EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. Instrumentation work space Requirements
All local instrumentation and associated control equipment shall be 34-SAMSS-831
A1
readily accessible from grade, platform, fixed walkway, or fixed ladder. Sec 8.1.1
Page 1 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Different instruments signals shall be segregated from each other and 34-SAMSS-831,
A14
from power wiring. Sec. 8.1.1
Tagging Instruments shall have permanently attached engraved
phoenolic / laminate or plastic nameplates, showing instrument tag 34-SAMSS-831,
A15
numbers. Phoenolic nameplates shall be installed with two stainless Sec. 8.1.2
steel screws.
Level Gauge Glasses Refer to Library Drawing DB-950046 (Attachment-
6) for typical liquid level gauge glasses installations. Weld pad type level 34-SAMSS-831,
A16
gauges are acceptable for lube oil tanks. Refer to SATIP-J-300-01 for Sec. 8.1.1.2
different types of installations
Orifice Runs, Venturi Tubes and Flow Nozzles The minimum required
lengths of straight and unobstructed pipe upstream and downstream of 34-SAMSS-831,
A17
the primary element shall be based on a beta ratio of 0.7, and be in Sec. 8.1.1.3
accordance with Standard Drawing AA-036197(Attachment -7)
Cable Seals. Seals shall be provided on cables at the first point of NEC Article
B2
termination after entry into the Zone 0 location. 505.16 (A)(2)
In Class I, Zone 1 locations, seals shall be located in accordance with
the following:
(1) Type of Protection “d” or “e” Enclosures. Conduit seals shall be NEC Article
B3
provided for each conduit entering enclosures having type of protection 505.16 (B)(1)
“d” or “e.” Exception: Where the enclosure having type of protection
“d” is marked to indicate that a seal is not required.
Explosion proof Equipment. Conduit seals shall be provided for each
conduit entering explosion proof equipment according to (a), (b), and (c).
(a) In each conduit entry into an explosion proof enclosure where either
(1) the enclosure contains apparatus,(2) the entry is metric designator 53
(trade size 2) or larger and the enclosure contains terminals, splices, or
taps.
NEC Article
B4 (b) Conduit seals shall be installed within 450 mm (18 in.) from the
505.16 (B)(2)
enclosure. Only explosion proof unions, that are not larger than the trade
size of the conduit shall be permitted between the sealing fitting and the
explosion proof enclosure
(c) Where two or more explosion proof enclosures for which conduit
seals are required , are connected by nipples or by runs of conduit not
more than 900 mm (36 in.) long.
Page 2 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
All piping, tubing and valves shall be adequately supported and fastened
01-SAMSS-017,
B11 in a manner which facilitates replacement, and prevents vibration. Refer
Sec. 5.1.4
to Drawing AB-036521 for valve bracing. Attachment 2)
The minimum size of auxiliary piping and tubing for mechanical
01-SAMSS-017,
B12 equipment shall be 1/2-inch NPS with the exception of air compressor
Sec. 5.1.3
packages which shall be 3/8-inch NPS.
All piping, tubing and valves shall be adequately supported and fastened
01-SAMSS-017,
B13 in a manner which facilitates replacement, and prevents vibration. Refer
Sec. 5.1.4
to Drawing AB-036521 for valve bracing. (Attachment 2)
Page 3 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Depth of Working Space. The depth of the working space in the direction
of live parts shall not be less than that specified in Table 110.26(A)(1)
(Attachment 2) unless the requirements of110.26(A)(1)(a), (b), or (c) are
met. (a) Dead-Front Assemblies where all connections and all renewable
or adjustable parts, are accessible. (b) Low Voltage. By special NEC Article
C3
permission, smaller working spaces shall be permitted where all un- 110.26(A)(1)
insulated parts operate at not greater than 30 volts rms, 42 volts peak, or
60 volts dc.
(c) Existing Buildings. In existing buildings where electrical equipment is
being replaced,
Page 4 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Primary and backup data link cables shall preferentially enter cabinets or
SAES-J-902 Sec
D2 consoles from opposite sides. Data link cables shall not be routed in the
12.3.2
same conduit, duct, or tray with other instrument cables.
Page 5 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Minimum separation requirements between various instrumentation
SAES-J-902 Sec
D4 cables and data link cables (copper or fiber optic) shall be per the
12.3.2
manufacturer's recommendation.
Tray Spacing: Table 3 indicates the minimum distance in millimeters
between the top of one tray and the bottom of the tray above, or between SAES-J-902 Sec
D5
the sides of adjacent trays. This also applies to the distance between 14.2.1
trays and power equipment of less than 100 kVA. (Attachment -1)
Tray-Conduit Spacing: Table 4 indicates the minimum distance in
millimeters between trays and conduits. This also applies to the distance SAES-J-902 Sec
D6
between trays or conduits and power equipment of less than 100 kVA. 14.2.2
(Attachment -1)
Conduit Spacing: Table 5 indicates the minimum distance in millimeters
between the outside surfaces of conduits being run in banks. This also SAES-J-902 Sec
D7
applies to the distance between conduits and power equipment of less 14.2.3
than 100 kVA.
SAES-J-902 Sec
D9 For direct buried cable, cable spacing shall be as shown in Table 3.
14.2.6
When entering terminal equipment (e.g., motor control center) and the
SAES-J-902 Sec
D10 spacing listed in tables 3, 4, or 5 cannot be maintained, parallel runs
14.2.7
shall not exceed 5 ft in the overall run.
SAES-J-902 Sec
D11 Minimum separation requirements between various instrumentation
14.2.8
The marshalling cabinets, from the front surface to the surface of rear
terminal blocks, shall not be more than 46 cm (18 inches) deep to
34-SAMSS-820,
D13 provide for safe access. The preferred design is to divide a 76 cm (30
Sec.6.3.10
inch) deep cabinet into 38 cm (15 inch) sections with front and rear
access.
All doors must be capable of swinging at least 90-degrees open at the 34-SAMSS-820,
D14
installed location. Sec.6.3.11
Page 6 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
ATTACHMENTS:
1. Attachment 1 Minimum distance in mm between top of one tray and the bottom of the tray above- Table 3
2. Attachment 2 -Work space requirements Minimum distance in mm
3. Attachment 3 -Electrical Equipment Temperature class NEC table 500.8(B)
4. Attachment 4 - Valve bracings std DWG AB-036521 sht 1 rev 08
5. Attachment 5 -- Details of heavy welding boss for threaded connections to vessels.
6. Attachment 6 -- Liquid level gauge glasses, instrument piping details lib. Dwg DB950046
7. Attachment 7 -- Straight pipe requirements for Orifice , Venturi and flow nozzles Std. Dwg AA-036197
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the
indicates compliance with appropriate standards or performance in a specified manner.
5. Remarks - (Does not apply for Custom engineered Package units but only for pre-engineered, pre-assembled and
pre- wired skid mounted packaged units)
Page 7 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Attachment 1 -- Minimum distance in mm between top of one tray and the bottom of the tray above- Table 3
Page 8 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Page 9 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Page 10 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Page 11 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Attachment 6 -- Liquid level guage glasses, instrument piping details lib. Dwg DB950046
Page 12 of 13
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General- Instrumentation Workspace Clearances. SAIC-J-6022 1-Oct-05 INST
Attachment 7 -- Straight pipe requirements for Orifice , Venturi and flow nozzles Std. Dwg AA-
Page 13 of 13