Professional Documents
Culture Documents
Pre-Feasibility Report
Pre-Feasibility Report
INSTITUTE OF ENGINEERING
KATHMANDU ENGINEERING COLLEGE
DEPARTMENT OF CIVIL ENGINEERING
A
FINAL YEAR PROJECT REPORT
ON
DARAM KHOLA
(A HYDROPOWER PROJECT)
Prepared By:
Kathmandu, Nepal
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
KATHMANDU ENGINEERING COLLEGE
DARAM KHOLA
(A HYDROPOWER PROJECT)
Prepared By:
September 2012
COPYRIGHT
The author has agreed that the Library, Department of Civil Engineering, Kathmandu
Engineering College, Institute of Engineering may make this report freely available for
inspection. Moreover, the author has agreed that permission for extensive copying of this project
report for scholarly purpose may be granted by the supervisors who supervised the project work
recorded herein or, in their absence, by the Head of the Department wherein the project report
was done. It is understood that the recognition will be given to the author of this report and to
the Department of Civil Engineering, Kathmandu Engineering College, Institute of Engineering
in any use of the material of this project report. Copying or publication or the other use of this
report for financial gain without approval of to the Department of Civil Engineering,
Kathmandu Engineering College, Institute of Engineering and author’s written permission is
prohibited. Request for permission to copy or to make any other use of the material in this report
in whole or in part should be addressed to:
We, the final year BE students, are highly obliged to Kathmandu Engineering College for
providing us such a great opportunity to research in our related field and build a project of our
own interest. The duration of completing this project has been a great opportunity for us to
explore the possibilities of different ideas in our field.
First of all we would like to thank “Department of civil engineering” and creditable teachers
who were invaluable for our project.
We are genuinely grateful to our project supervisor Er. Rajendra Kumar B.C for his guidance
and co-operation throughout the project and reviewing our project from time to time. We are
indebted to our teachers who helped us with our project by sharing their precious suggestion,
instructions and experiences.
Our strength was the support of the friends who have directly and indirectly encouraged and
assisted us in carrying out this work. Their constructive criticism and motivation is the key to
our success.
Project Group:
Manohar Sedhain (065/BCE/089)
Shiv Kumar Thapa (065/BCE/095)
Sunil Shah (065/BCE/109)
Suraj Pant (065/BCE/110)
Yogesh Subedi (065/BCE/118)
Ranjeet Thakali (065/BCE/119)
PREFACE
To introduce the students with the real civil engineering practice and to give them confidence,
ability to tackle problems related to civil engineering and idea of practical working in
professional field with the application of theoretical knowledge gained during the whole four
years, there is a provision of project work in the syllabus of TU.IOE on the final semester of
bachelor’s degree program. This project entitled “Pre-feasibility study on Daram Khola
hydropower project” is the one prepared by a group of six students in partial fulfillment of the
requirement for the bachelor’s degree in civil engineering.
Nepal has high potential in hydropower but the development made so far is only available for
a small portion of the population. In order to contribute in the generation of hydropower energy
for the improvement of GDP, the study for the execution of the project is made.
Hydropower engineering includes great diversified nature of work from meteorological analysis
to geological study, civil engineering structures, electromechanical installation, operation etc. In
order to complete this project, the period of one semester inclusive of the regular classes and
timely assessments is very difficult. However every effort has been made to collect the most
reliable data, past reports and relevant design information.
Two days field visit of the site was also made to determine the suitability of the structure’s
location, geological investigation and topographic features. One-day visit to the similar type
small- hydropower plant (Chaku khola hydropower) was also made to support the project and to
visualize the structure, its proper placement functions and many more unknown factors to be
considered.
From the very beginning of the project, from the hydrological analysis to hydraulic design
and then to turbine design every attempt had been made to cover all the parts of a hydropower
plant. This project group is sure that this report will be beneficial for the detail investigation and
design of the Daram Khola Small Hydropower Project. The group will also be delighted for any
feedback and suggestion to upgrade this report.
SALIENT FEATURES
Project location
Development Region : Western
Zone : Dhaulagiri
District : Baglung
Headwork site : Saddin village of Harichaur V.D.C
Power house site : Ghusmeli village of Argal V.D.C
Geographical Co-ordinates
Latitude : 28°17’52’’N to 28°16’45"N
Longitude : 83°25’27’’ E to 83°24’30’’E
General
Undersluice
No of openings : One
Channel Slope : 1 in 25
Width : 3m
Intake
Type : Orifice
Size : 2.2 m (W) x 1m (H)
No. of openings : 2
Invert Level of sill : 1595.7 masl
Gravel Trap
Type : Rectangular
Length : 23.25 m
Size : 2 m (w) x 2 m (H)
Settling Basin
Type : Surface
No. of Basins : Two
Designed particle size : 0.20 mm
Size : 60mx 7.4m x5.75m
Forebay
Penstock Pipe
Material : Steel
Length : 1730m (up to the bifurcation)
Finish Diameter : 1.3 m
Number of Anchor Blocks : 29(up to bifurcation)
Support piers : 76
Turbine
No of Unit : 2
Economy
2. BACKGROUND 4-6
2.1 Background 4
2.2 Location and Accessibility 4
2.3 Drainage and Basin Characteristics 4
2.4 Daram Khola A-Hydropower Project 5
2.5 Objective of the Study 6
2.6 Scope of Works 6
2.7 Methodology of the Study 6
3. GEOLOGY AND GEOLOGICAL STUDIES 7-10
3.1 General 7
3.2 Geology of Nepal 7
3.2.1 Terai Zone 8
3.2.2 Siwalik Zone 8
3.2.3 Lesser Himalaya Zone 9
3.2.4 Higher Himalaya Zone 9
3.2.5 Tibetan Tethys Himalaya Zone 9
3.3 Geology of the Project Site 9
4. HYDROLOGY 11-20
4.1 Objective of Hydrology Investigation 11
4.2 Scope of investigation 11
4.3 Physiographic characteristics of the Daram Khola basin 11
4.3.1 The catchment 11
4.3.2 The climate 12
4.4 Stream flow 13
4.4.1 Basic historic data 13
4.4.2 Long-term stream flow analysis 14
4.4.2.1 Riparian release 15
4.5 Flow duration curve 16
4.6 Flood flow 17
4.6.1 Regional flood frequency analysis 17
4.7 Rating curves 18
5. DESIGN ASPECTS 21-31
5.1 Introduction 21
5.2 Design basis 21
5.2.1 Headworks 21
5.2.2 Penstocks 26
5.2.3 Turbines 28
6. PLANNING AND CONSTRUCTION 32-34
6.1 General 32
6.2 Infrastructure Development 33
6.3 Phase of Construction 34
6.4 Schedule of Construction 34
7. ECONOMIC AND SENSITIVITY ANALYSIS 35-36
7.1 Economic Analysis 35
7.2 Sensitivity Analysis 35
8. ENVIRONMENTAL IMPACT ASSESSMENT 37-41
8.1 Introduction 37
8.2 Environment Impact Assessment in Nepal 37
8.3 Objective of EIA 38
8.4 Philosophy and Purpose behind EIA 38
8.5 Identification of Environmental Impacts 39
8.6 Environmental Impact Monitoring 40
8.7 Baseline Monitoring 40
8.8 Impact Monitoring 40
8.9 Compliance Monitoring 40
Pre-feasibility Study of Daram Khola A-Hydropower Project
1.0 INTRODUCTION
~1~
Pre-feasibility Study of Daram Khola A-Hydropower Project
for domestic consumption as well as to export hydropower, the former policy was replaced by
the Hydropower Development Policy 2001 to provide further impetus to active participation of
private sectors.
Development of hydropower in Nepal is a very complex task as it faces numerous challenges and
obstacles. Some of the factors attributed to the low level of hydropower development are lack of
capital, high cost of technology, political instability, and lower load factors due to lower level of
productive end-use of electricity and high technical and non technical losses.
Hydropower Potential of Nepal (in million KW) Source: Water Resources in Nepal,C. K.
Sharma
S.No. River Basins Theoretically feasible Technically feasible Economical feasible
1 Saptakoshi 22.35 11.40 10.48
2 Karnali 34.60 24.36 24.00
3 Gandaki 17.95 6.73 6.27
4 Mahakali 1.58 1.13 1.13
5 Others 3.07 0.98 0.98
Total 83.29 44.60 42.15
~2~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Hence, small hydropower plant is better suited and justified to generate electricity in Nepal.
~3~
Pre-feasibility Study of Daram Khola A-Hydropower Project
2.0 BACKGROUND
2.1 Background
Daram khola-A hydroelectric project is a run-of-river (ROR) type located in Baglung District,
Western Development Region of Nepal. The project will have installed capacity of 2.5MW. The
Headwork’s site of the project is located at Saddin village of Harichaur V.D.C and powerhouse
site is at Ghusmeli village of Argal V.D.C.
~4~
Pre-feasibility Study of Daram Khola A-Hydropower Project
The catchment area of Daram khola at the intake site is about 84 km2 and the catchment area at
the powerhouse site is 94 km2.The length of the river is about 13km and the maximum width of
the catchment is approximately 7 km.
The project is under the influence of southwest monsoon. The climate of the basin is also
influenced by the physiography of the region. The difference between the warm humid summer
and the cold dry winter becomes more marked with the change in the altitude. As the project area
in the high altitude, the catchment area experiences cool temperature to sub –arctic. Like other
parts of Nepal, the region is also influenced by the monsoon climate.
The closet climatologically station to the project site is Tamghas located at Latitude of 2804’ and
Longitude 83015’ at ELev.1530m. According to the records of Tamghas, the minimum extreme
temperature is about 0o C during the winter and the maximum extreme temperature is about
36.50o C during the summer. The relative humidity may be as high as 90% during the wet season
and as low as 40% during the dry season.
Mean annual ppt. in the region is 1000 to 3500mm and mean monsoon ppt. is 1500 to
3500mm.The lowest flow occurs in the month of April, while the highest flow occurs in the
month of august.
~5~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~6~
Pre-feasibility Study of Daram Khola A-Hydropower Project
3.1 General
The main objectives of the geological studies are to collect geological geomorphologic
information and to use the findings for the evaluation of the feasibility of the project in the pre-
feasibility stage. Geology of the site define the design type, quality etc of any structure on or
under the surface of earth.
The Himalaya is said to be the most active and fragile mountain range in the world, it is a live
mountain with active tectonics. The Himalaya is still rising and its rocks are under constant stress
as the northward moving Indian Plate pushes against the stable Tibetan plate. The active nature
of the range is also manifested in frequent earthquakes. Moreover the inherently weak geological
characteristics of the rocks make the Himalaya fundamentally very fragile.
Nepal can be divided from south to north into following 5 major tectonics zone separated by
major thrust and faults.
There are a number of other thrust and faults, such as Mahabharata Thrust (MT), but none of that
runs the length of the country. Each geological zone is characterized by its area lithology,
tectonics, and structure and geologic history. These features are summarized in the form of a
generalized geological map.
