Corrective/ Preventive Action Report FORM: QA/QC-002

Contractor: Departmental Representative


DAEWOO E & C
Contact Name: Contract No.

Contractor Representative: Fax Telephone: Fax:

Telephone NCR No.

Signature Date Signature Date

Completion Verification of
Details of Non Conformance Action Required
Date Completion
1. Non Compliance of
Compressive Strength
required for 28 days

2.

3.

Photos
Before After

Preventive Action Required


1. Re-check Design Mix for Dam Body (Modified C) against actual productions.
2. Aggregates frequency test for daily testing such as gradation and moisture content
should be strictly implemented.
3. Proper curing and handling of samples should be observed.