You are on page 1of 10

An Assessment Of Time Variation In

Solid And Hollow Floor Construction


In Lagos State

Olumide Afolarin Adenuga Gboyega Sotunbo


Department of Building, Department of Building,
Faculty of Environmental Sciences Faculty of Environmental Sciences
University of Lagos, Lagos Nigeria University of Lagos, Lagos Nigeria
oaadenuga@yahoo.com oaadenuga@yahoo.com

The choice of construction method employed for construct-


DOI 10.5592/otmcj.2014.1.8
Research paper ing suspended slabs in buildings tend to impact significantly
on the delivery time of building project. Thus, this study aims
at assessing the impact of various construction methods on
duration for constructing hollow and solid floor slabs in build-
ings in Lagos State, Nigeria. The research design for this study
was a survey design approach and the populations of the study
were professionals involved in construction projects; Architects,
Civil Engineers, Builders, Quantity Surveyors, Building Services
Consultant and Contractors. These are the major participants
in the construction industry in Lagos State, Nigeria. The anal-
Keywords ysis is based on 46 (forty-six) returned questionnaires out of
the 60 (Sixty) questionnaires administered. The data from the
Reinforced Concrete,
questionnaires were analyzed using descriptive statistics tools
Solid Slabs, Hollow Slab,
such as frequency, percentage mean ranking while the hypoth-
Time Variation and Project
esis were tested with a paired sample t-test tool. It was found
Delivery
that the systems or methods of slab construction well known
to the respondents are cast in situ, precast and semi-precast.
The Cast in-situ beam and slab construction ranked as the
most frequently adopted method followed by flat slab, hollow
clay pot and waffle slab construction. In terms of construc-
tion time, placing reinforcement and construction of formwork
takes more time than other processes in solid slab construction
while in construction of reinforced cast in situ concrete hollow
slab; formwork construction, placing hollow bricks or blocks or
moulds on formwork and curing concrete takes more time than
the other processes involved. The study’s major recommenda-
tion is that, adequate and careful analysis should be conducted
before taking a decision on the choice of floor system been
adopted for any project.

984 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(1)2014


Background to the study fabricated off-site (as pre-fabricated additional benefits of long span and
Building designs and constructions or pre-cast) and just brought to site high load-capacity can be obtained.
could be dated back to the existence for assemblage. The eventual on-site The precast floor elements are usually
of man on earth, and over the years, assemblage of these slabs will require simply supported before a topping con-
various designs and construction newer technology and methods differ- crete is placed to complete the system.
methods have evolved. These evolu- ent from the entire on-site cast in-situ Pre-cast floor systems are produced to
tions have led to the newest or modern construction with construction time specification and are all in modulus
designs and construction methods of variation. Lutz (2002) investigated (CCAA, 2010). Pre cast floor system
various components or elements of a hollow floors from the aspect of pre- could be subdivided into pre cast solid
building; such as floors, wall, ceilings fabrication. In this method, the floor reinforced slabs and hollow core (Pre
and roofs. For instance, the design and is manufactured or prefabricated from cast or Pre stressed).
construction of floor slabs are usually the factory and just brought to site for
solid, adequately reinforced in 2-direc- assemblage through anchorage. One Construction Methods Of Cast
tion and concreted. The construction of the advantages of this method is In-Situ Floor System
of these slabs usually requires much the delivery in time which cannot be Generally, the on-site construction
formwork, high number of reinforce- compared to the in-situ construction. method of any cast in-situ floor slabs
ment provided in both ways (top and Hence, the variations in the duration of could be summarized as follows:
bottom) and high volume of concrete construction of these structures cannot Construction of formwork, placing of
which resulted in an ample time or dura- be under rated. The variance in these reinforcements, Pouring of concrete
tion of construction. But over the recent two types of floor system could be or casting and removal of formwork
decades, engineering researches have linked to their method of construction (Rupasinghe & Nolan, 2007); under
brought forth new designs that have or installation. Therefore, the objec- these four steps, the construction
led to new construction methods of tives of the study are to identify the process of monolithic solid slab and
floor slabs. These modern designs construction methods of hollow and hollow clay pot slab will be examined.
now give birth to entirely new construc- solid floor slabs in construction proj-
tion methods that totally differ from ects in Lagos State and determine the Monolithic Solid Slab Construction
the traditional way of constructing a variation in the time of production of Monolithic reinforced solid slabs are
solid slab. Hollow floor slabs, a product the two floor systems. slabs which are constructed on-site as
of modern designs, now require less a unit with fresh concrete. Below is the
reinforcement, less formwork and less Types Of Concrete Floor construction process of a monolithic
concrete as a result of the holes, space, Systems reinforced slab.
foams and balls that are incorporated
in the slab. These now require a differ- Cast In-situ Floor Systems Formwork construction
ent method of on-site construction of This class of concrete floor system Formwork was described as a struc-
such slabs to achieve its design which entails physically constructing the ture, usually temporary, used to
could enhance time savings during floor slab by mixing, casting in between contain poured concrete to mould it
construction. Lai (2010) attested to formwork and hardening of concrete to the required dimensions and sup-
the fact that holes or voids, which are on site. Cast in-situ reinforced con- port until it is able to support itself. It
created in the floors replaces the inef- crete structures consist of horizon- consists primarily of the face contact
fective concrete in the neutral zone of tal elements (beams and floors) and material (platform) and the bearers
the slab, thereby decreasing the dead vertical elements (columns and walls) that directly support the face (prop)
weight and increasing the efficiency connected by rigid joints. Cast in-situ contact material (Rupasinghe & Nolan,
of the slab. Thus, voids or holes are floor system could be subdivided into 2007). Lightweight horizontal panel
formed within the slab system. These monolithic (solid) reinforced in-situ formwork systems used for slab con-
also give a significant advantage over floor slabs and monolithic hollow struction generally consist of a series
the conventional solid slabs in terms (ribbed) floor slabs. of interconnected falsework bays,
of reduced material usage (reinforce- independent props or system scaffolds
ment and concrete), reduced cost, Pre-cast Floor System and supporting pre-formed decking
enhance structural efficiency, decrease Pre-casting offers the advantages of panels. These can include primary
construction time and it is a new tech- off-site manufactured under factory beams spanning between props and
nology in the construction industry. conditions and fast erection on site. supporting a number of panels.
In either way, floor slabs could be When combined with pre-stressing,

