Professional Documents
Culture Documents
8
8
o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 985
Placing of reinforcement aggregate (sand, granite-19-25mm) and Construction of Monolithic Hollow
CCAA (2010) opined that the placement potable water. In addition to meeting Clay Pot Slab\
of reinforcement at strategic locations structural requirements, concrete for Hollow (Ribbed) floors are floors eco-
ensures great flexibility during the floors should provide adequate work- nomically designed and constructed
design and construction stages in in- ability, durability and strength neces- using hollow blocks, removable foams
situ concrete construction. Bimel and sary to obtain the required finish and or permanent voids former such as clay
Tipping (1997) stated that deformed floor surface profile (Bimel et al, 1997). pots. This type of floors have reduced
bars, bar mats, or welded wire rein- Concrete for floors, usually of mix 1:2:4- self weight compared to the solid slabs.
forcement usually are required in sus- 19mm is used on site. This batch is either This is due to the fact that some of
pended structural floors as part of the mixed by hand or by machine (mixer). the concrete in the neutral zone are
structural design. Reinforcements are A thorough mix is required to attain a removed. Ribbed slab are very adapt-
used to strengthen concrete for ten- required consistency and workability. able for accommodating a range of ser-
sion forces in structures as concrete In a situation where labours are used in vice openings. The methods of hollow
is weak in tension but strong in com- placing the concrete, the labours placed clay pot construction are as follows;
pression (Rwamamara, Simonsson, & the mixed concrete through head pans Construction or Laying of formwork,
Ojanen, 2010). Reinforcements are often carefully over the fixed reinforcements Placing of pots, Placing of reinforce-
delivered to sites in tonnes of standard and then vibrated to prevent any event ments, Pouring of concrete or casting
length in Nigeria and are later cut into void. The concrete is tapped to compact and Removal of formwork.
pieces of required length. The pieces are and give an even surface. The placed
then laid or placed on the form work, in concrete is allowed to set for at least 28 Construction of formwork
required or calculated spaces and then days with constant curing to attain its Formwork as described by Rupasinghe
fixed together by an experienced iron workable strength. and Nolan (2007) as a structure, usu-
fixer (bender) with a binding wire, in its In a situation where truck mixer is ally temporary, used to contain poured
final location or position. Rwamamara et used to mix and pneumatic concrete concrete to mould it to the required
al (2010) agreed with CCAA (2010) that pump or crane with bucket is used to dimensions and support until it is able
the placement of reinforcement on the discharge in position, the concrete is to support itself. It consists primarily
formwork on-site gives a great advantage pumped from the mixed truck through of the face contact material (platform)
of flexibility on site during placement. the pneumatic pump or carried through and the bearers that directly sup-
Generally, (BS 8110, 1997) the sizes of a bucket attached to a crane, up to the port the face (prop) contact material.
reinforcement used on sites varies from point of discharge and then discharged. Lightweight horizontal panel formwork
12mm – 25mm diameter, depending on Skilled masons immediately spread the systems used for slab construction gen-
the maximum moment to resist, and the concrete into position, tapped, com- erally consist of a series of intercon-
spaces between each bars varies from pacted and finished to requirement. The nected false work bays, independent
150mm – 250mm. floor is then left for 28 days to attain props or system scaffolds and sup-
After placement of reinforcement, its self-supportive strength before the porting pre-formed decking panels.
concrete spacers are used to maintain formwork is removed. The thickness of These can include primary beams span-
a good space between the formwork and the slab according to BS8110 (1997) is ning between props and supporting a
the bars to give a cover of at least 20mm. between 150 – 300mm depending on number of panels. This is similar to the
this is done to prevent the bars against the design. solid concrete slab formwork.
moisture attack and enhance fire resis- The constructions of the formwork for
tance. In solid slab construction, rein- Removal of the formwork hollow clay pot slabs are usually done
forcements are provided in both direc- After the concrete floor has attained in two ways. These are;
tions as shown above, except for one its 28 days strength or more, the form- 1. Constructing or laying the formwork
way solid slab that has its reinforcement work can then be struck off carefully by to cover the whole area of the floor
in just one direction. The provision of skilled carpenters. BS8110 (1997) sug- slab and then the pots laid on them.
reinforcement in two ways in a solid slab gested that formwork should be removed 2. Constructing or laying the formwork
is the aspect that affects delivery time. without shock, as the sudden removal just directly under the ribs of the pot.
of wedges is equivalent to an impact This form is actually the type that
Pouring or casting of concrete load on the partially hardened concrete. affects the time for formwork.
