Table 1.2. Gantt Chart of Sugareé Corporation’s Projected Activities
2020 2021 2022 2023 2024 2025 TASK Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Feasibility Study and Project Planning Incorporation Sourcing of Funds Hiring of Key Personnel Plant Site Acquisition Finalize Plant Layout Design Finalize Design and Specification Plant Construction Bidding Plant Construction Order of Equipment Equipment Fabrication and Delivery Hiring of Personnel Installation of Equipment Order and Delivery of Raw Material Pilot Testing Product testing Marketing Plan Normal Operation