Professional Documents
Culture Documents
Analisa Harga
Analisa Harga
A PEKERJAAN PERSIAPAN
B. PEKERJAAN TANAH
1 Penggalian Tanah Biasa sedalam 1 meter m3 Kap 929.56 WAKTU Kap x Waktu TENAGA
Tenaga : 1.29032258 15.00 19.35 48.03
0.7500 oh Pekerja 1.0 95,000.00 95,000.00 71,250.00 - 71,250.00 46.48
0.0250 oh Mandor 0.0 100,000.00 100,000.00 2,500.00 - 2,500.00 1.55
0.7750 73,750.00 - 73,750.00
Over Head + Profit 10 % : 7,375.00
Total : 81,125.00
C. PEKERJAAN PONDASI
7 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai. m2
Tenaga :
1.3000 oh Tukang batu 110,000.00 110,000.00 143,000.00 - 143,000.00
0.1300 oh Kepala Tukang Batu 120,000.00 120,000.00 15,600.00 - 15,600.00
0.6700 oh Pekerja 95,000.00 95,000.00 63,650.00 - 63,650.00
0.0030 oh Mandor 100,000.00 100,000.00 300.00 - 300.00
Material :
8.4000 m3 Bata ringan tebal 7,5 cm. 7,000.00 7,000.00 - 58,800.00 58,800.00
0.4730 kg Mortar siap pakai. 1,360.00 1,360.00 - 643.28 643.28
222,550.00 59,443.28 281,993.28
0.1000 Peralatan : 28,199.33
Over Head + Profit 10 % : 28,199.33
Total : 338,391.94
E. PEKERJAAN PLESTERAN
85,571.00 - 85,571.00
Over Head + Profit 10 % : 8,557.10
Total : 94,128.10
560,551.00 - 560,551.00
Over Head + Profit 10 % : 56,055.10
Total : 616,606.10
256,883.59 - 256,883.59
Over Head + Profit 10 % : 25,688.36
Total : 282,571.95
G. PEKERJAAN BETON
1 Pek. Membuat 1 m3 Lantai Kerja Beton mutu Fc = 7,4 Mpa slump ( 3.6 ) Cm,w/c = 0,87. m3
Tenaga :
0.2000 oh Tukang Batu 110,000.00 110,000.00 22,000.00 - 22,000.00
0.0200 oh Kepala Tukang Batu 120,000.00 120,000.00 2,400.00 - 2,400.00
1.2000 oh Pekerja 95,000.00 95,000.00 114,000.00 - 114,000.00
0.0600 oh Mandor 100,000.00 100,000.00 6,000.00 - 6,000.00
Material :
200.0000 Ltr Air 25.00 25.00 - 5,000.00 5,000.00
893.0000 kg Pasir beton 350.00 350.00 - 312,550.00 312,550.00
1,027.0000 kg Koral Beton 450.00 450.00 - 462,150.00 462,150.00
230.0000 kg Semen Tiga Roda / 50 Kg 1,360.00 1,360.00 - 312,800.00 312,800.00
144,400.00 1,092,500.00 ##########
Over Head + Profit 10 % : 123,690.00
Total : ##########
2 Pek. Membuat 1 m3 Lantai Kerja Beton mutu Fc = 14,5 Mpa slump ( 120 + 20) mm. m3
Tenaga :
0.2750 oh Tukang Batu 110,000.00 110,000.00 30,250.00 - 30,250.00
0.0280 oh Kepala Tukang Batu 120,000.00 120,000.00 3,360.00 - 3,360.00
1.6500 oh Pekerja 95,000.00 95,000.00 156,750.00 - 156,750.00
0.0830 oh Mandor 100,000.00 100,000.00 8,300.00 - 8,300.00
Material :
215.0000 Ltr Air 25.00 25.00 - 5,375.00 5,375.00
760.0000 kg Pasir beton 350.00 350.00 - 266,000.00 266,000.00
1,029.0000 kg Koral Beton 450.00 450.00 - 463,050.00 463,050.00
326.0000 kg Semen Tiga Roda / 50 Kg 1,360.00 1,360.00 - 443,360.00 443,360.00
198,660.00 1,177,785.00 ##########
Over Head + Profit 10 % : 137,644.50
Total : ##########
9 Pek. Membuat 1 m3 Lantai Kerja Beton mutu Fc = 31,2 Mpa,slump ( 120 + 20 ) mm. m3
Tenaga :
0.3500 oh Tukang Batu 110,000.00 110,000.00 38,500.00 - 38,500.00