~7~
Pre-feasibility Study of Daram Khola A-Hydropower Project
1 Terai Zone
2 Siwalik Zone
Terai Zone, the southern tectonics division of Nepal, represents the northern edge of Indo-
Gangentic alluvial basin. This plain is made up of alluvium of Pleistocene to recent age ( 1.8
million years to the present with an avg. thickness of about 1500m).
Siwalik zone also called Churia Hills consists of fluvial sedimentary rocks of Neogene to
quaternary age (14 to 1 million years). This zone is bounded to the north by MBT and to south
by MFT. In general, the rocks of siwalik zone dip northward at varying angles and overall strike
is East- West. The width of this zone varies from a few kilometers in eastern Nepal to about 33
km in the western Nepal. Rocks of this zone are divided stratigraphically into 3 parts. The lower
Siwalik consists of fine grained mudstone, siltstone and shale. The middle Siwalik is marked by
thick multistoried stone beds cycle of finding upward sequences is normally observed. The upper
Siwalik is characterized by very coarse grained rocks such as boulder conglomerates.
~8~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Lesser Himalayan Zone is boarded to the south by MBT and north by MCT. Three physiographic
units- the Mahabharat, Midland and parts of Fore Himalaya belong to this zone. It has an average
width of about 100 km. The zone is characterized by a mountain range of about 3000 m high in
the south and lower hills in the North. The zone consists of mainly of unfossiliferrous
sedimentary and various degree of metamorphism such as shale, sandstone, limestone dolomites,
slates, phylites, schist and quartzite ranging in age from pre-cambrian( as old as 1800 million
years) to Ecoene (about 40 million yrs). The rocks in this zone are highly folded into range
anticlines and synclines and faulted and have developed complicated structure. In the east it is
characterized by development of extensive thrust sheets of crystalline rocks of Higher Himalaya
(Gneisses and Schist) that have traveled southward to cover below the low grade metamorphic
rocks of lesser Himalaya. The low grade metamorphic rocks are called the Nuwakot complex and
high grade rocks are called the Kathmandu Complex.
Higher Himalaya zone includes rocks lying of MCT and below south of the fossiliferous Tethys
Himalayan Zone. The northern limit of this zone is STD. This zone consists of a 10-12 km thick
succession of high grade metamorphic rocks such as Gneiss, Migmatites, Schist, quartzite and
marbles of this zone form the basement of Tethys Himalayan zone some young granite occurs in
the upper part of the unit.
The Tethys Himalayan zone adjoins higher Himalayan zone with a normal fault contact (the
STD) and extends to the north into Tibet. This zone is composed of sedimentary rocks such as
shale, limestone and sandstones ranging in age from Cambrain (570 million yrs) to Cretaceous
(70 million yrs ago).
The project area is in the lower siwalik to middle siwalik. Its geology is highly fragile and the
rock types found are mostly low grade metamorphic rocks, and sedimentary rocks such as
phyllite, mudstone, shale, siltstone etc.
~9~
Pre-feasibility Study of Daram Khola A-Hydropower Project
There is no geological study carried out for the project area where the power plant is planned to
be located. A quick study of surface geology during reconnaissance visit revealed that the terrain
consisted essentially of rock bed through which river is following. The geological condition near
to the intake site is quite good than at the near to the power house site. As the river is flowing
through high grade near to the intake site big boulders can be seen. Near the power house the
deposition is mainly shingle rather than boulders as the gradient of river is lower than at the
intake site.
Since the river is in the boulder stage and the subsurface formation cannot be judge through the
surface investigation, it is recommended to carry out the geological study (surface and sub
surface) of the site in the Detailed Feasibility Study.
~ 10 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
4.0 HYDROLOGY
~ 11 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
The proposed powerhouse site of Daram Khola-A Hydroelectric Project lies at Latitude
28o16’45’’ N and Longitude 83o24’30’’ E, at about EI 1508 m and located at about 1.9 km
downstream of the proposed dam site. The total catchment area at proposed powerhouse site is
94 km2.
The average gradient of the river up to the dam site is about 16.25% and in between the dam site
and powerhouse site is about 5.25%.
Based on the topographical maps, there are no lakes within the Daram khola basin. All of the
above mentioned drainage areas have been estimated based on the latest topographical maps
compiled from 1:25000 scale aerial photographs by Survey Dept. The map of the project basin
and adjacent basins are shown in the annex.
~ 12 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Darbang, Kuhun and Beni lie in the north adjacent basin of Myagdi River. Baglung and
Rangkhani lie in the east adjacent basin, Bobang lies in the west in the Badi Gad basin and
Musikot, Tamghas and Ridi lies in the south in the Badigard and Ridi khola basins. But none of
them lie within the Daram khola basin. The closest climatological station to the project site is
Baglung.
The mean annual basin precipitation for the Daram khola- A Hydroelectric a Project at the dam
site is about 2680 mm (from DHM.). The mean annual basin precipitation for the Badigard River
at the confluence with Kali Gandaki River is about 2180mm. The monsoon rains contribute
about 80% of the total annual precipitation. The onset of monsoon starts from June to September.
According to the record of Baglung, the minimum extreme temperature is about 36oc during the
summer. The relative humidity may be as high as 90% during the wet season and as low as 35%
during the dry season.
~ 13 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
A
Qb Qi b
Ai
Where Qb and Qi are the discharges at the base and index stations, respectively, and Ab and Ai
are the corresponding basin areas. The long –Term mean monthly stream flow data series at the
proposed Intake site derived from monthly stream flow series of Badigad khola at Rudrabeni is
given in table 4.2:
Table 4.2 Long-term Mean Monthly Flow by Basin Area Ratio Method at Intake site
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annua
l
Badigad 26.3 28.7 18.9 19.6 23.9 64.6 261.2 395.0 284.0 110.3 52.7 32.8 109.8
Daram 1.1 1.2 0.8 0.8 1.0 2.7 11.3 17.1 12.2 4.7 2.2 1.4 4.7
~ 14 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
C) WECS/DHM Method
From WECS method long term flow was calculated by using following equation:
Q mean = C×(Total basin area)A1 ×(Basin area below 5000m +1)A2 ×(Monsoon wetness index)A3
Where,
C, A1, A2, A3 are constants derived from the regression analysis.
A is the catchment area in Km2.
Q is discharge in m3/sec
The result of this study is used as an alternate approach for estimation of mean monthly
discharges at the intake site. The following table3.4 shows the result from the above method.
Table 4.4 Long-term Mean monthly flow by WECS/DHM Method
Jan Feb Mar Arp May Jun Jul Aug Sep Oct Nov Dec Mean
1.1 0.9 0.8 0.8 1.0 3.8 11.9 14.4 11.1 4.9 2.1 1.4 4.5
Table 4.5 below shows the comparison of the derived long-term mean monthly flow at the
proposed intake site by various methods.
Table 4.5: Comparison of Derived Long-Term Mean Monthly Discharge at
Intake Site
Jan Feb Mar Arp May Jun Jul Aug Sep Oct Nov Dec Avg
Ref.STN 1.1 1.2 0.8 0.8 1.0 2.7 11.3 17.1 12.2 4.7 2.2 1.4 4.7
MIP 2.0 1.5 1.1 0.8 2.2 5.1 12.3 21.2 14.0 6.8 3.4 2.6 6.1
WECS 1.1 0.9 0.8 0.8 1.0 3.8 11.9 14.4 11.1 4.9 2.1 1.4 4.5
Since the reference station data are more reliable than the other regionally derived data, the mean
monthly flow as derived from the reference station data are used for the Pre-feasibility study of
Daram Khola -A Hydropower Project.
~ 15 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
From the above flow duration table, the 40% dependable flow is estimated to be about 3.67 m3/s,
which will be adopted as the design discharge. The flow duration curve is shown in fig 4.1.
~ 16 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
40.0
35.0
30.0
25.0
Discharge , m3/s
20.0
15.0
10.0
5.0
y = -6.24ln(x) + 27.33
0.0
0 20 40 60 80 100
Probability of exceedence ( % )
Fig 4.1: Flow duration Curve
QF=e(lnQ2+S*σlnQF
Where,
QF=the maximum flood discharge
lnQ2=the natural logarithm of the 2 year flood
S=standardized normal variate for a particular return period
σlnQF= Standerd deviation of the natural logarithms of annual flood given by
σlnQF=ln(Q100/Q2)/2.326
Where,
Q2 and Q100 are the 2 year and 100 year flood events.
The catchment area below EL 3000m at the damsite and powerhouse site are 79 km2 and 86 km2
respectively. The result of the flood estimates for the damsite and powerhouse site from the
above regional frequency analyses are presented in table 2.7
Table 4.7 Estimated Flood for Daram khola–A hydroelectric Project (m3/s)
Result Regional Analysis WECS/DHM Regional Analysis WECS/DHM
Period (yrs) Damsite Powerhouse
2 88.0 94.8
5 147.3 157.9
10 192.8 206.2
20 240.8 257.0
50 309.2 329.3
100 365.1 388.3
~ 18 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Manning’s coefficient of 0.04 for higher discharges, the estimated water levels for the high
discharges are conservative. At the powerhouse site, a Manning’s n of 0.04 has been used.
The rating curves are shown in below in Fig for the dam site and powerhouse site respectively.
2.0
1.5
Height(m)
Rating curve
1.0
0.5
0.0
0 100 200 300 400 500 600
Discharge(m3/s)
~ 19 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
2.25
2.00
1.75 Rating curve
1.50
1.25
1.00
0.75
0.50
0.25
0.00
0 100 200 300 400 500 600 700 800
Discharge(m3/s)
~ 20 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
5.1 introductions
Daram khola – A hydroelectric project is designed as a run – off river type project that utilizes
river flow in the Daram Khola and the gross head difference between proposed headworks and
power house.
The layout of the project has been selected considering topography , geology and available head
after due verification of the site. The main feature of the project are as follows:
Heaworks comprising of a concrete diversion weir , side intake , undersluice ,gravel trap,
gravel flushing conduict , approach cannel , surface settling basin, flushing conduit and
Steel penstock pipe as water way.
Surface powerhouse with installed capacity of 2.5 MW.
The general arrangement of the project is shown in the Drawing.
5.2.1 Headworks
The headworks designed of the project have been based on the following principles:
The structure will be able to divert necessary flow into the system.
Bed load entry to the intake is negligible and mostly passes through the undersluice.
Gravel trap and settling basins will ensure bed load and suspended sediment free
discharge into the system.
Structure will be safe from any hazardous floods and excess flood in the river will be
safely passed to downstream through ungated and uncontrolled spillway.
Any floating debris will not choke the intake and will safely pass to downstream.
~ 21 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
The design basis of each of the structure of the project is discussed below.
a. Diversion Canal
Diversion cannels and coffer dams are necessary to safeguard construction activities in the
headworks in particularly construction of diversion weir, bed load hopper, cut off walls,
undersluice, flood walls, upstreams and downstreams ripraps from any potential dry season flood
during months of November to May. Dry season 1 in 5 years return period flood of 147.38 m3/s
has been selected for sizing the river diversion works. The design has carried out by using
Mannings formula by taking consideration of limiting velocity for stabilizing the particle size
larger than 50 mm.
b. Weir
An uncontrolled concrete overflow weir having length of 21m crest length is designed to pass the
design discharge into the system through side intake and excess discharge including flood flow
to the downstream. The crest level has been fixed at an elevation 1597 masl. The heas over the
crest level has been calculated by using weir formula.
