SSRG International Journal of Civil Engineering (SSRG-IJCE) – Volume 6 Issue 5–May 2019

Delay Analysis of Flyover Bridge


Construction Using Primavera
1
Dilip Kumar E, 2Manishankar S
1
P.G. Scholar, Construction Engineering and Management, Mahendra Engineering College, Mallasamudram,
Namakkal, India
2
Assistant professor, Department of Civil Engineering, Mahendra Engineering College, Mallasamudram,
Namakkal, India

Abstract down of work without stopping construction


Delay is most common problem in the entirely and that can lead to time overrun either
construction industry. Project Scheduling and delay beyond the contract date or beyond the date that
analysis became an important a part of any project the parties have agreed upon for the delivery of
for completion of the project among the planned time
the project. Delays classified into non excusable
and cost. The application of construction schedule to
predict the project completion time. Delay in delays, excusable non compensable delays,
completion of project can increase the price of the excusable compensable delays and concurrent
project. Small projects will be managed with delays.
efficiency manually; whereas massive projects
aren't therefore massive projects will be better Delays in a construction project can be such
handled by the utilization of computers. In this a problem and a very serious issue for the parties
junction multinumber of software package are involved such as client, consultants and
offered with the assistance of that project contractors. There are many adverse effects that
management will be done simply. In bridge can occur as the results of the delays. To reduce
construction, totally different styles of resources
this problem from occurring, site management
are needed for execution and also the risk is
additional during this form of projects. So, should be made carefully. In our project
planning and scheduling is important task in massive conducted as the result of a various problems
projects. In our project an attempt is created in that arise in along with the delays in
scheduling and delay analysis of varied activities construction. There are different procedures to
concerned in flyover bridge construction in Salem be observed by all parties so that unwanted
district, Tamilnadu by using Primavera Software. things will not happen. Delays in construction
The Flyover bridge is 8111m length and its scheduled projects are of the utmost priority.
to 988 days. The primary goal of construction unit is
to complete the work as specific on schedule with B. Objective of the Study
correct utilization of all the resources like man
power, materials, cash and machinery. To achieve
the above goal is to execute the project most The main objective of this project is to
economically better in terms of money and time. The analyse the delays in a construction project by
main objective of this study is to analyse the delays in detailed literature study, site activities, and
construction of flyover bridge and also control the observations made were as follows.
time loss and cost manipulation of the project. a. Detailed literature study to define the
various reasons of delay in construction
Keywords: Delay analysis, Flyover Bridge, projects.
Primavera, Time and Cost b. Study on ongoing Project site to observe
the activities and to identify delay
I. INTRODUCTION
factors.
A. General c. Determination of Critical Path using
In construction, the word delay refers to Primavera.
something happening at a later time than d. The analysis also involves the process
planned, expected, and specified in a contract or of scheduling and tracking of a
beyond the date that the parties agreed upon for construction project activity in software
the delivery of a project. Delay is the slowing and related catch up programs due to
delays.

ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1


SSRG International Journal of Civil Engineering (SSRG-IJCE) – Volume 6 Issue 5–May 2019

delay have direct effect on time overrun and cost


II. LITERATURE REVIEW overrun for the whole project. Most of reasons
for delays are related with contractor. Some of
MuraliSambasivan and Yau wen soon the causes are beyond the control of all the
(2007) in research paper entitled "Causes and project parties such as differing site conditions,
effect of delay in Malaysian construction unforeseen weather etc. In the overall
industry", reviewed an integrated approach and responsibility of delay, contractor possesses near
attempted to analyze the impact of specific about most responsibility.
causes and specific effects of project delays.
They identified main causes and effects of delay
of construction projects in Malaysia by III. METHODOLOGY
conducting a properly designed questionnaire
survey with clients, consultants and contractors. Collection of Literatures
Also, they identified ten most important delay
causes and six important effects of delays and an
empirical relation between them was Selection of Study Area
established.
Field Investigation
Abd El-Razek. et al (2008) in their
research entitled “Causes of delay in Building
construction Projects in Egypt, a questionnaire Study on BOQ & Drawings
survey conducted and identified most important
causes of delay in construction project. They
concluded that owners and contractor‟s parties Study on Labour Productivity
do not agree on the relative importance of
various factors of delay, mostly blaming each
other of delays using importance index and Data entry in Primavera
spearman rank correlation. Survey results
suggested that joint team effort is required to
reduce delay. Setting of Baseline

B. Indhu, P. Ajai (May 2014) in the


case study entitled “Study of delay management Tracking of Schedule
in a construction project - A case study”
identified most important factors causing delay
and the effect of delay on the project duration. Comparison of Original with
Some of the factors causing delays are weather, Baseline schedule
no proper timely supply of budgets and
resources, contractor and client related and also
changes in design and drawing. The major Result & Conclusions
effects of delay are time and cost impact,
reduced labour productivity, postponement in
work, change in labour allocation etc. IV. ABOUT THE STUDY

