GENERAL INTRODUCTION
About the trainer manual 6
Learning objectives 7
Technical session
0202
Case study exercise HO 13b Instructions for the gap analysis exercise 45
Part 3 gap analysis of
control approaches HO 13c Inventory, risks assessment and health control approaches 46
table BC company printing section
1
Topics to be found in the annex of the guide
5
This trainer manual for the module “Chemical risk management and controls” contains instructions
and materials for the facilitators /consultants. The company guide “Chemical risk management and
controls” as well as this trainer manual module is complementary.
This trainer manual gives an overview of the different materials available for this module and makes
recommendations in form of trainer instructions on how to best use the worksheets/handouts and
which power point presentations are available to support your training /coaching of enterprises. The
training materials are organized in technical sessions.
An overview of the training materials is given indicating the page in the trainer manual where you
can find them.
A training sequence indicates the main tasks that have to be fulfilled by the facilitators for each day
and unit.
The worksheets/handouts of this trainer manual will be distributed session wise during the training.
8
LEARNING OBJECTIVES
At the end of module 2 Chemical Risk Management and Controls, the participants will be able to….
carry out a gap analysis between recommended / required control approaches and actual
controls on-site
identify priority areas in their company for improvement measures
assess and arrange/reorganize the storage of chemicals in their company
identify and select personal protective measure
prepare for chemical emergencies
develop and select control measures to mitigate critical situations / areas
plan steps for the further dissemination of chemicals management within their companies
Expected output:
Action plan to implement and to document specific improvement measures in the company with
regard to chemical risk management control and anchoring of chemicals management elements,
based on a company specific gap analysis of recommended and existing risk control measures.
9
Possible sequence and content of Hazardous Waste Management training for companies
Case study
exercise – and Preparing for Review of company Anchoring
(Technical
session 0206
Closing of
workshop
10
o Prepare action plan to implement and to document specific improvement measures in the
company with regard to chemical waste
At the beginning of the workshop, briefly recall together with the participants the subjects covered
during the last training. List the activities, the company teams were given to complete between the
last training and this one.
Start with a general reflection in the plenary on the challenges the company teams have faced during
the implementation of their actions plans as well as on the ways they have been able to overcome
the challenges.
Invite each company team to present their progress and results. Ask the teams to specifically refer to
the action plan, they had prepared during the last training.
Before using this session guide, read chapters Understanding the hierarchy and principles of controls
and Identify gaps between recommended and existing controls in your company in Practical Chemical
Management Toolkit for your Company, Module 2 – Managing the chemical risks.
SESSION DESIGN
This session introduces the concept of hierarchy and principles of controls for chemical risks and
explains how to systematically identify areas of interventions by assessing possible gaps between
recommended and existing controls of chemical risks on-site for given situations. At the end of this
session, the participants will be able to
determine the recommended control approaches for environment, physical and health
hazards, in line with ILO Control Banding and BAUA methodologies
relate the codes for control approaches used and identified in the inventory table to the
specific sets of control approaches for inhalation and skin exposure;
identify and document gaps between existing and recommended controls in their respective
companies.
Conclusion 15 min
Materials required:
DESCRIPTION OF STEPS
INTRODUCTION (20MIN)
Quickly review with the participants the process of identifying recommended control measures when
preparing the chemical inventory (See HO 9f, module 1; PPP 13). Explain that the codes used in
column 12 of the inventory table related to predefined groups of control approaches for the different
hazards and risk identified.
Provide an overview of the different control approaches and how they are linked to the coding of the
control banding tool in the inventory table, using PowerPoint presentation No 14a (about control
approaches. Encourage participants to give examples from their companies and experience.
For more specific guidance on recommended control approaches for given situations, refer to the ILO
control sheets at: http://www.ilo.org/legacy/english/protection/safework/ctrl_banding/toolkit/icct/sheets.htm
Request the participants to form groups of 4 - 5 persons. Referring to HO 9f (module 1) ask the
groups to identify the full description of the recommend control measures for the different codes in
column 13.
After 15 minutes of group work, review the results in the plenary. After discussion distribute HO 10d
Referring to the result of the exercise, explain that the different control approaches are structured in
a priority for risk management approaches, ranging from simple good housekeeping measures to
complex engineering solutions. Point out that the control approaches as such in turn consist of a
number of different interventions. Distribute HO 10f and HO 10g and review the questions together
with the participants.
Point out that the general objective in the control of chemical hazards is to reduce to the lowest
possible level of the risk that a hazardous chemical can pose, for example by coming in contact with
the worker or by contributing to a fire or an explosion when ignited by a possible source of ignition.
To eliminate or minimize risks in general, usually a four-point strategy of controls can be used to
prevent and reduce the possibility and thus the risk of accidents, health impacts, fire or explosion
14
and adverse effects on the environment. Better than reducing the risk would be eliminating the risk
altogether by simply avoiding or substituting the hazardous chemical with a non-hazardous one.
While this may not be possible in the short run, it still should be considered as long-term option.
You can easily demonstrate the concepts of the four point strategy in the classroom:
Use a water bottle as hazardous chemical and choose one volunteer to represent the worker,
position away from the bottle.
For the strategy 1 “substitution” simply remove the bottle and place a distinctively different
bottle there, indicating that this would represent a non- or less hazardous substance;
For strategy 2 “engineering control”, place the earlier bottle representing the hazardous
chemical again in front of the participants, but with any open cover or put some water into
an open cup and ask the volunteer to come closer to the bottle or cup. Place the cup on the
bottle to show an engineering solution such as enclosure. Move the bottle and volunteer to
an area with a ventilation.
For strategy 3 “administrative controls”, simple advice the volunteer to step back as the area
around the bottle is declared an area for authorized personnel only.
Finally hand over a personal protective device (e.g. mask, goggles, gloves) to the volunteer
and ask him to handle the bottle, representing the strategy 4 “personal protective measures”
After finishing your demonstration of the 4 control approaches with a bottle, distribute HO 10 e
and give instructions to the working groups.
Summarize the hierarchy of controls and point out that all relevant information can be found in the
Chemical Management guide as well as further information can be retrieved from the ILO Control
Banding website. Mention that the participants will have an opportunity of using the different
checklist tools during the next company application. Present PPP14b control guidance sheets (10min)
15
Control approaches for hazardous chemicals that can be inhalated are gathering under 4 points
(control approaches from 1 to 4) and control approaches for hazardous substances for skin under 3
categories (low, medium and high).
In your group…
Additional information:
(1) As you can observe in the dye kitchen of “Beautiful Colors”, small splashes of acetic acid fall
on to the hands and forearms of the concerned worker while pouring the acid. There is a
washbasin at the other side of the production area, where the worker washes his hands and
arms after preparing each batch. You estimate that in a day the total duration of exposure is
about 14 minutes.
(2) Reactive black 5 is manipulated for less than 10 min each time (4 times a day) but always
small quantities of powder are visible in the hands and forearms of the concern workers.
(3) In the printing section, you observe that the cloths of the worker are covered with some
kind of white dust for the whole day. He is wearing wrist-length gloves. But the worker is
frequently scratching and rubbing his bare forearms. He explains to you that this dust is
coming from the sodium hydroxide bags he has to carry from the trolley to the dosing point
in the printing section. He says that when he is washing off the dust in the evening the
itching usually stops.
(4) Once you have identified the recommended control approaches, follow the instructions in
HO 10e and use check lists in HO No 10f and 10gf to verify what each control approach
contain
Duration 60 min
16
Dustiness Appearance
LOW Pellet-like solids that do not break up.
Little dust is noticed during use (e.g. PVC pellets, waxed
flakes)
MEDIUM Crystalline. Granular solids
Dust settles quickly (e.g. detergents)
HIGH Fine, light powders
When used, dust clouds form and remain in the air for
several minutes (e.g. cement dust, carbon black, chalk dust)
11 12
2 3 4 5 6 7 8 9 10 13
Area/ Process Name Price/ SDS R-phrases/ Hazard Hazard Hazard Amount per Dustiness/ Quantity Duration of
Hazard type* Control approach
Suppli Yes/ statements group group skin batch/task volatility on skin exposure
er No P H E Inhalatio on skin Inhale Skin
Dye kitchen Acetic Acid Yes R 10, R35 C E 8l Liquid Small Short 3 high
Medium Medium
Dye kitchen C.l Reactive Yes R42/43 C C 3kg Medium Solid Small Long 3 medium
Black 5 Medium
Printing Unknown 1
Storage Unknown 2
HO NO 10E GAP ANALYSIS FOR CONTROL APPROACHES IN “BEAUTIFUL COLOURS”
You have now completed your inventory list for the company “Beautiful Colours”.
You know all chemicals existing in the company; you have collected all MSDS for each chemical. You
have done a risk assessment for each chemical and now you have determined which is the best
control measure for each chemical (See HO No 10d completed Inventory / Risk assessment / Control
Approach Table)
Tasks.( 30 min)
Unfortunately the manager of the company “Beautiful Colours” has not yet participated in training
on chemical management and there are no special control measures for any chemical in his
company.
Use the checklists HO No 10f (for knowing more details about what needs to be undertaken to
control the effects of chemicals harmful through inhalation) and HO No 10g of chemicals affecting
the skin.
Filling these checklists will allow you to do a gap analysis of what is recommended and what exists in
the company. In the Case of BC is easy since not a single control approach exist!
Work in five groups. Each group choose one chemical and one control approach listed below using
the corresponding checklist.
