PT. MULIAGLASS FLOAT…………………………


OPNAME PROGRESS

PROJECT NAME : JASA SERTIFIKASI INSTALLASI SAMBUNG PLN (UTILITY) PO No : 4330036326


PO DATE : 26/08/2019

OPNAME PROGRESS :
CONTRACTOR : PERORANGAN MULIA EXTERNAL DATE

CONTRACT PHYSICAL PROGRESS


ITEM DESCRIPTION UNIT WORK CURR UNIT RATE UP TO THIS MONTH UP TO LAST MONTH THIS MONTH TOTAL AMOUNT
VOLUME VOLUME % VOLUME % VOLUME %
1 JASA SERTIFIKASI INSTALLASI SAMBUNG PLN 1 AU IDR 10,835,000 100 IDR 10,835,000
0

Prepared by : Approved by :
Contractor * User HOD DIRECTOR Total value of work done to date IDR 10,835,000
Less advance payment 20%
Total 10,835,000
yang harus dibayar
Sub Total

Ppn 10% IDR 1,083,500

Less total amount previously paid

Date : Date : Date : Date : Payable IDR 11,918,500