QUESTION NO: 1

You are the project manager of a large project that will last four years. In this project, you would
like to model the risk based on its distribution, impact, and other factors. There are three modeling
techniques that a project manager can use to include both event-oriented and project-oriented
analysis. Which modeling technique does NOT provide event-oriented and project-oriented
analysis for identified risks?

A. Sensitivity analysis
B. Jo-Hari Window
C. Expected monetary value
D. Modeling and simulation

Answer: B

QUESTION NO: 2

Your organization has a project that is expected to last 20 months but the customer would really
like the project completed in 18 months. You have worked on similar projects in the past and
believe that you could fast track the project and reach the 18 month deadline. What increases
when you fast track a project?

A. Resources
B. Costs
C. Communication
D. Risks

Answer: D

QUESTION NO: 3

What approach can a project manager use to improve the project's performance during qualitative
risk analysis?

A. Focus on near-term risks first.


B. Create a risk breakdown structure and delegate the risk analysis to the appropriate project
team members.
C. Focus on high-priority risks.
D. Analyze as many risks as possible regardless of who initiated the risk event.

Answer: C

www.selftestengine.com 2
PMI PMI-RMP Exam

QUESTION NO: 4

In addition to monitoring and controlling the project risks for their status and information the risk
monitoring and controlling process accomplishes four key things for a project. Which one of the
following is NOT a determination that is made by the risk monitoring and controlling process?

A. Determines if the project assumptions are still valid


B. Determines if the risk management policies and procedures are being followed
C. Determines if the risk contingency reserves should be modified to be in alignment with the
current risk assessment
D. Determines if the project constraints are still valid

Answer: D

QUESTION NO: 5

You are the project manager of the GHG project. You are preparing for the quantitative risk
analysis process. You are using organizational process assets to help you complete the
quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize
organizational process assets as a part of the quantitative risk analysis process?

A. You will use organizational process assets for risk databases that may be available from
industry sources.
B. You will use organizational process assets for studies of similar projects by risk specialists.
C. You will use organizational process assets to determine costs of all risks events within the
current project.
D. You will use organizational process assets for information from prior similar projects.

Answer: C

QUESTION NO: 6

You are the project manager for a construction project. The project includes a work that involves
very high financial risks. You decide to insure processes so that any ill happening can be
compensated. Which type of strategies have you used to deal with the risks involved with that
particular work?

A. Mitigate

www.selftestengine.com 3
PMI PMI-RMP Exam
B. Avoid
C. Accept
D. Transfer

Answer: D

QUESTION NO: 7

Wendy is the project manager of the NNJ project for her company. As part of the variance and
trend analysis tool and technique for risk governance she is using earned value management. In
this approach, Wendy wants to track and compare the cost and schedule variances. What is the
point of this tool and technique in regard to risk?

A. Wendy can determine a true project completion date.


B. Wendy can track the cost and schedule variances.
C. Wendy can review quality performance on baselines.
D. Wendy can forecast deviation of the project cost and schedule for completion targets.

Answer: D

QUESTION NO: 8

Which risk response is acceptable for both positive and negative risk events?

A. Transferring
B. Acceptance
C. Sharing
D. Enhancing

Answer: B

QUESTION NO: 9

Gary is the project manager for his project. He and the project team have completed the
qualitative risk analysis process and are about to enter the quantitative risk analysis process when
Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the
following statements best defines what quantitative risk analysis will review?

A. The quantitative risk analysis process will review risk events for their probability and impact on
the project objectives.

www.selftestengine.com 4
PMI PMI-RMP Exam
B. The quantitative risk analysis seeks to determine the true cost of each identified risk event and
the probability of each risk event to determine the risk exposure.
C. The quantitative risk analysis process will analyze the effect of risk events that may
substantially impact the project's competing demands.
D. The quantitative risk analysis reviews the results of risk identification and prepares the project
for risk response management.

Answer: C

QUESTION NO: 10

You are the project manager of the GYH project for your organization. Management has asked
you to begin identifying risks and to use an information gathering technique. Which one of the
following risk identification approaches is an information gathering technique?

A. Root cause analysis


B. Assumptions analysis
C. SWOT analysis
D. Documentation reviews

Answer: A