.15 46857 46857
included in
annealed steel wire, including cost of all
concrete
materials, machinery, labour etc., complete
item
with initial lead upto 50 and all lifts. CCDW
2-1
Page 142 of 175
Unit
S.N Description of work
Cum
2 0.00 0 76.8 185.50 14246 14246
spreading in layer of specified thickness, SSR rates
breaking clods, sectioning, watering,
compacting each layer to density control of
not less than 98 percent or as stipulated by
sheep / pad foot roller etc., complete with
initial lead upto 1 km and all lifts. CAW -2- 6
8 Increase in
Providing and Constructing 30 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Cum
Previously
#REF! 3 0.00 0 #REF! #REF! #REF! #REF!
this item
rate was in
cum
Page 143 of 175
Unit
S.N Description of work
10
LS
1 25000 2 50000 100000 75000
materials including fixing charges SSR rates
11
Provision for Photographic charges charges / Increase in
3435 0 0.00 0 -3435
0
miscelleneous @ 2.5% SSR rates
1
Clearing thin jungle growth ( more than 50
percent open space ) including bushes upto
Increase in
Sqm
30 cm / parthenium and other weeds 24000 0.00 0 24000 1.10 26400 26400
SSR rates
including burning or disposing off the same
as directed etc., complete. PMW 1 - 1
Page 144 of 175
Unit
S.N Description of work
Cum
20149 0.00 0 20149 89.80 1809380 1809380
materials, machinery, labour, placing the SSR rates
excavated soil neatly in dump area or for the
formation of service road / embankment as
directed etc., complete with initial lead upto 1
km and all lifts. CAW -1-1
Unit
S.N Description of work
Cum
6650 0.00 0 6650 86.20 573230 573230
cm before compaction, breaking SSR rates
clods,sectioning, watering and compacting
each layer to density control of not less than
98 percent or as stipulated by sheep's foot /
pad foot roller etc., complete with lead upto 1
km for water. CAW 4-1
Unit
S.N Description of work
Cum
32351 0.00 -583388 32351 86.20 2788656 3372044
cm before compaction, breaking SSR rates
clods,sectioning, watering and compacting
each layer to density control of not less than
98 percent or as stipulated by sheep's foot /
pad foot roller etc., complete with lead upto 1
km for water. CAW 4-1
Unit
S.N Description of work
Cum
10586 0.00 0 10586 81.10 858525 858525
layers of 25 cm before compaction, breaking SSR rates
clods, sectioning, watering and compacting
each layer to density control of not less than
95 percent or as stipulated by sheep's foot /
pad foot roller etc., complete with lead upto 1
km for water. CAW - 4-4
Unit
S.N Description of work
10
Cum
41000 0.00 0 34327 185.50 6367659 6367659 the original
spreading in layer of specified thickness,
estimate by
breaking clods, sectioning, watering,
erroreneou
compacting each layer to density control of
sly
not less than 98 percent or as stipulated by
sheep / pad foot roller etc., complete with
initial lead upto 1 km and all lifts. CAW -2- 6
11
Unit
S.N Description of work
12
Cum
1776 0.00 0 1776 206.70 367099 367099
spreading in layer of specified thickness, SSR rates
breaking clods, sectioning, watering,
compacting to density control of not less than
95 percent or as stipulated by sheep's / pad
foot roller etc., complete with initial lead
upto 1 km and all lifts. CAW - 2- 4
13
Providing and constructing 0.50 m thick
vertical or inclined graded filter media
consisting of 15 cm thick sand layers and 20
cm thick 20 mm down coarse aggregate layer
using approved materials satisfying specified Increase in
Cum
Unit
S.N Description of work
14
Increase in
Providing and constructing 25 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Cum
materials, labour, hand packing, finishing 5898 0.00 0 5898 1280.90 7554748 7554748
this item
etc., complete ( rubble stones : 0.275
rate was in
cum/sqm) CAW 8 - 2
cum
15 Increase in
Providing and constructing 25 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Cum
materials, labour, hand packing, finishing 1573 0.00 0 1573 1280.90 2014856 2014856
this item
etc., complete ( rubble stones : 0.275
rate was in
cum/sqm) CAW 8 - 2
cum
16
Providing and constructing dry rubble rock-
toe using rubble and stone chips from
approved source including cost of all
materials, machinery, labour, hand packing Increase in
Cum
17
Increase in
Providing and laying 25 cm thick sand
SSR rates.
