You are on page 1of 10

OBLICON SD Plaintiff is then entitled to interest on the amount of the penalty because

02/07/2018 defendant refused to pay when demand was made by the former.
C2021
Art. 2210 of the NCC also provides that in the discretion of the court, interest may be
Cabarroguis v. Vicente allowed upon damages awarded for breach of contract. This interest is recoverable
G.R. No. L-14304 | March 23, 1960
 from the time of delay, which means from the date of judicial or extrajudicial
demand. Since there is no showing as to when demand for payment was made,
Gutierrez, J.
plaintiff must be considered to have made such demand only from the filing of
Arada, Group 2
the complaint.
Plaintiffs/appellees: Antonia Cabarroguis and Mamerto Cabarroguis
Issue:
Defendant/appellant: Telesforo Vicente
 W/N defendant should pay interest on the amount of the judgment from the
date of the filing of the complaint until its full payment – NO, interest only
Topic under which it is assigned: VII. Obligations With a Penal Clause, A. Purpose
of Penalty on the amount of the penalty

Art. 1226. In obligations with a penal clause, the penalty shall substitute the indemnity Facts:
for damages and the payment of interests in case of noncompliance, if there is no  Antonia Cabarroguis sustained physical injuries (which caused permanent
stipulation to the contrary. Nevertheless, damages shall be paid if the obligor refuses partial disability to her right forearm) as a result of an accident when the
to pay the penalty or is guilty of fraud in the fulfillment of the obligation. jeepney she was riding in hit another vehicle at a street corner in Davao City
The penalty may be enforced only when it is demandable in accordance with the  Defendant, owner and operator of the jeepney involved in the accident,
provisions of this Code. (1152a) entered into a compromise agreement with Cabarroguis to avoid court
litigation
Ratio: o Obligating himself to pay her Php2,500 "as actual and compensatory
General rule: if the obligation consists in a sum of money, the only damage a creditor exemplary and moral damages suffered by (her) . . . from the said
may recover if the debtor incurs in delay is the payment of the interest agreed upon, or accident"
the legal interest, unless the contrary is stipulated (Art. 2209, NCC). However, the o Should he fail to complete payment within a period of sixty (60)
creditor may also claim other damages, in addition to interest, the award of which is days, he would pay an "additional amount of Php200.00 as
left to the discretion of the court. liquidated damages"
 Defendant paid only a total of Php1,500.00, leaving a balance of Php1,000
In obligations with a penal clause, however, as provided in Art. 1226 of the NCC,  He failed and refused to comply with his obligation (despite repeated
the penalty shall substitute the indemnity for damages and the payment of demands) under the agreement after it became due and demandable, thus
interests. The exceptions are: (1) when the contrary is stipulated; (2) when the debtor plaintiff brought suit in the Municipal Court of Davao City
refuses to pay the penalty imposed in the obligation, in which case the creditor is  Defendant’s defense:
entitled to interest on the amount of the penalty, in accordance with Art. 2209; and o The injury sustained by plaintiff was not serious or consequential as
(3) when the obligor is guilty of fraud in the fulfillment of the obligation. to entitle her to the payment of the amount stipulated in the
compromise agreement
Applying Art.1226, it is evident that no interest can be awarded on the principal o The agreement did not express the true intention of the parties
obligation of defendant because of the stipulated Php200 penalty in the thereto "by reason of mistake, fraud, inequitable conduct or
agreement, which took the place of the payment of such interest and indemnity accident" so that a reformation of the agreement was in order
for damages. There was no stipulation to the contrary and the breach of the  MC ruled in favor of plaintiff; defendant appealed to CFI who then held that
compromise agreement by defendant was not occasioned by fraud. defendant was just trying to evade paying his obligation and sentenced him
to pay plaintiff Php1,200 with interest at legal rate from the date of filing of
As to the penalty attached to the principal obligation, it has been held that in the complaint until full payment
obligations for the payment of a sum of money when a penalty is stipulated for default,  Defendant appealed to the CA, saying that the CFI erred in sentencing him to
both the principal obligation and the penalty can be demanded by the creditor. pay interest on the amount of the judgment from the date of the filing of the
complaint until its full payment
o He cited Art. 1226 of the Civil Code, saying that in obligations with o Sy Deposited 600k – but OVEC stated that only 300k was given
a penal clause, the penalty substitutes the indemnity for damages and o Reduced the missed payment from 125,455 to 71,028
payment of interest o To pay for the amusement fees of 84,000
 CA certified the case to the SC because the question is a question of law, thus - After further demand, Sy still failed to pay OVEC
this petition - OVEC then locked the gates and theaters so that Sy’s business would not be
able to operate
- Sy filed an Action for reformation of the lease agreement + Damages and
Injunction
Country Bankers Insurance Corp. vs Court of Appeals o Praying to enjoin OVEC from taking possession of the theaters
Sept 9,1991 o Conditioned by a bond filed on behalf of Country Bankers Insurance
Medialdea J. (CBISCO)