0.0350 oh Kepala Tukang Batu 120,000.00 120,000.00 4,200.00 - 4,200.00
2.1000 oh Pekerja 95,000.00 95,000.00 199,500.00 - 199,500.00
0.1050 oh Mandor 100,000.00 100,000.00 10,500.00 - 10,500.00
Material :
215.0000 Ltr Air 25.00 25.00 - 5,375.00 5,375.00
667.0000 kg Pasir beton 350.00 350.00 - 233,450.00 233,450.00
1,000.0000 kg Koral Beton 450.00 450.00 - 450,000.00 450,000.00
448.0000 kg Semen Tiga Roda / 50 Kg 1,360.00 1,360.00 - 609,280.00 609,280.00
252,700.00 1,298,105.00 ##########
Over Head + Profit 10 % : 155,080.50
Total : ##########
3 Pek.Canal C.125X50X20X3,2 kg
Tenaga :
1.2000 oh Tukang Besi 110,000.00 110,000.00 132,000.00 - 132,000.00
2.4000 oh - Pekerja 95,000.00 95,000.00 228,000.00 - 228,000.00
1.2000 oh Kepala Tukang Besi 120,000.00 120,000.00 144,000.00 - 144,000.00
0.6000 oh - Mandor 100,000.00 100,000.00 60,000.00 - 60,000.00
Material :
110.0000 kg - Canal C.125x50x20x3,2. 11,044.00 11,044.00 - 1,214,840.00 1,214,840.00
110.0000 kg - Pek.Pengecatan. 1,000.00 1,000.00 - 110,000.00 110,000.00
15.0000 btg - Kawat Las.AW.SE.6013. 1,500.00 1,500.00 - 22,500.00 22,500.00
564,000.00 1,347,340.00 ##########
Over Head + Profit 10 % : 191,134.00
Total : ##########
Harga per kg : 21,024.74
Tenaga :
0.0150 oh Pekerja 95,000.00 95,000.00 1,425.00 - 1,425.00
0.0030 oh Mandor 100,000.00 100,000.00 300.00 - 300.00
Material :
0.0500 kg Sabun 22,500.00 35,000.00 - 1,750.00 1,750.00
1,725.00 1,750.00 3,475.00
Over Head + Profit 10 % : 347.50
Total : 3,822.50
Tenaga :
0.1500 oh Pekerja 95,000.00 95,000.00 14,250.00 - 14,250.00
0.0030 oh Mandor 100,000.00 100,000.00 300.00 - 300.00
Material :
0.0500 kg Soda api 22,500.00 40,000.00 - 2,000.00 2,000.00
14,550.00 2,000.00 16,550.00
Over Head + Profit 10 % : 1,655.00
Total : 18,205.00
M PEKERJAAN SANITASI
1 Pek. kloset duduk/monoblok Toto Type CW.660J/SW660J buah
Tenaga :
3.3000 oh Pekerja 95,000.00 95,000.00 313,500.00 - 313,500.00
0.1600 oh Mandor 100,000.00 100,000.00 16,000.00 - 16,000.00
1.1000 oh Tukang batu 110,000.00 110,000.00 121,000.00 - 121,000.00
0.0100 oh Kepala tukang Batu 120,000.00 120,000.00 1,200.00 - 1,200.00
Material :
1.0000 bh Kloset duduk/monoblok 3,400,000.00 ########## - 3,400,000.00 3,400,000.00
1.0000 ls Perlengkapan (6% harga kloset) 204,000.00 204,000.00 - 204,000.00 204,000.00
451,700.00 3,604,000.00 ##########
Over Head + Profit 10 % : 405,570.00
Total : ##########
4 Memasang bak kontrol pas. Batu bata uk. 30x30 cm,tinggi = 35 cm. buah
Tenaga :
2.1600 oh Pekerja 95,000.00 95,000.00 205,200.00 - 205,200.00
0.0110 oh Mandor 100,000.00 100,000.00 1,100.00 - 1,100.00
0.7200 oh Tukang batu 110,000.00 110,000.00 79,200.00 - 79,200.00
0.0720 oh Kepala tukang Batu 120,000.00 120,000.00 8,640.00 - 8,640.00
Tenaga :
3.2000 oh Pekerja 95,000.00 95,000.00 304,000.00 - 304,000.00
0.0160 oh Mandor 100,000.00 100,000.00 1,600.00 - 1,600.00