Q=CLH – 0.1Nh
Where,
C : weir discharge coefficient and assumed 2.2
L : weir length in meteres, which is 21m
H : flow depth over crest in meteres
n : number of ends
The diversion weir is designed to passs 1 in 100 years flood, which is estimated to be 365.17
cumec. The flood water level for 100 years flood at the weir area has been determined assuming
that the flushing gates remain closed considering worst of necessary diversion through the side
intake ensuring minimum downstream riparian flow when there is just sufficient flow in the
river.
In principle the undersluice gate shall be fully opened during monsoon and flood period and the
water head above the weir crest will always be less than mentioned above. During the monsoon
period the river transports heavy bed loads, which will erode the concrete surface. Therefore,
hard stone lining has been proposed to prevent concrete erosion on the weir surface.
~ 22 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
c. Undersluice
A channel of undersluice having width 3m has been designed to prevent bed load entering to the
intake and build up of the intake by flushing incoming boulders and bed load near the intake
through bed load hopper. Fixed wheel gates will regulate discharge downstream through the
undersluice channel ensuring necessary flow velocity to transport bed load.the undersluice has
been designed with the characteristics given below:
Maintain a guided uniform flow in front of the intake.
Enable the intake to draw desired discharge during normal flowin the river with no or
insignificant suspended sediments.
Scour and sluice the sediment deposited in front of the intake.
Pass the maximum pre – monsoon flood and part of the high flood during monsoon.
Maximum capacity of the undersluice at 100 years return period has been estimated by using
orifice formula and the details are given below:
Invert level of undersluice gate : 1593.7 masl
Top level of opening : 1596.7 masl
Opening width :3m
Opening height : 4.5 m
Opening area (A) : 13.5 m2
Invert slope (1 in S) : 25
Velocity : 13.3 m/sec
Maximum discharge : 112.5 m3/ sec
Largest spherical particle that will be flushed: 400 mm dia
Since the velocity is very high, therefore hard stone lining is provided to prevent erosion in the
channel surface.
d . Intake
An orifice type of side intake has been designed to divert design discharge of 3.6 m 3/sec and
30% additional discharge required to flush the sediment from the gravel flushing and settling
basins. In total the design discharge for the intake is 4.7 m3/sec. To prevent the sediment entry to
the intake the sill elevation has been fixed 4.4 m above the invert level of the undersluice. The
orifice size has been fixed considering low velocity of entry to minimize head loss and entry of
~ 23 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
floating debris. To prevent entry of large boulders from the intake orifice a net opening with
300*300 mm has been provisioned.
The intake orifice has been designed has submerged as submerged orifice. The minimum
submergence of 0.3 m has been provided for normal flow in the river and preventing floating
trash and wooden logs from entering into the intake. The vertical fixed wheel gates have been
proposed for controlling the discharge during high flood in case of emergency and for
maintainance purpose.
e. Gravel trap
A gravel trap has been provisioned to trap gravel, cobble and coarse sand particles that enter
through intake orifice during monsoon. It is important to continuously the gravel trap gate to
flush the sediment from the gravel trap during monsoon. On the other hand, during medium flow
season the gravel should be operated intermittently depending upon the flow condition in the
river.
The gravel trap consists of a hopper bottom, which is connected with flushing culvert/ channel.
The size of the gravel trap has been designed as such that it is able to trap the particle size 2 mm
and larger during the normal flood period. However, during high floods with return period of up
to 1 in 20 flood the gravel trap will be able to trap the sediment particle with a size 20mm and
above. A trash rack has been provisioned at the end of the gravel trap to prevent entry of such
material to approach cannel.
f. approach cannel
An approach box culvert is provisioned to convey water from gravel trap to the settling basin.
The size of each canal bay is calculated by using mannings formula given below.
Q=A*1/n*R2/3*S1/2
Where,
A = cross section area
Q= design discharge
S = bed slope (h/l)
L= total canal length
n= Mannings coefficient
~ 24 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
g. Spillway
As mentioned above, the box culvert will be full flow during flood conditions and the gates at the
intake are open. Such excessive flow will spilled out from a spillway provisioned at the end of
the box culvert at the beginning of regulating gates near settling basins.
h. Settling Basin
Two settling basin have been provisioned as such that the criteria for settling assigned sizes of
suspended sediment particles are met and there is provision for the flushing of the settled
particles. The settling and flushing performance of the settling basin is directly associated with
turbine wear and the particle size to be settled and flushed is decided based on the plant static
head and turbine type.
The settling basin is sized to trap 90 suspended particles of size 0.2mm or more. Most quartz and
feldspar particles larger than 0.2 mm are designed to settle and flushed from the settling basin to
minimize cost related to turbine wear and generation losses during maintenance of turbines.
Following parameters are used for sizing the settling basins.
Table 5-1 parameters used for the sizing of each chamber of settling basin
No of basins 2.0 nos
Design flow for each basin 2.2 m3/sec
Flushing discharge from each basin 0.7 m3/sec
Total discharge 4.4 m3/sec
Criteria: 90% settling of sediment particles 0.2 mm
Fall velocity of 0.2mm particle 0.02 m/sec
Water temperature 10.0 °C
The settling surface area has been calculated using Vetter's formula.
~ 25 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Based on settling surface area the geometry of the basin has been fixed, see table 3.2
Table 5.2: Geometry of settling basin
No of bays (one for each basin) 2.0
Flow per bay, 1.9 m3/sec
Assumed width 3.5m
Required length 60.0 m
Minimum depth 4.9 m
Provided depths 7.0 m
Maximum flow velocity 0.2 m/s
Sediment storage volume has been estimated for 6 hours storage when the river flow has
maximum suspended sediment concentration of up to 8000 ppm that enters the settling basin.
Such high concentration is expected to occur during high monsoon floods. The assumed
sediment concentration of 8000 ppm is high and is in conservative side and is safe. Depths of
sediment storage at the settling basin vary from 1.45 to 2.70 thus the total settling depth has been
designed as 7m.
A conventional hydraulic flushing system has been proposed for flushing deposits sediment. It is
assumed that one bay is closed off at a time and deposited sediment flushed out while sediment
deposition is allowed to other bay. A 1 in 50 slope has been provided for the flushing bed for safe
flushing of deposited sediments. The side of the hopper has been provided a slope of 1 in 1 (V:
H) at the parallel section and the bottom channel has width of 0.6m and the maximum depth at
the end is 1.28m.
i. Forbay
Forbay is provision adjacent to and immediately downstream of the settling basin. The waterway
will be under pressure from this forbay till powerhouse. The forbay is designed to discharge into
waterway even during sudden load acceptance.
5.2.2 Penstock
The total length of the pipe is 1730 m up to the bifurcation. The head loss in the penstock is
computed using Darcy Weisbach formula.
~ 26 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Where,
h = head loss in penstock
f = frictional coefficient, 0.015
l= length of waterway
v =velocity of flow
D = hydraulic diameter of tunnel
g = acceleration due to gravity
The diameter lf the penstock is optimized in consideration to the trad off between the cost of
penstock pipe and energy loss due to friction. The details of optimization are presented in the
annex and summary of the results is shown in Fig 4.1
31.0
22.0
Cost (NRs)
Energy
Loss
13.0 cost
4.0
Diameter(m)
~ 27 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
designed for the sum of static and water hammer pressure, the details of which are presented in
the annex.
5.2.3 Turbines
Two (2) number of horizontal shaft Francis turbines are proposed for Daram Khola – A
Hydroelectric Project. Each turbines capable of handling 1.83 m3/s discharge (design) at a rated
net head of 88.561 m, which results in the turbine shaft power of 1250 KW at average efficiency
of 0.85. The size and speed of the turbine is such that the total costs of civil, electric and
mechanical works will be minimized.
Type Selection
The selection of type of turbine primarily depends upon the net lead available and design
discharge. For the rated net head of 88.561 meter and design discharge of 3.67 m 3/s Francis
turbine having horizontal shaft arrangement is the choice of the turbine as presentation in
Figure below:
~ 28 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Unit capacity
The selection of unit capacity is based on the assumption that minimum number of units could be
installed for the more economic development of the project, reliability of generation, and
minimum loss of power during maintenance and operation at difference stage of time. Unit
capacity is generally determined by considering the available discharge throughout the seasons,
load demand, type of operations, efficiency of the machine, etc. Single unit is not preferred due
to the fact that total generation loss will occur in time of the unit breakdown and hence two or
three units will be suitable for the project. Considering the above factors two unit with 1250 kW
~ 29 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
installed capacity each is the best option for the project. Therefore the study of Daram Khola-A
Hydroelectric Project reveals that the installation of two (2) power units will be more economical
for the following reasons:
With two (2) turbines, peak power is the same as with three (3) or four (4)
Increase the reliability for energy generation though initial cost is little higher than the
cost of single unit and this cost will be compensated by extra energy in long run. The part load
efficiency of Francis turbine is in lower side and also operation of such turbine in discharge
below 50% will create vibration. Such kind of problem can be managed by installing two units
with more flexibility of operation in yearly dry season in comparison of single unit.
The required repair and maintenance works of the power units can be performed in the
yearly dry season in such a way that with exception of a temporary reduction of the plant power,
no energy loss will occur.
Turbine speeds
The calculated specific speed for the given rated head and discharge is 255 rpm(according to
Water power and Dam construction), and the highest corresponding permissible operating
turbine speed is 1624.17 rpm. Therefore the synchronous speed of the unit is 1000 rpm for the
frequency for 50 Hz and corresponding actual specific speed is 157 rpm.
Design Criteria
The general design and performance specification for the mechanical equipment are based on the
standards issued by IEC and other publication such as Water Power and Dam Construction, Unit
States Department of the Interior BUREAU OF RECLAMATION (USBR), IS-12800 (Part I) etc.
Description of Turbine
Each turbine is capable of handling 1.83 m3/ s discharge (design) at a rated net head of 82.56 m,
which result in the turbine shaft power of 1250 kW at maximum efficiency of 0.85. The size and
speed if the turbine is such that the total costs of civil, electrical and mechanical works will be
minimized.
For the given specific speed (157.02 rpm) of the turbine, a setting of the spiral centerline at an
elevation of 1507 92 masl. will be sufficient to prevent an undue cavitation attack.
~ 30 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
The Francis runner will be directly to the generator’s shaft. The turbine runner and the guide
vanes will be made of stainless cast or welded steel, and thus resistant to cavitation and sand
erosion. In addition the turbine will be equipped with replaceable wearing plates and labyrinth
rings (rotating type on the runner and fixed on the turbine side cover and side ring), all made of
stainless steel. To specific maintenance, all guide vanes bearing, joints of regulating mechanism
etc. will be self lubricating type. In addition, the link between the guide vanes and the regulating
ring will be equipped with a self-restoring safety system to prevent an overstress of the
regulating mechanism, if one or several guide vanes are blocked by squeezed trash material or
any other reason.