Petitioners, Country Bankers Insurance Corporation and Enrique Sy


Respondents, Court of Appeals and Oscar Ventanilla Enterprises Corporation RULING
 Forfeiture clause provides that the deposit shall be deemed forfeited,
Ponente: Romero, J.  Penalty however is added on top of the damages, which were worth Php
100,000
TOPIC  Purpose of a penal clause is to affirm the compliance to an obligation.
Obligations with a Penal Clause Noncompliance would lead to added fees and penalties.
o Therefore, obligee can recover from the obligor not only the penalty
RELEVANT PROVISION but also the damages resulting from the non-fulfillment or defective
performance of the principal obligation
Art 1226. In Obligations with a penal clause, the penalty shall substitute the indemnity
for damages and the payment of interests in case of noncompliance, If there is no
stipulation to the contrary. Nevertheless, damages shall be paid if the obligor refuses
to pay the penalty or is guilty of fraud in the fulfillment of the obligation Pamintuan v CA
G.R. No. L-26339
RATIO December 14, 1979
The Forfeiture Clause is a Valid Penal Clause that was agreed by both parties. Group 4 – Aniag
290,000 taken from the cash deposit and was given in favor to the respondent
Petitioners: Mariano Pamintuan
The penalty arising from the penal clause however cannot substitute the damages Respondent: Court of Appeals, and Yu Ping Kun Co., Inc.
suffered from the missed opportunity cost of OVEC from the months Feb-Nov
TOPIC UNDER WHICH IT IS ASSIGNED: VII. Obligations with a Penal
Clause
ISSUE A. Purpose of
- W/N Sy is liable to pay damages additional to the penalty due to the forfeiture Penalty
clause stipulated in the Lease agreement
RATIO: “The proven damages supersede the stipulated liquidated damages” is
FACTS
supported by the opinion of Manresa (whose comments were the bases of the new
- OVEC and Enrique Sy entered into a lease agreement wherein, Sy would be
Article 1226, not found in Article 1152) that in case of fraud the difference between
leasing for 6 years the movie theaters and land of OVEC in Cabanatuan City
the proven damages and the stipulated penalty may be recovered.
o After 2 Years: due to late payments by Sy, OVEC made a demand
for repossession.
- After negotiations, OVEC Reconsidered and allowed Sy to continue ISSUE AND DISPOSITION: WON YPKC (Private Respondent) is entitled to the
operations penalty? – YES. However, for reasons of justice and since actual damages have
already been determined by the Court, these actual damages should prevail over condition" and a house had already been built shortly after the period stipulated.
the penalty stipulated. Hence, the trial court’s reduction of penalty is fully justified.
RELEVANT PROVISION/TERMS:
MATERIAL FACTS: Pamintuan has barter license to send a Japanese company Art. 1229. The judge shall equitably reduce the penalty when the principal
white flint corn in exchange for plastic sheeting. Pamintuan thereafter executed a obligation has been partly or irregularly complied with by the debtor. Even if
contract with Yu Ping Kun Co. wherein he would send YPKC the plastic sheeting in there has been no performance, the penalty may also be reduced by the courts if it is
consideration of P265,550. The contract stipulated a penalty of P10,000 for any party
iniquitous or unconscionable. (1154a)
who violates the contract. The Court determined that it was “not easy to
categorize” whether the purpose of the clause is to enforce the contract or to ISSUE/S WITH RATIO:
accommodate prospective damages. Later, Pamintuan violates the contract by 1. W/N Andal was liable for the full amount of the bond upon his failure to build a
withholding the plastic sheeting (after YPKC has fully complied with its reciprocal house within the two-year period. NO. (FOR OUR CLASS: W/N Court can reduce
obligation) and overpricing the already delivered sheets (to offset the undelivered the penalty attached to an obligation with Penal Clause- YES)
sheets). Withholding and overpricing the sheets constitutes fraud for Court.
YPKC filed a suit. The "special condition" in the Deed of Sale is in reality an obligation- to build a house
with at least 50 per cent of which to be finished within two years. The penal clause of
NOTES: In determining the damages suffered by the Respondent, the Court computed payment of P12,000 in case of failure to comply with said obligation was inserted to
the following: 1) For the plastic sheeting, P67,174.17 as unrealized profits and secure its performance.
P12,282.26 as overpayment, 2) Pl,102.85 as premium paid by the company on the  In obligations with a penal sanction, the penalty takes the place of "damages
bond of P102,502.13 for the issuance of the writ of preliminary attachment and (d)
and the payment of interest in case of non-compliance" and the obligee is
P10,000 as attorney's fees.
Hence, the damages recoverable by the firm would amount to ninety thousand entitled to recover it upon the breach of the obligation without the need of
five hundred fifty-nine pesos and twenty-eight centavos (P90,559.28), with six proving damages.
percent interest a year from the filing of the complaint.
However, when there is partial performance of an obligation, the Court may
validly mitigate the obligor's liability. Art. 1229 of the Civil Code states: The judge
shall equitably reduce the penalty when the principal obligation has been partly
Makati Development v. Empire or irregularly complied with by the debtor. Even if there has been no performance,
G.R. No. L-21780 | June 30, 1967 | Castro, J. the penalty may also be reduced by the courts if it is iniquitous or unconscionable.
MAKATI DEVELOPMENT CORPORATION, petitioner vs.  The trial court found that Juan Carlos had finished more than 50 per cent
EMPIRE INSURANCE CO. and RODOLFO P. ANDAL, respondents of his house by April 1961, or barely a month after the expiration on March
Group 6- De Guzman 31, 1961 of the stipulated period. Therefore, there was a partial
performance of the obligation within the meaning and intendment of Art.
TOPIC: VII. Obligations with a Penal Clause 1229 and Court may validly reduce obligation from P12,000 to P1,500.
B. When courts may reduce (Art. 1229)
 The lower Court also note that even before March 1961, the entire area was
already fenced with a stone wall and building materials were stocked in the
SUMMARY:
premises which are clear indicia of the owner's desire to construct his house
MDC sold a lot to Andal. The Deed of Sale had a “special condition” that Andal should
with the least possible delay.
complete at least 50% of his residence by March 1961 or his bond of P11,123 will be
forfeited in favor of MDC. After failing to comply with said obligation, MDC filed a SC ruled that the penal clause was inserted not to indemnify MDC for any damage
complaint with CFI Rizal to collect the bond in full amount. The lower court granted it might suffer as a result of a breach of the contract but rather to compel
the petition but reduced the amount to P1,500. Upon appeal, SC ruled that if the performance of the "special condition" and thus encourage home building among
purpose of the penalty is to compel the performance of the obligation and punish non- lot owners in the Urdaneta Village.
compliance, then the court may reduce the penalty upon partial performance (Art.
1229). Here, the penal clause was inserted to compel performance of the "special
 Considering that a house had been built shortly after the period stipulated, the  MDC appealed directly to this Court.
substantial, although tardy, performance of the obligation fully justified the
HELD:
trial court’s reduction of penalty.
The appealed decision of CFI Rizal is AFFIRMED, at appellant's cost.

