Chiller plant audit frame work

- Determine types of equipment: Air cooled or water cooled


- Esco?
- Look for zero capex option  or at least option without replacing the chiller unit
- Chiller sequencing/scheduling/staging should be look after first when you visit a chiller plant 
easiest option
- Time of chiller starts?

What to do?

Chiller side:

- Look for refrigerant to water approach  low approach  HE cleans up

Pump & valve side

- Valve throttling  why is it?

Chiller running and valve not being closed???