Subject: Quotation for FS Hydro FS Study.

Sir,

We are please to submit our offer for conducting a feasibility study of the Hydro Plant located at
Bukidnon. Hereunder are the following scope of work:

1. Detailed Topographic Survey


2. Hydrological Study
3. Geological Study
4. Geotechnical study
5. Socio-environmental Study
6. Power/Market study
7. Preliminary Civil Design
8. EME Design
9. Electrical Facilities Design
10. Prelim. Project Cost Estimate/Financial Study
11 Submission & Compilation of Reports

Lot Price - - - - - - - - - - - - - - - - - - -- - - - - - -PHP 3,000,000 (Three Million Only)

30% Down payment - - - - - - - - - - - - - - -- -PHP 900,000 ( Nine hundred thousand pesos only)

Thanks and regards,

ENGR. FEDILINO FORNOLLES,


Study Proponent