Survey, Investigations and preparation of detailed project report for improvement of road MIGGING –

TUTTING from Km 13.56 to 35.00 to NH double lane specifications in Upper Siang dist. of Arunachal Pradesh

Resources Appreciation Report

Overview:
Border Roads Organisation ( BRO ) , Project Brahmank ,Government of India has decided to upgrade
existing single lane road connectivity from Migging to at least two lane standards and some of these
stretches are proposed to be taken up through the assistance from BRO, Brahmank. The work would
be taken up for up gradation on corridor concept. Therefore, corridors include strengthening in
addition to widening to 2 lane/ 2 lane with paved shoulder standards in order to have a better facility
in a long continuous stretch.

Construction Phasing:
Keeping facts in mind about the extreme climatic conditions in the region, availability of narrow
ROW & issues in accessibility , following construction phasing shall be advisable;

Section-2: Near Pango Village to Ningging Village (From Ex.Chg. Km.13+560 to Ex.Chg
Km.35+000)

Base Camp Location:


A base camp and plants can be located at Palsi Village area from where, the construction material can
be transported towards Migging end & Tutting end, with 50% lead on either side of stretch.

Lead Map (as per respective chainages): (Schematic)

FILL MATERIAL CEMENT


RIVER SAND FROM
LOCAL AV.2KMS TUTTING
km 21 & km 41
HQ 0.0KM

SINGGING PALSI TUTTING


15.00km 20KMS 35.00KM

CEMENT
MIGGING RIVER SAND
FILL MATERIAL
HQ 0.0KM FROM SIANG
LOCAL AV.4KMS
RIVER 11KMS

HYSD
MIGGING
HQ 0.0KM BITUMEN
GUWAHATI 855KM

Page 1

LRP Consultant Consortium Pvt. Ltd.


Survey, Investigations and preparation of detailed project report for improvement of road MIGGING –
TUTTING from Km 13.56 to 35.00 to NH double lane specifications in Upper Siang dist. of Arunachal Pradesh

WMM Plant site


0.400Km from
256.400 Stone Quarry at Km 278.400 and 1 Km
To Bille
approach road

DiteDimmai Migging Tuting Bona Gelling

191.00 Km 50.43 Km 17.00 Km 11.200 Km


Km Km
271.40 291.40

WORK Crusher, HMP site Sand Quarry Road side at Km


SITE at Km KM276.400 Km 299.21

Quarry & Distance Chart

Major Activities:

Being a road stretch in hilly/mountainous region, the new construction involves major activities of
Cutting & Filling, due to realignments proposed to ease the curves and other constraints along the
alignment.

Following are the major activities involved during execution-

1. Cutting/excavation in soft/hard soils.


2. Cutting/excavation in soft/hard rocks.
3. Earthwork in embankment.
4. Base construction-GSB.
5. Sub-base construction-WMM.
6. Plain cement concrete-all grades.
7. Reinforced cement concrete-all grades.
8. HYSD reinforcement cutting, bending & binding.
9. Bituminous courses.

Considering voluminous quantities of above listed items, to be executed in extreme climatic


conditions & difficult terrain, it will be certainly advisable to utilize departmental resources of BRO &
its ancillary execution units. This will save time to arrange outsourced procurement of resources. It
will also add to efficient utilization of locally available resources. Additionally, the execution related
issues may get addressed more efficiently as the manpower resources are well acquainted with local
environment & working conditions.

List of Resources:

In line with the items & its huge quantities, as listed above, following resources will be required to
be deployed, which may be readily available with BRO;

Total period of execution: 36 months

Page 2

LRP Consultant Consortium Pvt. Ltd.


Survey, Investigations and preparation of detailed project report for improvement of road MIGGING –
TUTTING from Km 13.56 to 35.00 to NH double lane specifications in Upper Siang dist. of Arunachal Pradesh

No Name of Resource Capacity No of Units Usage Deployment


A List of Major Machinery/Equipment
1 Hydraulic Excavator 1.00 cum 3 19 months
2 Dozer D-80, A-12 150cum/hr 2 11 months
3 Dozer D-80, A-15 120cum/hr 1 11 months
4 Front end loader 1.00 cum 2 20 months
5 GSB Plant 40 cum/hr 1 7 months
6 WMM Plant 60TPH 25 cum/hr 1 7 months
7 Hot mix plant 100TPH 30 cum/hr 1 7 months
8 Tippers 5 cum 4 16 months
9 Tractor trolley set 50 hp/2 cum 3 9 months
10 Integrated stone crusher 100 TPH 1 11 months
11 Emulsion pressure distributor 1750sq/hr 1 11 months
12 Paver machine with sensor 40 cum/hr 1 14 months
13 Concrete batching plant 15-20cum 2 15 months
14 Transit mixer 5 cum 4 15 months
15 Crane- Hydraulic 30 mt 1 15 months
16 Smooth wheeled roller 8 mt 2 14 months
17 Pneumatic road roller 8-10 mt 1 13 months
18 Tandem road roller Standard 1 13 months
19 Water tanker 1000 ltrs 2 21 months
20 Air compressor- chiselled 2 27 months
21 Ripper 60 cum/hr 1 14 months
22 Road marking machine 100sqm/hr 1 4 months
23 Truck trailer 30 mt 1 5 months
24 Generator 63 kva 63kva 2 18 months
B List of Manpower
1 Skilled manpower Man-hour 30 21 months
2 Unskilled manpower 85 21 months
** The outputs/capacities mentioned above are as per MoRTH standard Data Book.

Notes:

a. The above list includes need of machinery & manpower for haulage of cement, steel &
other materials from BRO headquarters to base camp at Palsi village.
b. It may be noted that, there are some additional periodic requirements of miscellaneous
tools/equipment in addition to above list as per the prevailing circumstances during
execution.
c. The listed machinery & manpower deployment is meant for only execution purpose and
further need for maintenance of constructed road way is not accounted here.

=====0x0=====

Page 3

LRP Consultant Consortium Pvt. Ltd.