All turbine instrumentation, such as unit control boards, and governor control cabinets will be
located close to the relevant units on the turbine floor. This is advantageous for commissioning,
service and maintenance.
The principle characteristics of the Francis turbines are as follows:
- Number of turbine : two (2)
- Shaft arrangement : horizontal
- Installed capacity for each unit : 1250 kW
- Turbine efficiency : 0.85
- Rated discharge for each unit : 1.83 m3/s
- Rated net head : 88.561 m
- Rated speed : 1000 rpm
- Specific speed : 157 m-kW
- Unit spacing : 3.0 m
- Runner entrance dia. : 0.5 m
- Tailrace water : El 1504.98 masl
- Runner center line : El 1507.92masl
~ 31 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
6.1 General
A better planning ensures efficiency, effectiveness, and economy. The planning of a project
involves specifying the objectives of the project, linking the various activities to be carried out,
determining the gross requirements of the various materials, equipment and manpower, preparing
estimates of the costs of the various activities for satisfactory completion of the project. Planning
is to decide in advance. For the successful run of the project, certain development such as access
road temporary camps, and facilities for drinking water, light should be provided on the project
site before the actual construction started.
The most important feature of large construction works is the necessity of preparatory work for
integrating different types of construction equipment and plants, supply of transportation and
communication facilities and provision for living and working of thousands of workers. Planning
of operation, the organization of labour and water supply are other allied facilities.
The Daram Small Hydropower project is planning to be completed in around two (2) years. The
work of design and tender will be done in about Six months. The construction work should be
started when enough operations are lined up and definite commitments are made for arrival of
materials and equipment. It is not better that labour has come but material is not or materials
arrived but starting facilities are lacking. The detail of the planning is shown in the “construction
schedules” attached herewith.
`
~ 32 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 33 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
iv) Stores/shops
v) Recreations/sanitary facilities
vi) First aid facilities
c) Equipments
Concrete mixer
Excavating equipment
Compaction equipment
Transporting equipment
~ 34 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 35 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 36 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
that includes environmental monitoring and auditing. Annex 3 provides a logic diagram of the
EIA process in Nepal. There are three major decision steps during the entire period of EIA
preparation and implementation. They are as follows:
i. The Scoping study should be made during the feasibility period. Based on the output of
the Scoping exercise a Terms of Reference (TOR) is prepared. The proponent should prepare the
Scoping and TOR documents. According to EPR54 (amended 2055) both of these documents
should be submitted to the Ministry of Population and Environment (MOPE) through the
Department of Electricity Development (DOED) and Ministry of Water Resources (MOWR) for
approval. This is the first decision step.
ii. Based on the approved TOR, the developer should complete an EIA study and submit it
to MOPE through DOED and MOWR. Approval of the EIA report invariably provides some
Daram Hydropower Project conditions to comply with during project construction. This is the
second decision step; its successful completion allows developer to go ahead with project
construction.
iii. Implementation of Environmental Management Plan (EMP) takes place during the
project construction phase. Environmental monitoring is a part of the EMP and continues for the
entire project cycle. Environmental auditing is carried out after the project has been in operation
for some time, in order to examine whether everything has gone as predicted. This is a one-time
activity and provides the final decision step. Based on this step, the decision is made if the
project will continue or be discontinued.
~ 38 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
but to describe the most importance ones. E.I.A provides a systematic examination of
environmental implication of proposed actions and alternatives to assist the decision making. The
cost benefit and trade off analyses between the project implementation and associated
environmental costs facilitate the decision makers in making decision which are more likely to
result in sustainable project.
Owing to its scheme for identifying and quantifying assumed environmental effects, the EIA
system can contribute to:
Identify potential environment impacts regarding the approval of a project.
Examine the significance of environmental implication.
Assess whether impacts can be mitigated.
Recommend preventive and corrective mitigating measures.
Inform decision makers and concerned parties of environmental implications.
Advise whether development should development should go ahead.
~ 39 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
c) Cultural Impacts
Due to the access road and availability of modern commodity and facilities, the life style of the
locals changes. Cultural change may occur due to workers of varying cultures, as well.
~ 40 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Since most of the impacts seem less significant in pre-feasibility stage, it is suggested that this
project can be carried out with simple mitigation measures. However, more detailed analysis of
environmental parameters are recommended by environmental experts at feasibility stage with
necessary field investigations.
~ 41 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
9.1 Conclusion
The pre-feasibility study of the most feasible alternative as shown by energy mapping and
alternative analysis has been done to analyze the technical, financial and environmental
feasibility. The following conclusion has been drawn from the study.
The installed capacity of the project is 2.5 MW that comprises 2 generating units driven by
Francis turbine operating at gross head 91.34 meters and design discharge 3.67 m3/s. The project
is capable of generating 14.56 Gwh net energy annually among which 2.48 GWh is during the
dry season and 12.08 GWh is during the wet season. The total cost of the project is Rs 320
Million at the price level of 2012.
The project is financially feasible with the weighted average energy selling price of NRS 8.4
/Kwh in Dry season and NRS 4.8/KwH in dry seasom considered in the base year 2012. The
financial internal rate of return of the project is 16.21%, B/C 1.18
9.2 Recommendations
For further analysis of the project at detailed feasibility level, the following studies and
explorations are necessary.
Detailed topographic mapping of the headworks, penstock alignment and powerhouse area
and strip survey over the headrace culvert and headrace tunnel alignment.
Surface geological mapping and subsurface geological investigations should be carried out at
the headworks, waterway and powerhouse area.
A physical hydraulic modeling of the headworks, its performance in all different flow
conditions and study of the river hydrology should be conducted to verify and validate the
design.
Preliminary prediction of the environmental impacts of the projects has been done at this
level. Detailed Environmental impact assessment has to be carried out.
Continuous hydrological measurements, both low flow and monsoon floods should be
continued.
Suspended sediment sampling shall be carried out during the monsoon period.
~ 42 ~
ANNEXES
ANNEX-A
HYDROLOGY
CALCULATION
Pre-feasibility Study of Daram Khola A-Hydropower Project
HYDROLOGY CALCULATION
Discharge data from DHM
Average discharges in m3/s
Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec.
1976 35.9 29.9 23.5 22.0 26.4 57.9 250.0 293.0 226.0 91.3 50.8 33.6
1977 26.5 21.8 16.8 16.2 20.3 65.6 170.0 472.0 212.0 90.4 54.6 37.8
1978 29.5 25.4 22.8 23.8 30.4 160.0 356.0 380.0 207.0 120.0 60.3 41.8
1979 31.9 29.8 22.1 19.8 18.9 70.4 174.0 340.0 119.0 51.7 41.0 26.4
1980 21.2 17.2 20.4 36.4 46.4 82.8 214.0 276.0 460.0 123.0 72.6 49.7
1981 40.1 34.9 28.8 29.8 34.7 52.1 345.0 570.0 455.0 292.0 81.8 53.3
1982 44.9 39.2 37.3 35.6 32.9 72.1 255.0 385.0 346.0 93.7 50.8 35.5
1983 24.2 20.3 16.1 14.3 27.4 21.3 139.0 350.0 565.0 206.0 85.8 33.4
1984 23.3 15.0 11.4 16.2 43.8 75.9 464.0 290.0 364.0 76.8 36.5 21.2
1985 15.1 11.5 15.6 39.6 62.3 73.7 349.0 237.0 281.0 129.0 51.8 24.8
1986 17.6 12.6 9.3 33.6 53.7 89.4 290.0 226.0 433.0 149.0 76.5 36.4
1987 36.4 30.7 28.9 23.2 23.8 86.3 344.0 517.0 266.0 80.9 47.6 31.8
1988 24.2 20.6 19.0 16.9 17.1 33.3 369.0 489.0 279.0 80.6 47.2 35.1
1989 33.1 24.9 22.1 18.3 21.8 36.3 400.0 571.0 284.0 108.0 48.6 30.9
1990 22.0 20.6 19.9 20.0 16.8 56.6 332.0 315.0 159.0 80.1 37.7 25.3
1991 22.7 15.8 14.8 12.1 11.1 54.7 177.0 334.0 352.0 86.0 43.3 31.7
1992 26.0 222.4 18.0 14.1 20.0 15.5 58.7 316.0 151.0 79.8 28.7 19.8
1993 13.8 10.5 9.3 9.4 12.6 15.4 104.0 431.0 378.0 114.0 56.4 37.4
1994 32.5 27.9 22.9 20.1 21.0 95.7 161.0 306.0 166.0 40.6 14.2 15.0
1995 11.5 11.4 10.3 8.9 7.7 156.0 430.0 395.0 253.0 65.2 26.2 16.0
1996 15.7 15.9 11.9 8.7 7.0 17.3 148.2 1260.0 290.0 46.5 60.4 38.1
1997 31.4 25.1 19.1 21.8 18.7 64.6 370.0 266.0 97.9 66.1 38.1 32.9
1998 28.7 22.1 18.7 15.7 21.6 110.0 371.0 595.0 346.0 98.3 52.8 34.4
1999 28.9 23.8 19.2 17.4 23.3 56.2 269.0 368.0 290.2 126.8 39.8 26.6