o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 985
Placing of reinforcement aggregate (sand, granite-19-25mm) and Construction of Monolithic Hollow
CCAA (2010) opined that the placement potable water. In addition to meeting Clay Pot Slab\
of reinforcement at strategic locations structural requirements, concrete for Hollow (Ribbed) floors are floors eco-
ensures great flexibility during the floors should provide adequate work- nomically designed and constructed
design and construction stages in in- ability, durability and strength neces- using hollow blocks, removable foams
situ concrete construction. Bimel and sary to obtain the required finish and or permanent voids former such as clay
Tipping (1997) stated that deformed floor surface profile (Bimel et al, 1997). pots. This type of floors have reduced
bars, bar mats, or welded wire rein- Concrete for floors, usually of mix 1:2:4- self weight compared to the solid slabs.
forcement usually are required in sus- 19mm is used on site. This batch is either This is due to the fact that some of
pended structural floors as part of the mixed by hand or by machine (mixer). the concrete in the neutral zone are
structural design. Reinforcements are A thorough mix is required to attain a removed. Ribbed slab are very adapt-
used to strengthen concrete for ten- required consistency and workability. able for accommodating a range of ser-
sion forces in structures as concrete In a situation where labours are used in vice openings. The methods of hollow
is weak in tension but strong in com- placing the concrete, the labours placed clay pot construction are as follows;
pression (Rwamamara, Simonsson, & the mixed concrete through head pans Construction or Laying of formwork,
Ojanen, 2010). Reinforcements are often carefully over the fixed reinforcements Placing of pots, Placing of reinforce-
delivered to sites in tonnes of standard and then vibrated to prevent any event ments, Pouring of concrete or casting
length in Nigeria and are later cut into void. The concrete is tapped to compact and Removal of formwork.
pieces of required length. The pieces are and give an even surface. The placed
then laid or placed on the form work, in concrete is allowed to set for at least 28 Construction of formwork
required or calculated spaces and then days with constant curing to attain its Formwork as described by Rupasinghe
fixed together by an experienced iron workable strength. and Nolan (2007) as a structure, usu-
fixer (bender) with a binding wire, in its In a situation where truck mixer is ally temporary, used to contain poured
final location or position. Rwamamara et used to mix and pneumatic concrete concrete to mould it to the required
al (2010) agreed with CCAA (2010) that pump or crane with bucket is used to dimensions and support until it is able
the placement of reinforcement on the discharge in position, the concrete is to support itself. It consists primarily
formwork on-site gives a great advantage pumped from the mixed truck through of the face contact material (platform)
of flexibility on site during placement. the pneumatic pump or carried through and the bearers that directly sup-
Generally, (BS 8110, 1997) the sizes of a bucket attached to a crane, up to the port the face (prop) contact material.
reinforcement used on sites varies from point of discharge and then discharged. Lightweight horizontal panel formwork
12mm – 25mm diameter, depending on Skilled masons immediately spread the systems used for slab construction gen-
the maximum moment to resist, and the concrete into position, tapped, com- erally consist of a series of intercon-
spaces between each bars varies from pacted and finished to requirement. The nected false work bays, independent
150mm – 250mm. floor is then left for 28 days to attain props or system scaffolds and sup-
After placement of reinforcement, its self-supportive strength before the porting pre-formed decking panels.
concrete spacers are used to maintain formwork is removed. The thickness of These can include primary beams span-
a good space between the formwork and the slab according to BS8110 (1997) is ning between props and supporting a
the bars to give a cover of at least 20mm. between 150 – 300mm depending on number of panels. This is similar to the
this is done to prevent the bars against the design. solid concrete slab formwork.
moisture attack and enhance fire resis- The constructions of the formwork for
tance. In solid slab construction, rein- Removal of the formwork hollow clay pot slabs are usually done
forcements are provided in both direc- After the concrete floor has attained in two ways. These are;
tions as shown above, except for one its 28 days strength or more, the form- 1. Constructing or laying the formwork
way solid slab that has its reinforcement work can then be struck off carefully by to cover the whole area of the floor
in just one direction. The provision of skilled carpenters. BS8110 (1997) sug- slab and then the pots laid on them.
reinforcement in two ways in a solid slab gested that formwork should be removed 2. Constructing or laying the formwork
is the aspect that affects delivery time. without shock, as the sudden removal just directly under the ribs of the pot.
of wedges is equivalent to an impact This form is actually the type that
Pouring or casting of concrete load on the partially hardened concrete. affects the time for formwork.
Floor concrete requirement differ from The code suggested also that formwork
those of other concrete used in the struc- should not be removed or struck off the
ture. Concrete is made up of cement, suffix of the slab earlier than 28 days.

