Main contractor : YBS Tenaga Sdn Bhd

Sub Contractor : Karisma Energy & Construction


Sdn Bhd

PROPOSED WORK PLAN FOR DEFECT WORK AT PMU PANDAN MESRA

No Start End Date


No Activity Remarks
days date date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 To provide FRP garting for drain & sump 00-Jan done

2 To close floor opening (gap) at walkway with Chequred plate 7 03-Apr 10-Apr

3 To rectify damage on anti vermin net at cable cellar room 7 03-Apr 10-Apr

4 To rectify door lock at Battery Room 3 03-Apr 06-Apr


5 To provide hook for roller shutter chain 1 03-Apr 04-Apr
6 To provide floor water trap at roof gutter done
7 To rectify malfunction door selector 7 03-Apr 10-Apr
8 To touch up epoxy paint 00-Jan done

9 To touch up wall painting ( due to change of break glass ) 7 05-Apr 12-Apr

10 To top up stone chipping at T6 bay 00-Jan done


11 To conduct house keeping 14 10-Apr 24-Apr
12 To label Building earth chamber 3 05-Apr 08-Apr
13 To update asbuilt drawing 30 03-Apr 03-May
00-Jan
00-Jan
00-Jan
00-Jan
00-Jan
00-Jan
00-Jan
00-Jan
TOTAL OF DAYS 79