2000 22.0 19.7 21.0 14.1 11.1 91.0 280.0 332.0 373.0 175.0 58.3 34.0
2001 29.5 20.1 15.0 16.6 15.9 24.0 144.0 245.8 191.0 127.0 59.9 30.3
2002 25.7 25.0 16.0 11.0 11.1 60.0 272.0 289.0 204.0 163.0 88.5 33.9
2003 23.6 16.6 19.5 17.0 17.0 37.7 183.0 168.0 161.0 104.0 68.8 49.7
2004 26.8 21.6 19.8 17.6 20.7 42.3 157.0 440.0 327.0 136.0 50.7 37.2
average 26.4 28.7 18.9 19.7 24.0 64.6 261.2 395.1 284.0 110.4 52.7 32.9
min 11.5 10.5 9.3 8.7 7.0 15.4 58.7 168.0 97.9 40.6 14.2 15.0
max 44.9 222.4 37.3 39.6 62.3 160.0 464.0 1260.0 565.0 292.0 88.5 53.3
st dev 7.8 37.9 6.1 8.3 13.4 36.3 107.1 198.9 112.4 51.9 17.5 9.1
var 60.6 1436.9 37.4 68.2 178.8 1319.5 11461.4 39569.1 12637.2 2690.6 307.2 82.6
~ 43 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
450.0
400.0
350.0
Discharge (m3/s)
300.0
250.0
200.0
150.0
100.0
50.0
0.0
0 2 4 6 8 10 12 14
Months
~ 44 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
A1
Catchment area ratio for Intake C c
A
Cc=0.043
Avg monthly
Discharge of gauge Predicted flow, Intake
Month station m3/sec
Jan 26.4 1.1
Feb 28.7 1.2
Mar 18.9 0.8
Apr 19.7 0.9
May 24.0 1.0
Jun 64.6 2.8
Jul 261.2 11.3
Aug 395.1 17.1
Sep 284.0 12.3
Oct 110.4 4.8
Nov 52.7 2.3
Dec 32.9 1.4
~ 45 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Wecs-Hydest Method
Flow duration curve calculation of Daram Khola
At Intake Site
WECS/ Department of Hydrology and metrology (DHM) method
Hydrological region=1
Basin area=84km
Area below 5000 m=84km2
Area below 3000 m=79km2
Monsoon wetness index=1500
Q2=88.08 m3/s
Q100=365.17 m3/s
a) Flood flows
~ 46 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
35.0
30.0
25.0
Flow in m3/sec
20.0
15.0
10.0
5.0
0.0
0% 20% 40% 60% 80% 100% 120%
Percentage of exceedence
~ 48 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
35.0
30.0
25.0
Flow in m3/sec
20.0
15.0
10.0
5.0
0.0
0% 20% 40% 60% 80% 100% 120%
Percentage of exceedence
~ 49 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
MIP
Calculation of the Hydrograph by the MIP method
Non Dimensional regional hydrograph
(Ref: Civil Works Guidelines for Micro Hydropower in Nepal, ITDG, Pg,157)
Region
Month 1 2 3 4 5 6 7
Jan 2.4 2.3 2.7 2.6 2.4 2.0 3.3
Feb 1.8 1.7 1.9 1.9 1.8 1.6 2.2
Mar 1.3 1.3 1.4 1.4 1.4 1.3 1.4
Apr 1.0 1.0 1.0 1.0 1.0 1.0 1.0
May 2.6 1.2 1.9 2.2 0.9 2.6 3.5
Jun 6.0 7.3 3.1 3.8 2.7 6.1 6.0
Jul 14.5 18.2 13.5 6.9 11.2 24.3 14.0
Aug 25.0 27.3 25.0 27.3 13.9 33.8 35.0
Sep 16.5 20.9 20.8 20.9 10.0 27.0 24.0
Oct 8.0 9.1 10.4 6.9 6.5 6.1 12.0
Nov 4.1 3.9 5.0 5.0 4.6 3.4 7.5
Dec 3.1 3.0 3.8 3.4 3.3 2.6 5.0
Region=1
Measured Predicted Predicted
flow m3/sec April Hydrograph
flow,
Month m3/sec
Jan 2.4 47.1
Feb 1.8 35.3
Mar 1.3 25.5
Apr 1.0 19.6 19.6 19.6
May 2.6 51.1
Jun 6.0 117.9
~ 50 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Avg monthly
Discharge of Predicted flow,
Month gauge station Intake m3/sec
Jan 47.1 2.0
Feb 35.3 1.5
Mar 25.5 1.1
Apr 19.6 0.8
May 51.1 2.2
Jun 117.9 5.1
Jul 285.0 12.3
Aug 491.5 21.2
Sep 324.4 14.0
Oct 157.2 6.8
Nov 80.6 3.4
Dec 60.9 2.6
~ 51 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
AVERAGE
HYDROLOGICAL CALCULATION
HYDEST Catchment Correlation Average of three
S.N. Month 1990 MIP Method Methods(m3/s)
1 Jan 1.1 2.0 1.1 1.4
2 Feb 0.9 1.5 1.2 1.2
3 Mar 0.8 1.1 0.8 0.9
4 Apr 0.8 0.9 0.9 0.8
5 May 1.1 2.2 1.0 1.4
6 Jun 3.9 5.1 2.8 3.9
7 Jul 11.9 12.3 11.3 11.9
8 Aug 14.5 21.3 17.1 17.6
9 Sep 11.2 14.0 12.3 12.5
10 Oct 4.9 6.8 4.8 5.5
11 Nov 2.2 3.5 2.3 2.6
12 Dec 1.4 2.6 1.4 1.8
25.00
Average
mean
monthly flow
Discharge, m3 /sec
20.00
15.00 Catchment
Correlation
10.00
5.00 HYDEST
1990
0.00
0 2 4 6 8 10 12 14
MIP
Month
~ 52 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
25.00
20.00
Discharge, m3 /sec
MIP
15.00
Catchment Correlation
Average
10.00
HYDEST
5.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12
Month
~ 53 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
FDC AT INTAKE
HYDROLOGICAL CALCULATION
Flow Flow Catc
in in hmen Flow in Flow
desce decen t decendi Aver in
nding ding Area ng age decen
order order Ratio order of ding Probabil
HYDES HYD MIP Meth Catch. three order ity of
Mon T EST od(C Correla Meth Aver Ran Frequ Exceden
Sn th 1990 1990 MIP AR) tion ods age k ency ce in %
1 Jan 1.1 14.4 2.0 21.2 1.1 17.1 1.4 17.6 1 13.0 7.6%
2 Feb 0.9 11.9 1.5 14.0 1.2 12.3 1.2 12.5 2 6.5 15.3%
3 Mar 0.8 11.1 1.1 12.3 0.8 11.3 0.9 11.8 3 4.3 23.0%
4 Apr 0.8 4.9 0.8 6.8 0.8 4.7 0.8 5.5 4 3.2 30.7%
5 May 1.0 3.8 2.2 5.1 1.0 2.8 1.4 3.9 5 2.6 38.4%
6 Jun 3.8 2.1 5.1 3.4 2.8 2.2 3.9 2.6 6 2.1 46.1%
7 Jul 11.9 1.4 12.3 2.6 11.3 1.4 11.8 1.8 7 1.8 53.8%
8 Aug 14.4 1.1 21.2 2.2 17.1 1.2 17.6 1.4 8 1.6 61.5%
9 Sep 11.1 1.0 14.0 2.0 12.3 1.1 12.5 1.4 9 1.4 69.2%
10 Oct 4.9 0.9 6.8 1.5 4.7 1.0 5.5 1.2 10 1.3 76.9%
11 Nov 2.1 0.8 3.4 1.1 2.2 0.8 2.6 0.9 11 1.1 84.6%
12 Dec 1.4 0.8 2.6 0.8 1.4 0.8 1.8 0.8 12 1.0 92.3%
~ 54 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
25.0
20.0
Discharge, m3 /sec
15.0
HYDEST
1990
MIP
10.0
Catch.
Corrlation
5.0 Average
0.0
0% 20% 40% 60% 80% 100%
Exceedance/ Probability, %
~ 55 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 56 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 57 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 58 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 59 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 60 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 61 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 62 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 63 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 64 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 65 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 66 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 67 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 68 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
F-D curve
40
35
30
25
Discharge , m3/s
20
15
10
5
y = -6.243ln(x) + 27.332
0
0 20 40 60 80 100
Probability of exceedence ( % )
~ 69 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Q at Badi gard
Q at intake site
SN Year station Remarks
Max Min Max Min
1 1976 293 22 12.6 0.9
Mean peak
2 1977 472 16.2 20.4 0.7
discharge
3 1978 380 22.8 16.4 0.9
= Qmean =
4 1979 340 18.9 14.7 0.8
18.7
5 1980 460 17.2 19.9 0.7
6 1981 570 28.8 24.6 1.2
Standard deviation
7 1982 385 32.9 16.6 1.4
(sd) =
8 1983 565 14.3 24.4 0.6
8.2
9 1984 464 11.4 20.0 0.4
10 1985 349 11.5 15.1 0.4
11 1986 433 9.32 18.7 0.4
12 1987 517 23.2 22.3 1.0
13 1988 489 16.9 21.1 0.7
14 1989 571 18.3 24.7 0.7
15 1990 332 16.8 14.3 0.7
16 1991 352 11.1 15.2 0.4
17 1992 316 14.1 13.6 0.6
18 1993 431 9.29 18.6 0.4
19 1994 306 14.2 13.2 0.6
20 1995 430 7.66 18.6 0.3
21 1996 1260 7.04 54.5 0.3
22 1997 370 18.7 16.0 0.8
~ 70 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 71 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
GUMBEL
Gumbel's Method for Flood frequency Analysis
~ 72 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
PLOTTING POSITION
Plotting position method of frequency analysis for flood estimation
GUMBEL CURVE
~ 73 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
60.000
50.000
40.000
data
Gumbels theoritical line
30.000
10.000
0.000
-1.000 1.000 3.000 5.000 7.000
YT = - ln ln ( T/T-1)
Fig:Gumbel curve
~ 74 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
LPC
Statistical Analysis for Log Pearson III method of flood prediction
N = 29
N - 1 =28
N - 2 =27
Q Z= (Z - mean
SN Year Remarks
Max Log Q Z)3
1 1976 12.6 1.1 0.0
2 1977 20.4 1.3 0.0
3 1978 16.4 1.2 0.0
4 1979 14.7 1.1 0.0
5 1980 19.9 1.2 0.0
6 1981 24.7 1.3 0.0
7 1982 16.7 1.2 0.0
8 1983 24.5 1.3 0.0
9 1984 20.1 1.3 0.0
10 1985 15.1 1.1 0.0
11 1986 18.7 1.2 0.0
12 1987 22.4 1.3 0.0
13 1988 21.2 1.3 0.0
14 1989 24.7 1.3 0.0
15 1990 14.3 1.1 0.0
16 1991 15.2 1.1 0.0
17 1992 13.6 1.1 0.0
Mean z =
18 1993 18.6 1.2 0.0 1.246m
19 1994 13.2 1.1 0.0
20 1995 18.6 1.2 0.0 standard deviation = sd =
21 1996 54.5 1.7 0.1 0.150
22 1997 16.1 1.2 0.0
23 1998 25.7 1.4 0.0 Cs =
24 1999 15.9 1.2 0.0 N∑(Z-meanZ)3/(N-1)(N-2)(sd)3 =
25 2000 16.1 1.2 0.0 0.807
26 2001 10.6 1.1 0.0
27 2002 12.5 1.1 0.0
~ 75 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
28 2003 7.9 0.9 0.1
29 2004 19.1 1.2 0.0
Average= 1.24 0.7
KZ from ZT =
Mean Z QT =
SN T(year) table function sd of Z mean Z +
(m) Antilog ZT
of cs sd*KZ
1 2 -0.2 1.2 16.8
2 10 1.3 1.4 27.9
3 25 2.0 1.5 35.1
4 50 2.4 1.24 0.15 1.6 41.0
5 100 2.9 1.6 47.7
6 200 3.3 1.7 55.2
7 1000 4.2 1.9 76.3
~ 76 ~
ANNEX-B
DESIGN
CALCULATION
Pre-feasibility Study of Daram Khola A-Hydropower Project
WEIR
Weir including Spillway
Flood Discharge (Q) = 365.17 m3/s
Return Period =100 yrs
From the inspection of topographic map
Width of river where headwork is going to construct =25m
Provide the length of weir portion, Le=21m
Provide 1 m wide divide wall
And, width of under sluice=3m
Here,
River bed level=1592.62masl
Take,
Crest level of weir=1597 masl
Height of the spillway from the river bed (P) = 4.38m
Weir coefficient, Cweir=2.2
We have,
Discharge through the weir,= Q Cweir Le H e
3/ 2
Where,
He =Total head on the crest
Including velocity of approach
Solving above equation we get,
He=3.42m
Trial (I)
Q
Velocity of Approach, = Va
Le P ho
Va=1.78 m/s
2
Velocity Head = Va m/s
2 g
=0.16m/s
ho =3.25m
~ 77 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Trial (II),
Velocity of Approach,
Va =1.82 m/s 2
Va
Velocity Head = 2 g m/s
=0.16
ho=3.25m
Trial (III) Q
Va
Velocity of Approach, Le P ho
Va=1.82 m/s
2
V
Velocity Head = a
2 g
=0.16m/s
ho =3.25m
Hd =3.25m
So,
Ratio of Dam height to head over weir (P/Hd)=1.35 >1.33 OK
Le L 2 N K p K a H e
Again,
Effective Length of the Spillway=