986 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(1)2014


Placing of the clay pots In design, the top reinforcements are ribs and over the pots. The rib must
After the formwork is set, next is the usually eliminated and the stirrups be vibrated to prevent any event void
placing of the hollow clay pots. There shaped in U-form to be hanged on the in it. The concrete is tapped to compact
are various types of pots available pots. This is due to the fact that the top and give an even surface.
for used, depending on the structural bars serve no purpose so it is elimi- In another situation where truck
design. The product varies from stan- nated. Unlike the solid slabs which are mixer is used to mix and pneumatic
dard classic pots of size 400 x 200 reinforced in both directions, ribbed concrete pump or crane with bucket
x 250mm and so on. The pots, when slabs of hollow clay pot are reinforced is used to discharge in position. The
delivered to site must be stacked prop- just in one direction of the rib. This, concrete is pumped from the mixed
erly before use. In the event of laying apart from the less form work, reduces truck through the pneumatic pump or
the pots, they must be carefully laid, construction period due to the reduc- carried through a bucket attached to
head to head along the shorter direc- tion in reinforcement. Generally, (BS a crane, up to the point of discharge
tion as shown in the pictures below. 8110, 1997) the size of reinforcement and then discharged. Skilled masons
The edged pots must be sealed with used on sites varies from 10mm – 16mm immediately spread the concrete into
cement and sand mortar to prevent diameter, depending on the maximum position, vibrated, tapped, compacted
the concrete filling the hole. Pots laid moment to resist. and finished to requirement. The super-
parallel to one another forms the rib in After placement of reinforcement, visor must ensure that the mesh is well
between them to receive reinforcement concrete spacers are used to maintain embedded in the concrete to avoid
and concrete. The rib formed could a good space between the formwork exposure. During casting, continual
be between 100mm - 150mm wide, and the bars in the ribs to give a cover check must be carried out on the prop-
thickness of topping between 50mm of at least 20mm. This is done to pre- ping to ensure that nothing has moved
– 170mm (BS8110, 1997). In any case vent the bars against moisture attack or sagged, as problems can only be
where it will require that the pot be and enhance fire resistance. In topping, rectified within half an hour of placing
cut into two at the side of the beam or no serious reinforcement is required the concrete over the affected area.
where it will go into the beam, the pot according to BS8110 (1997), but wire This is to ensure adequate prevention
is completely removed and the portion mesh is usually provided to prevent against deflection during casting. The
of the slab is designed and cast as solid cracks. Considering the cost of a stan- floor is then left and cured for 28 days
slab. In placing the pots, breakages dard wire mesh, 6mm mild steel bar to attain its self-supportive strength
must be avoided because breakages of are provided over the pots as mesh to before the formwork is removed. The
these pots will reduces the structural resist cracks in the thin 50 -75mm top- total depth of the slab according to
characteristics of the entire slab after ping. If 6mm diameter bars are used, BS8110 (1997) depends on the design
casting. Usually, after laying the pots the centre to centre space must not which is a factor of the height of pot
service pipe are laid and fixed in posi- be greater than 300mm (usually, 150- used and of topping.
tion through the pots or ribs. 200mm spacing are used on site). This
is to ensure that it lies within the top Removal of formwork
Placing of reinforcements of the pots and not protrude through After the concrete floor has attained
Bimel, et al (1997) stated that deformed the spacing. its 28 days strength or more, the form-
bars, bar mats, or welded wire rein- work can then be struck off carefully
forcement usually are required in sus- Casting of Concrete by skilled carpenters. BS8110 (1997)
pended structural floors as part of the Before casting, the deck must be kept suggested that formwork should be
structural design. Reinforcements are clean of any materials on the pots and removed without shock, as the sudden
used to strengthen concrete for ten- ribs, and the surface must be wet to removal of wedges is equivalent to an
sion forces in structures as concrete prevent sudden drying of the topping impact load on the partially hardened
is weak in tension but strong in com- which could lead to cracking. Concrete concrete. The code suggested also that
pression (Rwamamara et al, 2010). for this type of floors are usually of mix formwork should not be removed or
Reinforcements are often delivered to 1:2:4-19mm. This batch is machine struck off the suffix of the slab earlier
sites in tonnes of standard length in mixed. A thorough mix is required to than 28 days.
Nigeria and are later cut into pieces attain a required consistency and work-
of required length. The ribs usually ability. In a situation where labours Pre-cast or Prefabricated Floor Slabs
require two pieces of reinforcement are used in placing the concrete, the Traditional cast-in-situ concrete floor
(bottom) and may be one at the top to labours placed the mixed concrete systems involve the use of temporary
complete a triangular stirrups section. through head pans carefully in the shuttering which adds to the cost of