Floor concrete requirement differ from The code suggested also that formwork
those of other concrete used in the struc- should not be removed or struck off the
ture. Concrete is made up of cement, suffix of the slab earlier than 28 days.
o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 987
construction and time. Use of standard- construction, the neutral zone of the to delivery time. From these results, it
ized and optimized precast floor com- concrete is replaced with the hollow clay could be concluded that the difference
ponents where shuttering is avoided pots while in the case of hollow slabs, in actual labour productivity between
prove to be economical, fast and better the concrete in the neutral zone are conventional and precast system mainly
in quality. Some of the prefabricated removed without replacing it with any contributed by the cycle time (difference
flooring components available but other materials. Thus, voids or holes are of 76 per cent) rather than the crew size
not limited to, are: precast Reinforced formed within the slab system. These (difference of 18 per cent). Shorter cycle
Concrete slabs/ planks and precast also give a significant advantage over time implies that total project construc-
hollow concrete panels. the conventional solid slabs in terms of tion time would also be reduced, hence
reduced material usage (reinforcement minimizing management overhead and
Pre-cast Hollow Concrete Slab and concrete), reduced cost, enhance meaning that owners can occupy their
Hollow core floor planks (slabs) are structural efficiency, decrease construc- house earlier. Visser, (2009) discov-
precast, prestressed units produced tion time and it is a new technology in ered that waffle moulds or precast brick
on long-line casting beds using slide the construction industry. Lutz (2002) result into additional time of construc-
forming or extrusion methods. During investigated hollow floors from the tion for in situ hollow slabs due to the
manufacturing, cores are formed aspect of prefabrication. In this method, placement of forms on slab formwork,
throughout the length of the unit, the floor is manufactured or prefabri- erection time amounts to the time it
reducing its self-weight. Planks or slabs cated from the factory and just brought takes to construct a flat slab, with the
are usually 1200-mm-wide, though it to site for assemblage through anchor- additional time of moulds placement.
could be produce 2400-mm-wide units. age. The advantage of this method in Fixing of reinforcement between forms
These wider units may require increased material saving, good quality control, can also prove to be a more time con-
crane capacity but offer greater speed and delivery in time and within cost, suming task. The fixing of steel rein-
of placement, less joints, grouting and can not be compared to the in-situ forcement in between and on top of the
sealing. Thicknesses of slabs vary from construction. moulds or bricks is also more strenu-
150–400 mm in 50-mm increments. The Hollow floors, which could also be ous than on a flat surface and proves
thickness is determined by span, load- called hollow core slabs can be used to be more labour intensive. Thus, the
ing, fire rating and cover to reinforce- for most applications requiring a floor construction period for in-situ hollow
ment to satisfy exposure conditions. system in Office buildings, auditori- slabs may be higher than that of solid
The economical typical span for a pre- ums, hotels, commercial buildings, slabs due to the placement of moulds
cast hollow core unit is approximately residential dwellings, houses of wor- or bricks to form the hole on site. Basri,
D x 30 to D x 35 where D is the depth of ship, nursing homes and educational (2008) Captured in the study of con-
the precast unit plus topping. Where facilities, are all ideal applications. This struction period as one of the critical
slenderness ratios fall between 35:1 is because of the advantage it gives in factor in the choice of a slab system
and 45:1, panels should be checked large span and of course its aesthetics that, 83% of the respondents agreed
for vibration-resonance effects. Spans cannot be compared to that of the solid that precast construction would result
exceeding 45:1 should not be used. slabs. In either way, floor slabs could be to faster completion of projects. In this
Planks may be used as plain sections fabricated off- site (as pre-fabricated survey, 100% of the projects were either