Assuming, 90 degree cut water nose piers and rounded abutments shall be provided,
Then,
KP=0.01 and
Ka =0.1
Also, N=1
Le=20.25m
Take 20 m
Downstream Profile,
~ 78 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
( n 1)
xn K H d y
Then
X Y
0 0.00
0.5 -0.05
1 -0.18
1.5 -0.38
2 -0.66
2.5 -1.00
3 -1.40
3.5 -1.86
4 -2.38
4.63 -3.13
Beyond the point of tangency profile will be of straight line in slope of d/s
Upstream profile
~ 79 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Upstream profile
R1=0.5HD 1.62
R2=0.2HD = 0.65
a=0.175HD = 0.56
b=0.282HD = 0.91
Also, according to latest studies of US Army Corps, the U/S curve of the ogee spillway having a
vertical U/S face should have the following equation:
y 0.724
x 0.27 H d
1.85
0.126 H 0.4315 H d
0.375
x 0.27 H d 0.6250
0.85 d
Hd
The values of the coordinates y are determined below for different values of x upto maximum
value of x/Hd=-0.27 or x=-0.87 and y/Hd=0.12 or y=0.40
X x/Hd y
Energy dissipation
Hydraulic jump
~ 80 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 81 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
= 24.28 m
Pondage depth (Hd) =Y1 (9+F)/9
=1.74 m
Iteration due to change in (EO ) =9.37 m
EO Y1 Ψ V1 F Y2 Hd
9.37 1.15 0.96 12.20 3.63 5.37 1.61
9.24 1.14 0.95 12.07 3.59 5.29 1.60
9.23 1.15 0.95 12.06 3.58 5.30 1.61
9.24 1.15 0.95 12.06 3.58 5.30 1.61
9.24 1.15 0.95 12.06 3.58 5.30 1.61
Hence,
Y2=5.30 m
Pondage depth (Hd) = 1.61 m
Length of the sttiling basin (Lw) =5*(Y2-Y1)
=20.75 m
Height of dam from its crest to bed of stilling basin =P+Hd
=6.00 m
~ 82 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Calculation of Thickness
Assuming particle size (d) =3 mm
So, silt factor (f) =1.75*√ (dmm)
= 3.03
Depth of Scour (R)=1.35*(q^2/f) ^ (1/3)
= 5.39 m
~ 83 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 84 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Stability Analysis
Weight of weir
Unit weight of concrete= 24 KN/m3
~ 85 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Calculation of forces
Unit weight of concrete =24 KN/m3
Unit weight of water =10 KN/m3
Unit weight of silt =18 KN/m3
Assuming depth of silt deposit =0.5
S. Name of Horizont Lever Counter
N. Force Area al Vertical Arm Moment clockwise clockwise
weir with
1 stilling basin 70.0 1463.8 19.0 27861.9 27861.9
hydrostatic
2 pressure
Ph1 142.3 2.1 311.7 311.7
Ph2 95.9 1.46 140.0 140.0
4 uplift 95.9 20.6 1984.5 1984.3
5 silt 2.25 0.1667 0.3 0.3
Sum 240.5 1559.7 27861.9 2436.6
Resultant moment =25425.24KN
Check for sliding:
Fs=µV/H
=4.50>1.5
Check for overturning:
FO =resisting moment /overturning moment
=11.40>1.5 OK
Check for tension at heals:
X =M/V
=16.30m
Width = 31.00m
Eccentricity (e) = B/2-X
=-0.74 m
B/6=5.17m
=e<B/6 OK
~ 86 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Principal stress
Minimum Stress =sum (v)/B (1+ (6e/B))
=42.63 KN/m2
< 200KN/m2
Exit Gradient Check:
Maximum seepage Head =4.38 m
Depth of d/s cut off (d) = 3m
Total floor length (b =31.00 m
α =10.34
λ =5.696
Ge =0.19
=1 in 5.58
Since Ge is within 1in5 to 1in7 so OK
~ 87 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
UNDERSLUICE
Design of Undersluice
Head over crest (Hd) =3.25 m
Discharge through Orifice (QO) =4.77 m3/s
So,
Discharge through undersluice=20% of Q₁₀₀-Qo
=68.26 m3/s
Provide one bay having
Width (b) =3 m
Sluice Height (h) =4.5 m
Now from manning’s formula,
Discharge through Under sluice (Qu) =1/n*A*R^ (2/3)*S^0.5
Take n=0.015
S=1in25
= 0.04
So,
Qu=194.704 m3/s
>68.26 OK
Here, velocity=14.42 m/s
~ 88 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
INTAKE
~ 89 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Now,
Head Loss through trash rack (Hf) =Kt *(t/b) ^ (4/3)
*sin α*(v^2/(2*9.81)
=0.01m
Net area (A') =3.95m2
(A'/A) =0.91
Loss coefficient at the gate (Kt) =1.67
Approach velocity (v) =1.1 m/s
Angle (α) =75 degree
T =0.01m
Total width of intake =5.54m
Depth of intake =1m
Velocity of water =1.1m/s
Entry loss at intake (ce) =0.03 m
Total head loss =0.04m
~ 90 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
GRAVEL TRAP
Design of gravel trap
Design discharge through orifice =4.77m3/s
Size of particle to be settle =2 mm
S =2.65
Efficiency =90%
=0.9
For particle greater than 1mm
Settling velocity (w) = (3.33*g*d*(S-1))^0.5
=0.33m/s
From camps eqn
Critical Velocity (Vc) =0.55*√dmm
=0.77m/s
For settling surface area,
From Vetter's eqn
Efficiency =1-e^ (-wAp/Q)
Falling velocity of particle (w) =0.32m/s
Solving above equation, we get
AP =33.47m2
Adopt width of gravel trap (B) =5 m
Length (L) =Ap/B
=6.69
Increase length by 10%, L =7.23
=7.20m
Q =A*Vcrit
y =1.22 take 1.2m
Let Sludge Depth =0.2m
Freeboard =0.2m
Overall Depth =1.6m
Iteration I
Ap =36 m2
~ 91 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 92 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 93 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 94 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
SETTLING BASIN
We have
Vf after Temperature correction,
Vf =416*(S-1)*d^2*(3*t+70)/100
Vf =27.45 mm/sec
Re =(Vf*d)/µ
= 4.19
Cd = (24/Re+3/√(Re)+0.34)
=7.53
Vf = 0.02m/s
=23.94 mm/sec
Vf Re Cd Vf
23.94 3.65 8.47 22.56
22.56 3.44 8.92 21.99
21.99 3.35 9.12 21.75
21.75 3.32 9.21 21.64
21.64 3.30 9.25 21.59
21.59 3.29 9.27 21.57
21.57 3.29 9.27 21.56
Dimension
~ 96 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Check
L/b =8.10
Which lies in between 6-10 hence safe
Now, velocity of water flow in basin (V) = 0.12m/s
Transition design
Width of approach canal =2
Provide entrance angle =12°
Length of inlet Transition (L) = 9.41 m take 10 m
Storage Volume
Sediment concentration, (c) = 8000ppm
= 8 kg/m3
Sediment density, (Sd) = 2650 kg/m3
Flushing Interval = 6 hrs
Sediment Load =Q*t*c
=761381 kg
Volume of storage, (V) = (Sload/Sden)*Pfactor
= 574.63 m3
Pfactor =2
Depth of storage, Ystorage = (V/area)
= 1.36 m
Free board = 0.8 m
Required depth of basin =Freeboard+height of
settling basing+Ystorage
=7.1 m
Design of Flushing canal
~ 98 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 99 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
FORBAY
Design of forbay
Discharge passing through forbay (Q) = 3.67m3/s
Assume, mean velocity in forbay (V) = 0.15m/s
Assume storage time (t) = 1 min
= 60 sec
Storage volume required (Vo) = Q*t
=220.31 m3
Assuming width of forebay(b) =7.4 m
Depth of forebay needed (d) = Q/(V*b)
= 3.30 m
Provide depth of 5.5 m
Length of Forbey ( l )
Then,
l*b*d =Vo
l = 5.41 m
Provide length of 5.6 m
Design of contraction
Width of headrace canal =2.8 m
Provide entrance angle = 45°
Length of outlet Transition (L) = 2.3 m
~ 100 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 101 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
SUBMERGENCE
Design Discharge = 3.67 m3/s
Pipe Parameters
S kv d
S= submergence
v= velocity of flow at intake = 1.77 m/sec
d= height of intake (ft.) = 1.3 m
k= coefficient 0.3 for symmetrical approach = 0.3
0.4 for unsymmetrical approach
Submergence (S) = 0.95 m
Prosser (1977)
S 1.5d
ITDG Manual
v2
S 1.5
2g
~ 102 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 103 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 104 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Due to expansion
H˪ =k(v1^2-v2^2)/(2*g)
Where,
V1 =Velocity at outlet of canal
V2 =velocity at the basin
Take k =0.40
so,
HL =0.01 m
HL =Q^2*L/(A^2*C^2*R)
Where,
A =Cross sectional area
=34.45 m2
~ 105 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
P =Wetted perimeter
=16.84 m
R =Hydraulic radius
=2.04 m
C =(R^(1/6)/n)
=75.11
n =0.015
So,
HL =0.00 m
HL =Q^2*L/(A^2*C^2*R)
Where,
A =Cross sectional area
2
=40.7 m
P =Wetted perimeter
=18.4 m
R =Hydraulic radius
= 2.21 m
C =(R^(1/6)/n)
=76.09
n =0.015
So,
HL =0.00 m
Hcont =k(v^2/(2*g))
~ 106 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
k =0.50
=0.00 m
=0.00 m
Total loss in settling basin =0.01
Kirchmer's formula
Htr = Kt*(t/b)4/3 * (Vo2/2g)*sinф
= 0.00
Where,
Htr =headloss through trashrack
Thickness of rack bar, t = 0.01
Spacing between bars, b =0.02
Velocity of flow infront of Trashrack =0.12 m/s
Angle of bars with the horizontal (β) =75°
Kt =factors depending on the
cross section of the bar
=1.67
~ 107 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Hbend =kv^2/2g
= 0.19 m
Total pressure pipe loss = 8.17 m
Net head before surge tank = 82.72 m
Head loss in penstock:
L = 10.97 m
f = 0.016
v = 2.77 m/sec
d =1m
Head loss due to friction (hf) = fLV^2/2gd
= 0.06 m
Total head loss =8.68 m
~ 108 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 109 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
BIFURCATION
Design Discharge
Q =3.67 m3/s
After bifurcation design in each pipe =1.83 m3/s
Velocity (V) = 2.77 m/s
Velocity in pipe remains same
Area
A =Q/V
=0.66 m2
Internal diameter of pipe (d) =1m
Calculation of thickness
S =1020 kgf/cm2
Efficiency =85%
Head (H) =82.65 m
γ =1000.00 kgf/m3
Total pressure in pipe (P) = γ*H
2
=82652 kgf/m
Internal radius of pipe =0.50 m
=50.00 cm
t =((P*R)/(S*η+0.6*P)+0.15
t =0.19 cm
=19.76 mm
Take
t =20 mm
~ 110 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
TURBINE
Design of Francis Turbine
Calculation of specific speed(Ns):
Number of turbine =2
Discharge (Q) =1.83m3/s
Net head available (H) =82.65 m
Efficiency =85%
Power (P) =1265.28kw
=1698.36Hp
For Francis turbine,
Ns =2400/(H)^0.5
So,Ns =264rpm
From equation of the specific speed ,(N) =Ns*(H)^(5/4)/P^(0.5)
N =1160rpm
Number of poles, (n) =120f/N
N =3.7
Take Number of poles,(n) =6
Now, corrected runner speed, (N) =1000rpm
So, corrected specific speed, (Ns) =165rpm
Calculation of Diameter of the turbine, (D)
Φ =0.0197Ns^(2/3)+0.0275
Φ = 0.62
Now diameter of the runner, D = 84.6*Φ*(H)^(0.5)/N
D = 0.47m
=0.5m
Ns = 143rpm in S.I.
