Your organization has to follow some guidelines and policies while recruiting people to
the company. From your project perspective, these guidelines and policies will be
classified as:
1 Regulations
2 Best practices
3 Assumptions
4 Constraints
2. As a project manager, you advocate active participation of your team members - this is
because you believe in:
4 Referent power
3. You have been given a high priority task that needs to be completed within a short time
frame. Since you know what has to be done, you assign tasks to the different team
members and tell them when and how the tasks should be done. The management style
that you are following is:
1 Directing
2 Laissez Faire
3 Delegating
4 Task-oriented
1 Penalty
2 Expert
3 Legitimate
4 Referent
members regarding some pressing issues. You ask them to stop arguing
and do the tasks in the way in which you want them to be done. Your
conflict handling approach is:
1 Smoothing
6. In your project, you have started doing human resource planning and are studying
the Interpersonal relationships
Forcing among the candidates who are being considered for
2
the project team. Some factors you consider include:
- What type
3 Confrontation
of formal and informal reporting relationships exist amongst the
candidates for the project team?
- What are the candidates` job descriptions?
- What are Withdrawal
4 the supervisor-subordinate relationships?
- What cultural or language differences will affect working relationships among team
members?
- What levels of trust and respect currently exist?
2 Organization hierarchy
1 RACI Chart
4 Text-Oriented Chart
8. In your project, you invest a lot of time in team development to increase the
team`s performance, which increases the likelihood of meeting project objectives.
Which of the following indicators would you use to evaluate your team`s
effectiveness?
1 Team-building activities
2 Ground rules
4 Rules of conduct
14. Your project has two hundred and fifty people from five different
countries working to create a software solution which is going to be
deployed across fifteen countries. Managing your virtual team is a
challenge when compared with managing a collocated project. You
should spend more time working on enhancing your:
4 Communications Planning
15. You are the project manager managing the setting up of an oil rig in
the Pacific Ocean. Which of the following could be a valid constraint when
you are doing human resource planning for your project?
16. Ten members were assigned in advance to your project team. This
pre-assignment could be because of all the following reasons EXCEPT: