Professional Documents
Culture Documents
MECH350 Lecture 9
MECH350 Lecture 9
Engineering Design I
University of Victoria
Dept. of Mechanical Engineering
Lecture 9:
Project Planning
Outline:
T T
Fig. A Fig. B
The TF for each activity in the Table, is the amount of time by which
that activity can be delayed, without causing a delay in the project
duration.
Any delay in an activity that is on the critical path, will cause a delay
in the project duration.
Note: The values to and tp represent the left and right terminus
respectively, of a Beta probability density function.
z* -3.00 -2.75 -2.50 -2.25 -2.00 -1.75 -1.50 -1.25 -1.00 -0.75 -0.50 -0.25 0.00
Pr(z < z*) 0.001 0.003 0.006 0.012 0.023 0.040 0.067 0.106 0.159 0.227 0.308 0.401 0.500
Table 5.1. Abbreviated Table of Cumulative Distribution Function for the Standard Normal Distribution.
[ Hyman, Fundamentals of Engineering Design]
PERT has all the benefits of CPM, plus, you can make realistic
estimations of activity durations that account for uncertainty in the
estimates.