Calculation of setting height, (Hs)
σc (cavitation coefficient) = 0.08
Hence Hs, =2.72 m
2.5 m is taken
~ 111 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
POWER HOUSE
Machine hall
Length of hall =5.5D+3
= 5.47 Adopt5.5m
Width of hall =2d+D
=6.45 Adopt6.5m
Height of hall(assume) =2.5m
Loading bay
Length of bay =6.45m
Width of bay =4m
Control bay
Length of bay =5m
Width of bay =3.5m
Workshop annexes
Length of workshop =4m
Width of workshop =4m
~ 113 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
TAILRACE
After Merging
Number of tailrace canal after merging =1
Design discharge, (Qd) = 3.67 m3/s
Longitudinal slope = 1:2000
~ 114 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 115 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
GrossThk
teff 2.5
Effective Thickness = 1.1*1.2
Subtraction of 2.5mm is consideration of corrosion
effect for 25yr life period
(Refer: MH Design Manual ITDG, Pg 95)
200 * teff * S
Factor of Safety = SF
H tot * d
(Refer: MH Design Manual ITDG, Pg 95)
Surge Head = 0.33 x Static Head
Water Hammer =33 % of static head
~ 116 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Static head=5.93m
Length of penstock= 14.50m
~ 117 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 118 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 119 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 120 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 121 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 122 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 123 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 124 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 125 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 126 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 127 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Penstock flow velocity,V m/s 5.77 4.68 3.86 3.25 2.77 2.39 2.08 1.83
Gross thickness, mm 8 10 10 10 10 12 12 12
Effective thickness, teff mm 3.56 5.08 5.08 5.08 5.08 6.59 6.59 6.59
Surge Head, Hs m 24.98 24.98 24.98 24.98 24.98 24.98 24.98 24.98
Total Head, Htot m 100.7 100.7 100.7 100.7 100.7 100.7 100.7 100.7
Factor of safety 3.2 4.1 3.8 3.4 3.2 3.8 3.6 3.4
Check OK OK OK OK OK OK OK OK
Weight of steel, ton 16.3 23 25 27 29 38 41 43
~ 128 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 129 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 130 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 131 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Optimization of Pipe
Project life period =25yr
Discount rate =12%
Capital recovery factor =0.127
Dry season energy rate =8.4Nrs/Kwh
Wet season energy rate =4.8Nrs/Kwh
Design discharge, Qd =3.67 m3/s
Roughness value k =0.15mmFor Galvanised
Mild Steel
Length of penstock pipe =1730m
Overall efficiency of the system =85%
Dry season outage =5%
Wet season outage =10%
Headloss in pipe
fLv 2 fLQ 2
From Darcy's equation = HL
2 gD 12 D5
9.81fL 3
C 5
Q cons tan t * Q 3
Loss in capacity (kW) = 12D
Diameter ,mm 900 1000 1100 1200 1300 1400 1500 1600
k/d 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001
Friction factor, f 0.013 0.012 0.012 0.012 0.012 0.012 0.011 0.0112
~ 132 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Constantcorresponding
to Qd 26.94 15.58 9.49 6.04 3.99 2.71 1.90 1.36
MaximumCapacity
loss, Cmax 1333.71 771.22 469.97 299.06 197.34 134.31 93.88 67.16
~ 133 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
SADDLE DESIGN
Materials
Unit weight (γ), angle of friction (ø) and allowable bearing pressure for
different soil types
Soil
Allowabl
Unit Friction e
S.
the
Soil Type Weight, γ Angle, Bearing
No.
(kN/m3) ø° Pressure
Choose
Type
(kN/m2)
Firm clays and firm sandy
1
clays 17 25 100
Stiff clays and stiff sandy
2
clays 20 30 200
3 Very stiff boulder clays 20 32 350
4 Weathered Rock 23 33 350
5 Stiff Rock 25 35 400 2
Physical Characteristics of Common Materials
Material
Ultimat
Coefficien
Young's e Unit
t of
S. Modulu Tensile Weight
Material Linear
No. s (E) Strengt (γ) the
Expansio
N/mm2 h (S) kN/m2
Choose
n (α1) /°C
Type
N/mm2
2.00E+0
1 Steel (ungraded) 5 1.25E-05 320 77
Steel to IS 226/75 or IS 2.00E+0
2 2062/84 5 1.25E-05 410 77
3 PVC 2750 3.00E-05 45.00 14
4 HDPE 1000 1.50E-04 30.00 9.3 1
~ 134 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
If the steel quality is uncertain it is best to ask for samples and have them independently tested
at laboratories. Properties of PVC and HDPE vary considerably; they should be confirmed from
manufactures' catalogues or by laboratory tests.
Friction Coefficient (f), Depends on the Material against which the
penstock slides
Choos
1 Steel on Concrete 0.6 e Type
2 Steel on Steel, Rusry Plates 0.5
3 Steel on Steel, greased plates or tar paper in between 0.25 1
Design Inputs
Penstock Details
Penstock inclination in Degree, α° 4.00
Internal Diameter of Penstock, d in mm 1,300.00
Penstock pipe thickness, t in mm 8.00
Distance to upstream support pier, (m) 6.00
Distance to downstream support pier, (m) 6.00
Distance to upstream expansion joint, L4u (m) 0.00
Distance to downstream expansion joint, L4d (m) 0.00
Coeff. Of friction between pipe & support piers, f 0.60
Number of Piers at Upstream 0.00
Number of Piers at Downstream 0.00
Uphill ground slope in Degree, i° 5.00
Unit weight of soil, γsoil (kN/m3) 20.00
Friction Angle in Degree, ø° 30.00
Allowable Bearing Pressure, (kN/m2) 200.00
Coefficient of Limiting Friction at Base of Block, µ 0.50
Unit weight of concrete, γconcrete (kN/m3) 22.00
Unit weight of pipe material, γpipe material (kN/m3) 77.00
Unit weight of water, γwater (kN/m3) 9.81
~ 135 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 136 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Resolution of Forces
Forces (kN) X- Component (kN), → '+' Y- Component (kN), ↓ '+'
F1u 46.54 -3.25 46.43
F1d 46.54 -3.25 46.43
F2u 27.93 27.86 1.95
F2d 27.93 27.86 1.95
F10 0.00 0.00 0.00
WB 1,364.63 0.00 1,364.63
Expansion Case -6.49 1,457.49
SUM
Contraction Case -6.49 1,457.49
Calculation for Acting Forces at the centreline of Penstock
~ 137 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 138 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Expansion Case
(µ x Σ V)/(ΣH) 112.23 4.63
Allowable FOS for Sliding Stability =1.20 Ok Ok
Contraction Case
(µ x Σ V)/(ΣH) 112.23 4.63
Allowable FOS for Sliding Stability =1.20 Ok Ok
~ 139 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Unit weight (γ), angle of friction (ø) and allowable bearing pressure for different
soil types
Allowable
S. Unit Weight, γ Friction Bearing
Soil Type
N. (kN/m3) Angle, ø° Pressure
(kN/m2)
Friction Coefficient, f, Depends on the material against which the penstock slides
~ 140 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Penstock Details:
Horizontal bend angle of Penstock in degree, θ˚ 35
Upstream penstock inclination in Degree, α° 8
Downstream penstock inclination in Degree, β° 23
Internal Diameter of Penstock, d in mm 1300
Is there change in Diameter of Penstock, Put 'Y' or 'N' N
If Yes, then Changes Diameter of Penstock is, in mm 0
Change Internal Diameter of Penstock, dchange in mm 1300
Penstock pipe thickness, t in mm 8
Distance to upstream support pier, (m) 6
Distance to downstream support pier, (m) 6
Distance to upstream expansion joint, L4u (m) 37.59
Distance to downstream expansion joint, L4d (m) 0
Coeff. Of friction between pipe & support piers, f 0.25
~ 141 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Materials Properties
Uphill ground slope in Degree, i° 14
3
Unit weight of soil, γsoil (kN/m ) 20
~ 142 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 143 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Resolution of Forces
X- Component Y- Component (kN),
Forces (kN) (kN), → '+' ↓ '+'
F1u 75.97 -10.57 45.75
F1d 70.62 -27.59 39.53
F2u 303.88 300.92 9.65
~ 144 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 145 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 146 ~
ANNEX-C
ENERGY
CALCULATION
Pre-feasibility Study of Daram Khola A-Hydropower Project
ENERGY CALCULATION
~ 147 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 148 ~
ANNEX-D
COST
ESTIMATE
Pre-feasibility Study of Daram Khola A-Hydropower Project
Item no.1: Soft rock excavation including 1.5m lift and disposal including Unit: 1
lead up to 10m. m3
A Manpower
. md
Unskilled md 1.00 350.00 350.00
Sub Total
C Tools and Plants
3% of A 10.50
Sub Total 10.50
D Sub Total of (A+B+C) 360.50
E Overhead and Profit (15% of D) 54.08
F Sub Total of (D+E) 414.58
Rate per Unit 414.58
Item no.2: Medium rock excavation including 1.5m lift and disposal Unit: 1
including lead up to 10 m. m3
A Manpower
Skilled md
Unskilled md 2.50 350.00 875.00
~ 149 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Sub Total
C Tools and Plants
3% of A 26.25
Sub Total
C Tools and Plants
3% of A 44.10
~ 150 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
Overhead and Profit (15% of
E D) 227.12
F Sub Total of (D+E) 1,741.22
Rate per Unit 1,741.22
Item no.4: Earth filling with compaction in 15 cm thick layer with ordinary Unit: 1
excavated soil With sprinkling water including lead up to 10m. m3
A Manpower
Skilled md
Unskilled md 0.50 350.00 175.00
Sub Total
C Tools and Plants
3% of A 5.25
~ 151 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
Item no.5: Boulder lining with 1.5m size river boulders Unit: 1 m3
A Manpower
Skilled md 1 450.00 450.00
Unskilled md 4.40 350.00 1,540.00
~ 152 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
B Materials
Cement bags 6.643 845.00 5613.21
Add 55% for
Sand m3 0.443 1500.00 664.29
dry volume
Aggregates m3 0.886 1500.00 1328.57
Sub Total 7606.07
C Tools and Plants
3% of A 88.50
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
A Manpower
Skilled md 1.5 450.00 675.00
Unskilled md 6.50 350.00 2,275.00
Sub Total 2,950.00
B Materials
Cement bags 8.455 845.00 7144.48
Add 55% for
Sand m3 0.423 1500.00 634.50
dry volume
Aggregates m3 0.845 1500.00 1267.50
Sub Total 9046.48
~ 153 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
~ 154 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
Item no.9: Reinforcement Works including laying,cutting and bending Unit: 1 Ton
A Manpower
Skilled md 12 450.00 5400.00
Unskilled md 12 350.00 4,200.00
~ 155 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
~ 156 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
Item no.12: Random rubble masonry with 1:4 cement sand mortar Unit: 1 m3
A Manpower
Skilled md 1.2 450.00 540.00
Unskilled md 4.00 350.00 1400.00
Sub Total 1,940.00
~ 157 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
S. Rate Amount
Description Unit Quantity Remarks
N. (NRs/Unit) (NRs)
B Materials
Cement Bags 2.5 845.00 2112.50
Sand m3 0.44 1500.00 660.00
Block Stone m3 1 700.00 700.00
Bond Stone m3 0.1 700.00 70.00
Sub Total 3542.50
C Tools and Plants
3% of A 58.20
~ 158 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Basic Rates
B Material Rate
1 Cement Bag 845.00
Free from all kinds of
2 Sand m3 1500.00 impurities mentioned
in Specification
3
3 Graded filter material m 1200.00
4 Aggregates m3 1500.00
5 Stone m3 700.00
6 Reinforcement bars kg 85.00 10-20 mm ToR Steel
Reinforcement-
7 kg 100.00
Binding Wire
~ 159 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Measurement Sheet
Avg.