MATERIAL FACTS:
March 31, 1959: Makati Development Corporation (MDC) sold to Rodolfo P. Andal
a 1,589 square meters lot in Urdaneta Village, Makati, Rizal, for P55,615.
Deed of Sale contained a "special condition" that: "[T]he VENDEE/S shall
FILINVEST V. CA
commence the construction and complete at least 50% of his residence on the
property within two (2) years from March 31, 1959 to the satisfaction of the VENDOR
G.R. No. 138980 | September 20, 2005 | Chico-Nazario, J.
and, in the event of his failure to do so, the bond which the VENDEE/S has delivered Maog | Group 6
to the VENDOR in the sum of P11,123.00 and evidenced by a cash bond receipt dated PETITIONER: Filinvest Land, Inc.
April 10, 1959 will be forfeited in favor of the VENDOR by the mere fact of failure RESPONDENTS: Hon. Court of Appeals, Philippine American General Insurance
of the VENDEE/S to comply with this special condition." Company and Pacific Equipment Corporation
 To insure compliance with "condition," Andal gave a surety bond wherein
TOPIC
he, as principal, and the Empire Insurance Company (Empire), as surety,
WHEN COURTS MAY REDUCE (Article 1229)
jointly and severally, undertook to pay MDC P12,000 in case he failed to Art. 1229. The judge shall equitably reduce the penalty when the principal obligation
comply with his obligation. has been partly or irregularly complied with by the debtor. Even if there has been no
performance, the penalty may also be reduced by the courts if it is iniquitous or
Andal did not build a house and instead sold the lot to Juan Carlos, who likewise did unconscionable. (1154a)
not build a house within the stipulated period. Hence, on April 3, 1961, MDC sent a
notice of claim to Empire. TOPIC IN DISCUSSION
 The demand for P12,000 was refused by Empire, which led to MDC filing a As a general rule, courts are not at liberty to ignore the freedom of the parties to agree
complaint in CFI Rizal to recover the bond in the full amount, plus attorney's on such terms and conditions as they see fit as long as they are not contrary to law,
morals, good customs, public order or public policy. Nevertheless, courts may
fees.
equitably reduce a stipulated penalty in the contract in two instances: (1) if the
o Empire Insurance Co. asked that the complaint be dismissed or, in principal obligation has been partly or irregularly complied; and (2) even if there has
the event of a judgment in favor of MDC, that the Court order Andal been no compliance if the penalty is iniquitous or unconscionable in accordance
to pay Empire whatever amount it will be ordered to pay MDC, plus with Article 1229 of the Civil Code…
interest at 12%, from the date of the filing of the complaint until said
amount was fully reimbursed, and attorney's fees. The judge shall equitably reduce the penalty when the principal obligation has
o Andal admitted the execution of the bond but alleged that the been partly or irregularly complied with by the debtor. Even if there has been no
performance, the penalty may also be reduced by the courts if it is iniquitous or
"special condition" in the Deed of Sale was contrary to law, morals
unconscionable (Art. 1229, New Civil Code).
and public policy. He also averred that Juan Carlos had started
construction of a house on the lot. We are hamstrung to reverse the Court of Appeals as it is rudimentary that the
application of Article 1229 is essentially addressed to the sound discretion of the
CFI Rizal: Reducing the liability for breach of the undertaking from the stipulated court.
P12,000, the lower court ordered Empire to pay MDC P1,500, with 12% interest from
the time of the filing of the complaint until the amount was fully paid, P500 for RATIO
attorney's fees, and the proportionate part of the costs. CA decision is AFFIRMED.
 Andal should in turn reimburse Empire all the amounts and costs it payed to Penalty was mutually agreed upon by parties, but the Court has power, by virtue
of Art. 1229, to reduce the amount of the penalty if they deem it iniquitous or
MDC.
unconscionable.
 Penal clause: accessory undertaking to assume greater liability in case of breach.
It is attached to an obligation in order to insure performance and has two ISSUE
functions; (1) to provide for liquidated damages, and (2) to strengthen the coercive 1) W/N the liquidated damages agreed upon by the parties should be
force of the obligation by the threat of greater responsibility in the event of breach. required, considering that (a) time if of the essence of the contract, (b)
 As a general rule, courts are not at a liberty to ignore the freedom of the parties to liquidated damages was fixed by the parties [as penalty in case of delay and
agree on such terms and conditions as long as not contrary to law, morals, etc. anticipated damages Filinvest may suffer because of this], and (c) the total
 Nevertheless, courts may equitably reduce a stipulated penalty in the liquidated damages sought is only 32% of the total contract price, the same