19/95
HO 10F – CHECKLIST „CONTROL APPROACHES“- INHALATION CHEMICALS
Control approach 1 - General ventilation/Housekeeping
General ventilation is suitable for a range of small, medium and large-scale tasks involving
solid and liquid chemicals. This control approach identifies minimum standards you need to
apply to protect you and your workers’ health. These recommendations should not be used to
justify a lower standard of control than that which may be required for process control or
control of other risks.
20/95
Individual control measures Yes2 No Comments
Access
Do you keep people away from the work area, whose
presence is not required in the work process?
Do you ensure that no one is working close by or
downwind to the source of contaminants?
Design and equipment
Do you ensure that there is unrestricted access to fresh
air? For example, this can be done by working outdoors.
When working indoors, doors and windows may need to
be opened or fresh air supply can be ensured by using
powered fans.
If you work inside a factory building, does a wall mounted
fan remove the dirty air and airbricks or louvers or ceiling
vents allow fresh, clean air into the workroom?
Is the release of dirty (exhaust) air near the clean air
intake avoided?
Do you ensure, where possible, that clean air firstly flows
past the worker and then past the work area?
In the open, do you make sure that the wind blows dirty
air away from you (upwind)?
For factories, do you ensure that the size and number of
fans is sufficient to remove the dirty air from the
workplace (more than one fan may be needed)?
Note: A minimum of 5 air changes per hour is
recommended.
Maintenance
Do you keep fans and/or extractors in good working
order?
Examination and testing
2
How to use these lists:
These checklists should be used for each chemical where its control approach has been already identified. You go directly to
the corresponding control approach number (1, 2, 3 or 4) and apply only this number of the list.
You will find three columns with no, yes and comments.
21/95
Individual control measures Yes2 No Comments
Do you check every day that the fans are working when
they are switched on?
Note: A ribbon strip attached to the exhaust side of the
fan cage can be used as an indicator that the fan is
working.
Cleaning/Housekeeping
Do you clean the work equipment and work area on a
daily basis?
Do you clean up spills immediately when they occur?
Do you avoid cleaning up dust with a brush/ broom or
compressed air, instead using a damp cloth or vacuum
where possible?
Do you put lids on containers immediately after use or
when not in use?
Do you store containers/bags in a safe place where they
will not get damaged?
Do you store volatile liquid containers away from direct
sunlight or sources of high temperature?
Training and supervision
Do you tell your workers about the harmful nature of the
substances they are working with and why they must use
the controls provided?
Do you teach and instruct the workers how to handle
chemicals safely?
Do you teach and instruct the workers how to check that
controls (e.g. fans) are working?
Do you teach and instruct the workers about what to do if
something goes wrong?
Do you have a system in place to check that the
precautions you have put in place are being followed?
22/95
Control Approach 2: Local exhaust ventilation (LEV), the most common form of engineering
control
3
This velocity is referred to as the capture velocity. Thus, the proper design of an exterior hood not
only needs considerations of local exhaust ventilation such as shape of the hood, unobstructed
ductwork and fan capacities but also the determination of the required capture velocity (m/s).
23/95
Individual control measures Yes No Comments
Is there a sufficient airflow to capture the dust or vapour
before it disperses in the workplace?
Have you measured the airflow at the origin of the dust or
4
vapour with an anemometer?
Do you contain the source of dust or vapour as much as
possible to stop it from spreading?
Do you prevent workers from getting in between the
source of exposure and the LEV? (Note: Otherwise he or
she will be in the path of the contaminated air)
Where possible, do you locate the work away from doors
and windows to stop draughts from interfering with the
LEV and spreading dust or vapours?
Do you keep extraction ducts short and simple and avoid
long sections of flexible duct?
Do you provide an easy way of checking that the LEV is
working (such as a ribbon strip attached to the output
side)?
Do you discharge extracted air in a safe place away from
doors, windows and air inlets? (Note: Be careful that
extracted air does not affect neighbours.)
Do you keep the hood as close as possible to the source
of exposure?
Maintenance
Do you keep the LEV system in good working order?
Examination and testing
Do you check every day that the extraction system is
working when it is switched on before starting work?
Do you check ducts once a week for signs of damage
and repair when necessary?
Do you have the system thoroughly examined and tested
at least once a year?
4
For dust, airflows greater than 1 m/s will generally be needed and for vapours, airflows greater than
0.5 m/s.
24/95
Control Approach 3: Putting distance or shielding/containment between the substance and the
worker
An example of isolation is separating a spray painting process from the other processes of the
plant by means of a barrier or wall. A similar isolating effect can be obtained by the safe
storage of hazardous chemicals and by restricting the amounts of these chemicals in the
workplace to that required in a day or a shift. Such restriction is useful if the process can be
carried out by a very small number of workers and when control by other methods is difficult
or impossible. The workers engaged in this process however, should be given adequate
personal protection.
The measure gives good practice advice on containment and describes the key points you
have to follow to reduce exposure to an adequate level. Containment can be applied to a range
of small, medium and large scale tasks involving solids and liquids. This control approach
identifies the minimum standards you need to apply to protect your health. lt should not be
used to justify a lower standard of control than that which may be required for process control
or control of other risks.
25/95
Individual control measures Yes No Comments
Access
Is the work area and equipment clearly marked?
Is entry to the work area controlled?
Are only workers actually needed and trained for that
work process allowed into hazardous work areas?
Design and equipment
Is the material handling taking place in a closed system
that separates the worker from the hazardous material by
a solid barrier?
In case limited breaches of the close system are
permitted under controlled conditions, is the exposure
times limited to a few minutes and the quantity of material
handled small (for example for quality control sampling)?
Is the design of the closed system so that it can be easily
maintained?
Where possible, do you keep equipment under negative
pressure to reduce leakage?
Do you vent any exhaust air in a safe place away from
doors, windows, walkways and air inlets?
Do you take care that the exhaust air does not affect
neighbours or other work areas?
Do you provide a sump or separate drainage system to
prevent leaks and spills from contaminating communal
drains and waterways?
Maintenance
Do make sure that all equipment used is well repaired if
necessary and maintained in good and efficient working
order?
Do you adopt a ‘permit to work’ system for all
maintenance work?
Do you document and follow any special procedures that
are needed before the system is opened or entered, e.g.
during purging or washing?
Do you prevent entry into any closed vessel until it has
been checked for hazardous, toxic or flammable
substances and sufficient oxygen (between 19.5% and
23.5%)?
Examination and testing
Do you check all the equipment once a week for signs of
damage and repair when necessary?
Do you have the system thoroughly examined and tested
at least once a year?
Cleaning/Housekeeping
Do you clean the work equipment and work area on a
daily basis?
26/95
Individual control measures Yes No Comments
Do you clean up spills immediately when they occur?
Do you avoid cleaning up dust with a brush/broom or
compressed air, but use a damp cloth or vacuum where
possible, instead?
Do you put lids on containers immediately after use or
when not in use?
Do you store containers in a safe place where they will
not be damaged?
Do you store volatile liquid containers away from direct
sunlight or sources of high temperature?
Personal Protective Equipment (PPE)
Do you avoid using Respiratory Protective Equipment
(RPE) for routine tasks except for cleaning and
maintenance activities and when dealing with spills?
Are you aware that some maintenance tasks may involve
entry into confined spaces where Supplied Air
Respiratory Protective Equipment may be needed?
Do you use such equipment in such situations?
27/95
Control Approach 4: Special advice
Try to reduce the risk by eliminating the chemical hazard or replacing the chemical with a less
hazardous one.
The most efficient way to reduce chemical hazards is to avoid using toxic substances or substances that pose a
risk of fire or explosion. The selection of the substituting chemical substance should be made at the design and
planning stage of the process. For existing processes, the substitution method should be used wherever
hazardous substances or processes may be replaced by others that are less hazardous. The choice of alternative
substances may be limited, especially where the use of that particular substance is unavoidable if specific
technical and economic requirements are to be met. It is always useful to look for alternative substances by
learning from experience in similar circumstances/processes, sectors.
Substitution unfortunately is not always chosen by enterprises. Main reasons for this are:
No priority given at enterprise. Dealing with the existing problems is already too laborious.
Companies want no additional problems which might occur with a new, innovative approach
Uncertainty in risk assessment
Substitutes are often less tested in practice integration in the production chain makes an innovation
beyond enterprise borders necessary
Technological or economic difficulties
If you are really engaged in chemical management you will understand that sooner or later you have
to substitute your most hazardous chemicals.
Not substituting the hazardous chemicals means that you also will have problems when managing
their disposal. And disposal of hazardous chemicals is expensive and has implications on the
environment and on generations to come.
28/95
HO 10G – CHECKLIST „CONTROL APPROACHES – SKIN“
Control approach “Low”
29/95
Control approach “Medium”
30/95
Control approach “High”
In addition to the measures listed under control approach “low and medium” the following
measures should be implemented if a high level of control is needed (this is for instance true
for corrosive substances as well as for toxic substances which can be absorbed by the skin.
31/95
TECHNICAL SESSION GUIDE 0202– CRITICAL ARES/SITUATIONS
Before using this session guide, read chapters Understanding the hierarchy and principles of controls
and Identify gaps between recommended and existing controls in your company in Practical Chemical
Management Toolkit for your Company, Module 2 – Managing the chemical risks.
This session combines various concepts, which the participants have already used during previous
sessions, in particular non-product outputs (NPOs), inventory table/ risk sheet, control approaches and
gap analysis. Therefore this session, with its case study exercise, allows the participants to recollect
and deepen the understanding of these concepts.
