You are on page 1of 7

Tutorial 13 Rapid Drawdown (B-bar method)

• Full drawdown
• Initial pore pressure
• Partial drawdown
• Negative excess pore pressure
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Introduction
The concept of excess pore pressure using the B-bar method can also be applied to
unloading scenarios. If a load is removed quickly from a low permeability material, a
“negative excess pore pressure” can be induced.
The change in pore pressure is given by:

∆u = B ∆σ v Equation 1

where B (B-bar) is the overall pore pressure coefficient for a material. In Slide, this can be
used to simulate the pore pressure changes due to rapid drawdown of ponded water in
earth dams.
In the Slide Rapid Drawdown (B-bar method) analysis:
1. An initial water table is defined. This defines the initial pore pressure distribution
and the initial weight of ponded water.
2. For a complete drawdown scenario, it is assumed that all ponded water is removed
from the model. The change in pore pressure for undrained materials is calculated
due to the removal (unloading) of the ponded water according to Equation 1. The
final pore pressure at any point is the sum of the initial pore pressure and the
(negative) excess pore pressure.
3. For a partial drawdown scenario, a drawdown water table is also defined. In this
case, the unloading is due to removal of ponded water to the drawdown level. This
determines the change in pore pressure for undrained materials. The pore pressure
in drained materials will be calculated from the drawdown water table.
This tutorial will demonstrate rapid drawdown analysis using the B-bar method in Slide. The
following scenarios will be analyzed: full reservoir, complete drawdown, partial drawdown.
The finished file can be found in File > Recent Folders > Tutorials Folder > Tutorial 13 Rapid
Drawdown.slmd.

Other Drawdown Methods


See Tutorial 17 for other rapid drawdown methods available in Slide:
• Duncan and Wright 3-stage (1990)
• Army Corps 2-stage (1970)
• Lowe and Karafiath (1960)

13 - 2
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Full Reservoir, Steady State


First we will analyze a dam with a full reservoir.
From the Slide main menu, select File > Recent Folders > Tutorials Folder and read in the
Tutorial 13 Drawdown1.slmd file. You can rename Group 1 to “Full Reservoir Steady State”.

Dam with full reservoir.


The model represents a dam with a clay core, a transition zone, and a granular fill outer
layer.
Run Compute and then view the results in Interpret. The critical slip circle has a safety
factor = 1.99. Select the Show Slices option to highlight the sliding region.

Critical slip circle with full reservoir.

13 - 3
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Rapid Drawdown of entire reservoir


Go back to the Modeler. Duplicate the “Full Reservoir Steady State” group and name the
new group “Rapid Drawdown (Entire)”.
In this group we will simulate complete drawdown of the reservoir.

Project Settings
1. Select Project Settings > Groundwater
2. Check the Advanced checkbox and specify Rapid Drawdown Method = Effective
Stress using B-bar. The change in pore pressure due to removal of the ponded
water will be calculated using the B-bar method.
3. Click OK to save the settings.
Note that the water table is labeled as “initial” and no ponded water is displayed. This is to
indicate that a complete drawdown state exists, i.e. the ponded water will be removed for
the final stage of the analysis (i.e. the safety factor calculation).

Material Properties
1. Select Define Materials.
2. For the “clay core”, “transition” and “hard bottom” materials click the Undrained
Behaviour checkbox and enter B-bar = 1. This will result in a negative pore pressure
change for any of these materials which is located beneath the ponded water,
calculated according to Equation 1.

3. The “granular fill” is assumed to be free-draining, so the “undrained” checkbox is


NOT selected. For a complete drawdown scenario, this will result in zero final pore
pressure for this material.
4. Click OK to save the changes.
Run Compute, and view the results in Interpret. You should see the following critical slip
surface (FS = 1.44). Select the Show Slices option.

13 - 4
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Critical slip surface after rapid drawdown.


The critical safety factor after rapid drawdown is significantly lower than the safety factor of
the full reservoir, as we would expect, due to the removal of the support provided by the
ponded water against the slope. For this example, the critical slip circles, before and after
drawdown, are quite similar (i.e. large, deep seated surfaces passing through the core of the
dam).
Let’s examine the pore pressure along this slip surface. Select Graph Query from the
toolbar.
Select Pore Pressure as the primary data, and Initial Pore pressure as the secondary data,
and select Create Plot. You should see the following plots.

Initial Pore Pressure and Final Pore pressure.


13 - 5
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Notice that the (final) Pore Pressure is lower than the Initial Pore Pressure for most of the
slip surface.
• For the portion of the slip surface within the “transition” material (B-bar = 1) this is
due to the negative change in pore pressure due to removal of the ponded water
load.
• For the portion of the slip surface within the “granular fill” material (free draining)
the final pore pressure is zero due to the complete drainage of the fill material.
Let’s plot the Excess Pore pressure. Right-click on the graph, and select “Change Plot Data”
from the popup menu. Select Excess Pore Pressure as the secondary data, and select Create
Plot. You should see the following plot.

Final pore pressure and excess pore pressure, rapid drawdown analysis.
The negative excess pore pressure is clearly visible on the plot.
• For the portion of the slip surface within the “transition” material (B-bar = 1) this is
due to the negative change in pore pressure due to removal of the ponded water
load.
• For the “granular fill” material, the “negative excess pore pressure” is actually the
change in pore pressure due to the lowering of the water table. Since the granular
fill is free draining, the negative excess pore pressure is NOT due to the B-bar
unloading effect, but is simply the difference between the initial and final pore
pressure.

13 - 6
Slide 2018 Tutorial Manual Tutorial 13: Rapid Drawdown Analysis (B-bar method)

Rapid Drawdown to specified level


Finally, let’s demonstrate how we can model rapid drawdown to a specified water level,
rather than a full drawdown. Duplicate the “Rapid Drawdown (Entire)” group and name the
new group “Rapid Drawdown (Specific Level)”. We will be editing this group.
1. Select Boundaries > Add Drawdown Line.
2. In the prompt line enter t then Enter.
3. In the Coordinate Table that appears, copy and paste the following coordinates,
then click OK.

0 0
37.8530642196367 7.3830662547644
79.292 18.543
135.398610454628 45.5376610208739
175.1 20
265 20

4. Hit Enter to complete entering the water line.

Partial drawdown of reservoir.


Note that ponded water is defined where the drawdown water level is above the slope. In
this case, the change in loading is due to the difference in the weight of ponded water
between the initial and final water tables. This unloading creates a negative change in pore
pressure for undrained materials.
Run Compute, and view the results in Interpret.
For this example, the minimum safety factor at partial drawdown (FS = 1.25) is lower than
the minimum safety factor at full drawdown. This is due to the material properties and
geometry of the slope – e.g. complete drainage (zero pore pressure), assumed for the
granular material for the complete drawdown state. At partial drawdown, the drawdown
water table creates significant pore pressure in the granular material, towards the toe of
the slope, and this leads to the lower safety factor. For this particular model, a minimum
safety factor therefore exists at some intermediate drawdown level.

13 - 7

You might also like