contract in two instances freely and voluntarily agreed upon by the parties: NO
o If the principal obligation has been partly or irregularly complied, and
o Even if there has been no compliance if the penalty is iniquitous or MATERIAL FACTS
unconscionable in accordance with Art. 1229 of the Civil Code.  April 26, 1978: Filinvest Land, Inc. (FILINVEST), a corporation engaged in the
 Trial court ruled that penalty charge for delay (P15,000 per day of delay = development and sale of residential subdivisions, awarded to defendant Pacific
P3,990,000) was excessive and reduced to P1,881,867.66 “considering the Equipment Corporation (PACIFIC) the development of its residential
amount of work already performed and the fact that Filinvest consented to subdivisions consisting of two (2) parcels of land located at Payatas, Quezon City.
three prior extensions. CA affirmed this, adding that the penalty was  To guarantee its faithful compliance and pursuant to the agreement, defendant
unconscionable as the construction was already not far from completion posted two (2) Surety Bonds in favor of plaintiff, issued by Philippine American
(94.53%). General Insurance (PHILAMGEN).
 Laureano v. Kilayco (1915): cautions courts to distinguish between two kinds of  Despite three extensions, Pacific failed to finish the contracted works.
penalty clauses in order to better apply their authority in reducing the amount  Oct. 19, 1979: Plaintiff wrote Pacific advising the latter of its intention to takeover
recoverable and hold them liable for damages which it had incurred and will incur to finish
o SC held: in any case wherein there has been a partial/irregular the project.
compliance with the provisions in a contract for special indemnification  Oct. 29, 1979: Plaintiff submitted its claim against Philamgen under its
in the event of failure to comply with its terms, courts will rigidly apply performance and guarantee bond, but the latter refused to acknowledge its liability
the doctrine of strict construction against the enforcement in its entirety because its principal, Pacific, refused to acknowledge liability.
of the indemnification where it is clear from the terms of the contract that  Defense of Pacific: Failure to finish contracted work due to inclement weather
the amount of the indemnity is fixed without regard to the probable and the fact that several items of finished work and change order which plaintiff
damages which might be anticipated as a breach… But the courts will be refused to accept and pay for caused the disruption.
slow in exercising the jurisdiction conferred upon them in article 1154 o Contractual relationship = reciprocal obligation; failure of plaintiff to
(now 1229). pay its progressing bills estops it from demanding fulfilment of Pacific’s
o This doctrine is inapplicable. Distinction between penalty clause obligation
imposed in case of breach and penalty clause imposed as indemnity for o Three extensions = waiver of right to claim damages
damages should be made in cases where there has been neither partial o Unilateral and voluntary action of plaintiff’s preventing the completion
nor irregular compliance with the terms of the contract. of work has relieved Pacific from completing it.
 Filinvest’s argument that the first part of Art. 1229 on partial performance should  Defense of PHILAMGEN: Various amendments made on the principal contract
not apply because the penalty clause would kick in situations where Pacific had and the deviations in the implementation thereof which were resorted to by
already begun work but could not finish on time, thus being penalized for delay, plaintiff and co-defendant Pacific without PHILAMGEN’s written consent
is insufficient to reverse the CA ruling. thereto have automatically released the latter from any or all liability within the
o Penalty isn’t only being reduced for partial performance but also because purview of the coverage of the surety bonds it has issued.
the penalty was unconscionable.  July 7, 1981: Architect sent to conduct an ocular inspection to determine the
o Ligutan v. CA: question of whether a penalty is reasonable can be partly amount of work accomplished by Pacific and plaintiff to complete the project.
subjective and partly objective. Factors to consider: purpose of penalty,  Nov. 28, 1984: Contract billings and payments made by both parties were the best
nature of obligation, mode of breach & consequences, relationships of basis; no proper procedure in terminating the contract; lack of inventory work
parties, etc. accomplished; no logbook; inadequate documentation and system of construction
 Finally, Pacific substantially complied with their obligation in good faith, and management
Filinvest isn’t entirely faultless either (failed to pay Pacific for work actually o Billings: Pacific’s work – P11,788,282.40 (except last billing in
performed). P844,396.41); total amount of work to be accomplished by plaintiff was
based on the original contract amount less value of work accomplished  Pet’r demanded the release of the equipment seized and the return of security
