Professional Documents
Culture Documents
Hindalco - Q2FY11 - Presentation PDF
Hindalco - Q2FY11 - Presentation PDF
Investor Presentation
Q2 FY11
November 2010
Industry Backdrop
Results Highlights
Copper:
pp Business Conditions & p
performance Review
Projects – An Update
Industry Backdrop
3
Robust growth in global metals consumption …
2008 2009 2010 Q1 2010 Q2 2010 Q3 2008 2009 2010 Q1 2010 Q2 2010 Q3
H1FY10 H1FY11
Packaging
4%
6
Q2 FY 11: Highlights
7
Robust Performance amidst challenging conditions
Proactive Steps
Highest Ever Production at
Ever Production at
¾ Lower Cu Premium Efficiencies
i
improvement
Muri in Aluminium
¾Coal Price Surge
Reduced Inventory levels to Efficiencies improved
8
Financial Performance
10
Al: External Drivers
11
Aluminium Industry : Cost push to continue
32%
Power
- Electricity price hikes in China
- Power cuts in certain Chinese provinces leading
to cutbacks in production (~1.5 mt capacity)
Cost Push to continue – Support for prices?
12 Source: Industry &
company estimates
Strong Production performance despite Hirakud
production loss
FRP (ton) 2%
Extrusions (ton) Adverse impact
2%
contained through
54,042
,
53 150
53,150 9 815
9,815
9,637 •efficiency
improvement
•Higher alumina &
wire rod production
13 Q2 FY10 Q2 FY11 Q2 FY10 Q2 FY11
Steps taken to minimise impact of Hirakud
production loss
Increased third-party sale of Improved sales mix
specials and standard
138 kt
128 kt Primary-Exp
100.0 84 kt
90.0
80 0
80.0 48% 49%
54 kt Primary-
70.0 34.2 Dom ▼6%
60.0
50.0
40.0
33.5 VAP
44% 50%
▲6%
30.0
20.0
10.0
0.0
14
Q2 FY 11: Strong Aluminium numbers
15
Aluminium Business: Financial Performance
16
Copper: Business Conditions &
Performance Review
17
Copper: External Drivers
Ch ll
Challenging
i titimes
18
Custom Smelters : Low TCRC, Rising energy costs
13.2 13.1
13 0
13.0 13.0 % change H1FY11
12.8
Input
Vs HiFY10
12.4 12.5
12.3 12.2 Imported
>10
coal
Propane >25
2007 2008 2009 2010 2011
(E) (P)
LNG >5
•TCRC to continue to remain under pressure
•FY
FY 10 bench mark TCRC were significantly
higher than FY11 benchmark
19
Cu: Production Performance
Q2: Record cathode production and sharp jump in Own CCR production
C th d (kt)
Cathode O
Own CCR(kt)
5% 41%
94 43
90
31
St
Strong operational
ti l performance
f
20
Copper Business: Financial Performance
21
Mining : ABML Highlights
29491
11% 18%
89.7
26488 75 7
75.7
Strong Performance
22
Copper business – Strategic initiatives paying off III
Key focus areas Drivers
4 Global
Gl b l Cost
C t 9 Global Scale
Competitiveness 9 Top Quartile Cost Curve
Transforming the copper business into a globally competitive smelting value chain
23
Projects – An Update
24
Utkal Alumina
Statutory Obtained
Clearances
Commitment Over 82%
g
Site Progress More than 7,000 ppeople
p working g at site.
Major Contractors like L & T, Simplex, GDC mobilized fully at site.
94% of Piling work completed. RCC, structural, fabrication and
erection has been ramped up and is on track for timely completion.
Power Plant Erection of BTG units under progress
BTG Package:
g ESP#1: Hooper
p erection under progress
p g BTG Package: Boiler#1: Insulator erection
26
Mahan Aluminium
Around 12,000 people at site. Major Contractors like L & T, BHEL, Rohan
builders etc are working.
Concretingg & structural work p
progressing
g g in line with the first p
pot start up
p
schedule.
Site Progress
Power Plant Power plant Fabrication and erection in line with the start up of the power
plant. Foundation for 5 boiler units, 4 ESP units, 2 power house units
completed Work on other units in full swing.
completed. swing Work on all chimneys in full
swing. Two chimney completed- 125 m height. Erection of engineering
structure for boilers in progress.
GTC1 ID Fan
GTC1 BBag filt
filter &
foundations & Stack
crust bath silo
support structure
erection
28
Activity at Site: Mahan CPP
29
Aditya Smelter
Site Progress Area grading ,Piling undergoing. R & R under progress. Civil
contractor - HCC Team has mobilized well with hydraulic rigs
and civil work in permitted fronts is in full swing.
31
Hirakud Smelter and Power Plant Expansion
Smelter Capacity increase from 161 to 213 ktpa thru’ addition of 80 Pots of 235 kA
Expansion
Power Pl
P Plantt C
Capacity
it tto increase
i tto 467.5
467 5 MW by
b Addition
Additi off 100 MW
MW.
Expansion
Schedule 30 pots to be commissioned by Dec’2011 & balance 50 pots by Mar’2012
Technology GAMI Design
Progress Power Plant
1. DCPL has been engaged as the EPCM consultant, Engineering is
progressing well
2. Major orders for the power plant already placed.
Smelter
1. Basic Engineering by GAMI- completed.
2. Major orders like wagons, alumina handling placed. Other major orders
being finalized.
3. SPL has been vacated to storage shed. New plant rectifier station will
be erected over here.
4. Site grading 80% and boundary wall 90% completed.
Dismantling
Dismantling completed. All containers received at Vizag port -
and receipt of
13000 MT.
q p
equipments
Excavation
E ti andd ffoundation
d ti off building
b ildi column
l iin progress.
Civil work
Site Leveling and Boundary wall work in progress.
37
Th k you
Thank
38