or topped to give a composite unit. The or pre-cast) and just brought to site completed in the same period of time
topping increases plank capacity and for assemblage. The eventual on-site as conventional construction; or even
fire rating. It provides a level surface assemblage of these slabs will require faster. 26% of the projects cut the 83%
or drainage falls and is recommended newer technology and methods differ- construction time while 52% recorded
for most building work. For economy, ent from the entire on-site construction. an astonishing savings in time. Of
the structure should be dimensioned Floors, which is a component part of a cause, it is logical to note that the
to accommodate the 1200- or 2400-mm building was major course of the study. off-site production of the floor system
modular plank width (CCAA, 2003). has reduced greatly the on-site time
Lai (2010) attested to the fact that Construction Period required for construction. Because on-
holes or voids which are created in Comparison Between Hollow site activities are only left with hoisting,
the floors replace the ineffective con- Slabs And Solid Slabs System placing and finishes which takes less
crete in the neutral zone of the slab, Kadir, (2006) discovered that signifi- time and less work force. It then clearly
thereby decreasing the dead weight cant difference occur between in-situ showed that the reduction in construc-
and increasing the efficiency of the slab construction and precast system tion time is the most obvious benefit of
slab. For instance, in the clay pot slab up to about 76 per cent, with respect precast system of slab constructions.
o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 989
Types of slab construction precast hollow core/hollow slab, time
Mean Value Rank
(Cast in situ)
required for off-site fabrication of units
Beam and Slab 3.96 1 and transportation of units to site with
Flat Slab 3.65 2 mean value of 3.48 and 3.26 are the
two highest mean and are ranked 1st
Hollow Clay Pot 3.24 3
and 2nd respectively while the time
Hollow Block 2.80 4 required in erecting and placing units in
Waffle Floor 2.39 5 position, and time required in grouting
and casting toppings with mean value
(Precast)
of 2.98 and 2.76 are least as they are
Beam and Slab 3.37 1 ranked 3rd and 4th respectively.
Flat Slab 3.17 2
Duration of construction
Hollow Clay Pot 2.39 3
process of slabs
Hollow Block 2.13 4 Table 4 shows the result of response
Waffle Floor 2.11 5 of the respondents on duration of cast
in situ hollow slab to solid slab and
Note: Well Known = 4, Known = 3, Fairly Known = 2, Not Known = 1, No Response = 0, cast in situ to precast slabs. Majority
Percentage = % and Total Number of Respondents = N
of the respondent affirms that dura-
Table 2. Level of Usage of types of floor slab by the respondents tion or time of construction of cast in
situ hollow slab is higher than that of
solid slab (36 respondents) while just
Table 3 below. The table has four sec- 1st, 2nd and 3rd respectively. While only 10 respondents affirm that the
tions which are cast in situ solid slab, time required in lay reinforcement in construction duration is lower. In the
cast in situ hollow slab, precast solid ribs, required time to place concrete same vein, majority of the respondents
slab and precast hollow slab. On the and the time required strike-off form- (35 respondents) affirms also that the
process of construction of reinforced work with mean value of 3.15, 2.97 and duration of construction of cast in situ
cast in situ concrete solid slab, time 2.74 are the three least mean values slabs system is higher than that of pre-
required to place reinforcements, and are ranked 4th, 5th and 6th respec- cast system, while 10 and 1 respondent
time required for formwork construc- tively. It then implies that formwork did not obliged as they settled for low
tion and the time required for the con- construction, placing hollow bricks or and very low respectively. These shows
crete to cure with mean value of 3.93, mould on formwork and curing takes that cast in situ hollow slab takes more
3.72 and 3.22 are the three highest more time than other process in hollow time than cast in situ solid slabs as cast
mean values and ranked 1st, 2nd and slab construction process or method. in situ construction system takes more
3rd respectively. While the required Precast concrete slab have a differ- time to construct than precast slab.
