OF LIFTS CALCULATIONS

Nestle Users = 1500


If 20% people of peak time then, = 1500x20/100 = 300 persons
3 min time Duration of elevator = 300/3 = 100
If 16 persons in 1 elevator at one time so,
100/16 = 6.25 no of elevators
So we require 6 elevators required for nestle users

Nestle Users = 1820


If 20% people of peak time then, = 1820x20/100 = 364 persons
3 min time Duration of elevator = 364/3 = 121
If 16 persons in 1 elevator at one time so,
121/16 = 7.58 no of elevators
So we require 8 elevators required for rental users