by Pacific (P12,470,000-11,788,282.42 = P681,717.58) deposits, amounting to 192,000Php, turned over by Pet’r upon signing the
o Court Commissioner found no sufficient basis to justify alleged repairs Contract
made by plaintiff. Pacific had even done additional work. • Pet’r filed an action for specific performance, sum of money and
 RTC: On the basis of the commissioner’s report, the trial court dismissed damages before RTC
Filinvest’s complaint (and Pacific’s counterclaim)  Pet’r claims that Resp made verbal representations that the Contract will be
o Amount due defendant: P1,881,867.66 renewed, so she introduced improvements upon the store in Megamall in the
o However, Pacific was still in delay since April 25, 1979. Thus, they are sum of 200K.
liable. However, the claim of P3,990,000 in the form of penalty by reason • RTC: In favor of Pet’r, ordered Resp to give the security deposits
of delay was found to be too excessive. A forfeiture of the amount due back to Pet’r, return properties, reimburse for the improvement OR
defendant appears to be more reasonable. require the Pet’r to remove improvements
 CA: Affirmed the decision. • CA: Pet’r is not entitled for the security deposits and
 Filinvest @ SC: The penalty in its entirety should be respected; it was a product reimbursements for improvements, but Resp should return
of mutual agreement; represents only 32% of the P12,470,000 contract price, thus properties after Pet’r settles her obligations
not shocking. It was fixed not only to ensure compliance with the terms but to
provide for anticipated liquidated damages. Thus, pursuant to Laureano v. Issues:
Kilayco, courts should be slow in exercising the authority conferred by Art. 1229  W/N Resp is liable to return the security deposits. ONLY HALF.
of the Civil Code.  W/N Resp is liable to reimburse Pet’r for the sum of the improvements she
introduced in the leased premises. NO.
 W/N Resp is liable for attorney’s fees. NO.
Florentino v. Supervalue, Inc
G.R. 172384 | 12 Sep 2007 Ratio (Main):
Chico-Nazario, J.  Contract of Lease established in Secs. 5 & 18 that the security deposit was for the
full and faithful performance to each and every term, provision, covenant, and
Facts: condition and was not a pre-payment of rent; and that any breach of the terms and
 Pet’r is engaged in the retail of empanada with outlets in different malls and conditions shall constitute forfeit of the deposit
establishments, under the name “Empanada Royale” o Pet’r was guilty of several breaches of contract
 Resp Supervalue is a domestic corporation engaged in the business of leasing  Sec. 18 is a penal clause to ensure Pet’r’s faithful compliance with terms and
stalls located inside SM Malls conditions
 They executed a Contract of Lease over the cart-type stalls at SM North Edsa,  Penal clause: accessory undertaking to assume greater liability in case of
SM Southmall and SM Megamall. breach. It is attached to an obligation in order to insure performance and has
• 4-month term, which may be renewed upon agreement of both a double function:
 Before expiration of lease, Florentino received 2 letters from Resp o to provide for liquidated damages, and
• First letter: charging the Pet’r with the following violations: o to strengthen the coercive force of the obligation by the threat of
 Not opening twice greater responsibility in the event of breach
 Selling a different product (mini embutido) without Resp’s  Obligor bound to pay the stipulated indemnity without need of proof of the
prior approval existence and extent of damages
 Increasing the price of the goods (Php20-22) without  Art. 1226, NCC:
Resp’s prior approval o In obligations with a penal clause, the penalty shall substitute the
 Frequently closing earlier than usual mall hours indemnity for damages and the payment of interests in case of
• Second: informing Pet’r it will no longer renew the Contract of noncompliance, if there is no stipulation to the contrary.
Lease Nevertheless, damages shall be paid if the obligor refuses to pay the
 Resp took possession of the store space in Megamall and confiscated the penalty or is guilty of fraud in the fulfillment of the obligation
equipment and personal belongings of the Pet’r after the expiration of the o The penalty may be enforced only when it is demandable in
contract accordance with the provisions of this Code
 General rule: courts are not at liberty to ignore the freedoms of the parties to o It was not shown that RESP unjustifiably refused to grant the
agree on such terms and conditions as they see fit demands so as to compel the PET to initiate legal action to enforce
o As long as they are not contrary to law, morals, good customs, public her rights
order or public policy
 However, courts may equitably reduce a stipulated penalty in the contracts in
two instances: PRYCE CORPORATION v PHILIPPINE AMUSEMENT AND GAMING
o If the principal obligation has been partly or irregularly complied CORPORATION