1.1500 oh Tukang batu 110,000.00 110,000.00 126,500.00 - 126,500.00
0.0110 oh Kepala tukang Batu 120,000.00 120,000.00 1,320.00 - 1,320.00
Material :
70.0000 bh Batu Bata merah. 499.60 499.60 - 34,972.00 34,972.00
77.0000 kg Semen Tiga Roda / 50 Kg 1,360.00 1,360.00 - 104,720.00 104,720.00
0.1300 m3 Pasir pasang 103,000.00 103,000.00 - 13,390.00 13,390.00
0.0200 m3 Batu kerikil 350,000.00 350,000.00 - 7,000.00 7,000.00
2.6000 kg Besi beton 14,767.39 14,767.39 - 38,395.21 38,395.21
0.0900 m3 Pasir beton 215,000.00 215,000.00 - 19,350.00 19,350.00
433,420.00 217,827.21 651,247.21
Over Head + Profit 10 % : 65,124.72
Total : 716,371.94
6 Memasang bak kontrol pas. Batu bata uk. 60x60 cm,tinggi = 65 cm. buah
Tenaga :
3.2000 oh Pekerja 95,000.00 95,000.00 304,000.00 - 304,000.00
0.0160 oh Mandor 100,000.00 100,000.00 1,600.00 - 1,600.00
1.1500 oh Tukang batu 110,000.00 110,000.00 126,500.00 - 126,500.00
0.0110 oh Kepala tukang Batu 120,000.00 120,000.00 1,320.00 - 1,320.00
Material :
123.0000 bh Batu Bata merah. 499.60 499.60 - 61,450.80 61,450.80
114.0000 kg Semen Tiga Roda / 50 Kg 1,360.00 1,360.00 - 155,040.00 155,040.00
0.1840 m3 Pasir pasang 103,000.00 103,000.00 - 18,952.00 18,952.00
0.0330 m3 Batu kerikil 350,000.00 350,000.00 - 11,550.00 11,550.00
4.8500 kg Besi beton 14,767.39 14,767.39 - 71,621.84 71,621.84
0.1200 m3 Pasir beton 215,000.00 215,000.00 - 25,800.00 25,800.00
433,420.00 344,414.64 777,834.64
Over Head + Profit 10 % : 77,783.46
Total : 855,618.11
21 Pek. Kran Kitchen Sink Toto Type T.30 AR.13 V7N. buah
Tenaga :
0.0100 oh Pekerja 95,000.00 95,000.00 950.00 - 950.00
0.0050 oh Mandor 100,000.00 100,000.00 500.00 - 500.00
0.4000 oh Tukang batu 110,000.00 110,000.00 44,000.00 - 44,000.00
0.0400 oh Kepala tukang 120,000.00 120,000.00 4,800.00 - 4,800.00
Material :
1.0000 bh Kran 408,000.00 408,000.00 - 408,000.00 408,000.00
0.0250 set Seal tape 5,000.00 5,000.00 - 125.00 125.00
50,250.00 408,125.00 458,375.00
Over Head + Profit 10 % : 45,837.50
Total : 504,212.50
O PEKERJAAN ELEKTRIKAL.
B. Bahan :
1.0000 bh Saklar tunggal, 10 A, 250 VAC 21,750.00 21,750.00 - 21,750.00 21,750.00
C. Peralatan :
1.0000 ls Kotak sambung & alat bantu lainnya 2,175.00 2,175.00 - 2,175.00 2,175.00
60,520.00 23,925.00 84,445.00
Over Head + Profit 10 % : 8,444.50
Total : 92,889.50
2 Saklar Ganda, 10 A, 250 VAC Bh
A. Tenaga :
0.0170 oh Mandor. 100,000.00 100,000.00 1,700.00 - 1,700.00
0.0170 oh Kepala tukang listrik 120,000.00 120,000.00 2,040.00 - 2,040.00
0.1700 oh Tukang Listrik 114,000.00 114,000.00 19,380.00 - 19,380.00
0.3400 oh Pembantu Tukang Listrik 110,000.00 110,000.00 37,400.00 - 37,400.00
B. Bahan :
1.0000 bh Saklar tukar tunggal, 10 A, 250 V 24,805.00 24,805.00 - 24,805.00 24,805.00
C. Peralatan :
1.0000 ls Kotak sambung & alat bantu lainnya 2,480.50 2,480.50 - 2,480.50 2,480.50
60,520.00 27,285.50 87,805.50
Over Head + Profit 10 % : 8,780.55
Total : 96,586.05
4 Pasangan MCB Bh
A. Tenaga :