o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 987
construction and time. Use of standard- construction, the neutral zone of the to delivery time. From these results, it
ized and optimized precast floor com- concrete is replaced with the hollow clay could be concluded that the difference
ponents where shuttering is avoided pots while in the case of hollow slabs, in actual labour productivity between
prove to be economical, fast and better the concrete in the neutral zone are conventional and precast system mainly
in quality. Some of the prefabricated removed without replacing it with any contributed by the cycle time (difference
flooring components available but other materials. Thus, voids or holes are of 76 per cent) rather than the crew size
not limited to, are: precast Reinforced formed within the slab system. These (difference of 18 per cent). Shorter cycle
Concrete slabs/ planks and precast also give a significant advantage over time implies that total project construc-
hollow concrete panels. the conventional solid slabs in terms of tion time would also be reduced, hence
reduced material usage (reinforcement minimizing management overhead and
Pre-cast Hollow Concrete Slab and concrete), reduced cost, enhance meaning that owners can occupy their
Hollow core floor planks (slabs) are structural efficiency, decrease construc- house earlier. Visser, (2009) discov-
precast, prestressed units produced tion time and it is a new technology in ered that waffle moulds or precast brick
on long-line casting beds using slide the construction industry. Lutz (2002) result into additional time of construc-
forming or extrusion methods. During investigated hollow floors from the tion for in situ hollow slabs due to the
manufacturing, cores are formed aspect of prefabrication. In this method, placement of forms on slab formwork,
throughout the length of the unit, the floor is manufactured or prefabri- erection time amounts to the time it
reducing its self-weight. Planks or slabs cated from the factory and just brought takes to construct a flat slab, with the
are usually 1200-mm-wide, though it to site for assemblage through anchor- additional time of moulds placement.
could be produce 2400-mm-wide units. age. The advantage of this method in Fixing of reinforcement between forms
These wider units may require increased material saving, good quality control, can also prove to be a more time con-
crane capacity but offer greater speed and delivery in time and within cost, suming task. The fixing of steel rein-
of placement, less joints, grouting and can not be compared to the in-situ forcement in between and on top of the
sealing. Thicknesses of slabs vary from construction. moulds or bricks is also more strenu-
150–400 mm in 50-mm increments. The Hollow floors, which could also be ous than on a flat surface and proves
thickness is determined by span, load- called hollow core slabs can be used to be more labour intensive. Thus, the
ing, fire rating and cover to reinforce- for most applications requiring a floor construction period for in-situ hollow
ment to satisfy exposure conditions. system in Office buildings, auditori- slabs may be higher than that of solid
The economical typical span for a pre- ums, hotels, commercial buildings, slabs due to the placement of moulds
cast hollow core unit is approximately residential dwellings, houses of wor- or bricks to form the hole on site. Basri,
D x 30 to D x 35 where D is the depth of ship, nursing homes and educational (2008) Captured in the study of con-
the precast unit plus topping. Where facilities, are all ideal applications. This struction period as one of the critical
slenderness ratios fall between 35:1 is because of the advantage it gives in factor in the choice of a slab system
and 45:1, panels should be checked large span and of course its aesthetics that, 83% of the respondents agreed
for vibration-resonance effects. Spans cannot be compared to that of the solid that precast construction would result
exceeding 45:1 should not be used. slabs. In either way, floor slabs could be to faster completion of projects. In this
Planks may be used as plain sections fabricated off- site (as pre-fabricated survey, 100% of the projects were either
or topped to give a composite unit. The or pre-cast) and just brought to site completed in the same period of time
topping increases plank capacity and for assemblage. The eventual on-site as conventional construction; or even
fire rating. It provides a level surface assemblage of these slabs will require faster. 26% of the projects cut the 83%
or drainage falls and is recommended newer technology and methods differ- construction time while 52% recorded
for most building work. For economy, ent from the entire on-site construction. an astonishing savings in time. Of
the structure should be dimensioned Floors, which is a component part of a cause, it is logical to note that the
to accommodate the 1200- or 2400-mm building was major course of the study. off-site production of the floor system
modular plank width (CCAA, 2003). has reduced greatly the on-site time
Lai (2010) attested to the fact that Construction Period required for construction. Because on-
holes or voids which are created in Comparison Between Hollow site activities are only left with hoisting,
the floors replace the ineffective con- Slabs And Solid Slabs System placing and finishes which takes less
crete in the neutral zone of the slab, Kadir, (2006) discovered that signifi- time and less work force. It then clearly
thereby decreasing the dead weight cant difference occur between in-situ showed that the reduction in construc-
and increasing the efficiency of the slab construction and precast system tion time is the most obvious benefit of
slab. For instance, in the clay pot slab up to about 76 per cent, with respect precast system of slab constructions.

