PROJECT : PRPOSED INDUSTRIAL BUILDING (G+1) OF MR. ASHOK JAIN, MR. VIKASH JAIN & MR. TARA JAIN AT PLOT NO. 41A BRAHMAPUTRA INDUSTRIAL ESTATE, AMINGAON, DIST- KAMRUP, ASSAM.

Achivement
Sl Balance as on
Description of Work Unit Quantity as on Start Date Finish Date April May June July August September
No. 16.04.2019
16.04.2019 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4
1 Earth work in excavation Cum 3240.00 3105.00 135.00 Completed 28.02.2019
Filling available excavated earth (excluding rock) in
2 Cum 2110.00 1850.00 260.00 In Progress 19.04.2019
trenches, plinth, sides of foundations etc.
Providing and laying in position cement concrete of
3 Cum 361.47 322.56 38.91 In Progress 24.04.2019
specified grade - All work up to plinth level :
Providing and laying in position specified grade of
4 Cum 806.00 715.00 91.00 In Progress 28.04.2019
reinforced cement concrete, - All work up to plinth level :
Reinforced cement concrete work in walls, including
attached pilasters, buttresses, plinth and string courses,
5 Cum 155.00 103.76 51.24
fillets, columns, pillars, piers, abutments, posts and struts
etc. above plinth level up to floor five level:
a) In Column (upto plinth)-Pedestal Cum 43.33 43.33 Nil Completed 22.12.2018
b) In Column (upto plinth) Cum 40.93 40.93 Nil Completed 24.01.2019
c) In Ground Floor Column Cum 75.40 19.50 55.90 In Progress 28.04.2019
d) In First Floor Column Cum 1.86 Not Started 1.86 01.05.2019 08.05.2019
e) In Mezanine Floor Column Cum 2.21 Not Started 2.21 15.05.2019 30.05.2019
f) Wall Stiffner Cum 201.74 Not Started 201.74 01.05.2019 15.06.2019
Beams, suspended floors, roofs having slope up to 15°
landings, balconies, shelves, chajjas, lintels, bands, plain
6 Cum 857.40 162.63 694.77 In Progress 03.06.2019
window sills, staircases and spiral stair cases above plinth
level up to floor five level.
a) Plinth Beam Cum 124.81 124.81 Nil Completed 26.01.2019
b) Grade Beam Cum 145.32 138.88 6.44 In Progress 21.04.2019
c) Staircase Cum 78.93 12.5 66.43 In Progress 30.04.2019
d) Liftpit & Lift Cum 183.26 25.32 157.94 In Progress 30.04.2019
e) Lintel Beam
i) Ground Floor Cum 3.44 Not Started 3.44 21.04.2019 23.04.2019
ii) First Floor Cum 0.56 Not Started 0.56 07.05.2019 16.05.2019
iii) Mezanine Floor Cum 0.91 Not Started 0.91 01.05.2019 08.05.2019
iv) Cooling Tower Cum 9.73 Not Started 9.73 08.06.2019 15.06.2019
f) First Floor Beam Cum 147.88 Not Started 147.88 01.04.2019 30.04.2019
g) Mezzanine Floor Beam Cum 19.94 Not Started 19.94 07.05.2019 31.05.2019
Reinforcement with HYSD bars for RCC work including
7 straightening cutting bending placing in position and Kg 234889.00 59668.72 175220.28 In Progress 07.05.2019
binding all complete.
a) In Foundation Kg 79150.54 26674.23 52476.31 In Progress 26.04.2019
b) In Column Kg 37146.36 22585.36 14561.00 In Progress 30.04.2019
c) In Beams Kg 54449.81 18569.33 35880.48 In Progress 22.04.2019
d) In Slabs, Stairscases Kg 62829.31 1653.23 61176.08 In Progress 30.04.2019
BAR CHART
PROJECT : PRPOSED INDUSTRIAL BUILDING (G+1) OF MR. ASHOK JAIN, MR. VIKASH JAIN & MR. TARA JAIN AT PLOT NO. 41A BRAHMAPUTRA INDUSTRIAL ESTATE, AMINGAON, DIST- KAMRUP, ASSAM.

Achivement
Sl Balance as on
Description of Work Unit Quantity as on Start Date Finish Date April May June July August September
No. 16.04.2019
16.04.2019 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4
e) In Chajja, fins Kg 185.46 Not Started 185.46 15.04.2019 30.04.2019
f) Dowels in tremix flooring Kg 723.01 Not Started 723.01 08.06.2019 06.07.2019
Centering and shuttering including strutting, propping etc.
8
and removal of form work for :
(a) Foundations footings, bases of columns Sqm 850.32 850.32 Nil Completed 17.12.2018
(b)Retaining walls, return walls, walls (any thickness)
including attached pilasters,
Sqm 733.60 125.36 733.60 In Progress 27.04.2019
buttresses, plinth and string courses fillets, kerbs and
steps etc.
(c) Columns, pillars, piers, abutments, posts and struts. Sqm 1917.15 286.96 1630.19 In Progress 25.04.2019
(d) Lintels, beams, plinth beams, girders, bressumers and
Sqm 3237.75 1275.38 3237.75 In Progress 22.04.2019
cantilevers etc
(e) Suspended floors, roofs, landings shelves and their
Sqm 3513.59 Not Started 3513.59 08.02.2019 14.05.2019
support, balconies and chajjas, etc.
Brick work with modular calcium silicate bricks machine
moulded conforming to
9 IS:4139, class designation 10 average compressive Cum 290.02 Not Started 290.02 21.05.2019 22.06.2019
strength in super structure
above plinth level up to floor V level in :
Providing half brick masonry with common burnt clay
F.P.S. (non modular) bricks
of class designation 7.5 in cement mortar 1:3 (1 Cement : 3
10 coarse sand) in Sqm 1254.21 Not Started 1254.21 28.02.2019 14.05.2019
superstructure for closing cavity 5 to 7.5 cm wide in cavity
wall complete with 10
cm / 11.4 cm wide bitumen felt type 3 grade 1.
11 Pavers Block 80 mm thick Sqm 1700.00 Not Started 1700.00 01.07.2019 31.07.2019
12 Plain Cement Concrete 1:4:8 Cum 256.50 Not Started 256.50 23.06.2019 14.07.2019
13 50 mm thk. Tremix flooring (M20) Cum 219.00 Not Started 219.00 21.07.2019 14.08.2019
14 Vitrified Tiles in flooring Sqm 573.48 Not Started 573.48 15.07.2019 14.08.2019
15 Anti Skid Floor tile in toilet Sqm 88.29 Not Started 88.29 15.07.2019 22.07.2019
Coloured polished granite slab 20mm thick in skirting,
riser of steps, dado, vertical face of pedestal etc laid on
16 12mm (average) thick base of cement mortar 1:3 and Sqm 116.97 Not Started 116.97 23.07.2019 07.08.2019
jointed with white cement slurry including rubbing and
polishing complete
17 Epoxy Surfacing Sqm 1610.96 Not Started 1610.96 14.07.2019 15.08.2019
18 Cement Concrete Flooring Sqm 157.85 Not Started 157.85 14.07.2019 29.07.2019
19 Kota Stone / Metallic Flooring Sqm 440.67 Not Started 440.67 21.07.2019 07.08.2019
20 Flooring with liquid hardener Sqm 2237.85 Not Started 2237.85 02.08.2019 30.08.2019
21 Ceramic wall tiles Sqm 382.97 Not Started 382.97 22.06.2019 14.07.2019
BAR CHART
PROJECT : PRPOSED INDUSTRIAL BUILDING (G+1) OF MR. ASHOK JAIN, MR. VIKASH JAIN & MR. TARA JAIN AT PLOT NO. 41A BRAHMAPUTRA INDUSTRIAL ESTATE, AMINGAON, DIST- KAMRUP, ASSAM.

Achivement
Sl Balance as on
Description of Work Unit Quantity as on Start Date Finish Date April May June July August September
No. 16.04.2019
16.04.2019 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4
22 15 mm cement plaster 1 : 4 ( 1cement : 4 fine sand ) Sqm 1544.23 Not Started 1544.23 07.04.2019 30.04.2019
23 12 mm cement plaster 1 : 4 ( 1cement : 4 fine sand ) Sqm 10946.32 Not Started 10946.32 08.04.2019 08.06.2019
24 Neat cement punning Sqm 452.20 Not Started 452.20 01.05.2019 21.05.2019
Providing and applying wall putty of 2 mm thickness over
25 plastered surface to prepare the surface even and smooth Sqm 12490.55 Not Started 12490.55 22.05.2019 21.06.2019
inside and outside wall
26 Primer on prepared surface over putty Sqm 12490.55 Not Started 12490.55 02.06.2019 31.06.2019
27 Distemper in inside wall Sqm 10344.660 Not Started 10344.660 22.05.2019 21.06.2019
28 Weather coat in outside wall Sqm 1544.23 Not Started 1544.23 08.06.2019 30.06.2019
29 Enamel paint on wall Sqm 601.66 Not Started 601.66 21.06.2019 14.07.2019
30 Metallic Board False Ceiling Sqm 941.71 Not Started 941.71 01.06.2019 30.06.2019
31 AC Board False Ceiling Sqm 19.28 Not Started 19.28 06.06.2019 09.06.2019
32 Turbovent Nos 20.00 Not Started 20.00 17.06.2019 25.06.2019
33 0.50mm thick sheet for wall cladding Sqm 4196.77 Not Started 4196.77 21.06.2019 15.07.2019
34 Strcutral steel for roof truss kg 111250.00 Not Started 111250.00 08.07.2019 07.09.2019
Enamel Painting for roof truss, structural steel (2 coat over
35 Sqm 6312.00 Not Started 6312.00 15.08.2019 14.09.2019
one coat of red oxide)
36 Electrical Wiring Internal(Points Only)
Aluminium, Glass, GMP Doors, windows, door & window
37
fittings, water supply, sanitary
Rolling shutter, grill, fan clamps, sanitary fittings, painting
38
of rolling shutter, grill, etc