January 04, 2020(Saturday)
1. Concreting Works
a. High Dam Diversion Tunnel
i. Type of Concrete used: D3-Modified
ii. Structure: Upper Lining, Sta. 11+00~11+10
iii. Volume: 87 m3
iv. Max Temp: 32.1°C
v. Max Slump: 210 mm
vi. Time: 1511~1847 hrs
2|Page
January 08, 2020(Wednesday)
January 09, 2020(Thursday)
1. Concreting Works
a. Alibunan Catch Dam- Intake Barrel(Connecting Barrel)
i. Type of Concrete used: D1
ii. Structure: Leader Lining, Sta. 15+15~16+00,16+05~16+10
iii. Volume: 59 m3
iv. Max Temp: 30.6°C
v. Max Slump: 150 mm
vi. Time: 1441~1841 hrs