0.0170 oh Mandor. 100,000.00 100,000.00 1,700.00 - 1,700.00
0.0170 oh Kepala tukang listrik 120,000.00 120,000.00 2,040.00 - 2,040.00
0.1700 oh Tukang Listrik 114,000.00 114,000.00 19,380.00 - 19,380.00
0.3400 oh Pembantu Tukang Listrik 110,000.00 110,000.00 37,400.00 - 37,400.00
B. Bahan :
1.0000 bh MCB 53,000.00 53,000.00 - 53,000.00 53,000.00
C. Peralatan :
1.0000 ls Kotak sambung & alat bantu lainnya 4,053.50 4,053.50 - 4,053.50 4,053.50
60,520.00 57,053.50 117,573.50
Over Head + Profit 10 % : 11,757.35
Total : 129,330.85
B. Bahan :
1.0000 bh Saklar tripel, 10 A, 250 VAC 52,635.00 52,635.00 - 52,635.00 52,635.00
C. Peralatan :
1.0000 ls Kotak sambung & alat bantu lainnya 5,263.50 5,263.50 - 5,263.50 5,263.50
60,520.00 57,898.50 118,418.50
Over Head + Profit 10 % : 11,841.85
Total : 130,260.35
B. Bahan :
15.0000 m Kabel NYA 3x2,5 mm2 10,800.00 10,800.00 - 162,000.00 162,000.00
15.0000 m P\ipa konduit uPVC 20 mm 2,900.00 2,900.00 - 43,500.00 43,500.00
C. Peralatan :
1.0000 bh Fitting, kotak sambung, klem & alat bantu lainnya 685.00 685.00 - 685.00 685.00
35,600.00 206,185.00 241,785.00
Over Head + Profit 10 % : 24,178.50
Total : 265,963.50
KOTAK - KONTAK
7 Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80 cm) Bh
A. Tenaga :
0.6800 oh Mandor. 100,000.00 100,000.00 68,000.00 - 68,000.00
- oh Kepala tukang listrik 120,000.00 120,000.00 - - -
1.8700 oh Tukang Listrik 114,000.00 114,000.00 213,180.00 - 213,180.00
1.5500 oh Pembantu Tukang Listrik 110,000.00 110,000.00 170,500.00 - 170,500.00
B. Bahan :
1.0000 Bh MCCB 3 Pase 421,000.00 421,000.00 - 421,000.00 421,000.00
22.0000 Bh MCB 1 Phase 53,000.00 53,000.00 1.00 1,166,000.00 1,166,000.00
1.0000 Bh Arestar 3 Phase 25,000.00 25,000.00 2.00 25,000.00 25,000.00
3.0000 Bh Lampu Indikator 3,500.00 3,500.00 3.00 10,500.00 10,500.00
1.0000 Bh Volt Meter 125,000.00 125,000.00 4.00 125,000.00 125,000.00
3.0000 Bh Box Panel 125,000.00 125,000.00 5.00 375,000.00 375,000.00
1.0000 Bh Graunding 75,000.00 75,000.00 6.00 75,000.00 75,000.00
1.0000 Ttk Material Wiring dan ACC
C. Peralatan :
- bh Kotak sambung & alat bantu lainnya 3,327.50 3,327.50 - - -
451,701.00 2,197,500.00 ##########
Over Head + Profit 10 % : 264,918.00
Total : ##########
8 Kotak-kontak 1 fasa, 16 A, 250 VAC tahan air Bh
A. Tenaga :
0.0170 oh Mandor. 100,000.00 100,000.00 1,700.00 - 1,700.00
0.0170 oh Kepala tukang listrik 120,000.00 120,000.00 2,040.00 - 2,040.00
0.1700 oh Tukang Listrik 114,000.00 114,000.00 19,380.00 - 19,380.00
0.3400 oh Pembantu Tukang Listrik 110,000.00 110,000.00 37,400.00 - 37,400.00
B. Bahan :
1.0000 bh Kotak-kontak 1 fasa, 16 A, 250 VAC tahan air 52,700.00 52,700.00 - 52,700.00 52,700.00
C. Peralatan :
1.0000 bh Kotak sambung & alat bantu lainnya 5,270.00 5,270.00 - 5,270.00 5,270.00
60,520.00 57,970.00 118,490.00
Over Head + Profit 10 % : 11,849.00
Total : 130,339.00
Bahan :
