You are on page 1of 3

Datumanong v.

Malaga  Respondent replied with formal written demands that the


GR 204906 | June 5, 2017 | Del Castillo, J. project be awarded to her despite Datumanong's
directive, under pain of civil action and claim for damages.
Petitioners: DPWH Sec. Simeon Datumanong; DPWH Usec.  Lagoc wrote back disavowing any liability and claiming
Manuel Bonoan; DPWH Central Office Director IV Clarita that Datumanong's directive was a supervening event that
Bandonillo; DPWH Region VI Regional Director Wilfredo prevented the award of the subject project to respondent.
Agustino; DPWH Iloilo City District Engr. Vicente Tingson, Jr.;  Respondent then filed civil case for damages against
and (Members of Bids and Awards Committees) Engineers individual petitioners
Ruby Lagoc, Mavu Jerecia and Elizabeth Gardose o Individual petitioners conspired in bad faith to
Respondent: Maria Elena Malaga deprive her of subject project and thus opened
themselves to a damage suit in their respective
FACTS individual capacities
 Respondent Maria Malaga owns B.E. Construction, a o Reason behind individual petitioners' refusal to
private contractor and lowest bidder for two concreting award the project to her is to deny and deprive
projects of DPWH, particularly: her, "harass and teach her a lesson not to file
o Mandurriao-San Miguel Road, Brgy. Hibao-an cases against the them even when there are valid
Section in Iloilo City; and and lawful reasons to do so”
o Mandurriao-San Miguel Road, Guzman-Jesena o It was more expedient to implement the project
Section in Iloilo City by bid contract than by administration; that
 Bidding for projects was held on Nov. 6, 2001 and was individual petitioners are guilty of malice and
based upon an Aug. 2001 published invitation to bid. bad faith and intentionally delayed the
 However, before the scheduled bidding, the road processes relative to the bidding for the said
condition of Brgy. Hibao-an severely deteriorated to an project in order to defeat her valid claim
almost impassable state on account of prevailing typhoon thereto, even if she was the lowest bidder
and monsoon season, prompting calls for immediate o She was deprived of the project and reasonable
repairs and other appropriate action. profits she would have gained therefrom.
 Petitioner Tingson (DPWH Iloilo City District Engr.)  Petitioners prayed for dismissal of the case
requested his immediate superior Agustino (DPWH Region o Respondent had no right to the project since
VI Director) that the projects be implemented by under the IRR of PD 1594, a contractor is not
administration – undertaken directly and immediately by automatically entitled to an award of a project;
the gov’t and taken out of list of projects bid out to private he must still undergo a mandatory post-
contractors. qualification procedure regarding his legal,
 On Aug. 23, 2001, Agustino wrote to DPWH Sec. technical and financial capability and other
Datumanong, reiterating Tingson’s request. qualifications as under IB 10.5 of the IRR.
 DPWH Usec. Bonoan personally inspected the area and in o Under the published Invitation to Bid for the
a Memorandum to Datumanong, he recommended that project, it is particularly stated that gov’t
the projects be undertaken by administration. reserved the right to reject any or all bids, waive
 Agustino sent another letter to Datumanong, reiterating any minor defect therein, and accept the offer
earlier request. most advantageous to it
 Since there was no response from Datumanong, DPWH o Respondent had a mere inchoate right, but
Regional Office VI proceeded with the scheduled bidding. which does not give her a valid cause of action
Respondent won as the lowest bidder for the projects. o Respondent was awarded the other project she
 Nov. 7, 2001: Datumanong issued a Memorandum bid for, which indicates lack of bad faith and
approving the Aug. 23, 2001 request, but only with respect malice on their part
to the road in Brgy. Hibao-an Section. o Case is clearly an unauthorized suit against the
 Pursuant to such memorandum, the members of Bids and State, and since petitioners were sued in relation
Awards Committee (Lagoc, Jeresia, and Gardose) to acts committed in performance of official
conducted post-evaluation/qualification of respondent’s duties, they should be protected by the mantle of
firm, but only for the road in Guzman-Jesena Section. state immunity
Respondent was declared post-qualified for the project,  RTC ruled in favor of petitioners and dismissed
and the same was awarded to her. complaint.
 Respondent was then informed that the Mandurriao-San o Unauthorized suit against the state
Miguel Road, Brgy. Hibao-an Section may not be awarded o Respondent must undergo post-qualification as
to her, in view of Sec. Datumanong’s memorandum. mandated by law
o Rejection of gov’t to award project to respondent  Mere submission of lowest bid does not automatically
is well within its prerogative to serve interest of entitle petitioners to the award of the contract. Before a