Learning objective
document the findings in such a way to use these as basis for further planning or
communication within their company, amongst others using visual documentation techniques
such as flowcharts and eco-maps
Visualize the following definition of Critical Areas/Hot Spots/ Critical Situations on the flipchart so that it
is visible during the whole exercise.
Where economic losses can be identified, for example due to inefficient storage, handling, use
and/or disposal of chemicals
Where potential harm to the environment and outside neighborhood is possible due to the
release and emission of chemicals during use and disposal
Where potential harm to the workers handling chemicals is possible, in particular when there
are existing gaps between recommended control approaches and existing control approaches
with regard to inhalation and skin exposure
Trainers instructions for Case study exercise – identifying and analyzing gaps in control approaches,
critical areas and costs
32/95
SESSION DESIGN
This exercise deepens the concept of hierarchy and principles of controls for chemical risks and looks
into systematically identifying areas of interventions by assessing possible gaps between
recommended and existing controls of chemical risks on-site for given situations.
Introduction 20 min
Materials required:
HO 11a, HO 11b, HO 11c, HO 11d, HO 11e, HO 12a, HO 12b, HO 12c, HO 13a, HO13b, HO 13c,
HO 13d, HO 14
DESCRIPTION OF STEPS
Reiterate that the exercise is a continuation of the earlier case study of “Beautiful colours. It does not
really exist, but the situation described is typical of many medium-sized textile companies and similar
problems have already been identified in real cases. Explain that for this case study exercise, which
deals with the identification and analysis of gaps for critical areas in “Beautiful Colours”, the
participants will have to refer to different sources of information.
Present PPP 14a: What are critical areas and PPP 14b: Examples of hot spots
Referring to the stories “critical areas”( HO No 11a) and “gap analysis” (HO 13a) point out that some
changes have taken place in 'Beautiful Colours' since the first exercise.
Ask the participants to form groups of 4 - 5 persons each. Take care that the groups are mixed with
respect to the professional background of the participants, e.g. one entrepreneur, one
representative from an institution, one consultant etc.
33/95
EXERCISE PART 1 – CRITICAL AREAS/SITUATIONS (50 MIN)
Distribute for the first step the following handouts to participants (the story HO No 11a, the ground
plan (empty) HO NO 11b, and the instructions for group work (HO No 11c)
Remind participants again that important information may need to be extracted from different hand-
outs, for example the inventory table/ risk table.
The working groups complete the tasks as per instruction Ho 11c (first part) on the story of the textile
company ‘Beautiful Colours’.
As facilitator control the time so that participants start to prepare their presentations after 30 min.
Once every group has finished its presentation, distribute HO No 12a, 12b and second part of HO 11c
and ask the groups to do the exercise during the next 20 min.
Ask the groups to update the information by doing a final review of the findings they have gathered
so far for another 10 min and display their findings in the training room in form of an information
market.
Distribute and go through HO 13a Story gap analysis and instructions (third part of HO 11c and HO
13b). Go through the instructions (what to do, in what time frame and with what result) and
questions. Distribute HO 13c and explain how to fill the table.
Remind participants again that important information may need to be extracted from different hand-
outs, for example the inventory table/ risk table.
As facilitator control the time so that participants start to prepare their presentations after 30 min.
Request the participants to visit the stands of the other groups to review and discuss their findings
for about 10 min. Ask the groups to quickly compare these with their findings.
Explain that in most companies such work as done in the first part of the exercise may be entrusted
to a team or even a single person in the company. The implementation of improvement measures
34/95
usually require the support from management (e.g. providing the necessary go-ahead and funding)
and cooperation from colleagues/co-workers).
Ask each group to take 15 min to compile the information on one single flip chart and in such a way
that it can be used for communicating the findings to all management of “Beautiful Colours”. Tell the
groups that they will be invited to make a (max 5 min) presentation to the management. In case of
more than three groups, randomly select 3 groups to present (e.g. select by drawing names).
Each of the selected groups has 5 minutes to make their presentation to the management (remaining
participants, alternatively a management body of 2 - 3 persons can be constituted from within the
participants, with the remaining participants being observers) on the key findings and the critical
areas. Each group should also briefly explain how they arrived at their priority list. Make sure that
each group presents its results in plenary visualized on flipchart paper in form of an “eco map”
indicating location of critical areas identified in the company BC.
After each presentation, there will be 5 min for clarifications, additional questions, different views;
the facilitator asks whether the results of the respective group are complete and correct, and assures
that a large part of the model solutions are covered by the discussion. The model solutions are only a
reference that should be handled with some flexibility.
Hand out the solution sheets (HO 11d, HO13c) and give all groups 15 minutes to compare their
results with the solutions sheets and raise questions for discussion in the plenum.
Clarify any questions with regard to the solutions. Remind participants that sifting through all the
information and compiling the same in such a way to make easily comprehensible and a good basis
for further work, poses a great challenge. A systematic approach, such as by using standardized
forms, tools, visualization will help to overcome such challenges. Also point out that proper
preparation, breaking down the task in smaller and manageable parts and team work will make it
easier to accomplish this comprehensive task. Present PPP 16and distribute HO 11e and discuss HO
14 with participants after its distribution.
35/95
HO NO 11A STORY CRITICAL AREAS
“Beautiful colors” a textile company is specialized in done as per an experience based recipe known to
dyeing fabrics that after washing and drying are sent the supervisor, but sometimes also by the workers.
In the general storage area, the dyes and chemicals then poured by the workers into the hot water in the
are received from the suppliers without further coloring vessels; the pre-treated fabric is added and
quality control. One of the workers recently pointed dyed under stirring in the coloring vessels at high
out the red symbol with the black exclamation mark temperature. Occasionally, when the coloring
on a chemical bag wondering about its meaning, but vessels are filled too much, liquids spill out of the
the supervisor did not know. vessels onto the floor. Once the process is
complete, the waste dye liquor is drained into the
All the dyes and chemicals are stored in bags and drainage.
containers next to the fabrics, directly on the floor.
Since the last rainy season the roof of the storage They keep a few open bags and containers of
area has been leaking. A few bags got wet and powdery dyestuffs and other chemicals in the mixing
were put aside in a corner. New materials have place. Sometimes, bags get spoilt when they have
already been ordered. John, the most skilled been lying on the wet floor for too long. To clean the
worker, is the only one who is able to identify dye kitchen from dust and spilt materials, the floor is
different chemicals even if labels or markings on swept by the cleaning personnel every week. They
many chemical containers are damaged or missing. also hose the floor, with the wash water flowing out
into the sandy factory yard.
Because of his long experience, John hands out the
chemicals needed in dyeing or printing process to The cleaning effluent goes directly into the nearby
each worker individually. In case of any questions drainage. Several times the drainage is blocked by
regarding the chemicals everybody checks with him. some old packaging and the cleaning effluent flows
into the yard.
When the chemical containers in the storage area
have been emptied, some of the workers take them The factory has a simple wastewater treatment,
home in order to use them as storage for drinking which has been built ten years ago. However, local
water. Before taking them home, they clean the farmers in the neighborhood are concerned about
empty containers by washing off the remainders the daily color changes of the river water. The
with tap water in the factory yard. Empty chemical treatment sludge from the wastewater treatment is
bags are thrown out into the factory yard and dried and stored in the factory yard. Some solid
burned from time to time together with other types of wastes, including some empty hazardous chemical
waste collected from the different parts in the containers, of the factory are collected every week
36/95
HO 11B GROUND PLAN OF BC
37/95
HO NO 11C CASE STUDY EXERCISE 'BEAUTIFUL COLOURS' – CRITICAL AREAS
Instructions
During the next 160 minutes complete the following 5 tasks in your group, based on the story of the
textile company 'Beautiful Colours':
2. Indicate on the ground plan of the factory (Ho 11b) where chemicals can be found. In
particular, indicate where in the factory input chemicals and chemical NPOs (Non-Product-
Outputs) are present/ used, and how these move into, in and out of the factory.
3. Identify and indicate (on a separate copy of the ground plan) possible critical areas with
respect to
a. costs - describe the situations where chemicals are used in considerable quantities,
lost or spoilt
b. risks to environment - describe the possible effects of chemicals on the environment
4. Discussion in plenum of the results (30 min). Afterwards distribute HO 11d
Second part (30 min) “costs assessment” exercise: review the additional material provided
Having analyzed the cost of chemical inputs and chemical NPOs, use the information from
the story (HO 12a) and the filled cost assessment table (HO No 12b) to inform when
communicating yours recommendations to the management. Discuss with the other
groups the findings and distribute HO No 12c
Third part (40 min) “gap analysis between existing and recommended control approaches”
exercise: review the additional material provided
Add all the information you have already produced during the work
BC health control approaches (HO No 10d)
Ground plan (HO 11b)
Information you generated during the gap analysis between the recommended and actual
control approaches in the printing area of BC (HO No 13d)
Fourth part preparation for presentation of all results (20 min)
1. Compile the information in such a way, that it can be used for communicating the findings to
all relevant stakeholders within a company and as a basis for planning improvement
measures.
2. You will be invited to make a 5-minute presentation of your findings to the top management
of “Beautiful Colours”. The top management wants to know where the key problems are.