time to place concrete and the time ent construction method or process
required to strike-off formwork with from what is obtained in cast in situ. Testing of Hypothesis
mean value of 3.15 and 2.78 are the Here, the units are manufacturer off site Null Hypothesis (Ho): There is no signifi-
two least mean values and are ranked and brought to site for erection. Table 3 cant difference in the construction time
4th and 5th respectively. It thus, means below also shows various time required between solid and hollow floor slabs
that placing reinforcement and con- for various process of precast slab con- construction in construction projects.
struction of formwork takes more time struction. On precast solid slab, time Alternative Hypothesis (H1): There is
than other process in solid slab con- required for off-site fabrication of units significant difference in the construc-
struction process or method. On the and transportation of units to site with tion time between solid and hollow
process of construction of reinforced mean value of 3.52 and 3.33 are the floor slabs construction in construction
cast in situ concrete hollow slab, time two highest mean and are ranked 1st projects.
required for formwork construction, and 2nd respectively while the time To test this hypothesis, a paired
time required to place hollow bricks or required in erecting and placing units in sample t-test analysis was used.
blocks or moulds on formwork and time position, and time required in grouting Table 5 above shows a paired sample
required to cure concrete with mean and casting toppings with mean value t-test on difference in construction time
value of 3.70, 3.46 and 3.24 are the of 3.28 and 3.09 are least as they are between cast in situ solid and hollow
three highest mean values and ranked ranked 3rd and 4th respectively. On slabs in construction projects. The value
o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 991
Variables
Std. Error Sig.
(Time Mean Std. Deviation t df Decision
Mean (2-tailed)
comparison)
Cast in situ
solid slab & Significant
-2.457 3.908 .576 - 4.263 45 .000
Cast in situ (Accept H1)
Hollow slab
Std. Deviation = Standard Deviation, Std Error = Standard Error, Df = Degree of Freedom, Sig. = Significance and N = 46
Variables
Std. Std. Error Sig.
(time Mean t df Decision
Deviation Mean (2-tailed)
comparison)
Precast
Not
solid slab
.739 3.144 .464 1.594 45 .118 Significant
& Precast
(Accept H0)
Hollow slab
Std. Deviation = Standard Deviation, Std Error = Standard Error, Df = Degree of Freedom, Sig. = Significance and N = 46
Table 6. Paired sample t-test on Difference in construction time between precast solid and precast hollow slab
and are ranked 2nd and 3rd respectively. shows vividly that most respondents reinforced hollow concrete slab and
This means that the respondents are only know about precast beam and reinforced solid concrete slab revealed
familiar with cast in situ and pre cast/ slab, flat slab and hollow slab construc- that time required to place reinforce-
prefabrication method while in the case tion but knows less to nothing about ments, time required for formwork con-
of semi precast method, they are not precast waffle. struction and the time required for the
familiar with the method. The findings In terms of the level of usage, the concrete to cure are the three highest
correspond with Idrus and Newman, study revealed that cast in situ beam activities and are ranked 1st, 2nd and
(2002) and Seeley, (1995) in terms of and slab construction is the most used, 3rd respectively. While the required
their classification of solid slab construc- followed by flat slab while hollow block time to place concrete and the time
tion. They classified solid slab construc- slab and waffle slab construction are required strike-off formwork are the
tion in majorly cast in situ and precast less used. This implies that most two least activities and are ranked 4th
while semi precast was out of their clas- respondents use very often in construc- and 5th respectively for cast in situ
sifications. Therefore, the major classi- tion, cast in situ beam and slab, flat slab system of construction. Critically, this
fication of slabs construction methods and hollow slab while hollow block and means that placing reinforcement and
are cast in-situ and precast. waffle are rarely used in construction. construction of formwork takes more
Beam and slab construction of slab Of the pre-cast, precast beam and slab time than other process in solid slab
was discovered to be well known to the construction, precast flat slab construc- construction process or method. On the
respondents followed by flat slab and tion, pre-cast hollow clay pot slab con- process of construction of reinforced
hollow clay pot slab while the respon- struction are mostly used while waffle cast in situ concrete hollow slab, time
dents do not have a good knowledge of construction is the least used. One can required for formwork construction,
waffle slab construction under cast in then say, that cast in situ construction time required to place hollow bricks
situ method. Under precast method of method is most used in Nigeria con- or blocks or moulds on formwork and
construction, beam and slabs construc- struction industry while precast is still time required to cure concrete are the
tion is well known in the construction breeding or used mostly for special three highest activities and ranked 1st,
industry followed by precast flat slab construction that requires it. 2nd and 3rd respectively. While time
while the least known on the table is The result of the level of time required in laying reinforcement in ribs,
precast waffle slab construction. It then required in construction process of required time to place concrete and the
Time required for off-site fabrication and slab construction is mostly used Submitted to the Department of Civil and
of units and transportation of units to among the identified list, followed by Environmental Engineering, Massachusetts
Institutes of Technology. Massachusetts,
site are the two highest and are ranked flat slab, hollow clay pot and waffle
USA.