with; and G.R. No. 157480 | May 6, 2005
o Even without compliance, if the penalty is iniquitous or Panganiban, J.
unconscionable with respect to Art. 1229, NCC: Group 2
 The judge shall equitably reduce the penalty when the
principal obligation has been partly or irregularly complied What is it saying about the topic
with by the debtor. Even if there has been no performance,
the penalty may also be reduced by the courts if it is The termination or cancellation of a contract would necessarily entail enforcement of
iniquitous or unconscionable its terms prior to the declaration of its cancellation in the same way that before a lessee
 Ligutan v. CA: is ejected under a lease contract, he has to fulfill his obligations thereunder that had
o The question of W/N a penalty is reasonable or iniquitous is partly accrued prior to his ejectment. However, termination of a contract need not undergo
subjective and partly objective judicial intervention
o Depends on factors such as: type, extent and purpose of the penalty;
nature of the obligation; mode of breach and its consequences; To rescind is to declare a contract void in its inception and to put an end to it as though
supervening realities; standing and relationship of the parties; etc. it never were. It is not merely to terminate it and release parties from further obligations
o Discretion of the court to each other but to abrogate it from the beginning and restore the parties to relative
 Forfeiture of the entire amount of the security deposits worth Php 192,000 positions which they would have occupied had no contract ever been made.
was excessive and unconscionable considering the breaches were not so
grave as to prejudice Resp unduly Issue
o Reduced to 50% 1. WON there was only a right to termination, and not recission thereby
entitling PPC to future rentals or lease payments for the unexpired
[Ratio of other issues] period of its contract with PAGCOR – YES
 Sec. 11 of the Contract mandates that the PET should secure Resp’s consent
before making any improvements; Pet’r did not  Petitioners had the right to ask or termination plus the full payment of future
 To be entitled to reimbursement for improvements, PET must be considered rentals under the provisions of the Contract, rather than just rescission under
in good faith (Art. 1678, NCC) Article 1659 of the Civil Code. This Court is not unmindful of the fact
 Arts. 448 & 546, NCC, which allow full reimbursement of useful that termination and rescission are terms that have been used loosely and
improvements and retention of the premises until reimbursement is made, interchangeably in the past. But distinctions ought to be made, especially in
apply only to a possessor in good faith this controversy, in which the terms mean differently and lead to equally
 A builder in good faith is one who is unaware of any flaw in his title of the different consequences.
land at the time he builds on it
 Pet’r cannot claim that she was not aware of any flaw or was under the belief  The distinction between termination (or cancellation) and rescission (more
that she was the owner of the premises since she is merely a lessee properly, resolution), Huibonhoa v. CA held that, where the action prayed for
o Since Florentino’s interest in the store space is merely that of the the payment of rental arrearages, the aggrieved party actually sought the
lessee under the lease contract, she cannot be considered a builder partial enforcement of a lease contract. Thus, the remedy was not rescission,
in good faith but termination or cancellation, of the contract.
 Attorney’s fees may be awarded when a party is compelled to litigate or to  There is a distinction in law between cancellation of a contract and its
incur expenses to protect its interest by reason of unjustified act of the other rescission. To rescind is to declare a contract void in its inception and to
put an end to it as though it never were. It is not merely to terminate it
and release parties from further obligations to each other but to abrogate
it from the beginning and restore the parties to relative positions which  The question of whether a penalty is reasonable or iniquitous is addressed to
they would have occupied had no contract ever been made. the sound discretion of the courts. To be considered in fixing the amount of
 The termination or cancellation of a contract would necessarily entail penalty are factors such as -- but not limited to –
enforcement of its terms prior to the declaration of its cancellation in the o the type, extent and purpose of the penalty;
same way that before a lessee is ejected under a lease contract, he has to o the nature of the obligation;
fulfill his obligations thereunder that had accrued prior to his ejectment. o the mode of the breach and its consequences;
However, termination of a contract need not undergo judicial o the supervening realities; the standing and relationship of the parties;
intervention. and the like.