3. In order to prepare yourself for the meeting with the management, analyze the findings in your
group and try arriving at some kind of prioritization
Fifth part “Group presentations” each group 5 min (20 min) maximum 3 groups will present
38/95
HO NO 11D POSSIBLE ANSWERS TO Printing paste is washed off from screen
instead of being recollected/reused
‘BC’CRITICAL AREAS QUESTIONS FOR
Remainders in the containers are washed off
GROUP WORK/MODEL SOLUTIONS (not fully emptied and used)
Cost of medical treatment for workers who
1) Indicate on the factory’s ground plan where
regularly get sick due to exposure to chemicals
chemicals can be found
3) Identify possible hot spots with respect to risk
Incoming chemicals (transport from supplier)
– describe the possible effects of chemicals on
Storage (everything except for cloth)
workers’ health and/or the environment
Dye area
Risks for human health through exposure to
In the mixing and coloring vessels
chemicals
Chemicals spilled on the floor or dust coming
Ingestion of chemicals by contamination of
from powdery materials
food/drinks by dirty hands or vapours in the air
Bags of dyestuffs stored next to vessels
Cigarettes are fire or explosion hazards
Chemicals swept away/dust clouds caused by
Inhaling of dust/powdery material/solvent
sweeping
vapors (open bags of powdery dyestuffs, wrong
Printing
cleaning method (risk for workers and cleaning
Printing paste
personnel – effect on respiratory system and
Printing paste washed off with water or solvents
the organism as a whole) – can be worsened
(cleaning of screens) going into drainage
by smoking
Wastewater
Direct skin contact with certain chemicals (e.g.
Chemicals in wastewater from dyeing and
dyestuffs and printing paste in manual printing
printing
causing skin irritations/ rash and harming the
Chemicals in waste water from cleaning (floor
organism as a whole)
and containers)
Chemicals in effluent (risk for everyone getting
Waste
in contact with this water: workers, neighbours,
Remainders of chemicals in the containers (not
farmers, etc.)
completely washed out)
Chemical containers used for water storage
Remainders of chemicals in the textile sludge
(workers take containers home to their families)
Other chemical waste produced in the factory
Chemicals in the waste (workers, garbage
Product
collector)
Chemicals (colors and auxiliaries) in the cloth
Chemicals in the product, e.g. carcinogenic
2) Identify possible hot spots with respect to
substances (workers, buyers and customers).
costs – describe the situations where chemicals
Risks for environment
used in considerable quantities are lost or spoilt
Chemical emissions affect surface,
Inappropriate storage (white cloth next to
groundwater and soil (e.g. chemicals washed
chemicals, stored directly on the ground not on
off the containers in the yard/chemicals washed
pallets, water leaking through the roof damages
off from printing screen/solvents, chemicals
chemicals, without labels everything depends
from cleaning etc.)
on one knowledgeable worker)
Inadequate wastewater treatment
Bags/containers transported into the dye
kitchen may get wet and spoilt
age of chemicals in the work process
39/95
Storage of remaining chemicals (sludge, solid Reduce the hazard to workers to bring down
stored in the yard, affecting groundwater and medical costs
soil) Provide personal protection equipment (dust
Effects from inadequate waste disposal, e.g. no mask, gloves, boots)
special treatment and inadequate handling of Provide local exhaust ventilation
hazardous waste by local garbage collector Install proper wastewater treatment
Air emissions from vapours caused by Do not let workers take home containers.
chemicals (e.g. solvent vapours). Instead, return them to supplier for re-use (for
4) What are causes of the identified hotspots? chemicals again)
Who is responsible/involved? Training of workers
Possible causes Test sludge for hazardous substances. If
Convenience (e.g. bringing dyestuff bags into necessary, dispose of it on special landfill for
dye kitchen) hazardous waste
Lack of knowledge of health risks/ environment Separate waste and dispose hazardous waste
risks caused by chemicals (e.g. sickness is properly (on special landfill, etc.)
related to other causes) Install collection tanks in order to re-use
Lack of knowledge of proper handling (e.g. chemicals spilt in the processes.
sweeping the floor instead of using industrial
vacuum cleaner or damp cloth)
No calculation of losses
Working based on experience – no interest in
labelling (only one person knows what is what)
Who is responsible/involved?
Suppliers
Owner
Second level management (production
manager)
Workers
Buyers, customers
Garbage collector
Farmers
5) What are possible measures to mitigate
critical areas/hot spots?
Repair the roof/reorganize storage (e.g. pallets)
Label all (!!) chemicals properly
Do not allow anyone to bring open dyestuff
bags into the dye kitchen. Or use other (safer)
systems, such as small closed containers, etc.
Do not sweep the floor but use the vacuum
cleaner or a damp cloth (and dispose of
contents as hazardous waste)
Reuse printing paste as much as possible
(don’t simply wash it off)
Always completely empty containers
40/95
HO 11 E USING ECO- MAPS IN CHEMICAL MANAGEMENT
Eco-maps are simple and practical tools, designed to document and present complex information in a simple
and generally understandable way. As eco-maps are mostly present the information through graphics and
symbols, these tools are suitable for involving person with lower literacy skills.
Eco-maps are basically based on the ground plan(s) of a company and build up a picture of key environmental,
health, safety and other information by using symbols on a simple plan of the site. Information such as on
environmental, health and safety aspects, production set-up (inputs, outputs), production flow, etc. can be
gathered through observations or discussions on-site and are then systematically entered into the map as per
the specific needs.
The visual approach of the method makes it a useful and powerful support tool for raising the awareness of
employees and stakeholders of the environmental, health safety and other impacts of an organization’s
activities. It also enables you to get more people involved at an early stage without needing huge amounts of
special know-how.
You can use several maps in order to facilitate and visualize different problems (“critical situations/hot spots”)
within a company. The different maps (e.g. chemicals, water, energy, air, wastes) create a useful multi layer set
of graphical information and form a readily available fundament for further analysis, planning of action,
monitoring and reporting.
In the context of the chemical management, you can use eco-maps to record flow of chemicals within a
company, their location, chemical NPOs and critical situations such as where money is lost on chemicals, where
specific risks exist for workers, where significant gaps exist between recommended and actual
controls/practices, or where these pose a hazard to neighborhood population and the environment.
A step-by-step approach:
41/95
1. Prepare the basic map
As a first step prepare a map of the company site, seen from above, including car parks, access areas, roads and
the surrounding environment. What is the big picture? Think also about your transport, subcontractors,
procurement policy and the impact of your products and services! In case a ground plan already exists, refer to
the same.
As a second step get an idea of your chemical flows (what is going in and out and where) and their very nature.
This will help you to pay more attention later in the work to some aspects like storage, health risk, resource
use, emergency preparedness and waste management. The material flow is also useful to get a feeling about
associated costs. You can add other maps (chemicals, storage, production, control approaches, energy,
water,…) according to your needs
Before you start entering the information, decide on standardized symbols, colors which need to be
consistently used for all further maps.
Making an inventory of environmental, health & safety and production practices and problems
Using it as a systematic method of conducting an on-site review and audit
Encouraging employee involvement and participation
Using it as a support for training and awareness, and to assist with internal and external communication
an easy way to document and track (environmental) improvements
a catalogue of immediate small positive actions
During the process you will discover information deficits but also decide on which environmental steps and
actions to implement.
1. They are less strong on determining risks and future challenges and trends
2. The method is more difficult to use for a site that covers a large area.
3. It focuses on site premises and so may be difficult for organizations that work at multiple sites or in a more
diverse set of places
For further reading on eco-maps and the scope of their application, please visit following website:
www.ecomapping.org
42/95
HO NO 12A EXERCISE 'BEAUTIFUL COLOURS' – COSTS ASSESSMENT, BASIC DATA
While checking the different chemical NPOs during the walk-through and discussing with the
responsible staff in “Beautiful Colours”, we were able to gather the following additional data:
150 kg of screen printing ink has already expired and can no longer be used.
Further 300 kg of Reactive Black 5 got wet and spoilt due to the leaking roof and can no longer be
used (during the rainy season earlier this year).
Both chemicals have to be replaced in the coming year.
percentage of NPO costs in relation to the overall annual cost of the respective chemicals
(column 10)
43/95
HO 12B CALCULATION TABLE COST ASSESSMENT
Additional
costs caused Losses per Losses per
Amount used Total cost of NPO as % of
Price (kg or Value of Costs per by spoilt or year from year from
Chemical per day (kg chemical NPO total annual
l) in $ daily input year ($) expired chemicals chemicals
or l) per year ($) input
($) chemicals per spilled ($) overuse ($)
year ($)
1 2 3 4 5 6 7 8 9 10
Acetone 10 20 l 200
Reactive black
20 30 kg 600
5
Screen
10 50 l 1.000
printing ink
Total 3.700
44/95
HO 12 C CALCULATION TABLE SOLUTION
Additional
costs caused Losses per Losses per
Amount used Total cost of NPO as % of
Price (kg or Value of Costs per by spoilt or year from year from
Chemical per day (kg chemical NPO total annual
l) in $ daily input year ($) expired chemicals chemicals
or l) per year ($) input
($) chemicals per spilled ($) overuse ($)
year ($)
1 2 3 4 5 6 7 8 9 10
Reactive black
20 30 kg 600 180.000 6.000 9.000 18.000 23.000 13%
5
Screen
10 50 l 1.000 300.000 1.500 60.000 0 61.500 21%
printing ink
45/95
HO 13A GAP ANALYSIS OF INHALATION AND SKIN CONTROL APPROACHES IN THE
PRINTING SECTION
We are back in 'Beautiful Colours', the responsible person some time back to hand
medium-sized textile factory with its 150 out more chemicals at a time. They keep a few
workers. During our previous visits, we have open bags and containers in the mixing place
collected basic information on the main in one corner of the printing section. Since the
production flows, the chemicals in use and all mixing table is not big enough many of these
other chemicals in the company. Based on this chemicals “are stocked” at the floor. They put
information we were able to prepare an together all liquids under the table like acetic
inventory sheet of these chemicals and carry and nitric acid, hydrogen peroxide and caustic
out an assessment of their potential risks and soda. They have also under the table a big
determine the control approaches (see HO No metal container of around 40 liters filled with
11c). acetone that is not always tightly closed.