1st and 2nd respectively while the time slab construction respectively. This is
required in erecting and placing units in evident as most upper floor slabs of Lutz Clemens. (2002): Prestressed hollow core
concrete slabs – Problems and possibilities
position, and time required in grouting residential and some office buildings
in fastening techniques.Otto-Graf-Journal.
and casting toppings are least as they in Nigeria are constructed of beam
(2002), 13.
are ranked 3rd and 4th respectively for and slab while newer office buildings,
Rupasinghe, R., and Nolan, E. (2007): Formwork
precast solid slab. On precast hollow commercial and other heavy engineer-
for modern, efficient concrete construction.
core/hollow slab, time required for ing buildings are now constructed of
Publication of BRE. Garston, Watford.
off-site fabrication of units and trans- hollow slabs, flat slabs and waffle
U.K.978-1-86081-975-9.
portation of units to site are the two slabs. While under pre-cast system,
Rwamamara, R., Simonsson, P., and Ojanen, J.
highest and are ranked 1st and 2nd precast beam and slab construction,
(2010): Advantages of industrialized methods
respectively while the time required pre-cast hollow core or hollow slab and
used in small bridge construction.Poster
in erecting and placing units in posi- other forms of precast slabs are not session of the Proceedings at IGLC-18, (July),
tion, and time required in grouting and often used, thus, one can then say that Technion, Haifa, Israel.
casting toppings are least as they are based on the result of the study, cast in
Seeley, H. Ivor. (1995): Building Technology (5th.
ranked 3rd and 4th respectively. The situ construction method is most used Ed). Hampshire, UK: PALGRAVE.
study therefore affirms that the duration in Nigeria construction industry while
Vanderwerf, A. Pieter, and Ridsdale, C. (1998):
or time of construction of cast in situ precast is still under-used or are most
Concrete Floor Systems In Residential
hollow slab is higher than that of solid for special construction that requires it. Construction; Proliferation of homes built
slab. In the same vain, the duration of with insulating concrete forms inspires wider
construction of cast in situ slabs system References use of concrete floors.The Aberdeen Group.
is higher than that of precast system. Bimel. C., (1997): Guide for concrete floor and Scotland.
These shows that cast in situ hollow slab construction. Reported by American Visser, W. D. (2009): Which type of slab is
slab takes more time than cast in situ Concrete Istitute (ACI) committee 302.1R. the most effective solution to concrete
solid slabs as cast in situ construction USA. structures?. A Bachelor Degree Research
system takes more time to construct BS 8110, (1997): Structural Use of Concrete: Submitted the Department of Quantity
than precast slab. This findings sup- Part 1. Code of Practice for Design and Surveying, Faculty of Engineering, Built
ports, Yin et al, (2007) and Basri, (2008) Construction.Publication of British Standard Environment and Information Technology.
between the construction of solid and C and CAA, (2003): Guide to long-span concrete
hollow cast in situ slabs, and that floors. Cement and Concrete Aggregates
there is also a significant time savings Australia 73b, Second Edition, (August), ISBN
o. a. adenuga · g. sotunbo an assessment of time variation in solid and hollow floor construction in lagos state · pp 985 - 993 993