You are on page 1of 8

CRITICAL PATH METHOD (CPM)

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-1
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
CRITICAL PATH METHOD (CPM)
PROYEK PAKET 3 : PEMBANGUNAN AGLC, ASLC DAN IFFLC

Notasi :
Activity (A) ES : Early Start Time
ES EF
i LS Durasi (d)
j LF
EF
LS
: Early Finish Time
: Latest Start Time
LF : Latest Finish Time
i, j : Nomor Event
d : Durasi

Perhitungan :
Forward Pass (Perhitungan ke Muka):
EF = ES + d

Backward Pass (Perhitungan ke Belakang):


LS = LF – d

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-2
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
Notasi Pekerjaan :
Durasi
No Nama Pekerjaan Predesessors
(Days)
1 A Start 0 SS
2 B Preparation Works 295 1SS
3 C Sub Structure (AGLC Building) 47 2SS
4 D 1st Floor (-0.020) (AGLC Building) 24 3SS
5 E 2nd Floor (+4.980) (AGLC Building) 24 4SS
6 F 3rd Floor (+9.480) (AGLC Building) 29 5SS
7 G 4th Floor (+13.980) (AGLC Building) 34 6SS
8 H 5th Floor (+22.980) (AGLC Building) 39 7SS
9 I 6th Floor (+22.980) (AGLC Building) 40 8SS
10 J Roof (+27.500; +30.000) (AGLC Building) 9 9SS
11 K Metal Works (AGLC Building) 77 10SS
12 L Architectural Works (AGLC Building) 191 11SS
13 M Elelctrical Works (AGLC Building) 191 12SS
14 N Mechanical Works (AGLC Building) 191 13SS
15 O Site Constraction Works (AGLC Building) 213 14SS
16 P Defect & Test Com (AGLC Building) 52 345SS
17 Q Elevation -3.20 (ASLC Building) 37 3ss
18 R Elevation -2.20 (ASLC Building) 23 17SS
19 S Elevation +1.92 (ASLC Building) 19 18SS
20 T Elevation +6.92 (ASLC Building) 24 19SS
21 U Elevation +11.42 (ASLC Building) 31 20SS
22 V Elevation +15.92 (ASLC Building) 38 21SS
23 W Elevation +20.42 (ASLC Building) 41 22SS
24 Q Elevation +25.00 (ASLC Building) 12 23SS

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-3
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
Notasi Pekerjaan :
Durasi
No Nama Pekerjaan Predesessors
(Days)
25 Y Work Roof Truss (ASLC Building) 30 24SS
26 Z Architectural Works (ASLC Building) 205 25SS
27 AA Electrical Works (ASLC Building) 205 26SS
28 AB Mechanical Works (ASLC Building) 205 27SS
29 AC Site Construction Works (ASLC 191 28SS
Building)
30 AD Defect & test Com (ASLC Building) 48 29SS
31 AE Elevation -1.60 (IFFLC Building) 31 3SS
32 AF Elevation -0.60 (IFFLC Building) 14 31SS
33 AG Elevation +4.95 (IFFLC Building) 15 32SS
34 AH Elevation +9.45 (IFFLC Building) 19 33SS
35 AI Elevation +13.95 (IFFLC Building) 24 34SS
36 AJ Elevation +18.45 (IFFLC Building) 29 35SS
37 AK Elevation +22.95 (IFFLC Building) 30 36SS
38 AL Elevation +27.45 (IFFLC Building) 35 37SS
39 AM Roof (Elevation +33.50) (IFFLC 8 38SS
Building)
40 AN Work Roof Truss and Cover (IFFLC 22 39SS
Building)
41 AO Architectural Works (IFFLC Building) 212 40SS
42 AP Electrical Works (IFFLC Building) 212 39SS
43 AQ Mechanical Works (IFFLC Building) 212 40SS
44 AR Site Construction Works (IFFLC 178 41SS
Building)
45 AS Defect & Test Com (IFFLC Building) 49 44SS
46 AT Hand Over 1 30FS
47 AU Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk.
Finish 0 46FS CPM-4
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
CRITICAL PATH METHOD (CPM)

C
Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-5
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
CRITICAL PATH METHOD (CPM)

DETAIL A

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-6
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
CRITICAL PATH METHOD (CPM)

DETAIL B

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-7
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.
CRITICAL PATH METHOD (CPM)

DETAIL C

Proposal teknis ini merupakan hak cipta PT. Wijaya Karya Bangunan Gedung, Tbk. CPM-8
WIKA-WG KSO
Dilarang mengcopy dan menggandakan isi dari proposal teknis ini tanpa seijin PT. Wijaya Karya Bangunan Gedung, Tbk.