Sometimes they are spills of acetone and they
After dyeing the fabrics, they are washed and are clean with a cloth and used cloths are
dried. The dried colored cloth is taken to the collected in a bucket in the corner.
printing area.
There is no control for the access of workers
Printing is done manually by applying a printing from other sections to the printing section so
screen ink for a colorful pattern on the cloth. that during the breaks, other workers come
Since it is very hot in the printing area, the here.
workers do not like to wear gloves.
The production manager recently complained
Several times a day the screens are sprayed to the owner, about the low productivity of work
off with water and cleaned with acetone for caused by regular absenteeism due to coughs,
some minutes. The effluents go directly into head-aches and skin rash. The workers do not
the drainage. always leave the production areas during the
breaks but eat, drink and sometimes even
Two wall-mounted ventilators are installed in
smoke at their workplaces.
the printing area of which only one is working.
The printing area has no windows and a typical In the printing section there is a pressurized
smell (a mixture of odors from acetic acid/ water fire extinguisher.
acetone/ printing ink) can be perceived by the
visitors but apparently not by the workers. In An old and very faded signboard with a hardly
the middle of the printing section there is a visible picture of a face mask is hanging near
hood but since the motor makes big noise it is the entrance to the dye kitchen but none of the
all the time switch off. workers know why it is there. The last training
of workers in chemical safety has been
As the workers do not like to walk back and organized by the production manager some
forth between storage and printing section too years ago.
often, they have convinced the storage
46/95
HO 13B INSTRUCTIONS FOR THE GAP ANALYSIS EXERCISE
Make a gap analysis between the existing health control approaches and the recommended
health control approaches in the printing section for Screen Ink Color 110 as recommended in
the risk sheet (HO No 11c). Consult also the MSDS for ink for additional information. Use the
HO10f (Checklist for actions that guarantee an inhalation control according to the control
approach 1) and HO10g (Checklist for actions that guarantee a medium dermal control
approach)
Group 2
Make a gap analysis between the existing health control approaches and the recommended
health control approaches in the printing section for Acetone as recommended in the risk
sheet (HO No 11c). Consult also the MSDS for acetone for additional information. Use HO
No 10f (checklist for actions that guarantees an inhalation control according to control
approach 2) and HO 10g (Checklist for actions that guarantee a medium dermal control
approach)
Present your results in the market place using the form in HO 13d
47/95
HO 13 C: INVENTORY, RISKS ASSESSMENT AND HEALTH CONTROL APPROACHES TABLE BC PRINTING SECTION
Control approaches
Name Cost per l or MSDS R-phrases Hazard type Hazard Hazard Amount per Dustiness/ Inhalation Skin
kg Yes/No group group batch/task volatility
skin
($) P H E Inhalat.
R66,
R67
printing
R21, 2l
Ink colour
R52
110
48/95
HO 13 D SUGGESTION FOR PRESENTATION OF FINDINGS OF THE GAP ANALYSIS
Working process Chemical Actions already done according to Which other actions need to be done or
area used checklists completed according to checklists
Inhalation skin Inhalation skin
49/95
HO NO 14 DECISION MATRIX 5
A Decision Matrix, also called an Evaluation Matrix, is used to achieve collective agreement among
members of a group in decision-making. It is obvious that decisions based on real data are ideal, but
in practice data are difficult to obtain in the initial stage of the project. However, this tool can be
bias if most members of the group give high ratings to a particular problem or option. Nevertheless,
Quality Circles or Project Teams still use the Decision Matrix to achieve consensus among the
members. In general, the steps to create a Decision Matrix are:
55
From Handbook on Green productivity (APO, 2006)
50/95
TECHNICAL SESSION GUIDE 0202 – SAFE STORAGE OF CHEMICALS
Before using this session guide, read: Understanding the hierarchy and principles of controls and
Identify gaps between recommended and existing controls in your company as well as refer to tool 7
- Safe storage of chemicals in Practical Chemical Management Toolkit for your Company, Module 2
– Managing the chemical risks.
SESSION DESIGN
This session introduces the concept of safe chemical storage as part of the chemical risk
management process. At the end of this session, the participants will be able to
1. Identify and point out basic safety features and requirements of a chemical store
2. Correctly arrange different types of chemicals in a chemical store, while taking into
considerations aspects such as compatibility of chemicals, ergonomic requirements and
productive storage layout.
3. Understand the importance of referring to the safety data sheet on chemical storage
requirements.
Introduction 5 min
Exercise 30 min
Conclusion 15 min
One sample storage layout for each group (see drawing in HO 15a)
HO 15b - One compatibility chart for each group
One set of cut-outs of chemical containers with name, symbol, indication of quantity for
each group
51/95
MSDS of each chemical
One solution sheet for each participant (HO 15c)
HO 15d chemical storage guidelines
HO 15 e - Checklist on safe storage and handling
Topic 7
Pin boards
PPP 17
Optional exercise how to calculate net savings and pay back periods when implementing an
improvement measure in the storage ( see HO No 15f, 20 minutes)
DESCRIPTION OF STEPS
INTRODUCTION (5 MIN)
Give the title of the session. Point out that organising the chemical storage is an important part of
the chemical risk management process. Usually many NPOs can be found in the storage area.
Emphasize the point that well-organised chemicals storage contributes to the reduction of chemical
risks in a company while also contributing to a higher productivity in the handling of chemicals.
Explain that the participants will now be given the task of organising a simple chemical store.
Divide participants in equal groups (ideally 4 - 5) and distribute storage layout, set of chemicals
containers and compatibility chart to each group. Explain that the objective of the exercise is to find
a suitable place for the different chemical containers in the storage, considering the information
available so to ensure safe storage and productive handling of chemicals. Give the groups 30
minutes to complete the exercise. During the exercise check correctness of layout, point out any
mistakes and ask group to verify and find out. At the end of the exercise each group should display
the completed storage layout.
Choose one group to present their storage layout in the plenum and ask participants to comment or
ask questions. Ask guided questions in case shortcoming are not identified. Distribute the solutrion
sheet to the participants.
52/95
Invite participants to point out the safety features displayed in the chemical store as well as
additional features (e.g. connection of emergency drain to effluent treatment plant, signboard
limiting access to chemical store for authorised personnel only, control of humidity and
temperature). Highlight the importance of considering the storage also from a possible angle with
regard to fire risk.
Alternatively, you can also refer PPP 14 at this point to review and summarise the important points
about safe storage of chemicals.
Summarize the session by showing pictures of good chemical stores or the solution sheet. Remind
participants of the triple-win benefits of a well organized chemical storage (reduction of risk of fire
and explosion, reducing wastage of chemicals, better and faster overview of stocks in hand;
reduction of health and safety risks to workers,….).
Refer participants to the checklists on safe storage and handling of chemicals in HO 26 e for further
assessment of prevalent conditions and practices in the storage area. Explain that they will use this
checklist during the next company application. Ask the participants to go through HO 26e and clarify
any questions arising.
Point out that further information can be found in the company guidebook. Invite participants to
check the chemical stores in their respective companies using the compatibility chart and referring
to the storage requirements in the safety data sheets or supplier guidelines.
Distribute HO 15d (chemical storage guidelines) and HO 15e self assessment checklist storage and
handling.
53/95
HO 15A SKETCH OF A CHEMICAL STORAGE
54/95
HO NO 15B COMPATIBILITY CHECK FOR HAZARDOUS SUBSTANCES
C Xi, Xn T, T+ F, F+ O E
C o
Xi
X o
T,
T o o
F,
o
F+
O o
E
55/95
HO 15C SOLUTION SKETCH CHEMICALM STORAGE
56/95
HO 15D CHEMICAL STORAGE GUIDELINES
Solids: Low tendency for reaction (when dry) so most can be shelved alphabetically,
exceptions:
Sulfides should be stored away from acids
Cyanide compounds must be segregated from acids, especially liquid acids
Phenol crystals must be stored separately from oxidizers
Liquids: Store liquid chemicals below shoulder height
Acids:. Separate organic acids from inorganic acids, e.g., acetic from nitric
Perchloric acid should be stored alone
Flammable Liquids: The excess of 10 liters must be stored in safety cabinets or in safety cans
Oxidizers: Keep away from acids, bases, organics, and metals Store in cool place
57/95
Incompatible Chemicals
Chemical supply:
59/95
Yes Further No
action action WHAT ACTION DO Y OU PROPOSE?
needed needed
12. Are the chemical requisitions from
the various workplaces being
recorded in the chemical store and
the respective workplace?
13. Does your supplier provide you with
the chemical/ material safety data
sheets for all the chemicals?
14. Do you keep the chemical safety data
sheets in a separate file for easy
reference?
15. Do the workers have access to this
information?
16. Have you or your supervisor
informed the workers unloading or
handling chemicals on the hazardous
nature of chemicals?
17. Do all the chemical containers/bags/
drums/ barrels have proper labels
attached - clearly indicating the
following:
content
trade name
name/ address/telephone
number of the supplier
hazard symbols
specials risks associated
Safety and emergency
procedures
18. Do you or persons assigned by you
take samples to check whether the
chemicals comply with your quality
specifications?