 In this case, PAGCORs breach was occasioned by events that, although not
 Thus, mutual restitution is required in a rescission (or resolution), in order to
fortuitous in law, were in fact real and pressing.
bring back the parties to their original situation prior to the inception of the
o From the CAs factual findings, which are not contested by either
contract. Applying this principle to this case, it means that PPC would re-
party, we find that PAGCOR conducted a series of negotiations and
acquire possession of the leased premises, and PAGCOR would get back the
consultations before entering into the Contract. It did so not only
rentals it paid the former for the use of the hotel space.
with the PPC, but also with local government officials, who assured
 In contrast, the parties in a case of termination are not restored to their original it that the problems were surmountable.
situation; neither is the contract treated as if it never existed. Prior to its o Likewise, PAGCOR took pains to contest the ordinances before the
termination, the parties are obliged to comply with their contractual courts, which consequently declared them unconstitutional. On top
obligations. Only after the contract has been cancelled will they be released of these developments, the gaming corporation was advised by the
from their obligations. Office of the President to stop the games in Cagayan de Oro City,
prompting the former to cease operations prior to September 1993.
 In this case, the actions and pleadings of petitioner show that it never intended
to rescind the Lease Contract from the beginning. This fact was evident when  Also worth mentioning is the CAs finding that PAGCORs casino operations
it first sought to collect the accrued rentals from September to November had to be suspended for days on end since their start in December 1992; and
1993 because, as previously stated, it actually demanded the enforcement of indefinitely from July 15, 1993, upon the advice of the Office of President,
the Lease Contract prior to termination. Any intent to rescind was not shown, until the formal cessation of operations in September 1993. Needless to say,
even when it abrogated the Contract on November 25, 1993, because such these interruptions and stoppages meant that PAGCOR suffered a tremendous
abrogation was not the rescission provided for under Article 1659. loss of expected revenues, not to mention the fact that it had fully operated
under the Contract only for a limited time.
2. WON the penalty of PAGCOR should be equitably reduced
 While petitioners right to a stipulated penalty is affirmed, we consider the
 In certain cases, a stipulated penalty may nevertheless be equitably reduced claim for future rentals to the tune of P7,037,835.40 to be highly iniquitous.
by the courts. This power is explicitly sanctioned by Articles 1229 and 2227 The amount should be equitably reduced. Under the circumstances, the
of the Civil Code, which we quote: advanced rental deposits in the sum of P687,289.50 should be sufficient
penalty for respondents breach.
Art. 1229. The judge shall equitably reduce the penalty when the principal obligation
has been partly or irregularly complied with by the debtor. Even if there has been no FACTS
performance, the penalty may also be reduced by the courts if it is iniquitous or  Pryce Properties Corporation (PPC) executed a contract of lease with
unconscionable. PAGCOR involving the ball of Pryce Plaza Hotel for a period of 3 years
for the purpose of opening a casino in Cagayan de Oro City.
Art. 2227. Liquidated damages, whether intended as an indemnity or a penalty, shall  Parties executed an addendum to the contract which included a lease of
be equitably reduced if they are iniquitous or unconscionable. an additional 1000 square meters of the hotel grounds

