Professional Documents
Culture Documents
Topic 4 – Scheduling
Kestrel Stone
Widely available project management software will create Gantt charts automatically
based on data such as durations, resources, etc.. But to truly understand how these
tools work (and common pitfalls with using them), it is useful to examine these
processes from first principles.
2.13
Id. WBS 1.01
Move in
1 Phase 1: Planning
Client meeting
1.01 Meet with client to discuss requirements 2.08
2.02
1.02 Develop plans and submit to Council Plumbing
1.03 Pour foundation
DA approval
1.04 Engage builder 1.02
2 Phase 2: Construction Plans
2.06
2.01 Site preparation
Plumbing work
2.02 Pour foundations 2.09
– Key terms:
– Predecessors
– Successors
– Merge Activities
– Burst Activities 2.08
Kit/bath
fittings
2.09
2.06
Painting
Plumbing
2.07 2.12
2.05 3
1.01 Decorate
2.03 Closure
Client meeting Walls/floors/ Electrical
Build frame
1.03 ceilings
DA approval
2.11
2.04 Inspection
2.10 2.13
1.02 Install roof Move in
Landscape
Plans to 2.01 2.02
council Pour
Site prep
foundations
1.04
Engage
builder
Activity
• For each segment of the WBS, select the level at which you will develop
the schedule (high/mid/low-level). Remember: select either a category
item OR everything within it, to ensure that you capture all the work in
the WBS. For the purposes of this activity, you should select between 15
and 20 items in total.
Example
– A task will take between 5 and 10 days
– 5 days is the mean (50% likelihood that the task will take 5 days or less)
Large σ =
high variability
Activity
• Estimate the duration of each activity (including effort, lead and lag)
2.08
Kit/bath
fittings
2.09
2.06 2
Painting
Plumbing
20
3
2.07 2.12
2.05 3
1.01 Decorate
2.03 Closure
Client meeting Electrical
Build frame
Walls/floors/ 3
1.03 ceilings 3
10 4
DA approval 2 4
2.11
60 2.04 Inspection
2.10 2.13
1.02 Install roof 1 Move in
Landscape
Plans to 2.01 2.02 1
council 2
Site prep
Pour 10
20 foundations
1.04 3 2
Engage
builder
15
100 2.08
Kit/bath
Start with the first 97 2.06
fittings
105 2.09
102 2
node, where ES = 0 Plumbing
Painting
125 20
100 3
EF Dur LF
Activity
30 1.04 75
– Convert this information into a Gantt Chart 45
Engage
builder
45 15 90
Late
Early Finish
Early
Start Float
Finish
Activity
– Project scheduling tools (Microsoft Project, Primavera, Zoho, etc) use user-entered data to
automatically produce the Network Diagram and Gantt chart
– The software only automates the calculations in forward pass, backward pass and critical
path analysis
– But remember: “rubbish in; rubbish out”
– Make sure that you have included all items of scope
o Especially if adapting the schedule from a previous project (each project is
unique)
– Ensure that you have identified all dependencies
– Resource allocations must be accurate and reflect likely availability of staff
– Duration estimates must be as accurate as possible, reflecting schedule risk