19. Do have access to and use facilities to
analyses quality/purity of chemicals?
Storage layout
20. Is the storage area being locked?
60/95
Yes Further No
action action WHAT ACTION DO Y OU PROPOSE?
needed needed
22. Do you store chemicals chemical-
wise in separate places/on separate
pallets?
23. Are the heavier chemical containers
stored on the lower racks?
24. Are the hazardous liquid chemicals
stored on the lower racks?
25. Are the designated storage places
clearly indicated by separate boards
or labels?
26. Do you store sulphide containing
chemicals in air tight containers?
27. Does the supplier take the
containers/barrels/drums back?
28. Do you dispose empty chemical
containers, barrels as per clearly
established procedures or legal
requirements?
29. Do you clean/rinse all
container/barrels before disposing?
61/95
Yes Further No
action action WHAT ACTION DO Y OU PROPOSE?
needed needed
34. Do you know which chemicals are
being considered hazardous? (Please
note: Mixing of different chemicals
can generated even more hazardous
combinations!)
35. Have you listed out and displayed
hazardous chemicals in the store?
36. Are the workers dealing with
chemicals trained in safe handling
them?
37. Do the workers use special tools for
taking out chemicals from original
storage container? (spatula, spoons,
taps, etc.)
38. Do use a separate
space/room/location outside
chemical storage for preparing
chemicals (mixing, diluting,…)?
39. Do you prepare correct chemical
mixes/dosages before transporting to
workplace?
40. Are proper containers used for
transferring chemicals from storage
to workplaces?
41. Do you transport the chemicals on a
special trolley/cart instead of carrying
by hand?
42. Have the workers handling the
chemicals at each stage been
informed and trained about the
hazards involved in handling the
chemicals?
43. Are these workers trained and
capable to take necessary emergency
measures to cope with chemical
hazards?
44. Have you conducted a refresher
training during the last six months?
Personal protection and hygiene
62/95
Yes Further No
action action WHAT ACTION DO Y OU PROPOSE?
needed needed
45. Do the workers wear all the
protective gear (goggles, gloves,
footwear, apron, face mask,..) as
prescribed on the chemical safety
data sheets while handling hazardous
chemicals?
46. Are washing facilities provided to the
worker in the staking yard?
47. Is a separate first-aid box provided in
the storage area?
48. Are relevant emergency procedures
visibly displayed and understood by
each worker in the storage area?
63/95
HO NO 15F HOW TO CALCULATE NET SAVINGS/PAYBACK PERIOD?
Chemicals in the company BC are disorderly ‘stored’, directly on the floor. This leads
to losses due to chemicals getting wet and being spilled/spoiled. After a company
visit and an analysis of causes and formulation of an action plan you find that an
improvement measure in the storage area has been proposed.
In the table here below is explain which information is necessary to calculate the net
savings and the payback period of the identified measure and how do you calculate
the net savings and the payback period.
The identified measure is the organization of the storage and installation of shelves
Calculation of measure: Organization of storage and installation of shelves in a company in South Africa
Required
Criteria Formula Result Information
information
Total cost of Amount chemicals - supplier of
1t per month x
chemicals per year in stored per year and 7560$/year chemicals
630 $/t
the storage costs of chemicals - Accounting
Losses due to Estimated by
inappropriate storage 5% 5 % of total 378$/year country team during
(estimation) the workshop
Yearly gross savings 5 % =- 1 %
through the Reduction of losses (378$ =- 75.6$) Estimation and
302.4$ /year
implementation of the from 5 % to 1 % Equivalent to 80% calculation
measure reduction in losses
Additional operational
costs caused by the
None --- --- ---
implementation of the
measure per year
Costs of shelves
Investment in USD 215$ Supplier
and installation
64/95
TECHNICAL SESSION GUIDE 0203 - SELECTING AND USING PERSONAL PROTECTION
Before using this session guide, read chapter personal protection and hygiene, and go through topics
4d (setting a respiratory protection program) 4e (selecting the correct respirators), 5d(select and use
protective equipment for skin and eyes) and 5e (special guidance on selection of protective gloves) in
the annex of Practical Chemical Management Toolkit for your Company, Module 2 – Managing the
risks in your company – control measures and gap analysis.
SESSION DESIGN
This session introduces the important aspects of personal protection and use of personal protective
equipment as a means of controlling exposure to chemical hazards. At the end of this session, the
participants will be able to
Introduction 5 min
Exercise 30 min
Conclusion 5 min
Materials required:
65/95
DESCRIPTION OF STEPS
INTRODUCTION (5 MIN)
At the beginning of the session, refer back to module 2 (chapter hierarchy of controls). Point out that
one of the four strategies presented has been the use of personal protective measures, which
includes the use of different personal protective equipment. Emphasize that personal protective
equipment should also be considered as the last choice for exposure protection. If this last barrier
between a hazardous chemical and the person fails, the person will be fully exposed to the chemical.
Similarly wrongly chosen personal protective equipment will create the illusion of protection for its
user.
Ask the participants to form groups of 4 - 5 persons. Distribute the safety data sheets from the
inventory exercises, Module 1. Each groups is given 15 min to identify and extract different
recommendations on personal protective measures from the safety data sheets and to group this in
terms of different types of exposure they control (e.g. inhalation, skin contact).
Quickly review the findings of the groups in the plenum. Ask whether they would be able to prepare
a specification for the purchase of personal protective equipment such as gloves, masks etc. Explain
that not all types of PPE are suitable for all types of chemicals and further clarification needs to be
sought.
Distribute HO 16 and ask the groups to use the information and instructions to further specify the
type of gloves they would have to order for the situation in “Beautiful Colours” (10 min).
Point out that further information on the selection of PPE for skin and eye protection is available in
topic 5d.
Explain that similar guidelines exist for the selection of respiratory protecive equipment. Distribute
topic 4e. Referring to the following guiding questions and to the information from the safety data
sheets used in “Beautiful Colours”, go through the questions in the plenum to demonstrate how to
select the correct respirator:
66/95
What is the applicable Occupational Exposure Limit (OEL)?
What is the protection factor of the respirator?
Are the contaminants gaseous or particulate or a combination of both?
Do the contaminants have adequate warning properties such as smell and/or taste?
Are the contaminants immediately dangerous to life and health?
Does the atmosphere contain enough oxygen?
Make some assumptions about concentrations in order to be able to proceed with the
demonstration.
CONCLUSION
Re-emphasize that personal protective equipment should only be considered as the last choice for
exposure protection. PPE is more intended to be used in case where exposure is unavoidable (e.g.
sampling, maintenance). Remind the participants that wrongly selected PPE can do more harm.
Furthermore, point out that provision of PPE always needs to be accompanied by training which
familiarizes the user in the proper wear and care.
Finally, encourage the participants to use the topics in the annexes of the guide when they have to
prepare specifications for PPEs required or when interacting with a potential supplier. A good PPE
supplier would ask similar questions.
67/95
HO NO 16 GLOVE MATERIAL SELECTION CHART
Selecting the proper chemical protection glove is a process that requires examining the
chemicals used, the processes and exposure times. Not all "rubber" type chemical protection
gloves are the same. You cannot determine the applicability of a specific chemical protective
glove without knowing the exact material and the materials resistance to decomposition for
specific chemicals. In the table the following abbreviations are used:
S - Superior
E - Excellent
G - Good
F - Fair
NR - Not Recommended
*Not recommended for Acetaldehyde, use Butyl Rubber
BUTYL Polyvinyl NATURAL
CHEMICAL FAMILY NEOPRENE NITRILE
RUBBER chloride LATEX
Acetates G NR NR NR NR
Acids, inorganic G E E E E
Acids, organic E E E E E
Acetonitrile, Acrylonitrile G E G S E
Alcohols E E NR E E
Aldehydes E G NR S* NR
Amines S NR NR F NR
Bases, inorganic E E E E E
Ethers G F NR E NR
Halogens (liquids) G NR F E NR
Inks G E E S F
Ketones E G NR NR G
Nitro compounds
(Nitrobenzene, G NR NR NR NR
Nitromethane)
Oleic Acid E E F E NR
Phenols E E NR NR G
Quinones NR E G E E
Solvents, Aliphatic NR NR F G NR
Solvents, Aromatic NR NR F F NR
68/95
TECHNICAL SESSION GUIDE 0204 – MANAGING CHEMICAL EMERGENCIES
Before using this session guide, read chapter Emergency preparedness and response in Practical
Chemical Management Toolkit for your Company, Module 2 – Managing the chemical risks.
SESSION DESIGN
This session familiarizes the participants with the key elements of managing chemical emergencies.
At the end of this session, the participants will be able to
Introduction 15 min
Exercise 60 min
Conclusion 5 min
Materials required:
69/95
DESCRIPTION OF STEPS
Start the session by asking the participants to list different emergency situations they might have
experienced or heard of. Cluster the replies in groups (e.g. fire/explosion, accidental releases, and
medical emergencies). Add some examples, if not mentioned (e.g. Seveso, Bhopal, Hungary, Golf of
Mexico, Basle,...). Ask the participants to identify those emergencies which directly or indirectly
involve chemicals.
Explain that chemical emergencies are a special category of emergencies. One role of chemical risk
management includes the prevention of such chemical emergencies. However, as part of the overall
emergency management in a company, chemical risk management also comprises steps of preparing
for and being able to respond to chemical emergencies. Point out that even after taking preventive
and precautionary measures in the storage and handling of chemicals, there is still a chance that
emergencies involving chemicals may occur. As with the preventive and control measures, the key to
being able to respond to an emergency lies with sound knowledge of the chemical substances and
waste used or present in your company.