 Afterwards, PAGCOR started their casino operations however, numerous


Resolutions were passed by the Sangguniang Panlungsod ng Cagayan de Oro
City that prohibited the issuance of business permits and allowed the
canceling of existing of business permits to any establishment that allow the
use of their premises for casino operations.
 The said Resolutions were declared by the CA as unconstitutional. This
was affirmed by the SC.

 PAGCOR resumed operations however, due to incessant public


demonstrations, it was forced to indefinitely suspend operations.
 After a while, PAGCOR decided to stop its casino operations as per
advice of the President of the Philippines.

 In 2 statements of account, PAGCOR was informed of its outstanding


account for the quarter Sept. 1 to Nov. 20, 1993.
 PPC sent PAGCOR another letter as follow-up.
 PAGCOR answered through a letter stating that:
- it was not amenable to the payment of the full rentals citing as
reasons unforeseen legal and other circumstances which prevented
it from complying with its obligations.
- it had no other alternative but to pre-terminate the lease agreement
due to the relentless and vehement opposition to their casino
operations.

 In a letter dated October 12, 1993 PAGCOR asked PPC to refund the total
of P1,437,582.25 representing the reimbursable rental deposits and expenses
for the permanent improvement of the Hotels parking lot.

 In a letter dated November 5, 1993, PAGCOR formally demanded from PPC


the payment of its claim for reimbursement.

 On November 15, 1993, PPC filed a case for sum of money in the Regional
Trial Court of Manila, while on November 19, 1993, PAGCOR also filed a
case for sum of money in the Regional Trial Court of Manila.

You might also like