Inspection Plan
Inspection
Check List and / Responsibility
Item No. Project Phase Task Activity Quality Record Risk Level Assignments Remarks
or Test Record
Cont Aramco
RECEIVING
2.0
INSPECTION
2.4 Copper Communications Cable On Reel Acceptance Testing See Remarks See Remarks H H
3.0 INSTALLATION
3.2 Cable Pulling Visual Inspection OSP Cable Pulling SAIC-T-5507 SAIC-T-5507 H H
3.3 Cable Pulling Visual Inspection ISP Cable Pulling SAIC-T-5508 SAIC-T-5508 H H
4.0 PRE-COMMISSIONING
4.2 Cable Termination Stab (wire pull-out) or Torque Testing SAIC-T-5507 SAIC-T-5507 H W