Before specifically looking into chemical emergency, briefly explain import elements of general
emergency management. You can use PPP 18 (Emergency management, 15 min).
Ask the participants to form groups (4-5 persons each) and distribute HO 17a “A hot day at Beautiful
Colours” – quickly review the tasks given. Remind the participants to refer to the safety data sheets
for further information and guidance on emergency requirements. Ask participants to also use topic
6c /fire safety and extinguishers) for completing the exercise. The groups have 45 min to complete
the task and compile their findings.
Ask the participants what information sources they used to complete the tasks given (e.g. How useful
was the information in the safety data sheets? What other information did you use for example
inventory table, flow chart, floor plan?). to
70/95
Ask selected groups make a short presentation (not longer than 5 min) of the preventive and
preparedness measures identified, followed by discussion in the plenary to discuss or complement
the results.
Conclude the review of the exercises by pointing out that the provision of the emergency facilities is
not sufficient to ensure a good response to an emergency. Preparedness also means to have an
emergency plan which lays down procedures for
- Evacuation of workers, including a system of accounting for all workers outside the premises
- Methods of notifying outside assistance such as fire brigade, ambulance, hospital, spill control
experts, local and national emergency focal points
- Role of different persons on site (management, supervisors, company’s own emergency services
e.g. company doctor, trained fire fighters)
- Role of selected workers
- Location, use and maintenance of emergency equipment in the company
In case the participant’s company do not have an emergency plan, encourage them to prepare and to
communicate a simple emergency plan for every workplace giving clear and easily understandable
instructions what to do in a case of an emergency. In case there is already an emergency plan,
suggest that the participants review the same and check whether the workers in their company know
what to do.
Using the same control banding methodology presents PPP18b (fire and explosions) as an
introduction to the following exercise. Distribute HO No 17b, 17c, 17d and by using control banding
make a fire risk assessment and determination of the appropriate control approach for the different
chemicals. At the end of the exercise distribute the completely filled table (HO 17e)
CONCLUSION
Summarise that one will find immediate guidance on how to respond to emergency situations such
as fire, explosion, spill and accidental exposure in the safety data sheets. From this information one
can easily derive what measures you might have to take to be prepared for such emergencies; for
example what type of fire extinguisher do you need, what fire fighting techniques are suitable what
type of material you can use to absorb or clean spilled or leaked material, what first aid provisions do
you need (e.g. any antidotes, special cream, ointments).
71/95
Distribute HO 17f fire check list and HO 17g Emergency Checklist and explain that the participants
will assess the emergency preparedness in their respective companies as part of their next company
application, identifying gaps between recommended good practices and situation and requirements
in the workplace with regard to emergency prevention and preparedness.
Referring to the initial brainstorming on different types of chemical emergencies, select following
scenarios for the exercise: (1) fire/explosion, (2) spillage and accidental release (including release of
toxic gases), (3) medical emergency involving chemicals).
Form mixed groups with 3 to 4 persons (in each group: one representative of a company, institution,
one consultant and/or one person with good knowledge and experience with chemicals)
Then ask the groups to identify relevant recommendations on emergency procedures and measures
as listed in the safety data sheet, referring to the different emergency situations selected. Time
given: 15 min
As a second step, ask each group to review the recommendations in the assigned sections of the
emergency checklist and prepares a 5 min plenary presentation on the key recommendations, also
referring to information found in the safety data sheet.
Review the exercise in the plenary (30 min). Ask selected groups to make a short presentation (not
longer than 5 min) of the preventive and preparedness measures identified, followed by discussion in
the plenary to discuss or complement the results.
72/95
HO 17A A HOT DAY AT „BEAUTIFUL COLOURS“
It is a hot summer day and work in “BC” is in full swing. One of the workers has noticed that in the store room
of “BC” one of the barrels containing cleaning solvent has developed a leak. As it is only a small wet batch on
floor, he does pay any more attention to it. It seems that one of the other workers in the store had accidentally
hit the barrel with the newly acquired forklift when reversing in the storage area.
The sun is shining onto the roof of the store room. The small wall mounted fan hardly makes a difference to
easy the hot air inside. The store-in-charge has placed an old stand fan in the store to increase the air
circulation. As he had not found a proper plug point, he had plugged the blank wires into a socket, near the
chemical containers. Unknown by the store-in-charge, the barrel’s side has been cracked quite severely and
more liquids are spilling out and collecting near the stand fan. Due to the heat the solvent is quickly
evaporating.
Suddenly, there is a flash and the floor around the stand fan is on fire. Quickly the fire makes it ways to the
barrel with the solvent, which blows up in flames with a loud crackling sound. The store-in-charge rushes out
into the open yard in panic. There is a fire extinguisher somewhere, which has been installed by the
management some months ago. So far, he had not received any training on how to use it. Shouting loud he
runs into the production areas to alert the other workers. Confused the workers try rushing to different exits
from the work area. Eventually the production supervisor alerted by all the running around emerges from his
office. Somehow is able to extract the information from the store-in-charge an about what has happened.
Quickly he runs back into the office and calls the fire brigade. Then he joins the other workers who have
gathered outside the factory building in different locations. It appears that somebody is still inside the
building…..
This is what might happen at “Beautiful Colours”. To prepare for possible chemical emergencies at “Beautiful
Colours”, the management has called your team to a meeting to discuss how “Beautiful Colours” could prepare
for possible emergencies.
1. Identify possible chemical emergency scenarios in “Beautiful Colours” – use the different documents
you have prepared so far, in particularly floor plans, flow charts, inventory table
2. Decide what and where emergency equipment may be required in the company, in particular in terms
of
Active and passive fire fighting facilities (e.g. type of fire extinguishers)
Emergency leak control kits and provisions (e.g. dyking, clean-up)
Emergency vessels and containers to hold leaking material
Medical first aid provisions
General and special personal protective equipment for emergency personnel
3. Compile your group’s findings for presentation in the plenum.
Time: 45 min
73/95
HO NO 17B STORY FIRE AND EXPLOSION IN BC
BC is located in a residential area and has around 150 workers. Many different workshops are group
together in great proximity to the storage. The storage room has roof ventilation and can be closed
by key. Very near to the storage room is a vast workshop where in case of fire or explosion smoke
can propagate easily due to lack of division of the workshop sections.
Three propane gas cylinders are stored in one corner of the storage room close to an extinguisher.
On the other corner in a wood container are stored around 50 kg of clean cloth (to be used as
wipers).
In the storage of BC you find additionally the following chemicals and materials:
Task:
Form 3-4 company groups and make a fire and explosion risk assessment for BC by filling HO 17c
(consult SDS) and determine the appropriate control approach for each chemical
Time: 30 min
74/95
HO NO 17C RISK ASSESSMENT TABLE FOR FIRE AND EXPLOSION (EMPTY)
Area/ Name SDS R-phrases/ Hazard Physic Boiling Liberation Dustiness Quantities Duration Level of Potential Control
Process Yes/ Flash point type al point/ group for for solids in use of use hazard extend of approach
Hazard vapor liquids (I,II,III) damage
No P H E
group pressur
Storage Acetone Yes R11, R36, C 56.2°C medium 200 l Long III high 3
R66, R67
24 kPa medium
-20°C
Storage Acetic
acid
Storage Toluene
Storage Diesel
storage Propane
gas
75/95
HO 17D FIRE RISK ASSESSMENT USING CONTROL BANDING
According to BAuA, 2011 you can determine the control approach for fire and explosion for a specific
chemical after you have considered the 3 following parameters:
Low ml or g
Medium l or kg
High m3 or t
76/95
(2) Duration of use:
Short < 15 min sporadically
Medium < 15 min in series
Long >15 min
By combining the two parameters in Table 2 you obtain the level of hazard atmospheres (I, II or III)
for the chemical in question.
6
These control approaches 1-4 are the same as the ones recommended for control chemicals that causes harm to human health through
inhalation
77/95
HO NO 17E RISK ASSESSMENT TABLE FOR FIRE AND EXPLOSION (FILLED)
Area/ Name SDS R-phrases/ Hazard Physic Boiling Liberation Dustiness Quantities Duration Level of Potential Control
Process Yes/N Flash point type al point/ group for for solids in use of use hazard extend of approach
o Hazard vapor liquids (I,II,III) damage
P H E
group pressur
Storage Acetone Yes R11, R36, C 56.2°C medium 200 l long III high 3
R66, R67
24 kPa medium
-20°C
Storage Acetic Yes R10, R35 B 118°C medium 50 l long III high 3
acid
38°C 15,5 kPa medium
Storage Toluene Yes R11, R38, C 3-3.5 kPa medium 100 l long III high 3
R48/20, medium
R63, R65,
R67
Storage Diesel R40, R65, A > 160 - Low 200 l long II high 2
R66, 385°C
medium
R51/53
< 0.04
Min 56°C kPa
storage Propane Yes R12 C - 42.1 °C high Medium long III high 3
gas
830 kPa
78/95
HO NO 17F SAMPLE CHECKLIST FIRE PREVENTION FOR SUPERVISORS
Supervisor:
Date: Department/Area
Hot Work permits are used for all welding and spark producing operations
combustible & flammable material is not stored near gas fired equipment
79/95
HO NO 17G EMERGENCY CHECKLIST
80/95
Point to consider Your assessment
All personnel familiar with the meaning of warning signals and the
required action to be taken?