988 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(1)2014


Research Method frame for the study therefore contain cast in-situ because it is more of labour
The study was carried out in Lagos 27 (twenty-seven) Civil Engineers, 14 based and less of plant based, but other
State, Nigeria. Lagos State is situated in (fourteen) Quantity Surveyors and 4 methods like pre cast are more of tech-
the South Western part of Nigeria. Lagos (four) Builders to make a total of 46 nology and plant based that cast in situ.
state was chosen as a result of the large respondents. The sampling technique
number of construction works going on for this study was non-probabilistic, Level of usage of floor systems
in the state. The populations for this specifically convenience sampling tech- The analysis of the level of usage of dif-
study are Architects, Civil Engineers, nique. This was adapted to source for ferent types of floor system are shown in
Builders, Quantity Surveyors, the required information for the study Table 2 above. Cast in situ and pre cast
Consultant and Contractors who are within Lagos State. This technique was were considered. Of the cast in situ, it
major participant in the construction used because of its ease in getting in was observed that beam and slab con-
activities in the construction industry contact with those who are qualified struction is used very often by all the
in Lagos State. The research design for and experienced to provide informa- respondents as it pulled a mean value
this study is a survey design approach tion based on the objectives and the of 3.96 and ranked 1st among other
(quantitative) through which data were direction of the study (transverse). system. Flat slab followed closely with
collected. Survey design approach was Descriptive and inferential tools were a mean value of 3.65 and ranked 2nd.
adopted because this will give varying used to analyze the data for the study. Hollow clay pot slab construction was
opinions on the subject by different pro- Descriptive statistical tools such as fairly used as it ranked 3rd with a mean
fessional respondents which would be frequency, percentage, mean, ranking value of 3.24 while waffle, another type
of great influence on the analysis. The and paired sample t-test tool (inferential of floor was only said to be least used as
primary data were collected through tool) were used in the analysis. it ranked 5th with a mean value of 2.39.
the administration of structured ques- This shows vividly that most respon-
tionnaire and site visitation while the Data analysis and findings dents used very often in construction,
secondary data were gathered from Table 1 above described the responses cast in situ beam and slab, flat slab
the review of past projects, journals, of the respondents on the various meth- and hollow slab while hollow block and
conference proceedings articles and ods of floor construction known to the waffle are rarely used in construction.
the internet. respondents. It was observed from the Of the pre-cast, the table above
A total number of 60 (sixty) question- study that cast in-situ method of slab shows that precast beam and slab
naires were distributed which represent construction is well known to almost all construction is used very often in con-
100% for the study. In all, a total of 46 the respondents with a mean value of struction as it is ranked 1st with a mean
questionnaires were returned which 3.93 and ranked 1st, while precast and value of 3.37 among the precast group.
represent 76.7% and 14 question- semi-precast followed with mean value Precast flat slab which ranked 2nd with
naires were not returned which repre- of 3.43 and 2.63 and are ranked 2nd a mean value of 3.17 has a low usage
sent 23.3% of the total 100%. Since the and 3rd respectively among the known level compared to precast beam and
46 returned questionnaires represent methods of slab construction in Nigeria slab while pre-cast hollow clay pot slab
over 75% (i.e 76.7%) of the total distrib- construction industry. This could be as a and precast waffle slab construction are
uted, the sample size for the research result of the technological development not frequently used or are not even used
was set at 46 (forty-six) based on the of the Nigeria construction industry. at all in the construction industry. It thus
returned questionnaire. The sample Contractors are more knowledgeable on shows obviously that most respondents
only know about precast beam and slab,
flat slab and hollow slab construction
Mean but knows next to nothing about pre-
Construction method Rank
Value cast waffle. The table also revealed a
trend that cast in-situ method of slab
Cast in-situ 3.93 1
construction has a high level of usage
Precast/ prefabricated 3.43 2 than precast method.

