You are on page 1of 10

Triton

Arco Interiors
Mobile Crane
Installation & Rental
Proposal
2019

November 19, 2019

1.2

1.1

© 2019 Triton Consultancies


Table of Contents
1 Brief ...................................................................................................... 3
2 Proposal ................................................................................................ 4
2.1 Included Items/Services ................................................................................................................ 4
2.2 Excluded Items/Services ............................................................................................................... 4
2.3 Assumption ................................................................................................................................... 4
2.4 Execution process ......................................................................................................................... 4
3 Lifting plan (First Draft) ........................................................................ 5
4 Next Action .......................................................................................... 10
5 Financials ............................................................................................ 11
6 Customer References........................................................................... 11

© 2019 Triton Consultancies


1 Brief
Triton quality consultancies (Triton) is pleased to share this proposal with “Arco Interiors”, for Mobile
Crane installation and rental at their site in Abu Dhabi

Arco Interiors, also referred as “Arco”, is looking for preferred partner to for Portable Cabins in their new
site in Abu Dhabi. This proposal includes scope of required work and associated financials. Triton will
commence the work on Arco’s approval of proposal and financials.

Triton works as integrator in the market to assure fulfillment of all required services for its customers with
its extended reach and by assuring to offer authorized, certified equipment testing on regular frequency.

It is our pleasure to offer our services for the engagement.

This information in this document is confidential, and the reader is bound to treat it as confidential in
accordance to the local laws.

On the agreement & approval of proposal, “Arco Interiors” may duplicate, use or disclose the data with
appropriate associates within the organization.

© 2019 Triton Consultancies


2 Proposal
This is first proposal draft, with the following sections,

Scope Draft
Lifting plan
Execution of plan

2.1 Included Items/Services


Final Lifting plan with accuracy
Mobile Crane for the purpose
Rigger & Crane operator

2.2 Excluded Items/Services


Following services are not covered in the proposal,

Civil foundation works


External connections such as electrical, water, drainage, sewage, etc.
All Governments and Municipal approvals and clearances, custom and border
charges, airport and seaport passes are excluded.
Fire/safety protection devices are excluded.

2.3 Assumption
We presume that the site is accessible by normal road trailer. Extra charges incurred due to
inaccessibility of site/road will be charged to you in actual.

The site is access ale, including the the


tomblifting
andof FAHU
glass sucking equipment is available and tested for the
job.

2.4 Execution process


Triton will follow below execution process for this engagement,

Triton is submitting first draft of proposal for Arco’s review


On first level of approval from Arco, Triton will engage the Engineer to visit the site to
finalize calculations for the lifting plan
At the same time/ day Triton will also bring the crane to demonstrate required lifting
under the plan
Triton’s Engineer will make required adjustments to the plan, according to demo lifting
Triton will submit final commercial proposal for Arco’s review
Arco will issue the LPO
© 2019 Triton Consultancies
Triton will engage required crane and human resource to perform required duties
Triton’s consultant will take required signoff from Arco site
Triton will submit associated invoices and Arco will make to the payment in favor of
Triton

3 Lifting plan (First Draft)


Following lifting plan is created for initial review, hence the calculation in this plan are subjected to our
final site visit and Arco’s approval on submitted proposal.

Client Name : Arco Interiors Lifting Plan Arco-1119-001 Location :Abu Dhabi

Date Of issue: 19th Nov 19 Date Of revision: subject to approval Date of expiry : Upon completion /
revision
Subject to final site visit

Lifting ofofFAHU
Job description: Removal Equipment
glass section form from
doomGround
from thetoheight
roof of
floor upto 40using
40 meters mtr using
Mobile crane of appropriate specification

Glass suckers

Load Description: `1. Solid X 2. Contains Liquid X FAHU √X


3. Glass

Lifting Lug description ( If not provided, provide description for method for anchoring) : Unknown

Dimension: Length = Unknown MM Width= Unknown MM Height/ Thickness = Unknown MM

Center of gravity: 1. Calculated X 2. Provided X 3.Estimated √

Precaution : Suitable packing and proper securing must be provided

Type of lifting:

1. Routine lifting X
2. Complex lifting X
3. Tandem lifting X
4. Non Routine lifting √

© 2019 Triton Consultancies


Plan View :

FAHUpiece
Crane Details : We have many Cranes for the purpose, as per our understanding the weight of glass 3100
is is approximately 350
5000
Kg, so all calculations are based upon 500 KGkg Load.
load.

Make ----

Model ------

Certificate Validity and company name of TP company

Maximum Capacity 100 T

Maximum Boom Length 80+ m

Maximum Radius 50+m

© 2019 Triton Consultancies


Capacity at maximum boom length 4T

Working Radius 30m

Boom length at working radius 42 m

Lifting height at working radius 42 m

Capacity on working boom length and radius X

Crane capacity 1.25 times of weight of load @ point of lifting. Yes / No

Suitable Mat size Provided & Ground condition YES Mat Size : Unknown

Side View

© 2019 Triton Consultancies


Lifting Gear Details: will be provided if selected for service

Equipment WLL Length Certificate No

Wire Rope sling X

Chain Sling X

Webbing Sling Unknown

Spreader Beam X

Glass Lifter Unknown

Shackle X

Eye Bolt X

Assessment
Risk Assuagement

Wind Speed exceeds 12.5 M/S or 25 Knot If yes, Lifting must be stop

Rain If yes, Lifting must be stop

Working under Electrical supply If yes provide detail for safe practice

Excavation work nearby location If yes provide detail for safe practice

Other crane working in the same area If yes provide detail for safe practice

Other People working in same area If yes provide detail for safe practice

Over Head Hazards If yes provide detail for safe practice

Crossing load over residential building If yes provide detail for safe practice

Crane operator Certificate Will be provided

Rigger certificate Will be provided

Lifting Inspection carried out and defect observed Will be provided

Crane pre use checkup carried out and found satisfactory Will be done when required

Remark :

© 2019 Triton Consultancies


Method of Statement:

1. Park Crane near to entrance (at 40 meter of working radius) with full extension of our rigger illustrated in picture
check for safe movement of boom.

2. Working area and turn table area must be barricaded.

3. Check for crane stability and leveling

5.Trail movement

4. Connect glass Lifter to crane hook is safe and organized manner

5. Rigger banks man give signal main boom.

5. Rigger banks man give signal for boom up

6. Rigger banks man give signal turn left

7. Rigger banks man give signal boom extend up to 60 Mtr

8. Positin will be achived at height of 41 Mtr Radious 40 Mtr and boom lenghth 60 mtr

© 2019 Triton Consultancies


9. Hook up glass lifter with load . Loose weight hold life line in proper mananer load should not be hit its own
doom.
10. Hook slow up one it tight leve load then move load to right. By giving right signal

11. Then boom down and hook up

12. Identfy location to land load once load close to ground level park it slowllly at safe place.
13. Repeat process.

1. Rigger Name

2. Rigger name

Lifting plan Prepared by

Safety officer

Lifting Plan approved by

4 Next Action
Triton will submit final lifting & execution plan on Arco’s approval.