SIMPLE INSPECTION UNIT 10

PT. PJB UBJ O&M REMBANG


TAHUN 2017

DAILY REPORT

Pekerjaan Yang Dilaksanakan Hari Ini Pekerjaan Yang Akan Dilaksanakan Besok
No Bidang Kondisi Target Pelaksana / Keterangan
(Work To be Done) (Work To Do)
Tanggal : 24 September 2017
1 Mekanik Turbin Utama Turbin Utama
Disassembly Cross Over Pipe 100% Disassembly bolt outer casing HIP 75% Rio Brammasta
Disassembly Turbine Casing Outer 100% Disassembly bolt inner casing LP 50% Rio Brammasta
Disassembly bolt casing outer HIP 10%
2 Mekanik Valve Turbin Valve Turbin
Disassembly Lever CV 2, 4 25% Disassembly Lever CV 2, 4 50% Januar Prasetyo
3 Mekanik BFPT BFPT
Disassembly casing turbine BFPT 20 A 100% Disassembly baut casing BFPT 20 B 100% Venda Chandra
Disassembly cover labirynt depan BFPT 20 A 100% Disassembly flange coupling BFPT 20 B 50%
Disassembly cover labirynt belakang BFPT 20 A 100% Pull Out rotor 100%
Disassembly baut inlet steam 20 B 100%
Pengukuran axial rotor turbine BFPT 20 A 100%
Disassembly isolasi BFPT 20 B 100%
Mekanik LPH 6,7
Buka manhole outer dan inner 100%
Mekanik Deaerator Deaerator
Buka manhole deaerator storage water tank 100% Cleaning deaerator
Mekanik SWBP
Uncouple coupling SWBP A
Uncouple coupling SWBP B

Menyaksikan Mengetahui

I Ketut Suardana Mudjianto


Koordinator Overhoul Project Manager