blanket below embankment including cost of
Previously
Sqm
all materials, machinery, labour, spreading to 10336 0.00 0 6500 1288.70 8376550 8376550
this item
specified thickness etc., complete with initial
rate was in
lead upto 50 m and all lifts. CAW 5 - 3 - A
cum
Unit
S.N Description of work
19
Provision for clay blanket infront of toe wall
Increase in
on U/s of bund from chainage 1440 to 1500 ( 921400 0 0.00 1567420 646020
SSR rates
as per separate statement )
Unit
S.N Description of work
Cum
5300 0.00 0 6879 89.80 617734 617734
materials, machinery, labour, placing the SSR rates
excavated soil neatly in dump area or for the
formation of service road / embankment as
directed etc., complete with initial lead upto 1
km and all lifts. CAW -1-1
required level and profile, cost of all 540 0.00 0 701 121.50 85172 85172
SSR rates
materials, machinery, labour, placing the
excavated soft rock neatly in dump area or
for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
CAW 1 - 3
Page 153 of 175
Unit
S.N Description of work
Cum
910 0.00 0 1183 185.20 219092 219092
sides to required level and profile, cost of all SSR rates
materials, machinery, labour, placing the
excavated rock in dump area or for formation
of service road as directed etc., complete
with lead upto 1 km and all lifts. CAW 1- 5
operations such as compacting to density 1260 0.00 0 1260 5.80 7308 7308
SSR rates
control of not less than 90 percent or as
stipulated using 2T roller etc., complete with
initial lead upto 1 km and all lifts. PMW 3-
24
Page 154 of 175
Unit
S.N Description of work
Cum
operations such as excavation, sorting out, 4535 0.00 0 4535 95.30 432186 432186
SSR rates
transportation, spreading soil in layer of
specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto
1 km and all lifts. PMW 3 - 22
7
Provision towards construction of pipe barrel
Increase in
Nos
8
Provision towards construction of syphon
well for road crossing @ ch 1371 m of L/s Increase in
Nos
9
Provision towards construction of under
Increase in
Nos
10
Provision towards construction of pipe
Increase in
Nos
Unit
S.N Description of work
11
Provision towards construction of pipe
Increase in
Nos
sluices to distributaries ( as per separate 8 6000 48000 8 58800 470400 422400
SSR rates
statement )
12
Provision towards construction of drops to Increase in
Nos
4 0 0 4 58332 233328 233328
distributaries ( as per separate statement ) SSR rates
13
Provision or L/s approach channel ( as per Nos Increase in
1 0 0 1 86197 86197 86197
separate statement ) SSR rates
14
Provision or R/s approach channel ( as per Increase in
Nos
15
Provision for Photographic charges charges /
0 0 0.00 0 0
0
miscelleneous @ 2.5%
Unit
S.N Description of work
1
Excavation for Structures- Mechanical
Means Earth work in excavation in all kinds
of soils of foundation of structures as per
drawing and technical specification,
Increase in
Cum
including setting out, construction of shoring 40.51 0.00 0 40.51 65.90 2670 2670
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
2
Excavation in hard rock requiring blasting
including boulders above 0.6 m upto 1.2 m
dia. For foundations of canal cross drainage
and other appurtenant structures and placing Increase in
Cum
Unit
S.N Description of work
Cum
8.5 0.00 0 8.5 4974.27 42281 42281
mixing, placing in position, levelling, SSR rates
vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) CCDW 2 - 5
Unit
S.N Description of work
5
Increase in
Providing and constructing 25 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Sqm
materials, labour, hand packing, finishing 14.02 0.00 0 15.5 318.81 4942 4942
this item
etc., complete ( rubble stones : 0.275
rate was in
cum/sqm) CAW 8 - 2
cum
6
Supplying and fixing of RCC hume pipes of
Increase in
Rm
800 mm dia ( excluding laying and fixing ) at 15 0.00 0 15 1528.00 22920 22920
SSR rates
site
0 Increase in
SSR rates.
Supply of RCC collars for 800mm dia pipes Previously
Nos
5 0.00 0 5 0.00 0 0
at site this item
rate was in
cum
7
Laying and jointing 800 mm dia. NP- 2 class
or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all
materials ( excluding pipes and collars ),
machinery, labour, aligning, packing joints Increase in
0 5 567.91 2840 2840
with hemp, finishing, curing etc., complete SSR rates
with initial lead upto 50 m and all lifts.
(Cement content: 39.60 kg / joint, FA :
0.039cum/joint, Hemp Yarn : 0.31kg/joint)
CCDW 6 - 5
Unit
S.N Description of work
Sub work : - Syphon well for road crossing @ ch 1371 m of L/s canals and Ch 1578 of R/s canal
1
Excavation for Structures- Mechanical
Means Earth work in excavation in all kinds
of soils of foundation of structures as per
drawing and technical specification,
Increase in
Cum
including setting out, construction of shoring 110 0.00 0 110 65.90 7249 7249
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
Unit
S.N Description of work
Cum
materials, machinery, labour, formwork, 10.5 0.00 0 10.5 5682.53 59667 59667
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
4
Providing and filling murrum / gravely soil
( CNS soil ) for foundation or around pipes
including breaking clods, spreading in layers
Increase in
Cum
5 Increase in
Providing and Constructing 30 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Sqm
Unit
S.N Description of work
0 Increase in
Providing and Constructing 30 cm thick dry
SSR rates.
rubble stone pitching including cost of all
Previously
Sqm
materials,labour,hand packing,finishing 21 0.00 0 0 382.68 0 0
this item
etc.,complete ( rubble stones : 0.33
rate was in
cum/sqm) CAW 8 - 4
cum
6
Supplying and fixing of RCC hume pipes of
Increase in
Rm
800 mm dia ( excluding laying and fixing ) at 15 0.00 0 15 1528.00 22920 22920
SSR rates
site
0
Supply of RCC collars for 800mm dia pipes Increase in
Rm
5 0.00 0 0 504.00 0 0
at site SSR rates
10
Provision for Photographic charges charges /
0 0 0
miscelleneous @ 2.5%
Unit
S.N Description of work
Cum
including setting out, construction of shoring 130 0.00 0 33.4 65.90 2201 2201
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
Unit
S.N Description of work
Cum
materials, machinery, labour, formwork, 32 0.00 0 32 5683.53 181873 181873
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
4
Providing and Constructing 30 cm thick dry
rubble stone pitching including cost of all
Increase in
Sqm
5
Supplying and fixing of RCC hume pipes of
Increase in
Rm
600 mm dia ( excluding laying and fixing ) at 10 0.00 0 10 975.00 9750 9750
SSR rates
site
0
Supply of RCC collars for 600mm dia pipes Increase in
Rm
Unit
S.N Description of work
6
Laying and jointing 600 mm dia. NP- 2 class
or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all
materials ( excluding pipes and collars ),
machinery, labour, aligning, packing joints Increase in
Rm
0 3 409.67 1229 1229
with hemp, finishing, curing etc., complete SSR rates
with initial lead upto 50 m and all lifts.
(Cement content: 24.8 kg / joint, FA :
0.025cum/joint, Hemp Yarn : 0.22kg/joint)
CCDW 6 - 3
0
Provision for Photographic charges charges /
0 0
miscelleneous @ 2.5%
Unit
S.N Description of work
Unit
S.N Description of work
Cum
materials, machinery, labour, formwork, 1.8 0.00 0 0.52 5683.53 2955 2955
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
4
Providing and Constructing 30 cm thick dry
rubble stone pitching including cost of all
Increase in
Sqm
5
Supplying and fixing of RCC hume pipes of
Increase in
Rm
600 mm dia ( excluding laying and fixing ) at 20 0.00 0 20 975.00 19500 19500
SSR rates
site
Unit
S.N Description of work
6
Laying and jointing 600 mm dia. NP- 2 class
or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all
materials ( excluding pipes and collars ),
machinery, labour, aligning, packing joints Increase in
Rm
0 6 409.67 2458 2458
with hemp, finishing, curing etc., complete SSR rates
with initial lead upto 50 m and all lifts.