Keval J. Shah, Prof. M. R. Apte Case study on a Flyover bridge construction


(2015) in the case study entitled “Causes of project consisting of 213 spans and length of
Delay in Construction of Bridge Girders”, bridge is 8111m including 9 approach ramps.
Frequent site visits were carried out in an
ongoing bridge girders construction project and A. Project Specification
collected the data from site for each activity of a). Structures
construction of bridge girder and compared with Reinforced Concrete Structure
its planned duration and actual duration.
Identified the important causes of delay and the b). Concrete
effect of these in the project duration. Causes of M15 grade - Levelling course / P.C.C. below

ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 2


SSRG International Journal of Civil Engineering (SSRG-IJCE) – Volume 6 Issue 5–May 2019

foundations and approach slabs. and time to accomplish the activities. A plan
M30 grade - Approach slabs. includes the following terms:
M35 grade - Foundations, Piles, Pile caps, a. Budget
Abutments, Piers, Pier caps, Dirt b. Estimate
wall and Bracket. c. Time schedule
M40 grade - Crash Barriers and Centre median. d. Sequence of completion of each part of
M50 grade - PSC Segmental and Cast in-situ work
Box Girders. e. Cash flow budget
f. Manpower planning
c). Prestressing
g. Equipment and material planning.
Post Tensioning with High Tensile Steel
Wires/Strands

d). Steel A. Steps involved in Project Planning


High Yield Strength Deformed Bars Fe-500D
A project planning involves following steps:
e). Expansion joint a. Define the scope of work
40mm Strip Seal expansion joint system. b. Preparing list of activities to be
performed
f). Bearings c. Preparing network diagram or a logic to
POT/PTEF bearings establish relationship among different
activities
g). Wearing Course d. Analyzing the network diagram to work
Mastic Asphalt 25mm thick out project period, vital and noncritical
Bituminous Concrete 40mm thick activities during a project
e. Determine the critical path with the
h). Painting assistance of critical activities Establish
Providing and applying 2 coats of water-based standards for the resources (material,
cement paint to unplaster concrete surface men, machinery and money)
f. Resources allocation
V. PROJECT PLANNING g. Forecasting budget allocation to achieve
the target
Project planning is a very fundamental h. Organization of project information
and challenging activity to execute work in all i. Recording the status report of every
construction project. Planning involves listing of activity
activities or tasks in a project, manpower, listing j. Comparing the recorded report with the
the requirement of materials, machineries and original plan
money to accomplish the tasks. Also cost
estimation is done through planning process. B. About Primavera
A good planning process helps in
budgeting and in preparing schedule for the Primavera Systems, Inc was a private
work. Main objective of a project planning is to company providing Project Portfolio
identify the various tasks and activities required Management (PPM) software to help project-
to accomplish a work and to estimate proper intensive organizations identify, prioritize, and
time for the accomplishment of that particular select project investments and plan, manage, and
activity considering inter relationship with other control projects and project portfolios of all the
sequential activities involved in that work. management team including project manager,
To develop a proper plan in any project is a planning manager, construction manager, quality
very critical task. Proper logic, time analysis and and safety in charges work as a whole for all the
scheduling are included in project planning. For activities. In other words, It is a tool that helps
a planning process, inputs will be taken from you build Program consisting of Activities with
estimating departments, project managers, field Resources (Materials, Manpower, Machinery,
engineers, foremen and contractors. Proper Money) against Time. It also helps in analysing
planning helps in providing adequate resources of Critical Path, perform Earned Value analysis

ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 3


SSRG International Journal of Civil Engineering (SSRG-IJCE) – Volume 6 Issue 5–May 2019

(when project is under progress), generate


reports such as Manpower Histogram, Monthly
Budget and Overall Budget.

VI. CONSTRUCTION DELAY


From this project study, the causes of the delay
Time is money and that is particularly reasons can be listed as below table 1
true on a construction project. When
construction projects don‟t run on time - the Delay in
contractor suffers because his overhead and S.No. Reason for delay
days
expenses increase (eating into profits), and the Traffic permission /
owner suffers because he cannot open his new 1 32
diversion delay
business on time, which causes lost profits that 2 Design issue 28
he could have been gaining. So, keeping projects
on their critical path schedules is very important. 3 Shortage of skilled labour 23
Nevertheless, delays on massive 4 Shortage of Materials 13
construction projects are common as a result of
construction projects are difficult and involve 5 Shortage of machinery 16
plenty of various players. Everyone has to be 6 Weather condition (Rain) 34
working together seamlessly to avoid delays.
And, when a project is delayed, the question that 7 Utility issues 14
is inevitably asked is who is responsible, if 8 Cash flow issues 18
anybody, for the costs associated with the delay.
This will, of course, rely fully on the language 9 Land acquisition 26
within the contract governing the project. Total 204