Semi precast 2.63 3 Difference in construction period


Note: Well Known = 4, Known = 3, Fairly Known = 2, Not Known = 1, No Response = 0, The result of the level of time required
Percentage = % and Total Number of Respondents = N in construction process of reinforced
hollow concrete slab and reinforced
Table 1. Construction methods used for solid and hollow floors solid concrete slab are tabulated in

o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 989
Types of slab construction precast hollow core/hollow slab, time
Mean Value Rank
(Cast in situ)
required for off-site fabrication of units
Beam and Slab 3.96 1 and transportation of units to site with
Flat Slab 3.65 2 mean value of 3.48 and 3.26 are the
two highest mean and are ranked 1st
Hollow Clay Pot 3.24 3
and 2nd respectively while the time
Hollow Block 2.80 4 required in erecting and placing units in
Waffle Floor 2.39 5 position, and time required in grouting
and casting toppings with mean value
(Precast)
of 2.98 and 2.76 are least as they are
Beam and Slab 3.37 1 ranked 3rd and 4th respectively.
Flat Slab 3.17 2
Duration of construction
Hollow Clay Pot 2.39 3
process of slabs
Hollow Block 2.13 4 Table 4 shows the result of response
Waffle Floor 2.11 5 of the respondents on duration of cast
in situ hollow slab to solid slab and
Note: Well Known = 4, Known = 3, Fairly Known = 2, Not Known = 1, No Response = 0, cast in situ to precast slabs. Majority
Percentage = % and Total Number of Respondents = N
of the respondent affirms that dura-
Table 2. Level of Usage of types of floor slab by the respondents tion or time of construction of cast in
situ hollow slab is higher than that of
solid slab (36 respondents) while just
Table 3 below. The table has four sec- 1st, 2nd and 3rd respectively. While only 10 respondents affirm that the
tions which are cast in situ solid slab, time required in lay reinforcement in construction duration is lower. In the
cast in situ hollow slab, precast solid ribs, required time to place concrete same vein, majority of the respondents
slab and precast hollow slab. On the and the time required strike-off form- (35 respondents) affirms also that the
process of construction of reinforced work with mean value of 3.15, 2.97 and duration of construction of cast in situ
cast in situ concrete solid slab, time 2.74 are the three least mean values slabs system is higher than that of pre-
required to place reinforcements, and are ranked 4th, 5th and 6th respec- cast system, while 10 and 1 respondent
time required for formwork construc- tively. It then implies that formwork did not obliged as they settled for low
tion and the time required for the con- construction, placing hollow bricks or and very low respectively. These shows
crete to cure with mean value of 3.93, mould on formwork and curing takes that cast in situ hollow slab takes more
3.72 and 3.22 are the three highest more time than other process in hollow time than cast in situ solid slabs as cast
mean values and ranked 1st, 2nd and slab construction process or method. in situ construction system takes more
3rd respectively. While the required Precast concrete slab have a differ- time to construct than precast slab.
time to place concrete and the time ent construction method or process
required to strike-off formwork with from what is obtained in cast in situ. Testing of Hypothesis
mean value of 3.15 and 2.78 are the Here, the units are manufacturer off site Null Hypothesis (Ho): There is no signifi-
two least mean values and are ranked and brought to site for erection. Table 3 cant difference in the construction time
4th and 5th respectively. It thus, means below also shows various time required between solid and hollow floor slabs
that placing reinforcement and con- for various process of precast slab con- construction in construction projects.
struction of formwork takes more time struction. On precast solid slab, time Alternative Hypothesis (H1): There is
than other process in solid slab con- required for off-site fabrication of units significant difference in the construc-
struction process or method. On the and transportation of units to site with tion time between solid and hollow
process of construction of reinforced mean value of 3.52 and 3.33 are the floor slabs construction in construction
cast in situ concrete hollow slab, time two highest mean and are ranked 1st projects.
required for formwork construction, and 2nd respectively while the time To test this hypothesis, a paired
time required to place hollow bricks or required in erecting and placing units in sample t-test analysis was used.
blocks or moulds on formwork and time position, and time required in grouting Table 5 above shows a paired sample
required to cure concrete with mean and casting toppings with mean value t-test on difference in construction time
value of 3.70, 3.46 and 3.24 are the of 3.28 and 3.09 are least as they are between cast in situ solid and hollow
three highest mean values and ranked ranked 3rd and 4th respectively. On slabs in construction projects. The value

990 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(1)2014


Note: Very High = 5, Moderately High = 4,
Process of Reinforced Concrete Slab Construction Mean Value Rank
High = 3, Low = 2, Very Low = 1,
(Cast in-situ solid slab) No Response = 0 and Number of
3.93 1 Respondents = N
Time required for formwork construction