1.0000 bh Kontak kontak AC/FAN, 1 fasa 16 A, 250 VAC 53,800.00 53,800.00 - 53,800.00 53,800.00
C. Peralatan :
1.0000 bh Kotak sambung & alat bantu lainnya 5,380.00 5,380.00 - 5,380.00 5,380.00
60,520.00 59,180.00 119,700.00
Over Head + Profit 10 % : 11,970.00
Total : 131,670.00
B. Bahan :
15.0000 m Kabel NYM 3x2,5 mm2 10,800.00 10,800.00 - 162,000.00 162,000.00
15.0000 m Pipa konduit uPVC 20 mm 2,900.00 2,900.00 - 43,500.00 43,500.00
C. Peralatan :
1.0000 bh Fitting, kotak sambung, klem & alat bantu lainnya 1,370.00 1,370.00 - 1,370.00 1,370.00
35,600.00 206,870.00 242,470.00
Over Head + Profit 10 % : 24,247.00
Total : 266,717.00
B. Bahan :
1.0000 bh Lampu down light 11 Watt DL ARM 110,000.00 110,000.00 - 110,000.00 110,000.00
C. Peralatan :
1.0000 ls alat bantu lainya 53,700.00 53,700.00 - 53,700.00 53,700.00
35,600.00 163,700.00 199,300.00
Over Head + Profit 10 % : 19,930.00
Total : 219,230.00
B. Bahan :
1.0000 bh Lampu LED Armature Uk. 2x9 watt 350,000.00 350,000.00 - 350,000.00 350,000.00
C. Peralatan :
1.0000 ls alat bantu lainya 35,000.00 35,000.00 - 35,000.00 35,000.00
35,600.00 385,000.00 420,600.00
Over Head + Profit 10 % : 42,060.00
Total : 462,660.00
14 Lampu Down liht RD 125 LED BULD 1x9 W E 27 Bh
A. Tenaga :
0.0100 oh Mandor. 100,000.00 100,000.00 1,000.00 - 1,000.00
0.0100 oh Kepala tukang listrik 120,000.00 120,000.00 1,200.00 - 1,200.00
0.1000 oh Tukang Listrik 114,000.00 114,000.00 11,400.00 - 11,400.00
0.2000 oh Pembantu Tukang Listrik 110,000.00 110,000.00 22,000.00 - 22,000.00
B. Bahan :
1.0000 bh Lampu Downlight RD 125 LED BULB 1x 9 W E.27 275,000.00 275,000.00 - 275,000.00 275,000.00
C. Peralatan :
1.0000 ls alat bantu lainya 27,500.00 27,500.00 - 27,500.00 27,500.00
35,600.00 302,500.00 338,100.00
Over Head + Profit 10 % : 33,810.00
Total : 371,910.00
B. Bahan :
1.0000 mtr Kabel NYFGbY 4 x 4 mm² 85,000.00 85,000.00 - 85,000.00 85,000.00
1.0000 m Sepatu kabel, pengikat, klem dan alat bantu lainnya 12,750.00 12,750.00 - 12,750.00 12,750.00
C. Peralatan :
1.0000 ls alat bantu lainya 8,500.00 8,500.00 - 8,500.00 8,500.00
6,150.00 106,250.00 112,400.00
Over Head + Profit 10 % : 11,240.00
Total : 123,640.00
18 Kabel NYY 3 x 2,5 mm² m
A. Tenaga :
0.0050 oh Mandor. 100,000.00 100,000.00 500.00 - 500.00
0.0050 oh Kepala tukang listrik 120,000.00 120,000.00 600.00 - 600.00
0.0500 oh Tukang Listrik 114,000.00 114,000.00 5,700.00 - 5,700.00
0.0500 oh Pembantu Tukang Listrik 110,000.00 110,000.00 5,500.00 - 5,500.00
B. Bahan :
1.0000 mtr Kabel NYY 3 x 2,5 mm² 8,100.00 8,100.00 - 8,100.00 8,100.00
1.0000 m Sepatu kabel, pengikat, klem dan alat bantu lainnya 1,215.00 1,215.00 - 1,215.00 1,215.00
Tenaga kerja
0.0430 OH
0.0430 OH
0.0043 OH
0.0021 OH
4.40 M'
4.50 M2
0.27 Tube
Tenaga kerja
0.085 OH
0.085 OH
0.009 OH
0.005 OH
Bahan
0.05 M3
0.3359 Lbr
0.3359 Lbr
0.015 OH
0.0008 OH
174.6987952
203.6144578
261.4457831
289.1566265
3023.3
A TENAGA
1
3
4
B BAHAN
C PERALATAN
D
E
F