1.

Manhour Estimations and Staffing plan update for Project Scope of Work
2. Package preparation, , workload allocation and coordination with designers,
3. Quality checking of design drawings, which include Piping layouts, Plot Plans and
Isometric Drawings for Maintain Potential Projects
4. Preparation of Safety Instruction sheets (Pipe thickness calculation sheets)
5. Preparation of Valve data sheets for procurement activities and Preparation of
Mechanical BOQ for all areas including MPP Gas Remote headers
6. Preparation of Material Takeoff’s for the packages by selecting proper materials as per
the piping Material Specifications
7. Attending Weekly and monthly Scrums with the clients to discuss the progress and the
actions needed to achieve the milestone dates.
8. Inter discipline coordination and Attending Across Board Review meetings with Other
disciplines
9. Leading and Mentoring the Junior Discipline Engineers and allocating work to individuals
10. Handling TQ's (Technical Queries) for all areas, resolving the issues raised by
construction contractor/Client either by coordinating with them or by providing suitable
solution
11. Final complete package check and package submission on a scheduled time without
affecting any stream.