PROPOSED WORFLOW FOR OBPAS – BUILDING PERMISSION DEPARTMENT

Architect files the common Application Form as given in DCPR


(Appendix A1), uploads the Necessary Documents including
Documents needed for Fire as per given “Documents List” and
CAD Drawings and Drawing PDF.

ATP peruses the submitted Documents Scrutiny runs on OBPAS system

Reject Approve Approve Reject

If both things approved

Automated Scrutiny Challan

Paid within 7 Days Not Paid within 7 Days

Site Visit by Planning Assistant and scrutiny by Assistant Town Planner

Reject Approve with generation of draft challans and prepare Commencement Certificate

Scrutiny by Town Planner Scrutiny by Fire Department

Return to ATP Approve Approve Return to ATP

Scrutiny by Metropolitan Planner

Return to ATP Approve

Scrutiny by Metropolitan Commissioner

Return to ATP Approve

ATP will generate Final Challans

Payment by owner within 15 days, if not paid within 15 days automated revised value must be shown to owner

Commencement Certificate issues automatically