A. DELAY ANALYSIS RESULTS Table: 1 Reasons for delay in our project


The following reasons were determined
Item of % %
throughout this project work, which may be S.No.
Works Complete Incomplete
control accountable for delays,
 Lack of information regarding advanced 1 Foundation 99 1
construction techniques. 2 Pier 98 2
 Lack of trained workers.
 Lack of fund flow throughout the 3 Pier Cap 97 3
project progress. Casting of
4 100 0
 A major portion of working labor is Segments
from Andhra Pradesh and Bihar. 5 Cast In Situ 43 57
Regional festivals in these areas cause Erection of
fast delays in work progress. 6 64 36
Segments
 Sudden extension of monsoon rain
Crash
caused delay in project progress. 7 38 62
Barriers
 Sand non availability because of legal
Mastic
restrictions. 8 28 72
Asphalt
 Late delivery of resources.
Bituminous
 Improper planning of construction 9 28 72
Concrete
activities.
 Unforeseen underground utilities and Expansion
10 8 92
overhead utilities shifting/diversion Joint
delay. Approach
11 48 52
 Improper utilization of available Ramps
resources. 12 Painting 30 70

Table: 2 Work Completion Details as on Date

ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 4


SSRG International Journal of Civil Engineering (SSRG-IJCE) – Volume 6 Issue 5–May 2019

Completed works Incomplete works


REFERENCES

100
99
98
97

92
[1]. Abdulaziz A. Bubshait and Michael J. Cunningham

72
72

70
36 64
38 62
4357
(August 1998), "Comparison of delay analysis

52
48
methodologies", Journal of Construction Engineering

30
28
28
and Management, pp 315-322.
[2]. Abdalla M. Odeh and Hussaien T. Battaineh (2002),

8
3
2
1

0 “Causes of Construction delay: traditional contracts”,


International Journal of Project Management,
PERGAMON, 20, pp 67-73.
[3]. Sadi A. Assaf and Sadiq Al-Hejji (2006), „„Causes of
delay in large construction projects”, International
Journal of Project Management, ELSEVIER, 24, pp
349-357.
[4]. Aswathi R and Ciby Thomas (December 2013),
“Development of a Delay Analysis System for a
Railway Construction Project”, International Journal of
Innovative Research in Science, Engineering and
Technology, ICEE, Vol. 2, Special Issue 1, pp 531-541.
[5]. MuraliSambasivan and Yau Wen Soon (2007), “Causes
VII. CONCLUSION and Effects of Delays in Malaysian construction
industry”, International Journal of Project Management,
25, pp 517-526.
Based on our case study the [6]. M.E. Abd El-Razek, H.A. Bassioni and A.M. Mobarak
Construction started on February 2016 and the (Nov. 2008), “Causes of delay in Building construction
Projects in Egypt, Journal of Construction Engineering
duration of Project as per baseline Schedule is and Management, ASCE , pp 831- 841.
988 days. Tracking till April 2019 revealed 99% [7]. B. Indhu and P. Ajai (May 2014), “Study of Delay
completion of foundation and substructure work Management in a Construction Project – A Case
Study”, International Journal of Emerging Technology
and 100% casting of precast segments and 64% and Advanced Engineering, Vol. 4, Issue 5, pp 108 –
erection of segments, over all completion of the 113.
[8]. Keval J. Shah and Prof. M. R. Apte (2015), “Causes of
project is 58%. Causes of delay in our project Delay in Construction of Bridge Girders”, IOSR
are identified by direct site visit and predict the Journal of Mechanical and Civil Engineering (IOSR-
approximate date for completion of the project. JMCE), Volume 12, Issue 1 Ver. IV, pp 08-12.
From our case study the most important causes [9]. SreeLekshmi A and Vishnu Unnikrishnan (June 2018).
“Planning and Delay Analysis of a Residential
of delays in our bridge project is Traffic Complex: A Case Study”, International Journal of Civil
permission/diversion delay because of this Engineering and Technology, Vol. 9, Issue 6, pp 1191-
project is located at five road junction to bus 1201.
stand, delay in utility shifting/diversion, delay in
design works, shortage of resources and land
acquisition delay.

RECOMMENDATIONSFOR FUTURE STUDY

In this research we have studied causes


of delay in Flyover bridge construction. It is
recommended to further study and analyse the
cost of delayin this project.

ACKNOWLEDGEMENT

I am very grateful to all authors in


reference section. Their methods, conceptual
techniques were very helpful for my research.
All papers in the reference section were very
useful for my work.