Procedure in place to make outside persons (visitors, contractors,
suppliers, customers) aware of the emergency procedures?
Is there fire-fighting equipment located near flammable or hazardous
areas (e.g. generator area, fuel storage tank, transformer)?
Location of the fire fighting equipment easily accessible and in
clearly marked locations?
Firefighting equipment provided in the locations appropriate to
control the respective type of fire in these locations?
First-aid kits available in designated and clearly marked areas
Procedure established and maintained to check and replenish content
of first aid kits (e.g. designated persons in-charge of first aid box)
Certified first aiders available in each section/agency during office
hours
Names and locations of first aid personnel indicated on first aid boxes
81/95
PREPARE FOR COMPANY APPLICATION
After the participants have familiarised themselves with the basic steps of the gap analysis as
systematic approach to identifying differences between recommended and existing controls , the
participants will have the opportunity to practically carry out a first approximated gap analysis in
their company and apply different assessment tools in their respective companies. This will be done
in form of a “company application”. Some days later when all tables have been filled and all pendinhg
information has been collected a second approximation of a control approaches gap analysis should
be undertaken.
SESSION DESIGN
During this session, the participants will prepare the work plans for accomplishing the tasks assigned
to them for the company application. This will be done in company teams. Here often confusion
arises, as participants assume that everybody will visit all companies. This should be clarified to the
management of the participating companies in advance as companies often are reluctant to allow
external visitors into their premises.
Each company team will consist of the company representatives (those who are participating in the
training, plus additional company representatives assigned to the company’s change team). Each
team may be accompanied by one – two consultants who participate in the training (as part of TOT).
During the company visit the trainers are expected to visit each company to review the ongoing work
on site and to provide assistance to the company teams.
Materials required:
82/95
DESCRIPTION OF STEPS
Explain that after the participants have familiarised themselves with the basic concepts of NPOs,
preparation of an inventory and the assessment of hazards and risk using the control banding
methodology, they will have the opportunity to practically apply these tools in their respective
companies. This will be done in form of a “company application”. The purpose of this session is to
help them with guidance from the trainers to prepare for the tasks which will be assigned to them.
Point out that the work will be done in company teams only.
Distribute HO and go through the task to be performed by the company teams. Explain that each
company team is expected to complete the following tasks:
1. Select one work area in the company and carry out a gap analysis
2. Assess the storage of chemicals (conditions, practices)
3. Identify possible chemical emergency situations and assess the emergency preparedness of
the company
4. Collect other data and information which will the company teams to prepare an action plan
5. Prepare a short presentation of your visit on a flipchart for the next day of training.
Ask the participants to break up in company teams and start with the preparation of their work plans
for completing the tasks on-site. In case TOT participants are present, assign these to different
company teams to assist with the preparation of the work plans as well as the completion of tasks
on-site.
Advise the teams that before starting, they should consider points such as what information they
would need, from whom and where they can get it. They should also decide who will coordinate the
group work, distribute the responsibilities, etc.
At the end of this session, each company team should have a draft work plan for the company
application. Time allotted is 45 minutes.
83/95
Ask the participants to make sure that they have the following information/materials with them
when they go to the companies
Checklists
Before completing the session, remind the participants that each company team is expected to
present the results of the visit in the plenary (for about 5 – 10 min), also dealing with organizational
issues such as where did you find the information, how did it go, transport, lunch, etc., challenges,
surprises…)
84/95
HO NO 18 A PREPARATION OF COMPANY APPLICATIONS MODULE CONTROL
MEASURES
Transportation
Selection of responsible persons in the team for collecting specific data and ticking checklists.
During the visit the group prepare a ground plan of the company and fill Ho No 18b with names of
chemicals used and area they are used in, observation of critical situations, identified gaps, new
NPOs with the help of an Improved updated flow chart of a selected process
o Inventory and risk assessment table (filled) HO 10d for verification of existing control
approaches
85/95
WS NO 18 B FOR OBSERVATIONS OF CRITICAL SITUATIONS/ IDENTIFICATION OF
CONTROL GAPS DURING COMPANY VISIT
86/95
HO 18 C IDENTIFICATION OF “HOTSPOTS“
For identifying potential opportunities for cost savings and for reducing risks
Lids of chemical containers that are not tightly sealed and the
contents are exposed to air and humidity
Chemical containers that are used for other purposes than storing
the original chemical, e.g. for storing water, storing and
transferring other materials
87/95
TRAINER INSTRUCTION – ANALYSING RESULTS OF COMPANY APPLICATION AND
ACTION PLANNING
This session reviews the results after the company application, helping the company teams to refine
and analyze their results. At the end of this session, each company team will have prepared a
detailed action plan to (a) deal with the gaps in the selected work area and in the chemical store and
(b) initiate steps to improve the company’s ability to respond to emergency situations
Materials required
88/95
GENERAL REVIEW OF COMPANY APPLICATION (15 MIN)
Start with a general review of the company application in the plenary. Invite the participants in the
plenary to share their experience with the company application, for example what went well, where
they faced challenges, how the completed the task, whether and in which the preparation of the
work plan in advance had been of use, etc. In case not mention, verify the availability of safety
information such as safety data sheets, labels, markings, how useful the HOs and checklists have
been to assess the situation on-site
Check whether any common issues have come and provide further clarification, in case required.
Remind the participants that each team was expected to briefly present their results of
selecting one work area in the company and carry out a gap analysis
assessing the storage of chemicals (conditions, practices)
identifying possible chemical emergency situations and assess the emergency preparedness
of the company and
collect other data and information which will the company teams to prepare an action plan
Inform the participants that each company team will be given about 30 min to complete their
presentations and put them on display in an information market.
Allow for about 30 minutes for activity in the information market to learn about each other’s
experiences and results.
Request the participants to reorganize themselves in their company teams. Start this part with
recalling the different steps to arrive from a problem to a solution (refer to action planning in module
1).
Ask each company team to select a gap identified, which they would consider as a priority, using one
of these guiding questions:
- Which situations (handling etc.) cause the highest losses/NPOs and present
- Which are the most critical chemicals in terms of impact on environment and health?
- Which are the most critical situations in terms of impact on environment and health
89/95
Then request the company teams to proceed along the same line as during action planning in module
1 , by establishing the causes for the situation (e.g. Why do these situations occur?)
After completing the cause analysis, they should proceed with identifying possible ways of
addressing the situation. Ask the company teams to look at possible alternative measures, through
which they could deal with the different causes they had identified.
Distribute action planning sheet (HO 19) to the company teams and encourage them to proceed with
selecting the most promising/feasible measures with respect to reduce costs and/or risk linked to
chemicals and prepare an action plan for their implementation. Remind the participants that the
implementation of one measure can imply several actions!
At the end the company teams should document the action plan on pin board or flipchart paper and
present the results in the plenary (or on info market) (5 min per company).
90/95
HO NO 19 ACTION PLAN FOR CHEMICAL RISK MANAGEMENT – CONTROL MEASURES
Hazardous chemical/ Proposed measure Objective of proposed Necessary action/ Responsible person(s) Deadline Results to be monitored
critical situation/loss/ measure activities for
identified gap implementing measure
91/95
TECHNICAL SESSION GUIDE 0205 – ANCHORING CHEMICAL MANAGEMENT IN THE
COMPANY
Before using this session guide, read chapter Implement improvement measures in your company
and Evaluate and integrate your achievements and Topics 6 and 10 in annex to module 2 – Managing
the risks in your company –control measures and gap analysis.
SESSION DESIGN
This session summarizes the different elements of the chemical management process. At the end of
this session, the participants will be able to
Assess where their company stands in terms of integrating the different chemical
management elements in their company
Decide on the next steps to incorporate chemical management in their company
Introduction 5 min
Exercise 30 min
Conclusion 5 min
Materials required:
Topic 6
Topic 10
PPP 18 chemical management cycle module 2
DESCRIPTION OF STEPS
INTRODUCTION (5 MIN)
Referring to the chemical management cycle, indicate the different steps the participants have
completed in the two training modules. Point out that the different tools and approaches they have
92/95
familiarized themselves with, would need to become an integral part of the way their company
works, so ensure the continuation of the efforts as well as to reaping the full benefits.
Request the participants to go into their respective company teams. Distribute Topic 10 or ask the
teams to look at topic 10. Explain that the 11 points of action listed will help the participants
towards integrating the chemical management into their company. Each action point provides a
short description and ends with a set of guiding questions, which allow assessing the situation in the
company.
Quickly go through the 11 action points (10 – 15 min) and highlight some of the crucial features.
Following this ask the company teams to go through the guiding questions.
Point out that as in the case of other improvement measures, they can prepare an action plan with
measures helping them to address relevant issues. For example, what steps to take to ensure that
the chemical inventory will be maintained in future, or what steps to take that also other staff
members of the company can familiarize themselves with the information they have acquired during
the training, or how to guarantee that for each chemical in the company a risk assessment has been
done.
Ask each company team, which of the 11 action points has been already satisfactorily addressed in
their company and which points need to be addressed in due course.
CONCLUSION (5 MIN)
Clarify any questions with regard to the anchoring of the chemical management and close the
session.
93/95
CLOSING OF WORKSHOP
Time 30 Min
Close the workshop by summarizing the topics covered as well as the tasks to be completed until the
next workshop.
Request the company teams to take all their flipcharts and materials they have prepared in course of
the training workshop back to their companies for further training and reference.