CORTEZ, Kyle Eduard G.

BSCE 2Z
ACTIVITY 7
COMP 212

ESTIMATE
CHB Length 4.85 m
Height 1.9 m
Area = Length x Height 9.215 sq m
Quantity = Area x 12.5 115.1875 pcs
= ROUNDUP(quantity,0) 116 pcs

Mortar Cement = Area x 1.018 9.38087 bags


= ROUNDUP(Cement,0) 10 bags
Sand = Area x 0.0844 0.777746 cu m
= ROUNDUP(Sand,0) 1 cu m

Plaster Length 4.85 m


Height = Height of wall above ground 1.5 m
Area = Length x Height x 2 14.55 sq m
Cement = Area x 0.225 3.27375
= ROUNDUP(Cement,0) 4 bags
Sand = Area x 0.025 0.36375 cu m
= ROUNDUP(Sand,0) 1 cu m

SUMMARY
CHB 5" = total number of CHB 116 pcs
Cement = total number of Cement 14 bags
Sand = total number of Sand 2 cu m

Notes; 5'' CHB


CLASS B MIXTURE for MORTAR and PLASTER
25mm thick PLASTER

Instruction:
Create a similar excel program calculating Number of CHB, CEMENT and SAND for
mortar and plaster. USE THIS AS A BASIS. TO BE SUBMITTED and PRESENTED NEXT
MEETING.

Save your work as “CE212 _SECTION_ACT7E8_LASTNAME-FIRSTNAME-MI.xlsx”


ESTIMATE
VERTICAL REINFORCEMENT (10mm dia)
60cm spacing
Height 1.9 m
Length 4.85 m
Area 9.215 sq m
Length = Area x 2.13 20 m
Number of Bars =Length/5.5m 3.568718 pcs
=roundup(Number of bars, 0) 4 pcs
HORIZONTAL REINFORCEMENT (10mm)
every 3 layers
Height 1.9 m
Length 4.85 m
Area 9.215 pcs
Length = Area x 2.15 20 pcs
Number of Bars =Length/5.5m 3.602227 pcs
=roundup(Number of bars, 0) 4 pcs

WALL FOOTING

ESTIMATE
CONCRETE (CLASS B MIX)
60cm spacing
Height 0.1 m
Width 0.2 m
Length 4.85 m
Volume =L x W x H 0.097 cu m

Cement =Volume x 7.5 0.7275 bags


Sand =Volume x 0.5 0.0485 cu m
Gravel =Volume x 1 0.097 cu m

REBAR
MAIN BAR
Length =Width - (2 x 0.025) 0.15 m
Spacing 0.6 m
Number of bar =RoundUP ((Length/Spacing),0) + 1 10 pieces
Length of 10mm Main =bar
Number of Bars x Length 2 m
Number of 10mm bar = Length of 10mm Main Bars / 6 0.25 pcs

TEMPERATURE BARS
Length =Length of wall - (2 x 0.025) 4.8 m
Total Length =L x 3 14.4 m
Effective Length of 6m=6
bar- 0.5 5.5 m
Number of 10mm bars= Total L / Effective L 2.618182 pcs
3
SUMMARY
Cement = total number of Cement 1 pcs
Sand = total number of Sand 1 bags
Gravel = total number of Gravel 1 cu m
10 mm Bars 3 pcs
DRAWING:

MASONRY WORKS
QUANTITY OF CEMENT & SAND FOR CHB MORTAR /m 2
BAGS CEMENT MIXTURE
CHB (mm) NO/m2 SAND (m3)
A B C D
100 (4") 12.5 0.792 0.522 0.394 0.328 0.0435
125 (5") 12.5 1.526 1.018 0.763 0.633 0.0844
150 (6") 12.5 2.26 1.5 1.125 0.938 0.125
QUANTITY OF CEMENT & SAND FOR PLASTER / m 2 AREA
CEMENT ON BAGS / THICKNESS OF PLASTER
MIX. CLASS
8mm 12 mm 16mm 20 mm 25mm
AA 0.144 0.216 0.288 0.36 0.45
A 0.096 0.144 0.192 0.24 0.3
B 0.072 0.108 0.144 0.18 0.225
C 0.06 0.09 0.12 0.15 0.188
D 0.008 0.012 0.015 0.02 0.025
SAND 0.008 0.012 0.016 0.02 0.025
VERTICAL REINFORCEMENTS HORIZONTAL REINFORCEMENTS
SPACING
LENGTH OF BARS IN METER SPACING LENGTH OF BARS IN METERS
LAYER
cm PER BLOCK PER m2 PER BLOCK PER m2
40 0.235 2.93 2 0.264 3.3
60 0.171 2.13 3 0.172 2.15
80 0.128 1.6 4 1.138 1.72

MULTIPLIERS
CONCRETE WORKS

TABLE OF CONCRETE PROPORTION


MIX. CLASSPROPORTION CEMENT( 40KG) SAND(m3) GRAVEL(m3)
M 12 0.5 1
A 9 0.5 1
B 7.5 0.5 1
C 6 0.5 1

0.381818 2.290909