(Cement content: 24.8 kg / joint, FA :
0.025cum/joint, Hemp Yarn : 0.22kg/joint)
CCDW 6 - 3
Unit
S.N Description of work
1
Excavation for Structures- Mechanical
Means Earth work in excavation in all kinds
of soils of foundation of structures as per
drawing and technical specification,
Increase in
Cum
including setting out, construction of shoring 13.5 0.00 0 13.5 65.90 890 890
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
Unit
S.N Description of work
Cum
materials, machinery, labour, formwork, 3.5 0.00 0 3.54 5683.53 20120 20120
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
4
Supplying and fixing of RCC hume pipes of
Increase in
Rm
300 mm dia ( including laying and fixing ) at 2.5 0.00 0 2.5 341.00 853 853
SSR rates
site
5 Increase in
Nos
Supplying fixing screw gearing shutter 1 6000.00 6000 1 15000.00 15000 9000
SSR rates
0 Provision for Photographic charges charges / Increase in
0.00 0
miscelleneous @ 2.5% SSR rates
Unit
S.N Description of work
Cum
including setting out, construction of shoring 11.1 0.00 0 11.1 65.90 731 731
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
Unit
S.N Description of work
Cum
materials, machinery, labour, formwork, 6.8 0.00 0 6.72 5683.53 38193 38193
SSR rates
scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating,
finishing, curing etc., complete with initial
lead upto 50 m and all lifts.CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
CCDW 2-10
4
Providing and Constructing 30 cm thick dry
rubble stone pitching including cost of all
Increase in
Sqm
5
Provision for Photographic charges charges / Increase in
0.00 0
miscelleneous @ 2.5% SSR rates
Unit
S.N Description of work
Cum
including setting out, construction of shoring 1122 0.00 0 1308 65.90 86197 86197
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
Unit
S.N Description of work
Cum
including setting out, construction of shoring 431.2 0.00 0 432 65.90 28469 28469
SSR rates
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material. CCDW 1-2
0
Provision for Photographic charges charges /
0 0.00 0
miscelleneous @ 2.5%
FORMATION OF NEW M.I TANK ACROSS EDDULERU VAGU NEAR M.LINGAPURAM VILLAGE ( GOKAVARAM ) ,
Name of Work: 2003-04
KOTHAPALLE MANDAL, KURNOOL DT.
Deduct stacking
lead in K.M
LA & LI at 13%
LA & LI at 13%
Conveyance
Add blasting
Intial cost of
Seignorage
Loading &
Unloading
Net cost
charges
charges
charges
charges
material
charges
Sl.
Description
Total K.M
No of materials
Source of supply Unit Net cost
. MR CT
1 Cement ( SNo. 182) At site M.Ton - - - 2400 +1% for store shed 2424.00
2 Sand for mortor Hundri river Cum 88 3 42 68.00 -3.60 64.40 0.00 8.37 340.60 15.90 2.067 30.00 445.44
3 Sand for filling Hundri river Cum 88 3 42 18.00 -3.60 14.40 0.00 1.87 340.60 15.90 2.067 30.00 388.94
10mm H.B.Q
4 Crushed metal Venganna bavi Cum 94.0 3 98 313.00 -5.90 307.10 51.00 42.12 396.20 20.40 2.652 33.00 832.08
20mm H.B.Q
5 Crushed metal Venganna bavi Cum 94.0 3 98 450.00 -5.90 444.10 51.00 59.93 396.20 20.40 2.652 33.00 986.89
40mm H.B.Q
6 Crushed metal Venganna bavi Cum 94.0 3 98 258.00 -5.90 252.10 51.00 34.97 396.20 20.40 2.652 33.00 769.93
75 mm H.BQ
7 Hand broken metal
Venganna bavi Cum 94.0 3 98 125.00 -5.90 119.10 51.00 17.68 396.20 20.40 2.652 33.00 619.64
20 mm H.BQ
8 Hand broken metal
Nagaluty Cum 69.0 3 73 136.00 -5.90 130.10 0.00 16.91 323.00 20.40 2.652 33.00 505.67
25 mm H.BQ
9 Hand broken metal
Nagaluty Cum 69.0 3 73 134.00 -5.90 128.10 0.00 16.65 323.00 20.40 2.652 33.00 503.41
Deduct stacking
lead in K.M
LA & LI at 13%
LA & LI at 13%
Conveyance
Add blasting
Intial cost of
Seignorage
Loading &
Unloading
Net cost
charges
charges
charges
charges
charges
material
Sl.
Description
Total K.M
No of materials
Source of supply Unit Net cost
. MR CT
40 mm H.BQ
10 Hand broken metal Nagaluty Cum 69.0 3 73 79.00 -5.90 73.10 0.00 9.50 323.00 20.40 2.652 33.00 441.26
Rough stone
13 0.450mm thick Nagaluty Cum 69.0 3 73 75.00 -5.90 69.10 0.00 8.98 323.00 20.40 2.652 33.00 436.74
15 Gravel Local Cum - 6 6 37.00 -3.60 33.40 0.00 4.34 88.00 15.90 2.067 13.00 140.81