Time required to place reinforcement 3.72 2


of t (df = 45) is – 4.263, P < 0.05 with a
Time required to place concrete 3.22 3 two tailed P value, sig.(2-tailed) of .000,
t is significant at 5% level. Therefore the
Time required to cure 3.15 4 null hypothesis Ho; there is no signifi-
cant difference in the construction time
Time required to strike off formwork 2.78 5 between cast in situ solid and cast in
situ hollow floor slabs construction in
(In-situ hollow slab)
construction projects is rejected and the
Time required for formwork construction 3.70 1 alternative hypothesis H1: there is sig-
nificant difference in the construction
Time required to place hollow bricks or mould on time between solid and hollow slabs
3.46 2
formwork
construction in construction projects
Time required to place reinforcement in ribs 3.42 3 is accepted. Thus, there is difference in
the construction time of the method of
Time required to place concrete 2.15 4 construction of solid and hollow slabs.
The same test was also done on pre-
Time required to cure 3.94 5
cast method and the result is tabulated
Time required to strike off formwork 2.74 6 in Table 6.
Std. Deviation = Standard Deviation,
(Precast solid slab) Std Error = Standard Error, Df = Degree
of Freedom, Sig. = Significance and
Time required for off-site fabrication. 3.52 1 N = 46
Time required for transportation
Table 6 above shows a paired sample
3.33 2 t-test on difference in construction time
of units to site.
between precast solid and precast hollow
Time required for erection and placement
3.28 3 slabs in construction projects. The value
of units on site.
of t (df = 45) is 1.594, P < 0.05 with a two
Time required for grouting and casting topping 3.09 4 tailed P value, sig.(2-tailed) of .118, t
is significant at 5% level. Since 0.118
(Precast hollow slab)
is greater than 0.05 therefore the null
Time required for off-site fabrication. 3.48 1 hypothesis Ho; there is no significant dif-
ference in the construction time between
Time required for transportation of units to site. 3.26 2 cast in situ solid and cast in situ hollow
floor slabs construction in construction
Time required for erection and placement
2.98 3 projects is accepted for precast system.
of units on site.
This is expected because precast solid
Time required for grouting and casting topping 2.76 4 and hollow slabs are all manufactured
in the factory and all brought to site for
Table 3. Process of reinforced concrete slab construction erection and placement. The same pro-
cess of construction applies to all precast
units unlike cast in situ.
Duration of construction Mean Value

Cast in situ hollow slabs to solid Discussion of Findings


3.00
slab It was revealed that, the system or
method of slab construction well known
Cast in situ floors to precast floors
2.98 to the respondents is cast in situ with a
system
mean value of 3.93, precast and semi-
Table 4. Duration of construction process of solid and hollow slabs precast with mean value of 3.43 and 2.63

o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 991
Variables
Std. Error Sig.
(Time Mean Std. Deviation t df Decision
Mean (2-tailed)
comparison)

Cast in situ
solid slab & Significant
-2.457 3.908 .576 - 4.263 45 .000
Cast in situ (Accept H1)
Hollow slab

Std. Deviation = Standard Deviation, Std Error = Standard Error, Df = Degree of Freedom, Sig. = Significance and N = 46

Table 5. Paired sample t-test on Difference in construction time between cast


in situ solid and cast in situ hollow slab

Variables
Std. Std. Error Sig.
(time Mean t df Decision
Deviation Mean (2-tailed)
comparison)

Precast
Not
solid slab
.739 3.144 .464 1.594 45 .118 Significant
& Precast
(Accept H0)
Hollow slab

Std. Deviation = Standard Deviation, Std Error = Standard Error, Df = Degree of Freedom, Sig. = Significance and N = 46

Table 6. Paired sample t-test on Difference in construction time between precast solid and precast hollow slab

and are ranked 2nd and 3rd respectively. shows vividly that most respondents reinforced hollow concrete slab and
This means that the respondents are only know about precast beam and reinforced solid concrete slab revealed
familiar with cast in situ and pre cast/ slab, flat slab and hollow slab construc- that time required to place reinforce-
prefabrication method while in the case tion but knows less to nothing about ments, time required for formwork con-
of semi precast method, they are not precast waffle. struction and the time required for the
familiar with the method. The findings In terms of the level of usage, the concrete to cure are the three highest
correspond with Idrus and Newman, study revealed that cast in situ beam activities and are ranked 1st, 2nd and
(2002) and Seeley, (1995) in terms of and slab construction is the most used, 3rd respectively. While the required
their classification of solid slab construc- followed by flat slab while hollow block time to place concrete and the time
tion. They classified solid slab construc- slab and waffle slab construction are required strike-off formwork are the
tion in majorly cast in situ and precast less used. This implies that most two least activities and are ranked 4th
while semi precast was out of their clas- respondents use very often in construc- and 5th respectively for cast in situ
sifications. Therefore, the major classi- tion, cast in situ beam and slab, flat slab system of construction. Critically, this
fication of slabs construction methods and hollow slab while hollow block and means that placing reinforcement and
are cast in-situ and precast. waffle are rarely used in construction. construction of formwork takes more
Beam and slab construction of slab Of the pre-cast, precast beam and slab time than other process in solid slab
was discovered to be well known to the construction, precast flat slab construc- construction process or method. On the
respondents followed by flat slab and tion, pre-cast hollow clay pot slab con- process of construction of reinforced
hollow clay pot slab while the respon- struction are mostly used while waffle cast in situ concrete hollow slab, time
dents do not have a good knowledge of construction is the least used. One can required for formwork construction,
waffle slab construction under cast in then say, that cast in situ construction time required to place hollow bricks
situ method. Under precast method of method is most used in Nigeria con- or blocks or moulds on formwork and
construction, beam and slabs construc- struction industry while precast is still time required to cure concrete are the
tion is well known in the construction breeding or used mostly for special three highest activities and ranked 1st,
industry followed by precast flat slab construction that requires it. 2nd and 3rd respectively. While time
while the least known on the table is The result of the level of time required in laying reinforcement in ribs,
precast waffle slab construction. It then required in construction process of required time to place concrete and the

