FOUNDATION DETAILS

S.NO AREA LOCATION COVERING System SKID LOCATION TYPE OF FOUNDATION SKID E.L FOUNDATION E.L SYSTEM WEIGHT Length Width

Foundation Dimensions
1 Turbine Power House DELUGE South of Turbine area Concrete On Going On Going

2 White Sugar Dispatch, Palletizers & Packing Sprinkler West of Dispatch area Concrete On Going On Going

3 White Sugar CONSUMABLES,BUNDLES STORAGE Sprinkler + Fire Hose Cabinet East of Bandol Storage Concrete E.L.+4.000 W.W.L.+3.400 350 KG 2500 1000

4 Pump Room Pump Room Sprinkler West of Pump Room Concrete E.L.+4.000 FFL.+3.500 345 KG 2000 1000

5 A-Frame C-140 & TT-02 Sprinkler + Fire Hose Cabinet Near From TT-02 Concrete Done Done

6 A-Frame C-290 Sprinkler East A-Frame Concrete EL.+3.900 T.O.C.+3.500 390 KG 2500 1500

7 White Sugar C-080 & TT-06 Sprinkler + Fire Hose Cabinet West of TT-06 Concrete EL.+3.800 F.F.L +3.300 556 KG as per site condition

8 Refinery TT-05 Fire Hose Cabinet Near From TT-05 Concrete Pedestal .+7.180 T.O.C.+3.500 270 Kg 200*450 (Quantity as per site condition)

9 Refinery ANNEX BUILDING Fire Hose Cabinet North of Annex Buildding Concrete Pedestal 3.85 3.5 400 kG 200*450 (Quantity as per site condition)

10 Refinery Main Refinery Building Fire Hose Cabinet Front Center of Main Refinery Concrete Pedestal ELEV.+3.850 ELE. +3.500 450 KG 200*450 (Quantity as per site condition)

S.NO System Total FOUNDATION


TYPE OF FOUNDATION Foundation Length Width
E.L
Dimensions

1 FIRE HYDRANT 32

2 FIRE HYDRANT CABINET 32 Concrete as per site condition 1000 350