citizenry as there was public clamor of government project is awarded to the lowest calculated
impassable status of the road (drivers of PUVs, bidder, his bid must undergo a mandatory post-
transport groups, and residents thereof were qualification procedure whereby the "procuring entity
howling protest and indignant words against verifies, validates, and ascertains all statements made and
DPWH). documents submitted by the bidder with the lowest
o Petitioners’ acts were all committed in calculated or highest rated bid using a non-discretionary
performance of official functions and cannot be criteria as stated in the bidding documents."
said to have been tainted with malice and bad  Since respondent's lowest calculated bid for the subject
faith as it passed thru proper procedures as project did not undergo the required post-qualification
mandated by law process, then she cannot claim that the project was
 On appeal with CA, respondent argued that when DPWH awarded to her, thus, she has no right to undertake the
entered into a contract with her, it descended to the level same and she cannot demand indemnity for lost profits
of ordinary person and impliedly gave its consent to sue or actual damages suffered in the event of failure to carry
and be sued; and that her action was against individual out the same.
petitioners on ground that they acted in bad faith and  Without a formal award of the project in her favor, such a
malice in dealing with her, not against the State. demand would be premature. Consequently, she has no
 CA ruled in favor of respondent. right of action against petitioners.
o No relief was claimed against gov’t. Liability was
directly limited to the public officers as an (MAIN) WON respondent may claim damages under Art. 27
incident of their alleged wanton and malicious CC – NO.
acts.  It may be argued that respondent's claim for damages is
o Doctrine of immunity from suit will not apply and premised on Art. 27 CC and that individual petitioners'
may not be invoked where the public official is refusal to award the project to her is the cause of her
being sued in his private and personal capacity as injury.
an ordinary citizen. Well-settled principle of law o Art. 27. Any person suffering material or moral
that a public official may be liable in his personal loss because a public servant or employee
private capacity for whatever damage he may refuses or neglects, without just cause, to
have caused by act done with malice and in bad perform his official duty may file an action for
faith, or beyond the scope of his authority or damages and other relief against the latter,
jurisdiction. without prejudice to any disciplinary
o This suit was intended to compel the public administrative action that may be taken.
officers to compensate respondent for the  However, respondent still has no cause of action.
prospective profits she would have earned had Individual petitioners could not have awarded the project
she been awarded the project to her because her bid still had to undergo a post-
o Since there’s disputable presumption that official qualification procedure required under the law.
duty has been regularly performed, in order to However, such post-qualification was overtaken by
properly determine the supposed existence of events, particularly Datumanong's Nov. 7, 2001
capricious exercise of governmental discretion, in Memorandum.
the guise of performance of official duty, the  In short, respondent's causes of action solely and primarily
matter of damages should be fairly litigated based on a supposed award, actual or potential, do not
before RTC. exist. Such an award and the whole bidding process for
that matter, no longer exist, as they were mooted and
ISSUES superseded by the DPWH's decision to undertake the
WON the project was awarded to respondent – NO. project by administration, as well as by the reservation
 Procurement process basically involves the following contained in the Invitation to Bid that at any time during
steps: (1) pre-procurement conference; (2) advertisement the procurement process, government has the right to
of the invitation to bid; (3) pre-bid conference; (4) reject any or all bids.
eligibility check of prospective bidders; (5) submission and  Proper remedy for respondent should have been to seek
receipt of bids; (6) modification and withdrawal of bids; (7) reconsideration or the setting aside of Datumanong's
bid opening and examination; (8) bid evaluation; (9) post Memorandum, and then a reinstatement of the bidding or
qualification; (10) award of contract and notice to post-qualification process with a view to securing an
proceed award of the contract and notice to proceed therewith.
After all, said Memorandum enjoys the same presumption
of regularity that is attached to all official acts of
government.

RULING: Petition is GRANTED. Decision and Resolution of CA


are REVERSED and SET ASIDE. Civil Case before is ordered
DISMISSED.

You might also like