992 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(1)2014


choice of concrete floor system. Journal of
time required to strike-off formwork are Conclusions Construction Management and Economic.,
the three least and are ranked 4th, 5th At the design stage, the choice of slab (2002), 20, 13 – 19. Taylor and Francis Ltd.
and 6th respectively. It then implies that and its construction time or period 0144 – 6193.
formwork construction, placing hollow for any project should be critically Kadir, M. R. Abdul, Lee, W.P., Jaafar, M.S.,
bricks or mould on formwork and curing examined and analyzed to determine Sapuan, S. M. and Ali, A. A. A. (2006):
takes more time than other process in its implication on the total duration of Construction performance comparison
hollow slab construction process or the project so as to avoid prolonged between conventional and industrialised
method. Precast concrete slab have a construction period or unanticipated building systems in Malaysia. Structural
different construction method or pro- delay in the project delivery time which Survey. 24 (5), 412-424.
cess from what is obtained in cast in could be unpleasant to clients’ cash Lai Tina. (2010): Structural behaviours of
situ. Here, the units are manufacturer flow and anticipations bubble deck slabs and their applications to
off site and brought to site for erection. Under the cast in-situ system, beam light weight bridge deck. A Master’s Thesis

Time required for off-site fabrication and slab construction is mostly used Submitted to the Department of Civil and

of units and transportation of units to among the identified list, followed by Environmental Engineering, Massachusetts
Institutes of Technology. Massachusetts,
site are the two highest and are ranked flat slab, hollow clay pot and waffle
USA.
1st and 2nd respectively while the time slab construction respectively. This is
required in erecting and placing units in evident as most upper floor slabs of Lutz Clemens. (2002): Prestressed hollow core
concrete slabs – Problems and possibilities
position, and time required in grouting residential and some office buildings
in fastening techniques.Otto-Graf-Journal.
and casting toppings are least as they in Nigeria are constructed of beam
(2002), 13.
are ranked 3rd and 4th respectively for and slab while newer office buildings,
Rupasinghe, R., and Nolan, E. (2007): Formwork
precast solid slab. On precast hollow commercial and other heavy engineer-
for modern, efficient concrete construction.
core/hollow slab, time required for ing buildings are now constructed of
Publication of BRE. Garston, Watford.
off-site fabrication of units and trans- hollow slabs, flat slabs and waffle
U.K.978-1-86081-975-9.
portation of units to site are the two slabs. While under pre-cast system,
Rwamamara, R., Simonsson, P., and Ojanen, J.
highest and are ranked 1st and 2nd precast beam and slab construction,
(2010): Advantages of industrialized methods
respectively while the time required pre-cast hollow core or hollow slab and
used in small bridge construction.Poster
in erecting and placing units in posi- other forms of precast slabs are not session of the Proceedings at IGLC-18, (July),
tion, and time required in grouting and often used, thus, one can then say that Technion, Haifa, Israel.
casting toppings are least as they are based on the result of the study, cast in
Seeley, H. Ivor. (1995): Building Technology (5th.
ranked 3rd and 4th respectively. The situ construction method is most used Ed). Hampshire, UK: PALGRAVE.
study therefore affirms that the duration in Nigeria construction industry while
Vanderwerf, A. Pieter, and Ridsdale, C. (1998):
or time of construction of cast in situ precast is still under-used or are most
Concrete Floor Systems In Residential
hollow slab is higher than that of solid for special construction that requires it. Construction; Proliferation of homes built
slab. In the same vain, the duration of with insulating concrete forms inspires wider
construction of cast in situ slabs system References use of concrete floors.The Aberdeen Group.
is higher than that of precast system. Bimel. C., (1997): Guide for concrete floor and Scotland.
These shows that cast in situ hollow slab construction. Reported by American Visser, W. D. (2009): Which type of slab is
slab takes more time than cast in situ Concrete Istitute (ACI) committee 302.1R. the most effective solution to concrete
solid slabs as cast in situ construction USA. structures?. A Bachelor Degree Research
system takes more time to construct BS 8110, (1997): Structural Use of Concrete: Submitted the Department of Quantity
than precast slab. This findings sup- Part 1. Code of Practice for Design and Surveying, Faculty of Engineering, Built

ports, Yin et al, (2007) and Basri, (2008) Construction.Publication of British Standard Environment and Information Technology.

that, a significant time difference exists Institution, London. University of Pretoria. SA

between the construction of solid and C and CAA, (2003): Guide to long-span concrete
hollow cast in situ slabs, and that floors. Cement and Concrete Aggregates

there is also a significant time savings Australia 73b, Second Edition, (August), ISBN

between precast and cast in situ. 1 – 877023 – 09 – 4.

.Concrete Manufacturer Association, (2008):


Hollow core slab system; Information
Manual.First Edition.

Idrus, A. B and Newman, J. B, (2002):


Construction related factors influencing the

o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 993

You might also like