S.N. Description Unit No L B H A Area Quantity Remarks
Weir And Stilling
1 Basin
Earth work in
1.1 excavation Cu.m 1 21.0 165.24 3470.10
1.2 PCC (C25) Cu.m 1 21.0 55.45 1164.41
1.3 plumb concrete Cu.m 1 21.0 5.54 116.42
Boulder (launching
1.4 appron) Cu.m 1
1.4.1 U/s Cu.m 1 21.0 11.00 231.00
1.4.2 D/s Cu.m 1 21.0 21.00 441.00
2 undersluice
Earth work in
2.1 excavation Cu.m. 1 5.5 165.24 908.84
2.2 PCC (C25) Cu.m 1 3.0 18.18 54.54
2.3 Boulder Cu.m
2.3.1 U/s Cu.m 1 3.0 10.00 30.00
2.3.2 D/s Cu.m 1 3.0 24.00 72.00
hard stone lining
2.4 (40cm) Cu.m. 1 3.0 7.02 21.07
2.5 Steel gate kg 1 1400.0 1400.00
3 Intake
Earth work in
3.1 excavation Cu.m. 1 4.2 6.73 28.20
~ 160 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Avg.
S.N. Description Unit No L B H A Area Quantity Remarks
3.2 PCC (C25) Cu.m 1 14.23
3.3 Steel gate kg 2 300.00 600.00
3.4 Trash rack kg 2 40.00 80.00
5 Approach canal
Earth work in
5.1 excavation 30.19
Cu.m. 1 23.3 26.49 28.34 658.91
~ 161 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Avg.
S.N. Description Unit No L B H A Area Quantity Remarks
5.2 PCC(C25)
5.2.1 box culvert Cu.m. 1 13.3 2.76 36.57
open channel with
5.2.2 spillway Cu.m. 1 10.0 6.46 64.64
C10 binding
5.3 concrete Cu.m. 1 23.3 0.20 4.53
6 Settling Basin
Earth work in
6.1 excavation 18.75
Cu.m. 1 60.0 22.22 20.48 1228.92
6.2 PCC(C25) 18.75
Cu.m. 1 60.0 22.22 20.48 1228.92
6.3 Stone masonry Cu.m. 1 60.0 4.98 298.80
C10 binding
concrete Cu.m. 1 60.0 0.68 40.80
6.4 Steel gate
6.4.1 At starting kg 2 500.00 1000.00
6.4.2 At Flushing canal kg 1 200.00 200.00
7 Forebay
Earth work in
7.1 excavation Cu.m. 1 5.6 51.84 290.30
7.2 PCC(C25) Cu.m. 1 5.6 16.57 92.81
7.3 Steel gate
7.3.1 For penstock kg 1 300.00 300.00
7.3.2 For flushing canal kg 1 200.00 200.00
7.4 Trash rack kg 1 50.00 50.00
~ 162 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Avg.
S.N. Description Unit No L B H A Area Quantity Remarks
8 Penstock
8.1 E/W in excavation
Ch 0+ 33.7494 0.00
Ch 0+ 40 Cu.m. 1 6.3 57.34 28.67 179.21
Ch 0+ 49.6179 Cu.m. 1 9.6 0.00 28.67 275.75
Ch 0+ 71.5862 0.00
Ch 0+ 80 Cu.m. 1 8.4 13.10 6.55 55.11
Ch 0+ 100 Cu.m. 1 20.0 3.35 8.23 164.52
Ch 0+ 109.11 Cu.m. 1 9.1 0.00 1.68 15.27
Ch 0+ 132.3963 0.00
Ch 0+ 140 Cu.m. 1 7.6 58.34 29.17 221.82
Ch 0+ 160 Cu.m. 1 20.0 56.19 57.27 1145.34
Ch 0+ 180 Cu.m. 1 20.0 48.35 52.27 1045.40
Ch 0+ 200 Cu.m. 1 20.0 8.26 28.30 566.09
Ch 0+ 220 Cu.m. 1 20.0 3.66 5.96 119.15
Ch 0+ 240 Cu.m. 1 20.0 10.11 6.88 137.67
Ch 0+ 260 Cu.m. 1 20.0 17.84 13.98 279.51
Ch 0+ 280 Cu.m. 1 20.0 47.21 32.53 650.51
Ch 0+ 300 Cu.m. 1 20.0 40.87 44.04 880.78
Ch 0+ 320 Cu.m. 1 20.0 0.31 20.59 411.77
Ch 0+ 340 Cu.m. 1 20.0 0.76 0.53 10.68
Ch 0 360 Cu.m. 1 20.0 6.30 3.53 70.54
Ch 0+ 380 Cu.m. 1 20.0 18.30 12.30 245.98
Ch 0+ 400 Cu.m. 1 20.0 365.59 191.94 3838.89
Ch 0+ 420 Cu.m. 1 20.0 11.48 188.53 3770.66
Ch 0+ 440 Cu.m. 1 20.0 6.17 8.83 176.51
Ch 0+ 443.2523 Cu.m. 1 3.3 0.00 3.09 10.03
Ch 0+ 473.25 0.00
~ 163 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Avg.
S.N. Description Unit No L B H A Area Quantity Remarks
Ch 0+ 480 Cu.m. 1 6.8 24.57 12.28 82.92
Ch 0+ 489.22 Cu.m. 1 9.2 0.00 12.28 113.26
Ch 0+ 508.364 0.00
Ch 0+ 520 Cu.m. 1 11.6 10.06 5.03 58.52
Ch 0+ 540 Cu.m. 1 20.0 17.24 13.65 273.01
Ch 0+ 560 Cu.m. 1 20.0 6.70 11.97 239.40
Ch 0+ 580 Cu.m. 1 20.0 12.41 9.55 191.04
Ch 0+ 600 Cu.m. 1 20.0 35.62 24.01 480.26
Ch 0+ 609.7696 Cu.m. 1 9.8 0.00 17.81 174.00
Ch 0+ 755.68 0.00
Ch 0+ 760 Cu.m. 1 4.3 1.12 0.56 2.42
Ch 0+ 764.234 Cu.m. 1 4.2 0.00 0.56 2.37
Ch 0+ 796.24 Cu.m. 0.00
Ch 0+ 800 Cu.m. 1 3.8 1.63 0.82 3.07
Ch 0+ 802.24 Cu.m. 1 2.2 0.00 0.82 1.83
Ch 0 919.24 0.00
Ch 0 920 Cu.m. 1 0.8 0.20 0.10 0.08
Ch 1+ 40 Cu.m. 1 20.0 0.73 0.47 9.36
Ch 1+ 60 Cu.m. 1 20.0 3.25 1.99 39.79
Ch 1+ 80 Cu.m. 1 20.0 38.54 20.89 417.83
Ch 1+ 100 Cu.m. 1 20.0 81.13 59.83 1196.63
Ch 1+ 120 Cu.m. 1 20.0 18.84 49.99 999.71
Ch 1+ 140 Cu.m. 1 20.0 15.40 17.12 342.44
Ch 1+ 160 Cu.m. 1 20.0 19.35 17.37 347.48
Ch 1+ 180 Cu.m. 1 20.0 36.48 27.92 558.31
Ch 1+ 200 Cu.m. 1 20.0 9.43 22.96 459.19
Ch 1+ 220 Cu.m. 1 20.0 12.24 10.84 216.79
Ch 1+ 240 Cu.m. 1 20.0 14.55 13.40 267.93
~ 164 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 165 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
ESTIMATION OF COST
S.n. Description of Work Quantity Unit Rate(NRs.) Total Cost(NRs.)
Weir and stilling pool
1 Site Clearance Lump Sum 1000000 1000000
2 Excavation
Soft rock 2949.58 m3 414.58 1222825.25
Medium rock 347.01 m3 1,036.44 359654.48
Hard rock 173.50 m3 1,741.22 302109.76
3 P.C.C 1164.41 m3 13,897.72 16182617.81
4 Reinforcement (1%of PCC) 91.41 Ton 115,158.70 10526199.36
5 Plumb concrete 116.42 6,378.66 742576.08
~ 166 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 167 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 168 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
~ 169 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
Rate Total
Description of Work Quantity Unit (NRs.) Cost(NRs.)
Power House
Door,Windows,Ventilation,Painting,
Large shutter, Lumpsum 500000
Plaster and Floor
Finishing,excavation and soling
P.C.C
Diversion Work Lumpsum 700000
River Training Works Lumpsum 1200000
~ 170 ~
ANNEX-E
FINANCIAL
ANALYSIS
Pre-feasibility Study of Daram Khola A-Hydropower Project
FINANCIAL ANALYSIS
~ 171 ~
Pre-feasibility Study of Daram Khola A-Hydropower Project
B) IRR method
We have,
(B-O&M)*(P/A,I%,n)-I =0
(B-O&M)*((1+i)n-1)/(i(i+1)n)-P =0
Hence, by Iteration we determine the value of IRR =16.21%
~ 172 ~
ANNEX F
DRAWINGS